Anda di halaman 1dari 59

Chapter 12 - MRP and ERP

CHAPTER 12
MRP AND ERP

Solutions
1. a. Each E requires 2 F + 1 G + 1 H.
Each F requires 2 J + 4 D.
Each G requires 2 L + 2 J.
Each H requires 4 A + 2 D.
Total J required = (2 F * 2 J) + (1 G * 2 J) = 4 + 2 = 6.
Total D required = (2 F * 4 D) + (1 H * 2 D) = 8 + 2 = 10.
Total L required = 1 G * 2 L = 2.
Total A required = 1 H * 4 A = 4.

Total required of each:


F = 2, G = 1, H =1.
J = 6, D = 10, L = 2, A = 4.

b. Product structure tree (tree diagram) for stapler:

Stapler

Top Assembly Base Assembly

Cover Spring Slide Assembly Base Strike Pad Rubber Pad(2)

Slide Spring

12-1
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

2. Given:
We have the following information:

End Item

B(2) C D(3)

E(2) F(3) G(2) E(2) H(4) E(2)

Item End B C D E F G H
LT (wk) 1 2 3 3 1 2 1 2
Amount 0 10 10 25 12 30 5 0
on hand

a. If 20 units of the end item are to be assembled, how many additional units of E are
needed?
Step 1:
Determine the gross requirements and the net requirements for the End Item:

Item Gross Requirements On Hand = Net Requirements


End Item 20 0 = 20

Step 2:
Determine the gross requirements and the net requirements for B, C, & D.
Multiply the net requirements for the end item by the usage quantities of B, C, & D to
determine the gross requirements for B, C, & D.

Item Gross Requirements On Hand = Net Requirements


B (20 * 2) = 40 10 = 30
C (20 * 1) = 20 10 = 10
D (20 * 3) = 60 25 = 35

Step 3:
Determine the gross requirements and net requirements for E.
Multiply the net requirements for B, C, & D by the usage quantities of E to determine gross
requirements for E.

Item Gross Requirements On Hand = Net Requirements


E [(30 B * 2) + (10 C * 2) + (35 D * 2)] = 150 12 = 138

12-2
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

b. Given:
An order for the end item is to be shipped at the start of week 11. Determine the latest week
that the order could be started.

To solve this, we need to determine the longest sequence through the product structure tree
moving from the end item down to the lowest items. The lead time for each item is indicated
in bold to the left of each item in the product structure tree shown below.
1 wk End Item

2 wk B(2) 3 wk C 3 wk D(3)

1 wk E(2) 2 wk F(3) 1 wk G(2) 1 wk E(2) 2 wk H(4) 1 wk E(2)


1 wk 1 wk 1 wk 1 wk 1 wk
Total LT = 4 wk 5 wk 5 wk 5 wk 6 wk 5 wk

The longest sequence is 6 weeks (End Item D H). 11 6 weeks = start of week 5.

3. Given:
We have the following information:

Item End L C K B J G H
LT (wk) 1 2 3 3 2 3 3 2
Amount 0 10 15 20 30 30 5 0
on hand

Item Direct Components


End L(2), C(1), K(3)
L B(2), J(3)
C G(2), B(2)
K H(4), B(2)

Using the information above, we can construct a product structure tree as shown below:

End Item

L(2) C K(3)

B(2) J(3) G(2) B(2) H(4) B(2)

12-3
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

a. If 40 units of the end item are to be assembled, how many additional units of B are needed?
Step 1:
Determine the gross requirements and the net requirements for the end item:

Item Gross Requirements On Hand = Net Requirements


End Item 40 0 = 40

Step 2:
Determine the gross requirements and the net requirements for L, C, & K.
Multiply the net requirements for the end item by the usage quantities of L, C, & K to
determine the gross requirements for L, C, & K.

Item Gross Requirements On Hand = Net Requirements


L (40 * 2) = 80 10 = 70
C (40 * 1) = 40 15 = 25
K (40 * 3) = 120 20 = 100

Step 3:
Determine the gross requirements and net requirements for B.
Multiply the net requirements for L, C, & K by the usage quantities of B to determine gross
requirements for B.

Item Gross Requirements On Hand = Net Requirements


B [(70 L * 2) + (25 C * 2) + (100 K * 2)] = 390 30 = 360

b. Given:
An order for the end item is to be shipped at the start of week 8. Determine the latest week
that the order could be started.

To solve this, we need to determine the longest sequence through the product structure tree
moving from the end item down to the lowest items. The lead time for each item is indicated
in bold to the left of each item in the product structure tree shown below.

1 wk End Item

2 wk L(2) 3 wk C 3 wk K(3)

2 wk B(2) 3 wk J(3) 3 wk G(2) 2 wk B(2) 2 wk H(4) 2 wk B(2)

Total LT = 5 wk 6 wk 7 wk 6 wk 6 wk 6 wk

The longest sequence is 7 weeks (End Item C G). 8 7 weeks = start of week 1.
12-4
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

4. Given:
Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case)
of J have been ordered, and one case is scheduled to arrive in week 3, one in week 4, and one in
week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units.
There are 60 units of B and 20 units of J on hand. Lead times are 2 weeks each for E and B, and 1
week for J. The product structure tree is shown below:
E

B(2) J(3)

J(4) F(2)

a. Determine a material requirements plan for J. We will need to prepare material plans for E, B,
and J. All given information is highlighted in bold in the tables below.

POH is the projected on hand inventory at the beginning of each period.


All MRP problems below will use the following formula to determine POH:
POH (Current Period) = [POH + Planned-Order Receipts Gross Requirements (Prior
Period)] + Scheduled Receipts (Current Period) or using subscripts, we have the following:

POHt = [POHt-1 + Planned-Order Receiptst-1 Gross Requirementst-1] + Scheduled Receiptst

Net Requirements = Max[(Gross Requirements POH), 0].


Note: This ensures that we have net requirements only when the Gross Requirements > POH.

Master Week 1 2 3 4 5 6
Schedule for:
E Quantity 80

E LT = 2 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 80
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0
Net requirements 80
Planned-order receipts 80
Planned-order releases 80

12-5
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

B(2) LT = 2 Beg.
1 2 3 4 5 6
Lot size: Multiples of 120 Inv.
Gross requirements 160
Scheduled receipts
Projected on hand 60 60 60 60 60 20 20
Net requirements 100
Planned-order receipts 120
Planned-order releases 120
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 80 E * 2 = 160.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [60 + 0 0] + 0 = 60.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [60 + 120 160] + 0 = 20.

J(3) & J(4) LT = 1 Beg.


1 2 3 4 5 6
Lot size: Multiples of 30 Inv.
Gross requirements 480 240
Scheduled receipts 30 30 30
Projected on hand 20 20 20 50 80 50 50
Net requirements 460 160
Planned-order receipts 480 180
Planned-order releases 480 180
Notes:
Gross Requirements (week 2) = Planned-Order Releases of 120 B * 4 = 480.
Gross Requirements (week 4) = Planned-Order Releases of 80 E * 3 = 240.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3.
POH3 = [20 + 480 480] + 30 = 50.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4.
POH4 = [50 + 0 0] + 30 = 80.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5.
POH5 = [80 + 180 240] + 30 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6.
POH6 = [50 + 0 0] + 0 = 50.
Planned-Order Receipts (week 2) = 16 * 30 = 480 (must order in cases of 30).
Planned-Order Receipts (week 4) = 6 * 30 = 180 (must order in cases of 30).

12-6
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

b. Suppose that in week 4 the quantity of E needed is changed from 80 to 70 units. The
planned-order releases through week 3 have all been executed. How many more Bs and
Js will be on hand in week 6? Note: We are now at the start of week 4.

