CHAPTER 12
MRP AND ERP
Solutions
1. a. Each E requires 2 F + 1 G + 1 H.
Each F requires 2 J + 4 D.
Each G requires 2 L + 2 J.
Each H requires 4 A + 2 D.
Total J required = (2 F * 2 J) + (1 G * 2 J) = 4 + 2 = 6.
Total D required = (2 F * 4 D) + (1 H * 2 D) = 8 + 2 = 10.
Total L required = 1 G * 2 L = 2.
Total A required = 1 H * 4 A = 4.
Stapler
Slide Spring
12-1
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
2. Given:
We have the following information:
End Item
B(2) C D(3)
Item End B C D E F G H
LT (wk) 1 2 3 3 1 2 1 2
Amount 0 10 10 25 12 30 5 0
on hand
a. If 20 units of the end item are to be assembled, how many additional units of E are
needed?
Step 1:
Determine the gross requirements and the net requirements for the End Item:
Step 2:
Determine the gross requirements and the net requirements for B, C, & D.
Multiply the net requirements for the end item by the usage quantities of B, C, & D to
determine the gross requirements for B, C, & D.
Step 3:
Determine the gross requirements and net requirements for E.
Multiply the net requirements for B, C, & D by the usage quantities of E to determine gross
requirements for E.
12-2
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
b. Given:
An order for the end item is to be shipped at the start of week 11. Determine the latest week
that the order could be started.
To solve this, we need to determine the longest sequence through the product structure tree
moving from the end item down to the lowest items. The lead time for each item is indicated
in bold to the left of each item in the product structure tree shown below.
1 wk End Item
2 wk B(2) 3 wk C 3 wk D(3)
The longest sequence is 6 weeks (End Item D H). 11 6 weeks = start of week 5.
3. Given:
We have the following information:
Item End L C K B J G H
LT (wk) 1 2 3 3 2 3 3 2
Amount 0 10 15 20 30 30 5 0
on hand
Using the information above, we can construct a product structure tree as shown below:
End Item
L(2) C K(3)
12-3
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
a. If 40 units of the end item are to be assembled, how many additional units of B are needed?
Step 1:
Determine the gross requirements and the net requirements for the end item:
Step 2:
Determine the gross requirements and the net requirements for L, C, & K.
Multiply the net requirements for the end item by the usage quantities of L, C, & K to
determine the gross requirements for L, C, & K.
Step 3:
Determine the gross requirements and net requirements for B.
Multiply the net requirements for L, C, & K by the usage quantities of B to determine gross
requirements for B.
b. Given:
An order for the end item is to be shipped at the start of week 8. Determine the latest week
that the order could be started.
To solve this, we need to determine the longest sequence through the product structure tree
moving from the end item down to the lowest items. The lead time for each item is indicated
in bold to the left of each item in the product structure tree shown below.
1 wk End Item
2 wk L(2) 3 wk C 3 wk K(3)
Total LT = 5 wk 6 wk 7 wk 6 wk 6 wk 6 wk
The longest sequence is 7 weeks (End Item C G). 8 7 weeks = start of week 1.
12-4
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
4. Given:
Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case)
of J have been ordered, and one case is scheduled to arrive in week 3, one in week 4, and one in
week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units.
There are 60 units of B and 20 units of J on hand. Lead times are 2 weeks each for E and B, and 1
week for J. The product structure tree is shown below:
E
B(2) J(3)
J(4) F(2)
a. Determine a material requirements plan for J. We will need to prepare material plans for E, B,
and J. All given information is highlighted in bold in the tables below.
Master Week 1 2 3 4 5 6
Schedule for:
E Quantity 80
E LT = 2 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 80
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0
Net requirements 80
Planned-order receipts 80
Planned-order releases 80
12-5
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
B(2) LT = 2 Beg.
1 2 3 4 5 6
Lot size: Multiples of 120 Inv.
Gross requirements 160
Scheduled receipts
Projected on hand 60 60 60 60 60 20 20
Net requirements 100
Planned-order receipts 120
Planned-order releases 120
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 80 E * 2 = 160.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [60 + 0 0] + 0 = 60.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [60 + 120 160] + 0 = 20.
12-6
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
b. Suppose that in week 4 the quantity of E needed is changed from 80 to 70 units. The
planned-order releases through week 3 have all been executed. How many more Bs and
Js will be on hand in week 6? Note: We are now at the start of week 4.
Step 1:
Before we do the MRP processing, we list what changes have occurred:
1. All Planned-Order Releases in weeks 1 3 have been executed.
B had Planned-Order Releases in week 2 (120) corresponding to Planned-Order
Receipts (120) in week 4. Change the Planned-Order Receipts to Scheduled Receipts
in week 4.
J had Planned-Order Releases in week 1 (480) corresponding to Planned-Order
Receipts (480) in week 2. The Planned-Order Receipts would have been changed to
Scheduled Receipts and received in week 2 (this increases inventory).
J had Planned-Order Releases in week 3 (180) corresponding to Planned-Order
Receipts (180) in week 4. These will show up as Scheduled Receipts in week 4 and
will be added to the original amount of Scheduled Receipts (30) in week 4.
