6. Select the
best solution
0. Identify an
opportunity 1. Set or 2. Identify 4. Analyze the
for clarify a goal problems problem
improvement
4.
Analyze
7. Implement the solution,
the
problem begin again
temporary
unique
specific inputs
a procedure for
a set of specific outputs.
outputs
Monitoring and
Initiating Planning Executing
Controlling Closing Processes
Processes Processes Processes
Processes
13.2 Plan Stakeholder Management 10.1 Plan Communications Management 4.5 Perform Integrated Change Control 9.1 Plan Human Resource Management
13.3 Manage Stakeholder Engagement 4.4 Monitor and Control Project Work 11.4 Perform Quantitative Risk Analysis 5.4 Create WBS 4.6 Close Project or Phase
7.1 Plan Cost Management 6.3 Sequence Activities 5.1 Plan Scope Management 7.3 Determine Budget
12.2 Conduct Procurements 6.6 Develop Schedule 9.2 Acquire Project Team 13.1 Identify Stakeholders
6.2 Define Activities 12.3 Control Procurements 5.2 Collect Requirements 9.3 Develop Project Team
4.1 Develop Project Charter 6.7 Control Schedule 6.1 Plan Schedule Management 8.3 Control Quality
8.2 Perform Quality Assurance 11.2 Identify Risks 6.5 Estimate Activity Durations 5.5 Validate Scope
11.1 Plan Risk Management 11.6 Control Risks 7.2 Estimate Costs 10.2 Manage Communications
12.4 Close Procurements 11.5 Plan Risk Responses 5.6 Control Scope 5.3 Define Scope 7.4 Control Costs
9.4 Manage Project Team 10.3 Control Communications 6.4 Estimate Activity Resources 8.1 Plan Quality Management 4.3 Direct and Manage Project Work
12.1 Plan Procurement Management 13.4 Control Stakeholder Engagement 11.3 Perform Qualitative Risk Analysis 4.2 Develop Project Management Plan
PMBOK, pg. 61
West Jordan
St. George
Perry
Murray
Logan
Sandy
Vernal
Scipio
Salt Lake
Heber
Question: It is in an organizations
best interest to
T/F implement any
element of lean it can.
http://www.isixsigma.com/dictionary/value-added/ (1/8/15)
More than half of construction waste comes from poor design and
control of processes.
Relatively small effort and investment would provide a large return.
Most construction waste comes from friction loss between trades and
departments.
Self interest often places trade/department above the combined
organization.
50% 61%
32% 29%
32%
13%
8% 7% 6% 5%
0%
Direct work Waiting Traveling Instructions Tools, material Early quits/late Personal breaks
transport starts
Work Activity
From Forbes and Ahmed, Modern Construction, pg. 41
1.Over production
Transporting parts or
2.Waiting material. Multiple moves
3.Transporting multiply the waste.
4.Overprocessing Example: The nature of
5.Unnecessary inventory construction: bring lots of
6.Unnecessary motions materials to one location.
7.Defects
1.Over production
Extra effort that adds no
2.Waiting value to the product or
3.Transporting service.
4.Overprocessing Example: Overly complicated
5.Unnecessary inventory bidding processes.
6.Unnecessary motions
7.Defects
Revenue
Risk (schedule, cost)
Responsibility (blame)
Expenses
Net Income
Spreads responsibilities and risks fairly and transparently
Based on trust and partnership
Requires integrity, character, trustworthiness, competence
Team interests > legal agreement
Shared values, common goals
Interdependence is acknowledged
Open sharing of knowledge and ideas is required
Creates a culture that spreads through company and industry
= Total Time Projected
%
12
= 16 days
75%
1. Over production
2. Waiting
3. Transporting
4. Overprocessing 8. Neglect safety
5. Inventory
6. Unnecessary motions
7. Defects
1. Over production
2. Waiting
3. Transporting
4. Overprocessing
5. Inventory
6. Unnecessary motions
7. Defects
8. Neglect safety
Forbes and Ahmed, pg. 26
The last planner is in the best position to match labor and material
resources to accomplish assignments in response to downstream
demand.
Work planning may establish time frames but is not very effective in
establishing that the tasks assigned are capable of completion
The LPS technique decentralizes decisions and empowers the crews
that are in direct contact with the work to plan and schedule detailed
tasks; in effect, they become the last planner.
Forbes and Ahmed
Nancy Tague, The Quality Toolbox
Nancy Tague, The Quality Toolbox, pg. 353
Grounded outlet/plug Polarized outlet/plug Mistake-enabling
adaptor
Mistake-enabling tool
Mistake-prone back
Correct Wrong Proposed
A designer knows he has achieved perfection
not when there is nothing left to add, but
when there is nothing left to take away.
Antoine de Saint-Exupery
Charles Mingus
Mistake-Proofing = Poka-Yoke (Baka-Yoke)
Rank Player FT%
1. Steve Nash .9043
2. Mark Price .9039
3. Rick Barry .8998
4. Peja Stojakovic .8948
The obvious: The only way to permanently
5. Chauncey Billups .8940
eliminate defects is to
6. Ray Allen .8939
permanently eliminate the
7. Calvin Murphy .8916
potential to produce defects.
8. Scott Skiles .8891
9. Reggie Miller .8877
10. Larry Bird .8857
This can be done in one of two ways: 11. Bill Sharman .8831
1. Change the design of the product. 12. Kevin Durant .8818
13. Dirk Nowitzki .8786
2. Change the design of the process. 14. Jeff Hornacek .8770
Behavioral
Technical Solutions
Solutions
Cannot Accept or Procedures
Cannot Make Cannot Cycle Training
Pass
Inspection /
Flawed action is testing
Flawed action is
Eliminate or redesign detected during Control non-
detected during
action during design transition from one conforming
process execution
process to the next product
Increasing Desirability
Nancy Tague, The Quality Toolbox, pg. 353
Action Type Description Category
1. Omission Something missing
Errors of
2. Too much Excess energy or movement
Amount
3. Too little Insufficient energy or movement
4. Unevenly applied Consistently wrong Errors of
5. Erratically applied Inconsistently wrong Variation
6. Too fast Insufficient time spent Errors of
7. Too slow Too much time spent Time
We have ever-expanding "to do"
lists, trying to build momentum by
doing, doing, doingand doing
1. Time more Those who built the good-
to-great companies made as much
use of "stop doing" lists as "to do"
lists. Jim Collins
2. Money
3. Commitment
= Choices
Flawed Action Type Apply Epoxy Example Category
1. Omitted Did not apply epoxy; did not test
Errors of
2. Too Much Epoxy too thick
Amount
3. Too Little Epoxy too thin
4. Unevenly Applied Routinely applied poorly near border of
FBE coating Errors of
Variation
5. Erratically Applied Imprecise mix of base/hardener
6. Too Fast Operator not being conscientious Errors of
7. Too Slow Apply too slowly: Inadequate cure Time
Barcode tracking Create epoxy Provide training Form specialized
of base/hardener kits, which from epoxy crews
batches include manufacturer
traceability of everything
potentially needed to coat
compromised one joint
product
July 28, 1935
First Test Flight
October 30, 1935
Crash
Working
west-to-east
Working
east-to-west
Pavement open
Fast
moving
Slow
going
Lean Construction Institute
leanconstruction.org