Step 1:
Before we do the MRP processing, we list what changes have occurred:
1. All Planned-Order Releases in weeks 1 3 have been executed.
B had Planned-Order Releases in week 2 (120) corresponding to Planned-Order
Receipts (120) in week 4. Change the Planned-Order Receipts to Scheduled Receipts
in week 4.
J had Planned-Order Releases in week 1 (480) corresponding to Planned-Order
Receipts (480) in week 2. The Planned-Order Receipts would have been changed to
Scheduled Receipts and received in week 2 (this increases inventory).
J had Planned-Order Releases in week 3 (180) corresponding to Planned-Order
Receipts (180) in week 4. These will show up as Scheduled Receipts in week 4 and
will be added to the original amount of Scheduled Receipts (30) in week 4.
2. Scheduled Receipts for J in week 3 (30) would have been received (this increases
inventory).
3. Gross requirements for all items in weeks 1 3 would have been disbursed (these
transactions decrease inventory).

Step 2:
Determine the ending inventory for each item at the end of week 3. These will become
the beginning inventory balances in week 4.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements

Item E Week 1 Week 2 Week 3


Ending Inventory 0+00=0 0+00=0 0+00=0

Item B Week 1 Week 2 Week 3


Ending Inventory 60 + 0 0 = 60 60 + 0 0 = 60 60 + 0 0 = 60

Item J Week 1 Week 2 Week 3


Ending Inventory 20 + 0 0 = 20 20 + 480 480 = 20 20 + 30 0 = 50

12-7
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Step 3:
Fill in all beginning inventory balances and scheduled receipts, and then change E to 70
units in week 6 of the master schedule. Our MRP tables are shown for weeks 4 6 only.

Master Week 4 5 6
Schedule for:
E Quantity 70

E LT = 2 Beg.
4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 70
Scheduled receipts
Projected on hand 0 0 0 0
Net requirements 70
Planned-order receipts 70
Planned-order releases 70

B(2) LT = 2 Beg.
4 5 6
Lot size: Multiples of 120 Inv.
Gross requirements 140
Scheduled receipts 120
Projected on hand 60 180 40 40
Net requirements
Planned-order receipts
Planned-order releases
Notes:
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled
Receipts4.
POH4 = [60 + 0 0] + 120 = 180.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled
Receipts5.
POH5 = [180 + 0 140] + 0 = 40.

12-8
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

J(4) & J(3) LT = 1 Beg.


4 5 6
Lot size: Multiples of 30 Inv.
Gross requirements 210
Scheduled receipts 210 30
Projected on hand 50 260 80 80
Net requirements
Planned-order receipts
Planned-order releases
Notes:
Scheduled Receipts (week 4) = Original amount of 30 + 180 = 210.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled
Receipts4.
POH4 = [50 + 0 0] + 210 = 260.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled
Receipts5.
POH5 = [260 + 0 210] + 30 = 80.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled
Receipts6.
POH6 = [80 + 0 0] + 0 = 80.
Original on hand amounts (week 6): B = 20 & J = 50.
Revised on hand amounts (week 6): B = 40 & J = 80.
There will be an additional 20 units of B & 30 units of J on hand.

12-9
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

5. a. Given:
120 units of end item Z are needed at the beginning of week 7. On hand balances: Z = 40, A
70, B = 100, and C = 30 units. There is a scheduled receipt of 20 units of C in week 4. Lead
times are 2 weeks for Z and B, and 1 week for other items. Lot-for-lot ordering is used for all
items. The product structure tree is shown below:
Z

A(2) B(4)

C(3) D(2) E(2) C(2)

Prepare a material requirements plan for component C:


We will need to prepare material plans for Z, A, B, and C.

Master Week 1 2 3 4 5 6 7
Schedule for:
Z Quantity 120

Z LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 120
Scheduled receipts
Projected on hand 40 40 40 40 40 40 40 40
Net requirements 80
Planned-order receipts 80
Planned-order releases 80
Notes:
POH7 = [POH6 + Planned-Order Receipts6 Gross Requirements6] + Scheduled Receipts7
POH7 = [40 + 0 0] + 0 = 40.

A(2) LT = 1 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 160
Scheduled receipts
Projected on hand 70 70 70 70 70 70 0 0
Net requirements 90
Planned-order receipts 90
Planned-order releases 90
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 Z * 2 = 160.

12-10
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

B(4) LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 320
Scheduled receipts
Projected on hand 100 100 100 100 100 100 0 0
Net requirements 220
Planned-order receipts 220
Planned-order releases 220
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 Z * 4 = 320.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [100 + 220 320] + 0 = 0.

C(3) & C(2) LT = 1 Beg.


1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 440 270
Scheduled receipts 20
Projected on hand 30 30 30 30 20 0 0 0
Net requirements 410 250
Planned-order receipts 410 250
Planned-order releases 410 250
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 220 B * 2 = 440.
Gross Requirements (week 4) = Planned-Order Releases of 90 A * 3 = 270.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [30 + 410 440] + 20 = 20.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [20 + 250 270] + 0 = 0.

12-11
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

b. Given:
95 units of end item E are needed at the beginning of week 7. On hand balances: E = 5, B =
50, C = 100, and D = 80 units. There is a scheduled receipt of 30 units of C in week 4. Lead
times are 2 weeks for E and C, and 1 week for other items. Assume lot-for-lot ordering except
for D, where multiples of 40 must be used. The product structure tree is shown below:
E

B(3) C(2)

D(2) I(2) S(2) D(2)

Prepare a material requirements plan for component D:


We will need to prepare material plans for E, B, C, and D.

Master Week 1 2 3 4 5 6 7
Schedule for:
E Quantity 95

E LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 95
Scheduled receipts
Projected on hand 5 5 5 5 5 5 5 5
Net requirements 90
Planned-order receipts 90
Planned-order releases 90

B(3) LT = 1 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 270
Scheduled receipts
Projected on hand 50 50 50 50 50 50 0 0
Net requirements 220
Planned-order receipts 220
Planned-order releases 220
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 90 E * 3 = 270.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 220 270] + 0 = 0.

12-12
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

C(2) LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 180
Scheduled receipts 30
Projected on hand 100 100 100 100 130 130 0 0
Net requirements 50
Planned-order receipts 50
Planned-order releases 50
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 90 E * 2 = 180.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 0 0] + 30 = 130.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [130 + 0 0] + 0 = 130.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [130 + 50 180] + 0 = 0

D(2) & D(2) LT = 1 Beg.


1 2 3 4 5 6 7
Lot size: Multiples of 40 Inv.
Gross requirements 100 440
Scheduled receipts
Projected on hand 80 80 80 80 20 20 20 20
Net requirements 20 420
Planned-order receipts 40 440
Planned-order releases 40 440
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 50 C * 2 = 100.
Gross Requirements (week 4) = Planned-Order Releases of 220 B * 2 = 440.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [80 + 40 100] + 0 = 20.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [20 + 440 440] + 0 = 20.
Planned-Order Receipts (week 3) = 1 * 40 = 40 (multiples of 40 must be used).
Planned-Order Receipts (week 4) = 11 * 40 = 440 (multiples of 40 must be used).

12-13
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

6. Given:
The company that makes a table wants to ship 100 units at the beginning of day 4, 150 units at the
beginning of day 5, and 200 units at the beginning of day 7. Receipts of 100 wood sections are
scheduled at the beginning of day 2. On hand balances: Braces = 60 and Legs = 120. Lead times
(in days) for all items are shown in the table below. The product structure tree is shown below
also:

Quantity Lead Time


1-200 1
201-550 2
551-999 3

Table

Wood Sections(2) Braces(3) Legs(4)

Prepare a material requirements plan using lot-for-lot ordering for all items:

Master Day 1 2 3 4 5 6 7
Schedule for:
Table Quantity 100 150 200

Table Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 100 150 200
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0
Net requirements 100 150 200
Planned-order receipts 100 150 200
Planned-order releases 100 150 200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 100 100] + 0 = 0.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [0 + 150 150] + 0 = 0.
Planned-Order Releases (days 3, 4, & 6) were back-scheduled 1 day from their Planned-Order
Receipts because all lead times = 1 day for quantities of 1-200.

