Short Course on
Geotechnical Investigations for Structural Engineering
Contents
1. Ground Engineering & Foundation Systems (15 min)
3. Case Studies
i. Technical Expertise (10 min)
4. Conclusions (5 min)
Foundation Engineering
Shallow Deep
Foundations Foundations
Foundations on Natural Foundations on Weak Bored Cast In-Situ Pile Driven Pile
Soils (Un-Improved Soils) Soils (Improved Soils) Foundations Foundations
Settlements
Friction & End Driven Cast
within Tolerable
Bearing Piles In-Situ Piles
Limits
Open Foundations
Ground Improvement
Ground
Improvement
Chemical
Densification Consolidation Reinforcement Others
Modification
Compaction (Compaction
Grouting Grouting)
PILES
(bridge over weak soil)
Settlement
REINFORCED GI TECHNIQUE
(treat weak soil + strengthen with
stones, cement, etc.)
UNREINFORCED GI
TECHNIQUE
(consolidation by weight)
100% 50% 0%
PILES
Typical Settlement
50 to 200mm
GROUND IMPROVEMENT
TECHNIQUES
>300 mm
CONSOLIDATION BY
SURCHARGE
Vibro Techniques
Install compacted granular columns in all types of soils, Under the influence of the induced vibration, the soil particles
referred to as Vibro Replacement. within the zone of influence are rearranged and compacted.
Vibro Compaction
Before Treatment
After Treatment
Depth Vibrator
Penetration
Grouting Techniques
Introduction of liquid or dry binder (esp. cement material) into the weak soil mass, to improve its
strength, stiffness and reduce permeability.
TAM TAM
Choice of Technique
Suitability of Technique
Are the encountered soil and suggested technique fundamentally compatible?
Technical Compliance
Does the suggested technique satisfy the design requirements ? (strength or
stiffness?)
Availability of Material
Is the required material (stone, cement) readily available?
Cost
Is the proposed technique within the budget? What is the cost of time when
there is saving?
Design Challenges
Power Plant in UP
o Weak deposits / marine deposits / reclamation
o Design soil profile & parameters
o Selection of suitable foundation
o Fulfilling structural requirements
o Alternative foundation systems
Challenges
Low lateral capacity : < 2 T for BCIS Piles (desired > 7T)
Geotechnical Solutions
General Approach:
Shallow Foundations : for lightly loaded structures Pump House, Drive House, Cable
Gallery, Sub-Station etc.
Ground Improvement using Vibro Stone Columns (dry bottom feed method) was
suggested
To enhance Bearing Capacity > 10T/m2 for Open Foundations
0.5m dia. stone column grid was adopted for main works
Lateral Pile Load Test Results
Load in Tons
0 5 10 15 20 25
0
Settlement, mm
10
12
14
16
ITP-1
18
ITP-2
20
Alternative or approach that best fits the situation, employs resources in a most
effective and efficient manner, and yields the highest possible return under the
given circumstances.