2. Scheduled Receipts for J in week 3 (30) would have been received (this increases
inventory).
3. Gross requirements for all items in weeks 1 3 would have been disbursed (these
transactions decrease inventory).
Step 2:
Determine the ending inventory for each item at the end of week 3. These will become
the beginning inventory balances in week 4.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements
12-7
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Step 3:
Fill in all beginning inventory balances and scheduled receipts, and then change E to 70
units in week 6 of the master schedule. Our MRP tables are shown for weeks 4 6 only.
Master Week 4 5 6
Schedule for:
E Quantity 70
E LT = 2 Beg.
4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 70
Scheduled receipts
Projected on hand 0 0 0 0
Net requirements 70
Planned-order receipts 70
Planned-order releases 70
B(2) LT = 2 Beg.
4 5 6
Lot size: Multiples of 120 Inv.
Gross requirements 140
Scheduled receipts 120
Projected on hand 60 180 40 40
Net requirements
Planned-order receipts
Planned-order releases
Notes:
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled
Receipts4.
POH4 = [60 + 0 0] + 120 = 180.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled
Receipts5.
POH5 = [180 + 0 140] + 0 = 40.
12-8
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
12-9
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
5. a. Given:
120 units of end item Z are needed at the beginning of week 7. On hand balances: Z = 40, A
70, B = 100, and C = 30 units. There is a scheduled receipt of 20 units of C in week 4. Lead
times are 2 weeks for Z and B, and 1 week for other items. Lot-for-lot ordering is used for all
items. The product structure tree is shown below:
Z
A(2) B(4)
Master Week 1 2 3 4 5 6 7
Schedule for:
Z Quantity 120
Z LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 120
Scheduled receipts
Projected on hand 40 40 40 40 40 40 40 40
Net requirements 80
Planned-order receipts 80
Planned-order releases 80
Notes:
POH7 = [POH6 + Planned-Order Receipts6 Gross Requirements6] + Scheduled Receipts7
POH7 = [40 + 0 0] + 0 = 40.
A(2) LT = 1 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 160
Scheduled receipts
Projected on hand 70 70 70 70 70 70 0 0
Net requirements 90
Planned-order receipts 90
Planned-order releases 90
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 Z * 2 = 160.
12-10
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
B(4) LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 320
Scheduled receipts
Projected on hand 100 100 100 100 100 100 0 0
Net requirements 220
Planned-order receipts 220
Planned-order releases 220
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 Z * 4 = 320.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [100 + 220 320] + 0 = 0.
12-11
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
b. Given:
95 units of end item E are needed at the beginning of week 7. On hand balances: E = 5, B =
50, C = 100, and D = 80 units. There is a scheduled receipt of 30 units of C in week 4. Lead
times are 2 weeks for E and C, and 1 week for other items. Assume lot-for-lot ordering except
for D, where multiples of 40 must be used. The product structure tree is shown below:
E
B(3) C(2)
Master Week 1 2 3 4 5 6 7
Schedule for:
E Quantity 95
E LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 95
Scheduled receipts
Projected on hand 5 5 5 5 5 5 5 5
Net requirements 90
Planned-order receipts 90
Planned-order releases 90
B(3) LT = 1 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 270
Scheduled receipts
Projected on hand 50 50 50 50 50 50 0 0
Net requirements 220
Planned-order receipts 220
Planned-order releases 220
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 90 E * 3 = 270.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 220 270] + 0 = 0.
12-12
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
C(2) LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 180
Scheduled receipts 30
Projected on hand 100 100 100 100 130 130 0 0
Net requirements 50
Planned-order receipts 50
Planned-order releases 50
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 90 E * 2 = 180.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 0 0] + 30 = 130.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [130 + 0 0] + 0 = 130.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [130 + 50 180] + 0 = 0
12-13
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
6. Given:
The company that makes a table wants to ship 100 units at the beginning of day 4, 150 units at the
beginning of day 5, and 200 units at the beginning of day 7. Receipts of 100 wood sections are
scheduled at the beginning of day 2. On hand balances: Braces = 60 and Legs = 120. Lead times
(in days) for all items are shown in the table below. The product structure tree is shown below
also:
Table
Prepare a material requirements plan using lot-for-lot ordering for all items:
Master Day 1 2 3 4 5 6 7
Schedule for:
Table Quantity 100 150 200
Table Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 100 150 200
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0
Net requirements 100 150 200
Planned-order receipts 100 150 200
Planned-order releases 100 150 200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 100 100] + 0 = 0.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [0 + 150 150] + 0 = 0.
Planned-Order Releases (days 3, 4, & 6) were back-scheduled 1 day from their Planned-Order
Receipts because all lead times = 1 day for quantities of 1-200.
12-14
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Braces(3) Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 300 450 600
Scheduled receipts
Projected on hand 60 60 60 60 0 0 0 0
Net requirements 240 450 600
Planned-order receipts 240 450 600
Planned-order releases 240 450 600
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 3 = 300.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 3 = 450.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 3 = 600.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [60 + 240 300] + 0 = 0.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 450 450] + 0 = 0.
Planned-Order Releases (day 1) = 240 from Planned-Order Receipts of 240 in day 3 (lead time = 2
days for quantities of 201-550).