12-14
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Wood Sections(2) Beg. 1 2 3 4 5 6 7


Lot size: Lot-for-Lot Inv.
Gross requirements 200 300 400
Scheduled receipts 100
Projected on hand 0 0 100 100 0 0 0 0
Net requirements 100 300 400
Planned-order receipts 100 300 400
Planned-order releases 400 400
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 2 = 200.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 2 = 300.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 2 = 400.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [100 + 0 0] + 0 = 100.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 100 200] + 0 = 0.
Planned-Order Releases (day 2) = 100 from Planned-Order Receipts of 100 in day 3 (lead time = 1
day for quantities of 1-200) + 300 from Planned-Order Receipts of 300 in day 4 (lead time = 2 days
for quantities of 201-550) = 400.
Planned-Order Releases (day 4) = 400 from Planned-Order Receipts of 400 in day 6 (lead time = 2
days for quantities of 201-550).

Braces(3) Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 300 450 600
Scheduled receipts
Projected on hand 60 60 60 60 0 0 0 0
Net requirements 240 450 600
Planned-order receipts 240 450 600
Planned-order releases 240 450 600
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 3 = 300.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 3 = 450.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 3 = 600.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [60 + 240 300] + 0 = 0.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 450 450] + 0 = 0.
Planned-Order Releases (day 1) = 240 from Planned-Order Receipts of 240 in day 3 (lead time = 2
days for quantities of 201-550).
Planned-Order Releases (day 2) = 450 from Planned-Order Receipts of 450 in day 4 (lead time = 2
days for quantities of 201-550).
Planned-Order Releases (day 3) = 600 from Planned-Order Receipts of 600 in day 6 (lead time = 3
days for quantities of 551-999).

12-15
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Legs(4) Beg. 1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 400 600 800
Scheduled receipts
Projected on hand 120 120 120 120 0 0 0 0
Net requirements 280 600 800
Planned-order receipts 280 600 800
Planned-order releases 880 800
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 4 = 400.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 4 = 600.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 4 = 800.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [120 + 0 0] + 0 = 120.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [120 + 280 400] + 0 = 0.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 600 600] + 0 = 0.
Planned-Order Releases (day 1) = 280 from Planned-Order Receipts of 280 in day 3 (lead time = 2
days for quantities of 201-550) + 600 from Planned-Order Receipts of 600 in day 4 (lead time = 3
days for quantities of 551-999) = 880.
Planned-Order Releases (day 3) = 800 from Planned-Order Receipts of 800 in day 6 (lead time = 3
days for quantities of 551-999).

12-16
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

7. Given:
80 units of end item X are needed at the beginning of week 6, and another 30 units are needed at
the beginning of week 8. D can be ordered only in whole cases (50 units per case). One case of D
(50 units) is received automatically every other week, beginning in week 1. On hand balances: B
= 30 and D = 20 units. Lead times are a function of quantity as shown in the table below. The
product structure tree is shown below also:

Quantity Lead Time


1-100 1 wk
101-200 2 wk
201-300 3 wk
301+ 4 wk

B(2) D(3)

D(2) F(2)

Prepare a material requirements plan for component D using lot-for-lot ordering for all items
except D. We will need to prepare material plans for X, B, and D.

Master Week 1 2 3 4 5 6 7 8
Schedule for: X Quantity 80 30

X Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 80 30
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 80 30
Planned-order receipts 80 30
Planned-order releases 80 30
Notes:
Planned-Order Releases (week 5 and week 7) have a lead time of 1 week (lead time = 1 week for
quantities of 1-100).

12-17
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

B(2) Beg. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 160 60
Scheduled receipts
Projected on hand 30 30 30 30 30 30 0 0 0
Net requirements 130 60
Planned-order receipts 130 60
Planned-order releases 130 60
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 X * 2 = 160.
Gross Requirements (week 7) = Planned-Order Releases of 30 X * 2 = 60.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [30 +130 160] + 0 = 0.
Planned-Order Releases (week 3) = 130 from Planned-Order Receipts of 130 in week 5 (lead time = 2
weeks for quantities of 101-200).
Planned-Order Releases (week 6) = 60 from Planned-Order Receipts of 60 in week 7 (lead time = 1
week for quantities of 1-100).

D(2) & D(3) Beg.


1 2 3 4 5 6 7 8
Lot size: Multiples of 50 Inv.
Gross requirements 260 240 120 90
Scheduled receipts 50 50 50 50
Projected on hand 20 70 70 120 10 60 20 50 10
Net requirements 140 180 100 40
Planned-order receipts 150 200 100 50
Planned-order releases 150 200 100 50
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 130 B * 2 = 260.
Gross Requirements (week 5) = Planned-Order Releases of 80 X * 3 = 240.
Gross Requirements (week 6) = Planned-Order Releases of 60 B * 2 = 120.
Gross Requirements (week 7) = Planned-Order Releases of 30 X * 3 = 90.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [70 + 0 0] + 50 = 120.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [120 + 150 260] + 0 = 10.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [60 + 200 240] + 0 = 20.
POH7 = [POH6 + Planned-Order Receipts6 Gross Requirements6] + Scheduled Receipts7
POH7 = [20 + 100 120] + 50 = 50.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [50 + 50 90] + 0 = 10.

12-18
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

8. Given:
Oh No! Inc. sells three models: A, B, and C. Lead times are 1 week for all items except C (2
weeks). On hand balances: B = 10, C = 10, and D = 25 units. Lot-sizing rules are lot-for-lot for all
items except D, which must be ordered in multiples of 100. There is a scheduled receipt of 100
units of D in week 1. The master schedule shows that 40 units of A are needed at the beginning of
week 4, 60 units of B at the beginning of week 5, and 30 units of C at the beginning of week 6.
The product structure tree for each item is shown below:

A B C

D E D(2) F D(4) G

Prepare a material requirements plan for component D and its parents. We will need to prepare
material plans for A, B, C, and D.

Master Week 1 2 3 4 5 6
Schedule for: A Quantity 40

A LT = 1 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 40
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0
Net requirements 40
Planned-order receipts 40
Planned-order releases 40

Master Week 1 2 3 4 5 6
Schedule for: B Quantity 60

B LT = 1 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 60
Scheduled receipts
Projected on hand 10 10 10 10 10 10 0
Net requirements 50
Planned-order receipts 50
Planned-order releases 50

12-19
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Master Week 1 2 3 4 5 6
Schedule for: C Quantity 30

C LT = 2 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 30
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10
Net requirements 20
Planned-order receipts 20
Planned-order releases 20

D, D(2), & D(4) LT = 1 Beg.


1 2 3 4 5 6
Lot size: Multiples of 100 Inv.
Gross requirements 40 180
Scheduled receipts 100
Projected on hand 25 125 125 125 85 5 5
Net requirements 95
Planned-order receipts 100
Planned-order releases 100
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 40 A * 1 = 40.
Gross Requirements (week 4) = (Planned-Order Releases of 50 B * 2) + (Planned-Order
Releases of 20 C * 4) = 100 + 80 = 180.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [125 + 0 40] + 0 = 85.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [85 + 100 180] + 0 = 5.
Planned-Order Receipts (week 5) = 1 * 100 = 100 (must order in multiples of 100).

12-20
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

9. Given:
50 chain saws are needed at the start of week 8. The inventory information (shown in bold) and
the product structure tree are listed below in the problem solution:

a. Product tree structure:


Saw

A(2) B C(4)

E(3) D D(2) F(3) E(2) D(2)

Assembly time chart: D


A
E
F
B
Saw
D
D
C
E

1 2 3 4 5 6 7 8
week

Start of week 2 Start of week 8

Master schedule:
Master Week 1 2 3 4 5 6 7 8
Schedule for:
Saw Quantity 50

b. Material requirements plan for E using lot-for-lot ordering for all items. We will need to
prepare material plans for Saw, A, C, and E.
Master Week 1 2 3 4 5 6 7 8
Schedule for:
Saw Quantity 50

Saw LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 50
Scheduled receipts
Projected on hand 15 15 15 15 15 15 15 15 15
Net requirements 35
Planned-order receipts 35
Planned-order releases 35

12-21
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

A(2) LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 70
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10 0 0
Net requirements 60
Planned-order receipts 60
Planned-order releases 60
Notes:
Gross Requirements (week 6) = Planned-Order Releases of 35 Saws * 2 = 70.

