Table of Contents
INTRODUCTION ....................................................................................................................................................................2
FORECAST SETS: ...................................................................................................................................................................3
FORECASTS ...........................................................................................................................................................................4
MASTER DEMAND SCHEDULE (MDS).................................................................................................................................6
MRP MATERIAL REQUIREMENT PLANNING .................................................................................................................17
REPORTS: .........................................................................................................................................................................25
Introduction
The objective of this User Manual to introduce the Oracle Material Requirement planning
Module to the users of Sonakoyo and to train them in using this module for their operations.
This document is prepared keeping in view the requirements of Sonakoyo. For further and
full information on MRP module, reference may be made to the MRP User Guides, released
by Oracle Corporation.
Oracle Material Requirement Planning is one of the modules in the Manufacturing Suite. This
module is intended to define forecasts, define master demand schedules, and material
requirement plans. This module is tightly integrated with Inventory, Purchasing, Order
Management, Bills of Material, Costing, and Work in Process.
2
Forecast Sets:
3
Forecasts
Query the required Forecast set for which the Forecast has to be defined and
assigned
Enter the Forecast name
Click on the Forecast Items
4
Click on the Detail button
Enter the Details like Date and Quantity based on the Forecasting requirement
Save the Record
5
Similarly enter all the Forecasts for specific Forecast sets
6
Enter the name of the MDS
Enter the Description based on requirement
Save the Record
Click on Load/Copy/Merge
7
Submit Load/Copy/Merge MDS request
After the successful completion of the request, the demand defined in all the forecast sets listed in the
source list will be copied as Demand in the destination Master Demand Schedule.
8
Query MDS for viewing the results
Click Detail
9
MPS- Master Production Schedule
The MPS is a statement of supply required to meet the demand for the items contained in the
MDS. The master production schedule defines the anticipated build schedule for critical items. An
effective master production schedule provides the basis for order promising and links the aggregate
production plan to manufacturing by specific items, dates, and quantities. You can use the MPS to
10
level or smooth production so that you effectively utilize capacity to drive the material
requirements plan.
For a master production schedule, the schedule date for discrete items and the start
and
end dates for repetitive items must be valid workdays.
Enter Name
Enter Description
Select value for Organization selection
Save
Click on Options button
11
Disable Demand Time Fence Control
Disable Planning Time Fence Control
Disable Snapshot Lock tables
Disable Plan Capacity
Disable Pegging
Select Planned Items as Demand & Supply schedule items
Click Plan Organizations
Select appropriate values for Net WIP, Net Reservations, Net Purchasing & Plan Safety
Stock
Select appropriate MDS under Demand Schedules
12
Click Subinventory Netting
Select appropriate Net check box for relevant subinventories to consider MPS plan
Save
13
MPS Launch MPS
Once the Request is submitted many concurrent requests are run and after all these requests
are completed successfully, MPS will make its suggestions for the manufacture of finished
goods based on the demand specified in MDS.
MPS WORKBENCH
The suggestions made by the MPS plan can be directly released from the MPs workbench. On
release of the planned order for a make item, a discrete job is created and imported into the
Work in Process module.
14
Click on Items button (workbench main page)
Click on Find
All Items involved in the MPS plan are displayed
Select the Item and make the required queries like Components, Where used, Supply,
Demand etc.,
Click on Supply / Demand button (workbench main page)
Click Find
15
If the selected Item is Finished good then the MPS will suggest the required jobs to
fulfill the demand
If the Jobs are already created then the system will suggest the user to reschedule it
based on the demand dates
Suggested Jobs can be released directly and will be imported to WIP
Click on Supply button (workbench main page)
Click find
16
Suggested Jobs can be released
Click find
Based on the suggestions, purchase requisitions for buy items and discrete jobs for make
items can be directly released from the MRP workbench. If the demand is changed or
cancelled MRP will make new suggestions accordingly, next time it is launched.
17
Enter the name and description for the MRP
Check the Feedback check box
Save the Record
Click on Options button
Disable Snapshot Lock Tables, Demand Time Fence Control, Planning Time Fence
Control
Disable Pegging
Select All Planned items for Planned items
Select Plan Organizations
18
Enable appropriate Net WIP, Net Reservations, Net Purchasing & Plan Safety Stock
Attach the Demand by giving the MDS name in the schedule field
Click the Sub Inventory netting and check the Sub Inventories that this plan should
consider
Click ok
Once the Request is submitted many concurrent requests are run and after all these requests
are completed successfully, MRP will make its suggestions for the purchase of components
and the manufacture of finished goods based on the demand specified in MDS.
20
MRP WORKBENCH
The suggestions made by the MRP plan can be directly released from the MRP workbench. On
release of the planned order for a buy item an approved Purchase Requisition is automatically
created and imported to Purchasing module. The requisition can then be auto-created into a
Purchase Order and the items can be received into the organization. For make items after the
release of the planned from the workbench, a discrete job is created and imported into the
Work in Process module.
21
Click on Items button (workbench main page)
Click on Find
All Items involved in the MRP plan are displayed
Select the Item and make the required queries like Components, Where used, Supply,
Demand etc.,
Click on Supply / Demand button (workbench main page)
Click Find
22
If the selected Item is Finished good then the MRP will suggest the required jobs to
fulfill the demand
If the Jobs are already created then the system will suggest the user to reschedule it
based on the demand dates
Suggested Jobs can be released directly and will be imported to WIP
Suggested Purchase requisitions cane be released and will be imported to Purchasing
Click find
23
Suggested Jobs can be released
Click Find
24
The demand for the Items in the MDS is displayed
REPORTS:
The Material planner can access and run certain reports for his daily planning
activities and for better production to meet the demands as scheduled.
25
Click on OK button
Select the required report from the LOV
26
Click Submit
Click No
27
Navigate through View>Requests
Click Find
28
Report status should be Normal
Click View Output to view the report output
The Forecast Detail Report displays information for the forecast set or forecast
within a
29
set you specify. You can choose the number of periods and weeks for which to run the report.
You can display the data by horizontal time phased display, by vertical display, or by both.
You can report all items or a range of items associated with the forecast name.
Output:
The (Supply Chain) Planning Detail Report includes material requirements planning data for a
DRP, MPS, or MRP name that you specify. This is the central planning report that gives you all
the information you need to understand the material plan. The report may include the
following sections: Horizontal Listing, Vertical Listing, and detail sections showing gross
requirements, scheduled receipts, planned orders, bill of material and engineering changes,
repetitive schedules, substitute items, expired lot and byproduct information
30
Output:
31