REKAPITULASI ANGGARAN BIAYA

NO NAMA PEKERJAAN

I PEKERJAAN PERSIAPAN

II PEKERJAAN TANAH

III PEKERJAAN PONDASI

IV PEKERJAAN PASANGAN

V PEKERJAAN BETON

VI PEKERJAAN ATAP

VII PEKERJAAN KUSEN & JENDELA

VIII PEKERJAAN KUNCI & PENGGANTUNG

IX PEKERJAAN LANTAI

X PEKERJAAN LISTRIK

XI PEKERJAAN CAT & FINISHING

JUMLAH
GARAN BIAYA

JUMLAH
(Rp.)

250,000.00

770,730.00

2,168,345.60

2,885,720.00

2,001,741.98

17,708,441.86

19,765,756.00

300,520.00

596,670.00

309,500.00

3,065,889.70

49,823,315.14
RENCANA ANGGARAN BIAYA

No Uraian Pekerjaan Volume Satuan Harga Satuan


Rp.
1 2 3 4 9
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 1.00 ls 250,000.00

II PEKERJAAN TANAH
1 Galian tanah pondasi 6.40 m3 52,500.00
2 Urugan Tanah 2.88 m3 107,500.00
3 Urugan pasir 0.97 m3 129,000.00

III PEKERJAAN PONDASI


1 Pasangan Pondasi Batu kali 1 pc : 5 ps 3.52 m3 583,280.00
2 Pasanng Rollag Bata 0.58 m3 200,000.00

IV PEKERJAAN PASANGAN
1 Pasangan bata 24.32 m2 118,656.25

V PEKERJAAN BETON
1 Sloof 15/20 0.24 m3 3,115,630.00
2 Kolom Praktis 14.84 m1 57,746.00
3 Ring Balk 0.24 m1 69,048.50
4 Rabatan Lantai t = 5 cm 0.58 m3 658,250.00

VI PEKERJAAN ATAP
1 Pasang Jurai/ Kuda-kuda 0.23 m3 8,222,300.00
2 pasang gording, nok, Meranti 1.44 m3 8,222,300.00
5 Pasang lisplang ukuran ( 3x20) cm, kemfer 13.20 m1 102,400.00
7 Pasang Genteng Kluntung 20.67 m2 114,988.00
8 Pasang Bubungan Klutung motif 1.00 m1 98,680.00
9 Bubungan Mainan 1.00 bh 146,520.00

VII PEKERJAAN KUSEN & JENDELA


1 Pas kusen pintu & jendela ky. Meranti /merbau 1.60 m2 9,304,000.00
2 Pasang pintu panil kayu meranti/ merbau 2.80 m2 565,500.00
3 Pasang dinding papan Meranti/ merbau 3.38 m2 472,200.00
4 Pasang daun jendela kayu meranti 3.60 m1 472,200.00

VIII PEKERJAAN KUNCI & PENGGANTUNG


1 Pasang engsel pintu 2.00 bh 49,940.00
2 Pasang engsel jendela kupu-kupu 3.00 bh 29,960.00
3 Pasang hak angin 3.00 bh 36,920.00

IX PEKERJAAN LANTAI
1 Pasang lantai keramik ukuran 30 x 30 4.00 m2 149,167.50

X PEKERJAAN LISTRIK
1 Pasang titik lampu 2.00 bh 125,000.00
2 Pasang Lampu SL 24 Wat 1.00 bh 30,000.00
3 Pasang saklar seri 1.00 bh 15,000.00
4 Pasangstopkontak 1.00 bh 14,500.00

XI PEKERJAAN CAT & FINISHING


1 Polituran & coating 39.20 m2 59,156.00
2 Cat daun pintu dan jendela ( warna Natural ) 18.50 m2 40,377.00
JUMLAH TOTAL
Jumlah Total Jumlah Total
Bahan + upah Rp.
10 11