Planned-Order Releases (day 2) = 450 from Planned-Order Receipts of 450 in day 4 (lead time = 2
days for quantities of 201-550).
Planned-Order Releases (day 3) = 600 from Planned-Order Receipts of 600 in day 6 (lead time = 3
days for quantities of 551-999).
12-15
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Legs(4) Beg. 1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 400 600 800
Scheduled receipts
Projected on hand 120 120 120 120 0 0 0 0
Net requirements 280 600 800
Planned-order receipts 280 600 800
Planned-order releases 880 800
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 4 = 400.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 4 = 600.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 4 = 800.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [120 + 0 0] + 0 = 120.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [120 + 280 400] + 0 = 0.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 600 600] + 0 = 0.
Planned-Order Releases (day 1) = 280 from Planned-Order Receipts of 280 in day 3 (lead time = 2
days for quantities of 201-550) + 600 from Planned-Order Receipts of 600 in day 4 (lead time = 3
days for quantities of 551-999) = 880.
Planned-Order Releases (day 3) = 800 from Planned-Order Receipts of 800 in day 6 (lead time = 3
days for quantities of 551-999).
12-16
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
7. Given:
80 units of end item X are needed at the beginning of week 6, and another 30 units are needed at
the beginning of week 8. D can be ordered only in whole cases (50 units per case). One case of D
(50 units) is received automatically every other week, beginning in week 1. On hand balances: B
= 30 and D = 20 units. Lead times are a function of quantity as shown in the table below. The
product structure tree is shown below also:
B(2) D(3)
D(2) F(2)
Prepare a material requirements plan for component D using lot-for-lot ordering for all items
except D. We will need to prepare material plans for X, B, and D.
Master Week 1 2 3 4 5 6 7 8
Schedule for: X Quantity 80 30
X Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 80 30
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 80 30
Planned-order receipts 80 30
Planned-order releases 80 30
Notes:
Planned-Order Releases (week 5 and week 7) have a lead time of 1 week (lead time = 1 week for
quantities of 1-100).
12-17
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
B(2) Beg. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 160 60
Scheduled receipts
Projected on hand 30 30 30 30 30 30 0 0 0
Net requirements 130 60
Planned-order receipts 130 60
Planned-order releases 130 60
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 X * 2 = 160.
Gross Requirements (week 7) = Planned-Order Releases of 30 X * 2 = 60.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [30 +130 160] + 0 = 0.
Planned-Order Releases (week 3) = 130 from Planned-Order Receipts of 130 in week 5 (lead time = 2
weeks for quantities of 101-200).
Planned-Order Releases (week 6) = 60 from Planned-Order Receipts of 60 in week 7 (lead time = 1
week for quantities of 1-100).
12-18
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
8. Given:
Oh No! Inc. sells three models: A, B, and C. Lead times are 1 week for all items except C (2
weeks). On hand balances: B = 10, C = 10, and D = 25 units. Lot-sizing rules are lot-for-lot for all
items except D, which must be ordered in multiples of 100. There is a scheduled receipt of 100
units of D in week 1. The master schedule shows that 40 units of A are needed at the beginning of
week 4, 60 units of B at the beginning of week 5, and 30 units of C at the beginning of week 6.
The product structure tree for each item is shown below:
A B C
D E D(2) F D(4) G
Prepare a material requirements plan for component D and its parents. We will need to prepare
material plans for A, B, C, and D.
Master Week 1 2 3 4 5 6
Schedule for: A Quantity 40
A LT = 1 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 40
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0
Net requirements 40
Planned-order receipts 40
Planned-order releases 40
Master Week 1 2 3 4 5 6
Schedule for: B Quantity 60
B LT = 1 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 60
Scheduled receipts
Projected on hand 10 10 10 10 10 10 0
Net requirements 50
Planned-order receipts 50
Planned-order releases 50
12-19
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Master Week 1 2 3 4 5 6
Schedule for: C Quantity 30
C LT = 2 Beg.
1 2 3 4 5 6
Lot size: Lot-for-Lot Inv.
Gross requirements 30
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10
Net requirements 20
Planned-order receipts 20
Planned-order releases 20
12-20
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
9. Given:
50 chain saws are needed at the start of week 8. The inventory information (shown in bold) and
the product structure tree are listed below in the problem solution:
A(2) B C(4)
1 2 3 4 5 6 7 8
week
Master schedule:
Master Week 1 2 3 4 5 6 7 8
Schedule for:
Saw Quantity 50
b. Material requirements plan for E using lot-for-lot ordering for all items. We will need to
prepare material plans for Saw, A, C, and E.
Master Week 1 2 3 4 5 6 7 8
Schedule for:
Saw Quantity 50
Saw LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 50
Scheduled receipts
Projected on hand 15 15 15 15 15 15 15 15 15
Net requirements 35
Planned-order receipts 35
Planned-order releases 35
12-21
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
A(2) LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 70
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10 0 0
Net requirements 60
Planned-order receipts 60
Planned-order releases 60
Notes:
Gross Requirements (week 6) = Planned-Order Releases of 35 Saws * 2 = 70.
