zaki mossallam-leveling Classic Schedule Layout 23-May-17 13:55

Oct 22 Oct 29 Nov 05 Nov 12 Nov 19 Nov 26 Dec 03 Dec 10 Dec 17 Dec 24 Dec 31 Jan 07 Jan 14 Jan 21 Jan 28 Feb 04 Feb 11 Feb 18 Feb 25 Mar 04 Mar 11 Mar 18 Mar 25 Apr 01 Apr 08 Apr 15 Apr 22 Apr 29 May 06
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
03-Apr-18, z-2 zaki mossallam-leveling

30-Oct-17, z-2.1000 START


start, 30-Oct-17
09-Nov-17, z-2.100 Preparation
site cleaning
levelling
survey works
20-Dec-17, z-2.200 Foundation
20-Dec-17, z-2.200.001 soil works
excavation
backfilling
12-Dec-17, z-2.200.002 concrete works
formwork for pc footing
casting pc footing
formwork removal pc footing
formwork rc footing
steel fixing rc footing
casting rc footing
formwork removal rc footing
curing rc footing
01-Feb-18, z-2.300 RC skelleton
05-Jan-18, z-2.300.001 1st Floor
formwork rc columns
steel fixing rc columns
casting rc columns
formwork removal rc columns
curing rc columns
formwork rc slabs
steel fixing rc slabs
casting rc slabs
formwork removal rc slabs
curing rc slabs
01-Feb-18, z-2.300.002 2nd Floor
formwork rc columns
steel fixing rc columns
casting rc columns
formwork removal rc columns
curing rc columns
formwork rc slabs
steel fixing rc slabs
casting rc slabs
formwork removal rc slabs
curing rc slabs
27-Mar-18, z-2.400 Finishing
08-Mar-18, z-2.400.001 1st Floor
brickwork
primary electrical work
primary sanitary work
primary carpentry work
plastering
flooring
painting
finishing electrical works
finishing carpentry works
finishing sanitary works
27-Mar-18, z-2.400.002 2nd Floor
brickwork
primary electrical work
primary sanitary work
primary carpentry work
plastering
flooring
painting
finishing electrical works
finishing carpentry works
finishing sanitary works
03-Apr-18, z-2.500 Facing and Final Finishing
facing
water tank
final finishing
03-Apr-18, z-2.2000 FINISH
Finish,

30 1500

24 1200

18 900

12 600

6 300

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
Oct 22 Oct 29 Nov 05 Nov 12 Nov 19 Nov 26 Dec 03 Dec 10 Dec 17 Dec 24 Dec 31 Jan 07 Jan 14 Jan 21 Jan 28 Feb 04 Feb 11 Feb 18 Feb 25 Mar 04 Mar 11 Mar 18 Mar 25 Apr 01 Apr 08 Apr 15 Apr 22 Apr 29 May 06