Job Ref.
Engineering Consultants Group CHECKING AND PACKING HALL
Bldg. 2, Block 10, El Sefarat District Calc. By Date Checked By Date Rev.
Span = 10.00 m
Spacing = 1.90 m
Using tie rods = 1 tie rod 12
1)- APPLIED FORCES :-
DEAD LOAD
O.W of C.sheets = 10.00 Kg/m2
WYDL = 0.0484 t/m\
MYDL = 0.1513 m.t
LIVE LOAD
100 Kg concentrated load
PY = 100.00 Kg
MYLL = 0.1250 m.t
WIND LOAD
Ce = 0.80
K = 1.10
q = 50.00 Kg/m2
WXWL = 0.0836 t/m\
MXWL = 1.0450 m.t
QXWL = 0.42 t
2)-CHOICE OF SECTION :-
U.P.N. 220
Shear Stress
qw = 0.11 t/cm2 < 0.35xFy SAFE
h
4)- CHECK DEFLECTION :- X
W
B
ECG Project Name
Job Ref.
Engineering Consultants Group CHECKING AND PACKING HALL
Bldg. 2, Block 10, El Sefarat District Calc. By h Date Checked By Date Rev.
W
P.O.Box No. 1167, Cairo 11511, Egypt. M.Nour E
Sheet No.
L.L = 2.63 cm < span/300
B SAFE