C(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 140
Scheduled receipts
Projected on hand 65 65 65 65 65 65 65 0 0
Net requirements 75
Planned-order receipts 75
Planned-order releases 75
Notes:
Gross Requirements (week 6) = Planned-Order Releases of 35 Saws * 4 = 140.
12-22
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
10. Given:
40 units of an industrial robot are needed at the beginning of week 7. Subassembly G must be
ordered in multiples of 80 and all other components are ordered lot-for-lot. The inventory
information (shown in bold) and the product structure tree are listed below in the problem
solution. Prepare the material plan for G. We will need to prepare material plans for Robot, C, &
G.
Robot
B C(3)
E F G G(2) H
Master Week 1 2 3 4 5 6 7
Schedule for:
Robot Quantity 40
Robot LT = 2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 40
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10 10
Net requirements 30
Planned-order receipts 30
Planned-order releases 30
C(3) LT = 1 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 90
Scheduled receipts
Projected on hand 20 20 20 20 20 20 0 0
Net requirements 70
Planned-order receipts 70
Planned-order releases 70
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 30 Robots * 3 = 90.
12-23
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
11. a. Given:
Refer back to Solved Problem 3. On hand balances: N = 100 and E = 0. Scheduled receipts: I
= 40 and V = 10 at the beginning of week 3. 120 E are needed at the start of week 5. We have
the product structure tree shown below. Determine material requirements plans for E, I, N,
and V using lot-for-lot ordering as was used in Solved Problem 3:
E
M(3) I(2)
R(2) P N(4) V
Master Period 1 2 3 4 5 6 7 8
Schedule for:
E Quantity 120
E LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 120
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 120
Planned-order receipts 120
Planned-order releases 120
12-24
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
I(2) LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 240
Scheduled receipts 40
Projected on hand 0 0 0 40 40 0 0 0 0
Net requirements 200
Planned-order receipts 200
Planned-order releases 200
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 120 E * 2 = 240.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 200 240] + 0 = 0.
N(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 800
Scheduled receipts
Projected on hand 100 100 100 100 0 0 0 0 0
Net requirements 700
Planned order receipts 700
Planned order releases 700
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 200 I * 4 = 800.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 700 800] + 0 = 0.
V LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200
Scheduled receipts 10
Projected on hand 0 0 0 10 0 0 0 0 0
Net requirements 190
Planned order receipts 190
Planned order releases 190
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 200 I * 1 = 200.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 10 = 10.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 190 200] + 0 = 0.
12-25
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
b. Given:
Assume that on hand balances and scheduled receipts remain the same as in part a. On hand
balances: N = 100 and E = 0. Scheduled receipts: I = 40 and V = 10 at the beginning of week
3.
New information: 100 E are needed at the start of week 5 and 55 are needed at the start of
week 7. Determine the material requirements plans for E, I, N, and V using lot-for-lot
ordering for E and I, and multiples of these order sizes: N = 800 and V = 200.
E
M(3) I(2)
R(2) P N(4) V
Master Period 1 2 3 4 5 6 7 8
Schedule for:
E Quantity 100 55
E LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 100 55
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 100 55
Planned-order receipts 100 55
Planned-order releases 100 55
I(2) LT = 1 Beg. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200 110
Scheduled receipts 40
Projected on hand 0 0 0 40 40 0 0 0 0
Net requirements 160 110
Planned-order receipts 160 110
Planned-order releases 160 110
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 100 E * 2 = 200.
Gross Requirements (week 6) = Planned-Order Releases of 55 E * 2 = 110.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 160 200] + 0 = 0.
12-26
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
N(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 800 Inv.
Gross requirements 640 440
Scheduled receipts
Projected on hand 100 100 100 100 260 260 620 620 620
Net requirements 540 180
Planned order receipts 800 800
Planned order releases 800 800
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 4 = 640.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 4 = 440.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 800 640] + 0 = 260.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [260 + 800 440] + 0 = 620.
V LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 200 Inv.
Gross requirements 160 110
Scheduled receipts 10
Projected on hand 0 0 0 10 50 50 140 140 140
Net requirements 150 60
Planned order receipts 200 200
Planned order releases 200 200
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 1 = 160.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 1 = 110.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 10 = 10.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 200 160] + 0 = 50.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 0 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 200 110] + 0 = 140.
12-27
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
c. Case 1 Given:
Refer back to part b. 1 week has elapsed. It is now the start of week 2. 100 E are needed at
the start of week 9. Assume that all orders were released and received as planned.
Notes:
a. We will drop 1 week (week 1) from the material plans and add 1 week at the end of each
plan.
b. Any Planned-Order Releases from week 1 must now show up as Scheduled Receipts:
Item N: Change Planned-Order Receipts of 800 in week 3 to Scheduled Receipts in week 3.
Item V: Change Planned-Order Receipts of 200 in week 3 to Scheduled Receipts in week 3.
The revised amount of Scheduled Receipts (week 3) = original amount of 10 + 200 = 210.