250,000.00
Sub jumlah 250,000.00

336,000.00
309,600.00
125,130.00
Sub jumlah 770,730.00

2,053,145.60
115,200.00
Sub jumlah 2,168,345.60

2,885,720.00
Sub jumlah 2,885,720.00

747,751.20
856,950.64
16,571.64
380,468.50
Sub jumlah 2,001,741.98

1,894,417.92
11,840,112.00
1,351,680.00
2,377,031.94
98,680.00
146,520.00
Sub jumlah 17,708,441.86

14,886,400.00
1,583,400.00
1,596,036.00
1,699,920.00
Sub jumlah 19,765,756.00

99,880.00
89,880.00
110,760.00
Sub jumlah 300,520.00

596,670.00
Sub jumlah 596,670.00

250,000.00
30,000.00
15,000.00
14,500.00
Sub jumlah 309,500.00

2,318,915.20
746,974.50
Sub jumlah 3,065,889.70

49,823,315.14
RENCANA ANGGARAN BIAYA

No Uraian Pekerjaan Volume Satuan BAHAN UPAH


Harga Satuan Jumlah Harga Harga Satuan
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembongkaran teras lama 1.00 ls 300,000.00
2 Pembersihan lokasi 1.00 ls 300,000.00
SUB JUMLAH SUB JUMLAH
II PEKERJAAN TANAH
1 Urugan Tanah 6.36 m3 90,000.00 572,400.00 17,500.00
2 Urugan pasir 0.87 m3 108,000.00 93,960.00 21,000.00
SUB JUMLAH 666,360.00 SUB JUMLAH
III PEKERJAAN PONDASI
1 Pasangan Pondasi Batu kali 1 pc : 5 ps 7.03 m3 422,720.00 2,971,721.60 160,560.00
SUB JUMLAH 2,971,721.60 SUB JUMLAH
IV PEKERJAAN PASANGAN
1 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps 7.10 m2 61,160.00 434,236.00 31,660.00
2 Pasangan bata expose tanpa plester 29.80 m2 86,996.25 2,592,488.25 31,660.00
SUB JUMLAH 3,026,724.25 SUB JUMLAH
V PEKERJAAN BETON
1 Sloof 15/20 0.45 m3 4,070,225.00 1,831,601.25 646,006.00
2 Kolom Praktis 18.00 m1 47,990.00 863,820.00 9,756.00
3 Ring Balk 15.20 m1 52,872.50 803,662.00 16,176.00
4 Rabatan Lantai t = 5 cm 0.93 m3 519,600.00 483,228.00 138,650.00
SUB JUMLAH 3,982,311.25 SUB JUMLAH
VI PEKERJAAN ATAP
1 Pasang konstruksi kuda-kuda kayu Meranti 0.20 m3 6,831,100.00 1,366,220.00 1,391,200.00
2 pasang gording, nok, Meranti 0.25 m3 6,831,100.00 1,707,775.00 1,391,200.00
3 pasang Konsol 0.25 m3 6,831,100.00 1,707,775.00 1,391,200.00
4 Pasang kaso + reng kayu Meranti 59.86 m2 66,150.00 3,959,739.00 16,260.00
5 Pasang lisplang ukuran ( 3x20) cm, kemfer 21.20 m1 76,450.00 1,620,740.00 25,950.00
6 Pasang ruter 2/20 16.60 m2 48,370.00 802,942.00 25,950.00
7 Genteng Nglayur Trenggalek 59.86 m2 50,000.00 2,993,000.00 17,488.00
8 Bubungan Nglayur Trenggalek 16.60 m1 14,400.00 239,040.00 46,520.00
9 Bubungan Mainan 6.00 bh 100,000.00 600,000.00 46,520.00
SUB JUMLAH 14,997,231.00 SUB JUMLAH
VII PEKERJAAN KUSEN & JENDELA
1 Pasang kusen pintu & jendela ky. Meranti 0.15 m2 7,200,000.00 1,072,800.00 2,104,000.00
2 Pasang pintu panil kayu meranti 4.00 m2 264,000.00 1,056,000.00 301,500.00
3 Pasang daun jendela kayu meranti 3.60 m1 231,000.00 831,600.00 241,200.00
SUB JUMLAH 2,960,400.00 SUB JUMLAH
VIII PEKERJAAN SKET & PLAFOND
1 Pasang Triplek Taekwood rangka hollow 14.20 m2 102,000.00 1,448,400.00 33,650.00
SUB JUMLAH 1,448,400.00 SUB JUMLAH
IX PEKERJAAN KUNCI & PENGGANTUNG
1 Pasang kunci tanam biasa 1.00 bh 75,000.00 75,000.00 59,760.00
2 Pasang engsel pintu 2.00 bh 35,000.00 70,000.00 14,940.00
3 Pasang engsel jendela kupu-kupu 4.00 bh 20,000.00 80,000.00 9,960.00
4 Pasang hak angin biasa 4.00 bh 17,000.00 68,000.00 19,920.00
SUB JUMLAH 293,000.00 SUB JUMLAH
X PEKERJAAN LANTAI
1 Pasang lantai keramik ukuran 30 x 30 18.70 m2 73,357.50 1,371,785.25 75,810.00
SUB JUMLAH 1,371,785.25 SUB JUMLAH
XI PEKERJAAN LISTRIK
1 Pasang titik lampu 3.00 bh 125,000.00 375,000.00 30,000.00
2 Pasang saklar & STOPKONTAK 2.00 bh 15,000.00 30,000.00 2,500.00
SUB JUMLAH 405,000.00 SUB JUMLAH
XII PEKERJAAN CAT & FINISHING
1 Polituran & coating 42.25 m2 48,540.00 2,050,815.00 10,616.00
2 Cat daun pintu dan jendela ( warna Natural ) 16.70 m2 34,205.00 571,223.50 6,172.00
SUB JUMLAH 2,622,038.50 SUB JUMLAH
UPAH Harga Satuan Jumlah Total Jumlah Total
Jumlah Harga Rp. Bahan + upah Rp.
8 9 10 11