C(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 140
Scheduled receipts
Projected on hand 65 65 65 65 65 65 65 0 0
Net requirements 75
Planned-order receipts 75
Planned-order releases 75
Notes:
Gross Requirements (week 6) = Planned-Order Releases of 35 Saws * 4 = 140.

E(3) & E(2) LT = 1 Beg.


1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 150 180
Scheduled receipts
Projected on hand 10 10 10 10 10 0 0 0 0
Net requirements 140 180
Planned-order receipts 140 180
Planned-order releases 140 180
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 75 C * 2 = 150.
Gross Requirements (week 5) = Planned-Order Releases of 60 A * 3 = 180.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 0 0] + 0 = 10.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [10 + 140 150] + 0 = 0.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [0 + 180 180] + 0 = 0.

12-22
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

10. Given:
40 units of an industrial robot are needed at the beginning of week 7. Subassembly G must be
ordered in multiples of 80 and all other components are ordered lot-for-lot. The inventory
information (shown in bold) and the product structure tree are listed below in the problem
solution. Prepare the material plan for G. We will need to prepare material plans for Robot, C, &
G.
Robot

B C(3)

E F G G(2) H

Master Week 1 2 3 4 5 6 7
Schedule for:
Robot Quantity 40

Robot LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 40
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10 10
Net requirements 30
Planned-order receipts 30
Planned-order releases 30

C(3) LT = 1 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 90
Scheduled receipts
Projected on hand 20 20 20 20 20 20 0 0
Net requirements 70
Planned-order receipts 70
Planned-order releases 70
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 30 Robots * 3 = 90.

12-23
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

G & G(2) LT = 2 Beg.


1 2 3 4 5 6 7
Lot size: Multiples of 80 Inv.
Gross requirements 140 30
Scheduled receipts
Projected on hand 15 15 15 15 15 35 5 5
Net requirements 125
Planned-order receipts 160
Planned-order releases 160
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 70 C * 2 = 140.
Gross Requirements (week 5) = Planned-Order Releases of 30 Robots * 1 = 30.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [15 + 0 0] + 0 = 15.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [15 + 160 140] + 0 = 35.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [35 + 0 30] + 0 = 5.

11. a. Given:
Refer back to Solved Problem 3. On hand balances: N = 100 and E = 0. Scheduled receipts: I
= 40 and V = 10 at the beginning of week 3. 120 E are needed at the start of week 5. We have
the product structure tree shown below. Determine material requirements plans for E, I, N,
and V using lot-for-lot ordering as was used in Solved Problem 3:
E

M(3) I(2)

R(2) P N(4) V

Master Period 1 2 3 4 5 6 7 8
Schedule for:
E Quantity 120

E LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 120
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 120
Planned-order receipts 120
Planned-order releases 120

12-24
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

I(2) LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 240
Scheduled receipts 40
Projected on hand 0 0 0 40 40 0 0 0 0
Net requirements 200
Planned-order receipts 200
Planned-order releases 200
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 120 E * 2 = 240.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 200 240] + 0 = 0.

N(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 800
Scheduled receipts
Projected on hand 100 100 100 100 0 0 0 0 0
Net requirements 700
Planned order receipts 700
Planned order releases 700
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 200 I * 4 = 800.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 700 800] + 0 = 0.

V LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200
Scheduled receipts 10
Projected on hand 0 0 0 10 0 0 0 0 0
Net requirements 190
Planned order receipts 190
Planned order releases 190
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 200 I * 1 = 200.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 10 = 10.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 190 200] + 0 = 0.

12-25
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

b. Given:
Assume that on hand balances and scheduled receipts remain the same as in part a. On hand
balances: N = 100 and E = 0. Scheduled receipts: I = 40 and V = 10 at the beginning of week
3.
New information: 100 E are needed at the start of week 5 and 55 are needed at the start of
week 7. Determine the material requirements plans for E, I, N, and V using lot-for-lot
ordering for E and I, and multiples of these order sizes: N = 800 and V = 200.
E

M(3) I(2)

R(2) P N(4) V

Master Period 1 2 3 4 5 6 7 8
Schedule for:
E Quantity 100 55

E LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 100 55
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 100 55
Planned-order receipts 100 55
Planned-order releases 100 55

I(2) LT = 1 Beg. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200 110
Scheduled receipts 40
Projected on hand 0 0 0 40 40 0 0 0 0
Net requirements 160 110
Planned-order receipts 160 110
Planned-order releases 160 110
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 100 E * 2 = 200.
Gross Requirements (week 6) = Planned-Order Releases of 55 E * 2 = 110.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 160 200] + 0 = 0.

12-26
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

N(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 800 Inv.
Gross requirements 640 440
Scheduled receipts
Projected on hand 100 100 100 100 260 260 620 620 620
Net requirements 540 180
Planned order receipts 800 800
Planned order releases 800 800
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 4 = 640.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 4 = 440.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 800 640] + 0 = 260.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [260 + 800 440] + 0 = 620.

V LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 200 Inv.
Gross requirements 160 110
Scheduled receipts 10
Projected on hand 0 0 0 10 50 50 140 140 140
Net requirements 150 60
Planned order receipts 200 200
Planned order releases 200 200
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 1 = 160.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 1 = 110.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 10 = 10.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 200 160] + 0 = 50.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 0 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 200 110] + 0 = 140.

12-27
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

c. Case 1 Given:
Refer back to part b. 1 week has elapsed. It is now the start of week 2. 100 E are needed at
the start of week 9. Assume that all orders were released and received as planned.

Notes:
a. We will drop 1 week (week 1) from the material plans and add 1 week at the end of each
plan.

b. Any Planned-Order Releases from week 1 must now show up as Scheduled Receipts:
Item N: Change Planned-Order Receipts of 800 in week 3 to Scheduled Receipts in week 3.
Item V: Change Planned-Order Receipts of 200 in week 3 to Scheduled Receipts in week 3.
The revised amount of Scheduled Receipts (week 3) = original amount of 10 + 200 = 210.

c. Determine the on hand balances at the start of week 2:

Determine the ending inventory for each item at the end of week 1. These will become the
beginning inventory balances in week 2.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements

Item E Week 1
Ending Inventory 0+00=0

Item I Week 1
Ending Inventory 0+00=0

Item N Week 1
Ending Inventory 100 + 0 0 = 100

Item V Week 1
Ending Inventory 0+00=0

M(3) I(2)

R(2) P N(4) V

12-28
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

c. continued
Master Period 2 3 4 5 6 7 8 9
Schedule for:
E Quantity 100 55 100

E LT = 1 Beg.
2 3 4 5 6 7 8 9
Lot size: Lot-for-Lot Inv.
Gross requirements 100 55 100
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 100 55 100
Planned-order receipts 100 55 100
Planned-order releases 100 55 100

I(2) LT = 1 Beg.
2 3 4 5 6 7 8 9
Lot size: Lot-for-Lot Inv.
Gross requirements 200 110 200
Scheduled receipts 40
Projected on hand 0 0 40 40 0 0 0 0 0
Net requirements 160 110 200
Planned-order receipts 160 110 200
Planned-order releases 160 110 200
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 100 E * 2 = 200.
Gross Requirements (week 6) = Planned-Order Releases of 55 E * 2 = 110.
Gross Requirements (week 8) = Planned-Order Releases of 100 E * 2 = 200.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 160 200] + 0 = 0.
POH9 = [POH8 + Planned-Order Receipts8 Gross Requirements8] + Scheduled Receipts9
POH9 = [0 + 200 200] + 0 = 0.

12-29
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

N(4) LT = 2 Beg.
2 3 4 5 6 7 8 9
Lot size: Multiples of 800 Inv.
Gross requirements 640 440 800
Scheduled receipts 800
Projected on hand 100 100 900 260 260 620 620 620 620
Net requirements 180 180
Planned order receipts 800 800
Planned order releases 800 800
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 4 = 640.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 4 = 440.
Gross Requirements (week 7) = Planned-Order Releases of 200 I * 4 = 800.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [100 + 0 0] + 800 = 900.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [900 + 0 640] + 0 = 260.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [260 + 800 440] + 0 = 620.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [620 + 800 800] + 0 = 620.