Determine the ending inventory for each item at the end of week 1. These will become the
beginning inventory balances in week 2.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements
Item E Week 1
Ending Inventory 0+00=0
Item I Week 1
Ending Inventory 0+00=0
Item N Week 1
Ending Inventory 100 + 0 0 = 100
Item V Week 1
Ending Inventory 0+00=0
M(3) I(2)
R(2) P N(4) V
12-28
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
c. continued
Master Period 2 3 4 5 6 7 8 9
Schedule for:
E Quantity 100 55 100
E LT = 1 Beg.
2 3 4 5 6 7 8 9
Lot size: Lot-for-Lot Inv.
Gross requirements 100 55 100
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 100 55 100
Planned-order receipts 100 55 100
Planned-order releases 100 55 100
I(2) LT = 1 Beg.
2 3 4 5 6 7 8 9
Lot size: Lot-for-Lot Inv.
Gross requirements 200 110 200
Scheduled receipts 40
Projected on hand 0 0 40 40 0 0 0 0 0
Net requirements 160 110 200
Planned-order receipts 160 110 200
Planned-order releases 160 110 200
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 100 E * 2 = 200.
Gross Requirements (week 6) = Planned-Order Releases of 55 E * 2 = 110.
Gross Requirements (week 8) = Planned-Order Releases of 100 E * 2 = 200.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 160 200] + 0 = 0.
POH9 = [POH8 + Planned-Order Receipts8 Gross Requirements8] + Scheduled Receipts9
POH9 = [0 + 200 200] + 0 = 0.
12-29
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
N(4) LT = 2 Beg.
2 3 4 5 6 7 8 9
Lot size: Multiples of 800 Inv.
Gross requirements 640 440 800
Scheduled receipts 800
Projected on hand 100 100 900 260 260 620 620 620 620
Net requirements 180 180
Planned order receipts 800 800
Planned order releases 800 800
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 4 = 640.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 4 = 440.
Gross Requirements (week 7) = Planned-Order Releases of 200 I * 4 = 800.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [100 + 0 0] + 800 = 900.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [900 + 0 640] + 0 = 260.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [260 + 800 440] + 0 = 620.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [620 + 800 800] + 0 = 620.
V LT = 2 Beg.
2 3 4 5 6 7 8 9
Lot size: Multiples of 200 Inv.
Gross requirements 160 110 200
Scheduled receipts 210
Projected on hand 0 0 210 50 50 140 140 140 140
Net requirements 60 60
Planned order receipts 200 200
Planned order releases 200 200
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 1 = 160.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 1 = 110.
Gross Requirements (week 7) = Planned-Order Releases of 200 I * 1 = 200.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 210 = 210.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [210 + 0 160] + 0 = 50.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 0 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 200 110] + 0 = 140.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [140 + 200 200] + 0 = 140.
12-30
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Case 2 Given:
Refer back to the previous update. It is now the start of week 4. Assume that all orders were
released and received as planned in weeks 2 and 3.
Notes:
a. We will drop 2 weeks (weeks 2 & 3) from the material plans and add 2 weeks at the end of
each plan.
b. Any Planned-Order Releases from weeks 2 & 3 must now show up as Scheduled Receipts:
Item I: Change Planned-Order Receipts of 160 in week 4 to Scheduled Receipts in week 4.
Item N: Change Planned-Order Receipts of 800 in week 5 to Scheduled Receipts in week 5.
Item V: Change Planned-Order Receipts of 200 in week 5 to Scheduled Receipts in week 5.
Determine the ending inventory for each item at the end of week 3. These will become the
beginning inventory balances in week 4.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements
M(3) I(2)
R(2) P N(4) V
12-31
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Master Period 4 5 6 7 8 9 10 11
Schedule for:
E Quantity 100 55 100
E LT = 1 Beg.
4 5 6 7 8 9 10 11
Lot size: Lot-for-Lot Inv.
Gross requirements 100 55 100
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 100 55 100
Planned-order receipts 100 55 100
Planned-order releases 100 55 100
I(2) LT = 1 Beg.
4 5 6 7 8 9 10 11
Lot size: Lot-for-Lot Inv.
Gross requirements 200 110 200
Scheduled receipts 160
Projected on hand 40 200 0 0 0 0 0 0 0
Net requirements 110 200
Planned-order receipts 110 200
Planned-order releases 110 200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [200 + 0 200] + 0 = 0.
12-32
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
N(4) LT = 2 Beg.
4 5 6 7 8 9 10 11
Lot size: Multiples of 800 Inv.
Gross requirements 440 800
Scheduled receipts 800
Projected on hand 260 260 1060 620 620 620 620 620 620
Net requirements 180
Planned order receipts 800
Planned order releases 800
Notes:
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [1060 + 0 440] + 0 = 620.
V LT = 2 Beg.
4 5 6 7 8 9 10 11
Lot size: Multiples of 200 Inv.
Gross requirements 110 200
Scheduled receipts 200
Projected on hand 50 50 250 140 140 140 140 140 140
Net requirements 60
Planned order receipts 200
Planned order releases 200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 200 = 250.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [250 + 0 110] + 0 = 140.