Approaches
Land reclamation
Fill thickness 5m to 30m
Qc about 4 to 6 MPa
RD about 30% to 40%
Hull shop
Finished
product
delivery Automated
Automated
cutting and Steel Plate
assembly
forming Storage
Manual
assembly
Settlements
Steel Storage Area < 100mm
Other Areas < 50mm
Differential 1 in 1000
Legend
Existing Boreholes (56 nos)
Existing CPT
Additional Boreholes
Additional CPT (> 60 nos. more where you need them)
VC cranes
PVD rigs
Surcharge
Post CPT
Physics (NSF)
Cost
Time
Materials & Carbon Footprint
PVD Rigs
Project Background
Main Structures:
Sulphate of Potash (SOP)
Bromine Plant
Cogen Plant
Other Structures:
Storage Tanks
Workshops
Treatment Plants
Ancillary structures and other Amenities
Buildings and other Storage Areas
N = 40
Loading Conditions
-15.0
Foundation type : Piles for heavily loaded Structures
Hard Silty Clay
: Raft for light to medium loaded Structures
Pile Foundations
Sulphate of Potash (SOP)
Bromine Plant
Cogen Plant
Shallow Foundations on GI
Storage tanks
Workshop
Treatment Plant
Ancillary structures and amenities
Buildings and other storage areas
5
Settlement, mm
10
15
20
Project Background
Soil Data
Boreholes were explored to a depth of 20m to 25m below EGL
and Uniform Soil Conditions are found through out the site
Top 7.5m : Silty SAND, SPT N varies from 6 to 17
7.5m to 10.5m : Loose med. Sandy SILT, N 17 to 23
10m to 20m : Med. Dense Sandy SILT, N > 40
GWT was at 2m below EGL during investigation
Loading Conditions
Foundation type : Raft
Load vs Settlement
Load in 'Tons'
0 100 200 300 400
0
5
Settlement in 'mm'
10
15
20
25
30
35
40
Project Background
Soil Data
4 Boreholes were explored to a depth of 20m to 25m below EGL
and Uniform Soil Conditions through out the site
Top 6m : Silty sandy CLAY with 20 to 40% fines
Below 6m : Medium dense SAND up to 12m, followed firm to
stiff silty CLAY up to explored depth
GWT was at 3m below EGL during investigation (Sep 2012)
Loading Conditions
Foundation type : Raft
Monitoring of Settlements
To check post treatment performance of ground
Monitoring of Settlements
80
70
60
50
40
30
20
10
0
0
10
20
30
Settlement 'mm'
40
50
60
Completed Structure
Static Loads
Self weight of turbine : 150 T
Self weight of foundation: 300 T
Geotechnical Challenges
Site Layout
854
852
850
Elevation [m]
848
846
844
842
840
838
10
12
Rotational Stiffness
1. 2.
Typical Load Test Graph Determination of Es = Es, stat from the slope of
the curve till elastic limit.
G = Es/2(1+ )
.....DNV/RISO
2. These techniques can be used both for heavy, tall & settlement
sensitive structures and also for smaller simpler structures
Execution Challenges
1. Busy Traffic
2. Congested Roads and Limited Working Place
3. Limited working hours
4. Presence of Live Utilities
5. Weak soils up to 50m depth Pile Bore Stability
6. Large diameter piles (1.0m, 1.2m & 1.5m)
7. Pile lengths 40m to 56m
8. Maneuvering of heavy equipment in the limited working place
Water table 14 m
Stiff to Hard Clay
Vibrations or earthquake effects bulk, kN/m
g
3
18
Ave. N = 25
Height of unsupported face of the pile bore Ave. LL = 47
Ave. PI = 26
Poor knowledge on drilling fluid
Drilling fluid level inside the pile bore Weathered Rock Medium to Stiff clay
3
bulk, kN/m
g 2.0
Ave. N = >100
BH Termination level
42 m
Prior to
Frequency - After Mixing Once per shift
concreting
Bentonite
Earth
Bund
Introduction to Polymer
Advantages of Polymer over Bentonite
Operational convenience
Lesser plant
Lesser activities
Reduced time
Easy Disposal
Technical advantages
Environmental friendly
Note 2:
Set up the Silo, square tank and mixer based on standard layout. Always make provisions to
switch to Bentonite in case the soil report are inaccurate. There may be loose sand at depths
which is difficult to be sealed off by temporary casing. Always make provision to add desander.
Note 3:
FOR THE PURPOSE OF PREVENTING COLLAPSE , BENTONITE IS BETTER THAN
POLYMER.
Property to be Test and apparatus Fresh Polymer During Excavation Prior to Concreting
Measured
pH pH indicator 8 to 12 8 to 12 N.A
Summary
Design & Build Expertise will ensure savings in Cost & Time for the investor.
Also ensures, implementation of latest techniques in foundation construction.
Safety goal of zero accidents is possible with dedicated safety systems and
motivated leadership.
www.kellerindia.com