V LT = 2 Beg.
2 3 4 5 6 7 8 9
Lot size: Multiples of 200 Inv.
Gross requirements 160 110 200
Scheduled receipts 210
Projected on hand 0 0 210 50 50 140 140 140 140
Net requirements 60 60
Planned order receipts 200 200
Planned order releases 200 200
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 1 = 160.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 1 = 110.
Gross Requirements (week 7) = Planned-Order Releases of 200 I * 1 = 200.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 210 = 210.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [210 + 0 160] + 0 = 50.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 0 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 200 110] + 0 = 140.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [140 + 200 200] + 0 = 140.

12-30
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Case 2 Given:
Refer back to the previous update. It is now the start of week 4. Assume that all orders were
released and received as planned in weeks 2 and 3.

Notes:
a. We will drop 2 weeks (weeks 2 & 3) from the material plans and add 2 weeks at the end of
each plan.

b. Any Planned-Order Releases from weeks 2 & 3 must now show up as Scheduled Receipts:
Item I: Change Planned-Order Receipts of 160 in week 4 to Scheduled Receipts in week 4.
Item N: Change Planned-Order Receipts of 800 in week 5 to Scheduled Receipts in week 5.
Item V: Change Planned-Order Receipts of 200 in week 5 to Scheduled Receipts in week 5.

c. Determine the on hand balances at the start of week 4:

Determine the ending inventory for each item at the end of week 3. These will become the
beginning inventory balances in week 4.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements

Item E Week 2 Week 3


Ending Inventory 0+00=0 0+00=0

Item I Week 2 Week 3


Ending Inventory 0+00=0 0 + 40 0 = 40

Item N Week 2 Week 3


Ending Inventory 100 + 0 0 = 100 100 + 800 640 = 260

Item V Week 2 Week 3


Ending Inventory 0+00=0 0 + 210 160 = 50

M(3) I(2)

R(2) P N(4) V

12-31
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Master Period 4 5 6 7 8 9 10 11
Schedule for:
E Quantity 100 55 100

E LT = 1 Beg.
4 5 6 7 8 9 10 11
Lot size: Lot-for-Lot Inv.
Gross requirements 100 55 100
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 100 55 100
Planned-order receipts 100 55 100
Planned-order releases 100 55 100

I(2) LT = 1 Beg.
4 5 6 7 8 9 10 11
Lot size: Lot-for-Lot Inv.
Gross requirements 200 110 200
Scheduled receipts 160
Projected on hand 40 200 0 0 0 0 0 0 0
Net requirements 110 200
Planned-order receipts 110 200
Planned-order releases 110 200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [200 + 0 200] + 0 = 0.

12-32
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

N(4) LT = 2 Beg.
4 5 6 7 8 9 10 11
Lot size: Multiples of 800 Inv.
Gross requirements 440 800
Scheduled receipts 800
Projected on hand 260 260 1060 620 620 620 620 620 620
Net requirements 180
Planned order receipts 800
Planned order releases 800
Notes:
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [1060 + 0 440] + 0 = 620.

V LT = 2 Beg.
4 5 6 7 8 9 10 11
Lot size: Multiples of 200 Inv.
Gross requirements 110 200
Scheduled receipts 200
Projected on hand 50 50 250 140 140 140 140 140 140
Net requirements 60
Planned order receipts 200
Planned order releases 200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 200 = 250.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [250 + 0 110] + 0 = 140.

12-33
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

12. Given:
200 carts must be ready at the beginning of week 8. The product structure tree, assembly time
chart, and inventory information are shown in the solutions below:

a. Product structure tree:

Golf
Cart

Top Base

Supports(4) Cover Motor Body Seats(2)

Frame Controls Wheels(4)

Assembly Time Chart


Supports
Top
b.
Cover

Cart

Motor
Frame
Controls Body Base
Wheels
Seats

2 3 4 5 6 7
week

Start of week 2 Start of week 8

12-34
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

c. Develop a material requirements plan that will provide 200 golf carts by week 8 assuming
lot-for-lot ordering.

Master Week 1 2 3 4 5 6 7 8
Schedule for:
Golf Cart Quantity 200

Golf Cart LT = 1 Beg.


1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 200
Planned-order receipts 200
Planned-order releases 200

Top LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200
Scheduled receipts
Projected on hand 40 40 40 40 40 40 40 40 0
Net requirements 160
Planned-order receipts 160
Planned-order releases 160
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.

Supports(4) LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 640
Scheduled receipts
Projected on hand 200 200 200 200 200 200 200 0 0
Net requirements 440
Planned-order receipts 440
Planned-order releases 440
Notes: Gross Requirements (week 6) = Planned-Order Releases of 160 Tops * 4 = 640.

12-35
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

12. c. (continued)

Cover LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 160
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 160
Planned-order receipts 160
Planned-order releases 160
Notes: Gross Requirements (week 6) = Planned-Order Releases of 160 Tops * 1 = 160.

Base LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200
Scheduled receipts
Projected on hand 20 20 20 20 20 20 20 20 0
Net requirements 180
Planned-order receipts 180
Planned-order releases 180
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.

Motor LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 180
Scheduled receipts
Projected on hand 300 300 300 300 300 300 300 120 120
Net requirements
Planned-order receipts
Planned-order releases
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.

12-36
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

12. c. (Continued)

Body LT = 3 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 180
Scheduled receipts
Projected on hand 50 50 50 50 50 50 50 0 0
Net requirements 130
Planned-order receipts 130
Planned-order releases 130
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.

Seats(2) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 360
Scheduled receipts
Projected on hand 120 120 120 120 120 120 120 0 0
Net requirements 240
Planned-order receipts 240
Planned-order releases 240
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 2 = 360.

Frame LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 130
Scheduled receipts
Projected on hand 35 35 35 35 0 0 0 0 0
Net requirements 95
Planned-order receipts 95
Planned-order releases 95
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.

12-37
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

12. c. (Continued)

Controls LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 130
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 130
Planned-order receipts 130
Planned-order releases 130
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.

Wheel Assemblies(4) LT = 1 Beg.


1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 520
Scheduled receipts
Projected on hand 240 240 240 240 0 0 0 0 0
Net requirements 280
Planned-order receipts 280
Planned-order releases 280
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 4 = 520.

12-38
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

13. Given:
Refer back to Problem 12. The revised plan calls for 100 golf carts to be available at the start of
week 6, 100 at the start of week 8, and 100 at the start of week 9.

a. Develop a master schedule for this revised plan.

Master Week 1 2 3 4 5 6 7 8 9
Schedule for:
Golf Carts Quantity 100 100 100

b. Determine the timing and quantities for orders for tops and bases.

Golf Cart LT = 1 Beg.


1 2 3 4 5 6 7 8 9
Lot size: Lot-for-Lot Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0 0
Net requirements 100 100 100
Planned-order receipts 100 100 100
Planned-order releases 100 100 100

Top LT = 1 Beg.
Lot size: Lot-for-Lot Inv. 1 2 3 4 5 6 7 8 9

Gross requirements Inv. 100 100 100


Scheduled receipts
Projected on hand 40 40 40 40 40 40 0 0 0 0
Net requirements 60 100 100
Planned-order receipts 60 100 100
Planned-order releases 60 100 100

Base LT = 1 Beg.
Lot size: Lot-for-Lot 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 20 20 20 20 20 20 0 0 0 0
Net requirements 80 100 100
Planned-order receipts 80 100 100
Planned-order releases 80 100 100

12-39
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

c. The firms capacity limits the assembly of bases to 50 units per week. Revise the plan, but
still meet delivery dates. Note: We should try to minimize inventory also.
The key will be to move Planned-Order Receipts and Planned-Order Releases earlier in the
plan.
Consider the plan for Bases in b above:
Planned Order-Receipts (week 8) = 100
Planned Order-Receipts (week 7) = 100
Planned Order-Receipts (week 5) = 80
Given the capacity limit of 50 per week, we could divide the Planned-Order Receipts as
follows:
Week 8 (100): Week 7 (50) & Week 8 (50)
Week 7 (100): Week 5 (50) & Week 6 (50)
Week 5 (80): Week 3 (30) & Week 4 (50)
Note: Because some of these Planned-Order Receipts need to be planned earlier than they
should be, the planner will have to lock in the timing and quantity of these Planned-Order
Receipts by designating them as Firm Planned Orders so that the MRP system does not re-
schedule them automatically.

