NO URAIAN PEKERJAAN Satuan Volume Harga Satuan Jumlah Sub Total

(Rp) (Rp) (Rp)


A PEKERJAAN PONDASI 14,179,314
1 Galian tanah pondasi m3 32.64 28 913,92
Pasangan Pondasi Batu Kosong (aanstamping)
2 m3 8.16 394,188 3,216,574
tebal 20 cm
3 Pasangan Pondasi Batu adukan 1pc : 5 psr m3 13.77 719,324 9,905,091
4 Urugan tanah pondasi m3 10.71 13,42 143,728
PEKERJAAN BETON (adukan
B 113,431,613
1pc:2psr:3krikil)
Sloof Beton Tulang 15/20 (180 kg besi +
1 m3 2.45 5,128,142 12,553,692
bekisting) 4dia. 12 ring 8-15
Kolom, 15/20 (180 kg besi + bekisting) 4dia.12 ,
2 m3 3.28 5,808,000 19,027,008
ring 8 -15
Ring Balk, sofi-sofi (180 kg besi + bekisting)
3 m3 2.69 5,429,025 14,593,219
4dia. 12mm, ring 8mm -15
Tangga Beton (90 kg besi + bekisting), dia 10 &
4 m3 0.48 4,892,610 2,348,453
8 mm
Plat Lantai 10 cm ( 90 Kg Besi + Bekisting ) dia
5 m3 10.52 6,170,080 64,909,242
8mm, 2x 1515
C PEKERJAAN PASANGAN DINDING 85,401,132
1 Pasang bata merah adukan 1 pc : 5 psr m2 306.00 107,422 32,871,132
2 Plesteran tebal 2 cm 1 pc : 5 psr m2 612.00 53,073 32,480,676
3 Acian semen m2 612.00 25,316 15,493,392
4 Pasangan keramik dinding km. mandi 20 x 25 m2 28.00 133,998 3,751,944
5 Pasangan keramik dinding dapur 20 x 25 m2 6.00 133,998 803,988
D PEKERJAAN ATAP 7,502,904
1 Rangka atap baja ringan m2 27.00 150 4,050,000
2 Tutup atap genting plentong m2 27.00 66,536 1,796,472
3 Genting bubung plentong m 6.00 86,752 520,512
4 Listplang kayu kamper medan 2/20 m 12.00 94,66 1,135,920
5 Talang sudut (seng) m 0.00 121,856
E PEKERJAAN LANGIT-LANGIT 19,121,632
1 Langit-langit GRC 120 x 240 + rangka hollow m2 144.00 102,798 14,802,912
2 List gypsum m 224.00 19,28 4,318,720
F PEKERJAAN LANTAI 23,231,058
1 Lantai keramik, luar & dalam, 40 x 40 cm m2 144.00 121,491 17,494,704
2 Lantai keramik, kamar mandi, 30 x 30 m2 6.00 114,491 686,946
3 Plint Keramik 10 x 40, dalam m 224.00 22,542 5,049,408
G PEKERJAAN KAYU 26,138,180
Kusen pintu dan jendela, kayu balok kamper
1 m3 0.65 13,414,000 8,711,588
samarinda
Daun pintu panel, kayu papan kamper
2 m2 3.20 673,2 2,154,240
samarinda
Daun pintu triplek, rangka kayu papan kamper
3 m2 12.80 482,67 6,178,176
samarinda

Daun jendela ram kaca, kayu papan kamper


4 m2 13.44 566,4 7,612,416
samarinda
Daun pintu triplek lapis formika, rangka papan
5 m2 2.40 617,4 1,481,760
kamper samarinda
H PEKERJAAN KACA DAN KUNCI 8,595,687
1 Pasang kaca jendela 5 mm m2 10.75 140,86 1,514,527
2 Pasang kunci tanam bh 8.00 392,02 3,136,160
3 Pasang kunci kamar mandi bh 2.00 111,01 222,02
4 Pasang engsel pintu bh 30.00 51,36 1,540,800
5 Pasang engsel jendela bh 26.00 34,57 898,82
6 Pasang tulak angin bh 26.00 49,36 1,283,360
I PEKERJAAN SANITASI 17,439,078
1 Pasang closet duduk bh 1.00 1,786,092 1,786,092
2 Pasang closet jongkok bh 1.00 552,55 552,55
3 Pasang washtafel bh 1.00 1,119,350 1,119,350
4 Pasang bak mandi fibergalass bh 2.00 709,18 1,418,360
5 Pasang bak cuci piring stainless bh 1.00 466,71 466,71
6 Septictank uk 2 x 1.5 x 1.5 + rembesan unit 1.00 6,989,279 6,989,279
7 Keran air bh 5.00 55,145 275,725
8 Pipa pvc 1/2 instalasi air m 30.00 25,13 753,9
9 Pipa pvc 4 AW saluran air hujan dan air limbah m 26.00 156,812 4,077,112
J PEKERJAAN PENGECATAN 26,590,249
1 Pengecatan kusen, dengan cat kayu m2 32.47 45,518 1,478,060
2 Pengecatan pintu dan jendela, dengan cat kayu m2 37.38 45,518 1,701,281
Pengecatan Plapond 3x, dengan cat tembok
3 m2 144.00 52,76 7,597,440
Vinilex
4 Pengecatan tembok 3x dengan Cat Vinilex m2 612.00 25,839 15,813,468

TOTAL 341,630,847