12-33
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
12. Given:
200 carts must be ready at the beginning of week 8. The product structure tree, assembly time
chart, and inventory information are shown in the solutions below:
Golf
Cart
Top Base
Cart
Motor
Frame
Controls Body Base
Wheels
Seats
2 3 4 5 6 7
week
12-34
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
c. Develop a material requirements plan that will provide 200 golf carts by week 8 assuming
lot-for-lot ordering.
Master Week 1 2 3 4 5 6 7 8
Schedule for:
Golf Cart Quantity 200
Top LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200
Scheduled receipts
Projected on hand 40 40 40 40 40 40 40 40 0
Net requirements 160
Planned-order receipts 160
Planned-order releases 160
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.
Supports(4) LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 640
Scheduled receipts
Projected on hand 200 200 200 200 200 200 200 0 0
Net requirements 440
Planned-order receipts 440
Planned-order releases 440
Notes: Gross Requirements (week 6) = Planned-Order Releases of 160 Tops * 4 = 640.
12-35
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
12. c. (continued)
Cover LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 160
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 160
Planned-order receipts 160
Planned-order releases 160
Notes: Gross Requirements (week 6) = Planned-Order Releases of 160 Tops * 1 = 160.
Base LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 200
Scheduled receipts
Projected on hand 20 20 20 20 20 20 20 20 0
Net requirements 180
Planned-order receipts 180
Planned-order releases 180
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.
Motor LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 180
Scheduled receipts
Projected on hand 300 300 300 300 300 300 300 120 120
Net requirements
Planned-order receipts
Planned-order releases
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.
12-36
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
12. c. (Continued)
Body LT = 3 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 180
Scheduled receipts
Projected on hand 50 50 50 50 50 50 50 0 0
Net requirements 130
Planned-order receipts 130
Planned-order releases 130
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.
Seats(2) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 360
Scheduled receipts
Projected on hand 120 120 120 120 120 120 120 0 0
Net requirements 240
Planned-order receipts 240
Planned-order releases 240
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 2 = 360.
Frame LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 130
Scheduled receipts
Projected on hand 35 35 35 35 0 0 0 0 0
Net requirements 95
Planned-order receipts 95
Planned-order releases 95
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.
12-37
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
12. c. (Continued)
Controls LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 130
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 130
Planned-order receipts 130
Planned-order releases 130
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.
12-38
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
13. Given:
Refer back to Problem 12. The revised plan calls for 100 golf carts to be available at the start of
week 6, 100 at the start of week 8, and 100 at the start of week 9.
Master Week 1 2 3 4 5 6 7 8 9
Schedule for:
Golf Carts Quantity 100 100 100
b. Determine the timing and quantities for orders for tops and bases.
Top LT = 1 Beg.
Lot size: Lot-for-Lot Inv. 1 2 3 4 5 6 7 8 9
Base LT = 1 Beg.
Lot size: Lot-for-Lot 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 20 20 20 20 20 20 0 0 0 0
Net requirements 80 100 100
Planned-order receipts 80 100 100
Planned-order releases 80 100 100
12-39
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
c. The firms capacity limits the assembly of bases to 50 units per week. Revise the plan, but
still meet delivery dates. Note: We should try to minimize inventory also.
The key will be to move Planned-Order Receipts and Planned-Order Releases earlier in the
plan.
Consider the plan for Bases in b above:
Planned Order-Receipts (week 8) = 100
Planned Order-Receipts (week 7) = 100
Planned Order-Receipts (week 5) = 80
Given the capacity limit of 50 per week, we could divide the Planned-Order Receipts as
follows:
Week 8 (100): Week 7 (50) & Week 8 (50)
Week 7 (100): Week 5 (50) & Week 6 (50)
Week 5 (80): Week 3 (30) & Week 4 (50)
Note: Because some of these Planned-Order Receipts need to be planned earlier than they
should be, the planner will have to lock in the timing and quantity of these Planned-Order
Receipts by designating them as Firm Planned Orders so that the MRP system does not re-
schedule them automatically.
Master Week 1 2 3 4 5 6 7 8 9
Schedule for:
Golf Carts Quantity 100 100 100
Base LT = 1 Beg.
Lot size: Lot-for-Lot 1 2 3 4 5 6 7 8 9
Inv.
Gross requirements 100 100 100
Scheduled receipts
Projected on hand 20 20 20 20 50 100 50 100 50 0
Net requirements
Planned-order receipts 30 50 50 50 50 50
Planned-order releases 30 50 50 50 50 50
12-40
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
14. Given:
a. Draw a product structure tree (tree diagram) for the scissors. Lead times are 1 day for each
component and final scissor assembly, but 2 days for the plastic grips. 600 scissors are
needed on Day 6. On hand inventory: Straight blades = 200, bent blades = 350, and top blade
assembly = 40.
Scissors
Straight Blade Straight Plastic Grip Bent Blade Bent Plastic Grip
b. Material plans:
Master Beg.
Week 1 2 3 4 5 6 7 8
Schedule for: Inv.
Scissors Quantity 600
Scissors LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 600
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 600
Planned-order receipts 600
Planned-order releases 600
12-41
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Screw LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 600
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 600
Planned-order receipts 600
Planned-order releases 600
Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.