300,000.00 300,000.00 300,000.00 300,000.00


300,000.00 300,000.00 300,000.00 300,000.00
600,000.00 JUMLAH I 600,000.00 600,000.00

111,300.00 107,500.00 683,700.00 683,700.00


18,270.00 129,000.00 112,230.00 112,230.00
129,570.00 JUMLAH X 795,930.00 795,930.00

1,128,736.80 583,280.00 4,100,458.40 4,100,458.40


1,128,736.80 JUMLAH IV 4,100,458.40 4,100,458.40

224,786.00 92,820.00 659,022.00 659,022.00


943,468.00 118,656.25 3,535,956.25 3,535,956.25
1,168,254.00 JUMLAH IV 4,194,978.25 4,194,978.25

290,702.70 4,716,231.00 2,122,303.95 2,122,303.95


175,608.00 57,746.00 1,039,428.00 1,039,428.00
245,875.20 69,048.50 1,049,537.20 1,049,537.20
128,944.50 658,250.00 612,172.50 612,172.50
841,130.40 JUMLAH VIII 4,823,441.65 4,823,441.65

278,240.00 8,222,300.00 1,644,460.00 1,644,460.00


347,800.00 8,222,300.00 2,055,575.00 2,055,575.00
347,800.00 8,222,300.00 2,055,575.00 2,055,575.00
973,323.60 82,410.00 4,933,062.60 4,933,062.60
550,140.00 102,400.00 2,170,880.00 2,170,880.00
430,770.00 74,320.00 1,233,712.00 1,233,712.00
1,046,831.68 67,488.00 4,039,831.68 4,039,831.68
772,232.00 60,920.00 1,011,272.00 1,011,272.00
279,120.00 146,520.00 879,120.00 879,120.00
5,026,257.28 JUMLAH III 20,023,488.28 20,023,488.28