Master Week 1 2 3 4 5 6 7 8 9
Schedule for:
Golf Carts Quantity 100 100 100

Golf Cart LT = 1 Beg.


1 2 3 4 5 6 7 8 9
Lot size: Lot-for-Lot Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0 0
Net requirements 100 100 100
Planned-order receipts 100 100 100
Planned-order releases 100 100 100

Base LT = 1 Beg.
Lot size: Lot-for-Lot 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 20 20 20 20 50 100 50 100 50 0
Net requirements
Planned-order receipts 30 50 50 50 50 50
Planned-order releases 30 50 50 50 50 50

12-40
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

14. Given:
a. Draw a product structure tree (tree diagram) for the scissors. Lead times are 1 day for each
component and final scissor assembly, but 2 days for the plastic grips. 600 scissors are
needed on Day 6. On hand inventory: Straight blades = 200, bent blades = 350, and top blade
assembly = 40.

Scissors

Bottom Blade Assembly Screw Top Blade Assembly

Straight Blade Straight Plastic Grip Bent Blade Bent Plastic Grip

b. Material plans:

Master Beg.
Week 1 2 3 4 5 6 7 8
Schedule for: Inv.
Scissors Quantity 600

Scissors LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 600
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 600
Planned-order receipts 600
Planned-order releases 600

Bottom Blade Assembly Beg.


LT = 1 Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot
Gross requirements 600
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 600
Planned-order receipts 600
Planned-order releases 600
Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.

12-41
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Top Blade Assembly Beg.


LT = 1 Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot
Gross requirements 600
Scheduled receipts
Projected on hand 40 40 40 40 40 40 0 0 0
Net requirements 560
Planned-order receipts 560
Planned-order releases 560
Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.

Screw LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 600
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 600
Planned-order receipts 600
Planned-order releases 600
Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.

Straight Blade LT = 1 Beg.


1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 600
Scheduled receipts
Projected on hand 200 200 200 200 200 0 0 0 0
Net requirements 400
Planned-order receipts 400
Planned-order releases 400
Notes: Gross Requirements (week 4) = Planned-Order Releases of 600 Bottom Blade Assembly * 1 =
600.

12-42
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Straight Plastic Grip Beg.


LT = 2 Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot
Gross requirements 600
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 600
Planned-order receipts 600
Planned-order releases 600
Notes: Gross Requirements (week 4) = Planned-Order Releases of 600 Bottom Blade Assembly * 1 =
600.

Bent Blade LT = 1 Beg.


1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 560
Scheduled receipts
Projected on hand 350 350 350 350 350 0 0 0 0
Net requirements 210
Planned-order receipts 210
Planned-order releases 210
Notes: Gross Requirements (week 4) = Planned-Order Releases of 560 Top Blade Assembly * 1 = 560.

Bent Plastic Grip LT = 2 Beg.


1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 560
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 560
Planned-order receipts 560
Planned-order releases 560
Notes: Gross Requirements (week 4) = Planned-Order Releases of 560 Top Blade Assembly * 1 = 560.

12-43
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

15. Given:
A company has the following demand for its products, labor and machine standards, and available
capacities:

Week number 1 2 3 4
Material (tons) 40 80 60 70

Labor Machine
Production standard 4 3
(hours per ton)
Weekly production 300 200
capacity (hours)

a. Determine capacity utilization for labor and machine for each of the four weeks:
Capacity Requirements (Load) =
Units * Standard Labor and/or Machine Requirements per Unit

Labor and Machine Capacity Requirements (Load)


Week number 1 2 3 4
Material (tons) 40 80 60 70
Labor standard 4 4 4 4
Labor
requirements 40 * 4 = 160 80 * 4 = 320 60 * 4 = 240 70 * 4 = 280
(load)
Machine standard 3 3 3 3
Machine
requirements 40 * 3 = 120 80 * 3 = 240 60 * 3 = 180 70 * 3 = 210
(load)

Capacity Utilization (round % to two decimals)


Week number 1 2 3 4
Labor 160 320 240 280
requirements
Labor capacity 300 300 300 300
Labor 160/300 * 100 = 320/300 * 100 = 240/300 * 100 = 280/300 * 100 =
utilization 53.33% 106.67% 80.00% 93.33%
Machine 120 240 180 210
requirements
Machine capacity 200 200 200 200
Machine 120/200 * 100 = 240/200 * 100 = 180/200 * 100 = 210/200 * 100 =
utilization 60.00% 120.00% 90.00% 105.00%

b. Capacity utilization exceeds 100% for both labor and machine in week 2, and for machine in
week 4.
Production could be shifted to earlier or later weeks in which capacity is underutilized.
Shifting to an earlier week would result in added carrying costs; shifting to later weeks would
mean backorder costs.

Another option could be to work overtime. Labor cost would increase due to overtime
premium, a probable decrease in productivity, and a possible increase in accidents.

12-44
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

16. Given:
A company produces 2 products that go through a 3-day sequence of fabrication, assembly, and
packaging. Each step requires 1 day for a lot to be processed and moved to the next department.
Processing requirements for the departments (hours per unit) are:

FABRICATION ASSEMBLY PACKAGING


Product Labor Machine Labor Machine Labor Machine
A 2 1 1.5 1 1 .5
B 1 1 1 1 1.5 .5

Department capacities are all 700 hours of labor and 500 hours of machine time, except Friday,
when capacities are 200 hours for both labor and machine time. The following production
schedule is for next week:

Product Mon Tue Wed Thu Fri


A 200 400 100 300 100
B 300 200 200 200 200

a. Determine the labor and machine capacity requirements for each product and the total load at
each department for each day.

For example, the 200 units of Product A & 300 units of Product B will be processed at
Fabrication on Monday, Assembly on Tuesday, and Packaging on Wednesday.

Monday Fabrication Labor Load = (200 A * 2 = 400) + (300 B * 1 = 300) = 700.


Monday Fabrication Machine Load = (200 A * 1 = 200) + (300 B * 1 = 300) = 500.

Tuesday Assembly Labor Load = (200 A * 1.5 = 300) + (300 B * 1 = 300) = 600.
Tuesday Assembly Machine Load = (200 A * 1 = 200) + (300 B * 1 = 300) = 500.

Wednesday Packaging Labor Load = (200 A * 1 = 200) + (300 B * 1.5 = 450) = 650.
Wednesday Packaging Machine Load = (200 A * .5 = 100) + (300 B * .5 = 150) = 250.

12-45
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Fabrication Assembly Packaging


Day Product Labor Machine Labor Machine Labor Machine

Mon A 400 200


B 300 300
Load 700 500
Capacity 700 500

Tue A 800 400 300 200


B 200 200 300 300
Load 1000 600 600 500
Capacity 700 500 700 500

Wed A 200 100 600 400 200 100


B 200 200 200 200 450 150
Load 400 300 800 600 650 250
Capacity 700 500 700 500 700 500

Thu A 600 300 150 100 400 200


B 200 200 200 200 300 100
Load 800 500 350 300 700 300
Capacity 700 500 700 500 700 500

Fri A 200 100 450 300 100 50


B 200 200 200 200 300 100
Load 400 300 650 500 400 150
Capacity 200 200 200 200 200 200

b. Evaluate the loading for the first 3 days of the week:

Monday:
Fabrication: Load = capacity for both labor and machine.
Tuesday:
Fabrication: Labor load is over capacity by 300 hours. Machine load is over capacity by 100
hours.
Assembly: Labor load is under capacity by 100 hours. Machine load = capacity.
Wednesday:
Fabrication: Labor load is under capacity by 300 hours. Machine load is under capacity by
200 hours.
Assembly: Labor load is over capacity by 100 hours. Machine load is over capacity by 100
hours.
Packaging: Labor load is under capacity by 50 hours. Machine load is under capacity by 250
hours.