12-42
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
12-43
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
15. Given:
A company has the following demand for its products, labor and machine standards, and available
capacities:
Week number 1 2 3 4
Material (tons) 40 80 60 70
Labor Machine
Production standard 4 3
(hours per ton)
Weekly production 300 200
capacity (hours)
a. Determine capacity utilization for labor and machine for each of the four weeks:
Capacity Requirements (Load) =
Units * Standard Labor and/or Machine Requirements per Unit
b. Capacity utilization exceeds 100% for both labor and machine in week 2, and for machine in
week 4.
Production could be shifted to earlier or later weeks in which capacity is underutilized.
Shifting to an earlier week would result in added carrying costs; shifting to later weeks would
mean backorder costs.
Another option could be to work overtime. Labor cost would increase due to overtime
premium, a probable decrease in productivity, and a possible increase in accidents.
12-44
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
16. Given:
A company produces 2 products that go through a 3-day sequence of fabrication, assembly, and
packaging. Each step requires 1 day for a lot to be processed and moved to the next department.
Processing requirements for the departments (hours per unit) are:
Department capacities are all 700 hours of labor and 500 hours of machine time, except Friday,
when capacities are 200 hours for both labor and machine time. The following production
schedule is for next week:
a. Determine the labor and machine capacity requirements for each product and the total load at
each department for each day.
For example, the 200 units of Product A & 300 units of Product B will be processed at
Fabrication on Monday, Assembly on Tuesday, and Packaging on Wednesday.
Tuesday Assembly Labor Load = (200 A * 1.5 = 300) + (300 B * 1 = 300) = 600.
Tuesday Assembly Machine Load = (200 A * 1 = 200) + (300 B * 1 = 300) = 500.
Wednesday Packaging Labor Load = (200 A * 1 = 200) + (300 B * 1.5 = 450) = 650.
Wednesday Packaging Machine Load = (200 A * .5 = 100) + (300 B * .5 = 150) = 250.
12-45
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Monday:
Fabrication: Load = capacity for both labor and machine.
Tuesday:
Fabrication: Labor load is over capacity by 300 hours. Machine load is over capacity by 100
hours.
Assembly: Labor load is under capacity by 100 hours. Machine load = capacity.
Wednesday:
Fabrication: Labor load is under capacity by 300 hours. Machine load is under capacity by
200 hours.
Assembly: Labor load is over capacity by 100 hours. Machine load is over capacity by 100
hours.
Packaging: Labor load is under capacity by 50 hours. Machine load is under capacity by 250
hours.
The schedule does not appear to be feasible. Fabrication is overloaded for labor and machine
on Tuesday and underloaded for labor and machine on Wednesday. In addition, Assembly is
overloaded for labor and machine on Wednesday.
One solution could be to shift some of the 400 A & 200 B scheduled in Fabrication on
Tuesday to Wednesday. For example, we could shift 150 A in Fabrication from Tuesday to
12-46
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Wednesday. We now would schedule 250 A on Tuesday (400-150) and 250 A on Wednesday
(100+150). The new load values are highlighted in bold in the table below:
12-47
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
17. Given:
The MRP departments computer died just as it spit out the following information: Planned-Order
Releases for Item J27 = 640 units in week 2. We have the following product structure tree and
inventory information shown below:
565
J27(4) X43
Step 1:
Look at which items are linked together by the Planned-Order Releases for J27: J27, Y36, and
565.
Step 2:
Work from the bottom to the top of the product structure tree. Start with J27 to determine its
Planned-Order Receipts, Net Requirements, and Gross Requirements.
b. If the Gross Requirements for J27 = 640 in week 4, then the Planned-Order Releases for Y36
= 160 (640 / 4) in week 4.
The lead time for Y36 = 1 week. This means that the Planned-Order Receipts = 160 in week
5 (1 week later).
The lot size for Y36 is lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 5 = 160.
The on hand balance for Y36 = 200. This means that the Gross Requirements in week 5 = Net
Requirements + On Hand = 160 + 200 = 360.
12-48
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
c. If the Gross Requirements for Y36 = 360 in week 5, the Planned-Order Releases for 565 =
180 (360 / 2) in week 5.
The lead time for 565 = 1 week. This means that the Planned-Order Receipts = 180 in week 6
(1 week later).
The lot size for 565 is lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 6 = 180.
The on hand balance for 565 = 0. This means that the Gross Requirements in week 6 = Net
Requirements + On Hand = 180 + 0 = 180.
Conclusion: There should be a quantity of 180 listed in week 6 of the master schedule for
Item 565.
Below are the MRP tables verifying the proof discussed above:
Master Week 1 2 3 4 5 6 7 8
Schedule for:
565 Quantity 180
565 LT = 1 Beg.
Lot size: Lot-for-Lot Inv. 1 2 3 4 5 6 7 8
Y36(2) LT = 1 Beg.
Lot size: Lot-for-Lot 1 2 3 4 5 6 7 8
Inv.
Gross requirements 360
Scheduled receipts
Projected on hand 200 200 200 200 200 200 0 0 0
Net requirements 160
Planned-order receipts 160
Planned-order releases 160
J27(4) LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 640
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 640
Planned-order receipts 640
Planned-order releases 640
12-49
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
18. Given:
Develop a material requirements plan for component H. Use lot-for-lot ordering for all items.