313,496.00 9,304,000.00 1,386,296.00 1,386,296.00


1,206,000.00 565,500.00 2,262,000.00 2,262,000.00
868,320.00 472,200.00 1,699,920.00 1,699,920.00
2,387,816.00 JUMLAH III 5,348,216.00 5,348,216.00
477,830.00 135,650.00 1,926,230.00 1,926,230.00
477,830.00 JUMLAH II 1,926,230.00 1,926,230.00

59,760.00 134,760.00 134,760.00 134,760.00


29,880.00 49,940.00 99,880.00 99,880.00
39,840.00 29,960.00 119,840.00 119,840.00
79,680.00 36,920.00 147,680.00 147,680.00
209,160.00 JUMLAH VI 502,160.00 502,160.00

1,417,647.00 149,167.50 2,789,432.25 2,789,432.25


1,417,647.00 JUMLAH VII 2,789,432.25 2,789,432.25

90,000.00 155,000.00 465,000.00 465,000.00


5,000.00 17,500.00 35,000.00 35,000.00
95,000.00 JUMLAH VIII 500,000.00 500,000.00

448,526.00 59,156.00 2,499,341.00 2,499,341.00


103,072.40 40,377.00 674,295.90 674,295.90
551,598.40 JUMLAH IX 3,173,636.90 3,173,636.90

JUMLAH TOTAL 48,777,971.73

DIBULATKAN 48,777,000.00
JUMLAH BOBOT
NO NAMA PEKERJAAN
(Rp.) % MINGGU
1 2

I PEKERJAAN PERSIAPAN 250,000.00 0.502 0.25089 0.25089

II PEKERJAAN TANAH 770,730.00 1.547 0.77346

III PEKERJAAN PONDASI 2,168,345.60 4.352

IV PEKERJAAN PASANGAN 2,885,720.00 5.792

V PEKERJAAN BETON 2,001,741.98 4.018

VI PEKERJAAN ATAP 17,708,441.86 35.542

VII PEKERJAAN KUSEN & JENDELA 19,765,756.00 39.672

VIII PEKERJAAN KUNCI & PENGGANTUNG 300,520.00 0.603

IX PEKERJAAN LANTAI 596,670.00 1.198

X PEKERJAAN LISTRIK 309,500.00 0.621

XI PEKERJAAN CAT & FINISHING 3,065,889.70 6.154

TOTAL dan PENGAJUAN PEKERJAAN 49,823,315.14 100 0.25 1.02


KEMAJUAN PEKERJAAN KOMULATIF % 0 0.25 1.28
JADWAL WAKTU PELAKSANAAN / TIME SCHEDULE

JANGKA WAKTU PELAKSANAAN PEKERJAA


AGUSTUS 2017
MINGGU 1 MINGGU 2
3 4 5 6 7 8 9 10 11 12 13

0.773

2.17604 2.17604

1.93064 1.93064 1.93064

0.80354 0.80354 0.80354 0.80354 0.80354

5.92375 5.92375 5.92375 5.92375

0.77 2.18 4.11 2.73 2.73 0.80 0.80 6.73 5.92 5.92 5.92
2.05 4.22 8.33 11.07 13.80 14.60 15.41 22.13 28.06 33.98 39.91
/ TIME SCHEDULE

PELAKSANAAN PEKERJAAN 28 HARI KALENDER KERJA


AGUSTUS 2017
MINGGU 3 MINGGU 4
14 15 16 17 18 19 20 21 22 23 24

5.923747 5.923747

9.917925 9.917925 9.91792 9.917925

0.301586 0.30159

0.1996 0.1996 0.1996 0.1996 0.1996 0.1996

15.84 15.84 9.92 10.22 0.30 0.20 0.20 0.20 0.20 0.20 0.20
55.75 71.59 81.51 91.73 92.03 92.23 92.43 92.63 92.83 93.03 93.23
KET
MINGGU 4
25 26 27 28

100

50

0.3106 0.3106

2.05117 2.05117 2.05117

0.31 2.36 2.05 2.05


93.54 95.90 97.95 100.00