The schedule does not appear to be feasible. Fabrication is overloaded for labor and machine
on Tuesday and underloaded for labor and machine on Wednesday. In addition, Assembly is
overloaded for labor and machine on Wednesday.
One solution could be to shift some of the 400 A & 200 B scheduled in Fabrication on
Tuesday to Wednesday. For example, we could shift 150 A in Fabrication from Tuesday to
12-46
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Wednesday. We now would schedule 250 A on Tuesday (400-150) and 250 A on Wednesday
(100+150). The new load values are highlighted in bold in the table below:

Fabrication Assembly Packaging


Day Product Labor Machine Labor Machine Labor Machine

Mon A 400 200


B 300 300
Load 700 500
Capacity 700 500

Tue A 500 250 300 200


B 200 200 300 300
Load 700 450 600 500
Capacity 700 500 700 500

Wed A 500 250 375 250 200 100


B 200 200 200 200 450 150
Load 700 450 575 450 650 250
Capacity 700 500 700 500 700 500

Thu A 600 300 375 250 250 125


B 200 200 200 200 300 100
Load 800 500 575 450 550 225
Capacity 700 500 700 500 700 500

Fri A 200 100 450 300 250 125


B 200 200 200 200 300 100
Load 400 300 650 500 550 225
Capacity 200 200 200 200 200 200

12-47
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

17. Given:
The MRP departments computer died just as it spit out the following information: Planned-Order
Releases for Item J27 = 640 units in week 2. We have the following product structure tree and
inventory information shown below:

565

X43 Y36(2) N78

J27(4) X43

Part Number On Hand Lot Size Lead Time


565 0 Lot-for-lot 1 week
X43 60 Multiples 1 week
of 120
N78 0 Lot-for-lot 2 weeks
Y36 200 Lot-for-lot 1 week
J27 0 Lot-for-lot 2 weeks

Step 1:
Look at which items are linked together by the Planned-Order Releases for J27: J27, Y36, and
565.

Step 2:
Work from the bottom to the top of the product structure tree. Start with J27 to determine its
Planned-Order Receipts, Net Requirements, and Gross Requirements.

a. We know that J27 has a Planned-Order Release = 640 in week 2.


The lead time for J27 = 2 weeks. This means that the Planned-Order Receipts = 640 in week
4 (2 weeks later).
The lot size for J27 = lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 4 = 640.
The on hand balance for J27 = 0. This means that the Gross Requirements in week 4 = Net
Requirements + On Hand = 640 + 0 = 640.

b. If the Gross Requirements for J27 = 640 in week 4, then the Planned-Order Releases for Y36
= 160 (640 / 4) in week 4.
The lead time for Y36 = 1 week. This means that the Planned-Order Receipts = 160 in week
5 (1 week later).
The lot size for Y36 is lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 5 = 160.
The on hand balance for Y36 = 200. This means that the Gross Requirements in week 5 = Net
Requirements + On Hand = 160 + 200 = 360.

12-48
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

c. If the Gross Requirements for Y36 = 360 in week 5, the Planned-Order Releases for 565 =
180 (360 / 2) in week 5.
The lead time for 565 = 1 week. This means that the Planned-Order Receipts = 180 in week 6
(1 week later).
The lot size for 565 is lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 6 = 180.
The on hand balance for 565 = 0. This means that the Gross Requirements in week 6 = Net
Requirements + On Hand = 180 + 0 = 180.
Conclusion: There should be a quantity of 180 listed in week 6 of the master schedule for
Item 565.
Below are the MRP tables verifying the proof discussed above:

Master Week 1 2 3 4 5 6 7 8
Schedule for:
565 Quantity 180

565 LT = 1 Beg.
Lot size: Lot-for-Lot Inv. 1 2 3 4 5 6 7 8

Gross requirements 180


Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 180
Planned-order receipts 180
Planned-order releases 180

Y36(2) LT = 1 Beg.
Lot size: Lot-for-Lot 1 2 3 4 5 6 7 8
Inv.
Gross requirements 360
Scheduled receipts
Projected on hand 200 200 200 200 200 200 0 0 0
Net requirements 160
Planned-order receipts 160
Planned-order releases 160

J27(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 640
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 640
Planned-order receipts 640
Planned-order releases 640

12-49
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

18. Given:
Develop a material requirements plan for component H. Use lot-for-lot ordering for all items.
Lead times for the end item and each component (except B) = 1 week. The lead time for B = 3
weeks. On hand balances: B = 15 & E = 130. Scheduled Receipts for H = 50 in week 2. 60 units
of A are needed at the start of week 8. We have the following product structure tree:

B(2) C

D(2) E(2) D(2) E(4)

H(3) K H(3) K

We will need material plans for A, B, C, E, & H.

Master Week 1 2 3 4 5 6 7 8
Schedule Quantity
60
for: A

A LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.

Gross requirements 60
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 60
Planned-order receipts 60
Planned-order releases 60

12-50
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

B(2) LT = 3
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.

Gross requirements 120


Scheduled receipts
Projected on hand 15 15 15 15 15 15 15 15 0
Net requirements 105
Planned-order receipts 105
Planned-order releases 105

C LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.

Gross requirements 60
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 60
Planned-order receipts 60
Planned-order releases 60

E(2) & E(4) LT = 1


Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.

Gross requirements 210 240


Scheduled receipts
Projected on hand 130 130 130 130 130 0 0 0 0
Net requirements 80 240
Planned-order receipts 80 240
Planned-order releases 80 240
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 105 B * 2 = 210.
Gross Requirements (week 6) = Planned-Order Releases of 60 C * 4 = 240.

12-51
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

H(3) LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.

Gross requirements 240 720


Scheduled receipts 50
Projected on hand 0 0 50 50 0 0 0 0 0
Net requirements 190 720
Planned-order receipts 190 720
Planned-order releases 190 720
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 80 E * 3 = 240.
Gross Requirements (week 5) = Planned-Order Releases of 240 E * 3 = 720.

Case: Promotional Novelties


Given:
Promotional Novelties has received an order for 20,000 toy Tractor-Trailers to be ready at the beginning
of week 8. The company can complete final assembly of the Tractor-Trailers at a rate of 10,000 a week.
Tractors and Trailers are purchased and have a lead time = 3 weeks. The company has sufficient supply of
Brackets on hand. Assembly time = 1 week for Tractors, Trailers, and Wheel Assembly. However, the
Wheel Department can assemble a maximum of 100,000 Wheels a week. The manager plans to use the
Wheel Department to full capacity, starting in week 2 of the schedule, and order additional Wheels from a
supplier as needed. Wheels are ordered in sets (multiples) of 6,400, and the lead time from the supplier =
2 to 3 weeks. All items use lot-for-lot ordering except for the purchased Wheels (lot size = multiples of
6,400).

Comments on the product structure tree shown in the text:


The Wheel Assembly of the Tractor differs from the Wheel Assembly of the Trailer.
The Body of the Tractor differs from the Body of the Trailer.
The Tractor and the Trailer use the same Wheel.

We will develop material plans for Tractor-Trailer, Tractor, Trailer, Tractor Wheel Assembly, Trailer
Wheel Assembly, & Wheels.

If the order of 20,000 tractor-trailers is due at the start of week 8 and final assembly is limited to 10,000
per week, then we must list 10,000 in week 7 and 10,000 in week 8 of the master schedule.

12-52
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Master Week 1 2 3 4 5 6 7 8
Schedule Quantity 10,000 10,000

Tractor-Trailer
LT = 1 Beg.
1 2 3 4 5 6 7 8
Inv.
Lot size: Lot-for-Lot

Gross requirements 10,000 10,000

Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0

Net requirements 10,000 10,000

Planned-order receipts 10,000 10,000

Planned-order releases 10,000 10,000

Tractor LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.

Gross requirements 10,000 10,000

Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0

Net requirements 10,000 10,000

Planned-order receipts 10,000 10,000

Planned-order releases 10,000 10,000

Trailer LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.