Lead times for the end item and each component (except B) = 1 week. The lead time for B = 3
weeks. On hand balances: B = 15 & E = 130. Scheduled Receipts for H = 50 in week 2. 60 units
of A are needed at the start of week 8. We have the following product structure tree:
B(2) C
H(3) K H(3) K
Master Week 1 2 3 4 5 6 7 8
Schedule Quantity
60
for: A
A LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 60
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 60
Planned-order receipts 60
Planned-order releases 60
12-50
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
B(2) LT = 3
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
C LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 60
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Net requirements 60
Planned-order receipts 60
Planned-order releases 60
12-51
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
H(3) LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
We will develop material plans for Tractor-Trailer, Tractor, Trailer, Tractor Wheel Assembly, Trailer
Wheel Assembly, & Wheels.
If the order of 20,000 tractor-trailers is due at the start of week 8 and final assembly is limited to 10,000
per week, then we must list 10,000 in week 7 and 10,000 in week 8 of the master schedule.
12-52
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Master Week 1 2 3 4 5 6 7 8
Schedule Quantity 10,000 10,000
Tractor-Trailer
LT = 1 Beg.
1 2 3 4 5 6 7 8
Inv.
Lot size: Lot-for-Lot
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Tractor LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Trailer LT = 1
Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
12-53
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Tractor Wheel
Assembly LT = 1 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Trailer Wheel
Assembly LT = 1 Beg.
1 2 3 4 5 6 7 8
Inv.
Lot size: Lot-for-Lot
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
12-54
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Scheduled receipts
Projected on hand 0 0 0 0 100,000 20,000 4,000 4,000 4,000
1. The company will need a total of 360,000 Wheels. It will be able to produce only 300,000 during
weeks 2, 3, & 4. The company will need to order at least 60,000 Wheels as indicated with the * in
week 2. The company actually would have to purchase 10 sets of 6,400 Wheels per set = 64,000.
2. The company will need the Wheels in week 5. If lead time will be 2-3 weeks, then assume that it
will be 3 weeks, and order the Wheels from the supplier in week 2.
12-55
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Master Week 1 2 3 4 5 6 7 8
Schedule for:
Arrows Quantity 15 15 15 15 15
Master Week 1 2 3 4 5 6 7 8
Schedule for:
Darts Quantity 10 10 10 10 10
Arrows LT = 2 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot
Gross requirements 15 15 15 15 15
Scheduled receipts 20
Projected on hand 5 25 25 25 25 10 0 0 0
Net requirements 5 15 15 15
Planned-order receipts 5 15 15 15
Planned-order releases 5 15 15 15
Darts LT = 2 Beg.
1 2 3 4 5 6 7 8
Lot size: Lot-for-Lot Inv.
Gross requirements 10 10 10 10 10
Scheduled receipts 20
Projected on hand 2 2 22 22 22 12 2 0 0
Net requirements 8 10 10
Planned-order receipts 8 10 10
Planned-order releases 8 10 10
X LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 25 Inv.
Gross requirements 5 15 15 15
Scheduled receipts
Projected on hand 5 5 5 5 0 10 20 5 5
Net requirements 15 5
Planned-order receipts 25 25
Planned-order releases 25 25
12-56
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
K(2) LT = 1 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Lot-for-lot
Gross requirements 16 20 20
Scheduled receipts
Projected on hand 3 3 3 3 3 0 0 0 0
Net requirements 13 20 20
Planned-order receipts 13 20 20
Planned-order releases 13 20 20
Gross Requirements (week 4) = Planned-Order Releases of 8 Darts * 2 = 16.
Gross Requirements (week 5) = Planned-Order Releases of 10 Darts * 2 = 20.
Gross Requirements (week 6) = Planned-Order Releases of 10 Darts * 2 = 20.
F&F LT = 1 Beg.
1 2 3 4 5 6 7 8
Lot size: Multiples of 30 Inv.
Gross requirements 25 33 10 10
Scheduled receipts 15
Projected on hand 10 10 25 25 0 27 17 7 7
Net requirements 33 0 0
Planned-order receipts 60
Planned-order releases 60
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 25 X * 1 = 25.
Gross Requirements (week 4) = Planned-Order Releases of (8 Darts * 1) + (25 X * 1) = 8 + 25 = 33.
Gross Requirements (week 5) = Planned-Order Releases of 10 Darts * 1 = 10.
Gross Requirements (week 6) = Planned-Order Releases of 10 Darts * 1 = 10.
12-57
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
Q LT = 1 Beg.
Inv. 1 2 3 4 5 6 7 8
Lot size: Multiples of 30
Gross requirements 13 20 20
Scheduled receipts
Projected on hand 15 15 15 15 2 12 22 22 22
Net requirements 18 8
Planned-order receipts 30 30
Planned-order releases 30 30
Gross Requirements (week 3) = Planned-Order Releases of 13 K * 1 = 13.
Gross Requirements (week 4) = Planned-Order Releases of 20 K * 1 = 20.
Gross Requirements (week 5) = Planned-Order Releases of 20 K * 1 = 20.
12-58
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 12 - MRP and ERP
12-59
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.