Gross requirements 10,000 10,000

Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0

Net requirements 10,000 10,000

Planned-order receipts 10,000 10,000

Planned-order releases 10,000 10,000

12-53
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Tractor Wheel
Assembly LT = 1 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot

Gross requirements 10,000 10,000

Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0

Net requirements 10,000 10,000

Planned-order receipts 10,000 10,000

Planned-order releases 10,000 10,000

Trailer Wheel
Assembly LT = 1 Beg.
1 2 3 4 5 6 7 8
Inv.
Lot size: Lot-for-Lot

Gross requirements 10,000 10,000

Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0

Net requirements 10,000 10,000

Planned-order receipts 10,000 10,000

Planned-order releases 10,000 10,000

12-54
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Wheels (6) & (12)


LT = 1 Beg.
1 2 3 4 5 6 7 8
Inv.
Lot size: Lot-for-Lot

Gross requirements 180,000 180,000

Scheduled receipts
Projected on hand 0 0 0 0 100,000 20,000 4,000 4,000 4,000

Net requirements 80,000 160,000

Planned-order receipts 100,000


100,000 100,000
64,000*

Planned-order releases 100,000


100,000 100,000
64,000*
Notes:
Gross Requirements (week 4) = Planned-Order Releases of (10,000 Tractor Wheel Assembly * 6) +
(10,000 Trailer Wheel Assembly * 12) = 60,000 + 120,000 = 180,000.
Gross Requirements (week 5) = Planned-Order Releases of (10,000 Tractor Wheel Assembly * 6) +
(10,000 Trailer Wheel Assembly * 12) = 60,000 + 120,000 = 180,000.
The Planned-Order Receipts in weeks 3, 4, & 5 would be entered as Firm Planned Orders locked in by the
MRP planner so that the MRP system does not re-schedule these amounts automatically.
Planned-Order Releases (week 2) = [Planned-Order Receipts (week 3) of 100,000] + [Planned-Order
Receipts (week 5) of 64,000] = 100,000 + 64,000 = 164,000.

1. The company will need a total of 360,000 Wheels. It will be able to produce only 300,000 during
weeks 2, 3, & 4. The company will need to order at least 60,000 Wheels as indicated with the * in
week 2. The company actually would have to purchase 10 sets of 6,400 Wheels per set = 64,000.

2. The company will need the Wheels in week 5. If lead time will be 2-3 weeks, then assume that it
will be 3 weeks, and order the Wheels from the supplier in week 2.

12-55
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Case: DMD Enterprises


Given:
Marty wants to assemble 15 Arrows and 10 Darts each week to have them ready at the start of weeks 4
through 8. The product structure trees are given in the text along with inventory information on lead
times, on hand amounts, and lot sizing rules. Scheduled Receipts: Arrows = 20 in week 1 & W = 18 in
week 1. Darts = 20 in week 2 & F = 15 in week 2. Develop the material plans for all items.

Master Week 1 2 3 4 5 6 7 8
Schedule for:
Arrows Quantity 15 15 15 15 15

Master Week 1 2 3 4 5 6 7 8
Schedule for:
Darts Quantity 10 10 10 10 10

Arrows LT = 2 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot
Gross requirements 15 15 15 15 15
Scheduled receipts 20
Projected on hand 5 25 25 25 25 10 0 0 0
Net requirements 5 15 15 15
Planned-order receipts 5 15 15 15
Planned-order releases 5 15 15 15

Darts LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 10 10 10 10 10
Scheduled receipts 20
Projected on hand 2 2 22 22 22 12 2 0 0
Net requirements 8 10 10
Planned-order receipts 8 10 10
Planned-order releases 8 10 10

X LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 25 Inv.
Gross requirements 5 15 15 15
Scheduled receipts
Projected on hand 5 5 5 5 0 10 20 5 5
Net requirements 15 5
Planned-order receipts 25 25
Planned-order releases 25 25

12-56
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Case: DMD Enterprises (continued)


M LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-lot Inv.
Gross requirements 5 15 15 15
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 5 15 15 15
Planned-order receipts 5 15 15 15
Planned-order releases 5 15 15 15

K(2) LT = 1 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-lot
Gross requirements 16 20 20
Scheduled receipts
Projected on hand 3 3 3 3 3 0 0 0 0
Net requirements 13 20 20
Planned-order receipts 13 20 20
Planned-order releases 13 20 20
Gross Requirements (week 4) = Planned-Order Releases of 8 Darts * 2 = 16.
Gross Requirements (week 5) = Planned-Order Releases of 10 Darts * 2 = 20.
Gross Requirements (week 6) = Planned-Order Releases of 10 Darts * 2 = 20.

F&F LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 30 Inv.
Gross requirements 25 33 10 10
Scheduled receipts 15
Projected on hand 10 10 25 25 0 27 17 7 7
Net requirements 33 0 0
Planned-order receipts 60
Planned-order releases 60
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 25 X * 1 = 25.
Gross Requirements (week 4) = Planned-Order Releases of (8 Darts * 1) + (25 X * 1) = 8 + 25 = 33.
Gross Requirements (week 5) = Planned-Order Releases of 10 Darts * 1 = 10.
Gross Requirements (week 6) = Planned-Order Releases of 10 Darts * 1 = 10.

12-57
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

W & W(2) LT* = 2 or 3 Beg.


1 2 3 4 5 6 7 8
Lot size: Multiples of 12 Inv.
Gross requirements 31 55 55 15
Scheduled receipts 18
Projected on hand 2 20 20 20 1 6 11 8 8
Net requirements 11 54 49 4
Planned-order receipts 12 60 60 12
Planned-order releases 72 60 12
Notes:
Gross Requirements (week 3) = Planned-Order Releases of (5 Arrows *1) + (13 K * 2) = 5 + 26 =
31.
Gross Requirements (week 4) = Planned-Order Releases of (15 Arrows * 1) + (20 K * 2) = 15 + 40
= 55.
Gross Requirements (week 5) = Planned-Order Releases of (15 Arrows * 1) + (20 K * 2) = 15 + 40
= 55.
Gross Requirements (week 6) = Planned-Order Releases of 15 Arrows * 1 = 15.
*Lead time = 2 weeks for orders < 36 & 3 weeks for orders 36.
Planned-Order Releases (week 1) = [Planned-Order Receipts (week 3) = 12] + [Planned-Order
Receipts (week 4) = 60] = 72.

Q LT = 1 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Multiples of 30
Gross requirements 13 20 20
Scheduled receipts
Projected on hand 15 15 15 15 2 12 22 22 22
Net requirements 18 8
Planned-order receipts 30 30
Planned-order releases 30 30
Gross Requirements (week 3) = Planned-Order Releases of 13 K * 1 = 13.
Gross Requirements (week 4) = Planned-Order Releases of 20 K * 1 = 20.
Gross Requirements (week 5) = Planned-Order Releases of 20 K * 1 = 20.

12-58
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP

Operations Tour: Stickley Furniture


1. Batch processing is used with typical lot sizes of 25 to 60 pieces of different types of furniture,
such as tables, chairs, desks, dressers, etc. Repetitive processing is used at sawing, drilling,
finishing, etc. Job shop processing is used for expensive one-of-a-kind special orders that may be
received.
2. Each job is accompanied by a set of bar codes that identifies the job and the operation. As each
operation is completed, the operator removes a bar code sticker and delivers it to the scheduling
office, where it is scanned into a computer, thereby enabling production control to keep track of
progress on a job, and to know its location in the shop.
3. The information needed to plan, schedule, and process the order for 40 mission oak dining room
sets includes:
a. Number of finished units presently in inventory
b. Type of wood
c. Type of furniture
d. Style of furniture
e. Number of finished products needed
f. List of component parts for each finished product
g. Operations required for each component part
h. Inventory for each component part
i. Sequence of operations for each component
j. Sequence of operations for each finished product
k. Orders already in progress or scheduled to precede this order
l. Unutilized equipment and labor
m. Processing times for each component and total processing time for the finished product
4. One benefit would be the stability and improved morale brought about by maintaining a constant
size workforce. A problem could be the buildup of inventories during certain quarters of the year.
5. Because there is a dependent demand situation for all of the components that go into the finished
products, the installation of an MRP system might be of great help to this company in meeting its
delivery dates and in keeping inventory costs down.

12-59
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Anda mungkin juga menyukai