Anda di halaman 1dari 10

www.ietdl.

org

Published in IET Generation, Transmission & Distribution


Received on 5th June 2008
Revised on 30th May 2009
doi: 10.1049/iet-gtd.2008.0573

ISSN 1751-8687

Interior point methods application in optimum


operational scheduling of electric power
systems
I.A. Farhat M.E. El-Hawary
Department of Electrical and Computer Engineering, Dalhousie University, Halifax, NS B3J 2X4, Canada
E-mail: elhawary@dal.ca

Abstract: The topic of interior point (IP) methods has been one of the most active research areas since it was
rediscovered by Karmarkar in 1984. A variety of IP algorithms have been applied to many areas of power
systems optimisation. This study presents a survey of literature on the application of IP methods to planning
and operation of power systems. A review of research papers that have been published since 1994 in three
major power system optimisation problems is presented. The problems are economic dispatch, unit
commitment and hydrothermal coordination.

1 Introduction introduction of the interior-point revolution [6]. In his


paper, Karmarkar demonstrated that IP methods were
Solving power system optimisation problems is a central aspect capable to solve linear programs in a polynomial time
of the real-world power system endeavour [1, 2]. The target of manner. He also provided, for the rst time, direct
power system optimisation is the eld of study in which the evidence that IP methods were faster than the simplex
target is to minimise the xed and operational costs of the method especially in large-scale optimisation problems.
system. This is to optimise a specic objective function The earliest ideas for the IP methods can be traced back to
subjected to a number of constrains because of the system 1955 when Frisch [7] introduced what was called a log-
control and operational factors. Various conventional barrier function to replace the linear inequality constraints.
optimisation techniques have been employed in the eld. The term interior-point methods was originally introduced
The variety of these techniques is a consequence of the fact by Fiacco and McCormick [8, p. 41] in their book. Gill
that optimisation problems in electrical power systems are et al. [9] revealed the relationship between Karmarkars
diverse. Depending on the nature and characteristics of the method and Fiacco and McCormicks classical logarithmic
problems, they are typically classied according to their barrier method. In the literature, IP methods can be
objective function as well as the applicable constraints. The classied as projective methods, afne scaling methods or
objective function and constraints can be linear or non- primal dual methods [10]. The primal dual algorithm
linear, discrete or continuous. The optimisation techniques was rs outlined by Megiddo [11]. This primal dual path
in use to solve these problems are, classically, categorised as following approach proposed that the optimal solution
quadratic programming, Newton-based methods, linear should follow the centre path. Further, the predictor
programming, hybrid versions of linear and integer corrector technique was introduced by Mehrotra [12] in
programming and interior point (IP) methods etc. A 1992 to be integrated with the IP path following methods.
comprehensive summary of these techniques is offered in Subsequently, a remarkable number of papers and
[3, 4]. The IP methods have become one of the most publications have been introduced in the literature,
important techniques used to solve the optimisation however, primal dual methods are the most applied in
problems in electric power systems. optimisation problems. References [5 18] among others,
demonstrate a comprehensive discussion on the
Since Karmarkars [5] landmark paper in 1984, the eld classications of the various IP methods from a theoretical
of optimisation has been remarkably changed through the viewpoint.

1020 IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029
& The Institution of Engineering and Technology 2009 doi: 10.1049/iet-gtd.2008.0573
www.ietdl.org

2 Application of IP methods in
power system optimisation
Applying IP methods to power system optimisation problems
began early in 1990s. They were rst applied to power
systems by Clements et al. [19] in 1991. The objective of
Clements research was to apply a non-linear programming
IP technique to solve the state estimation problems in
power systems. Following that a large number of papers
dealing with the application of the IP methods in various
elds were introduced. A review of the IP methods that
were applied to a variety of power system optimisation
problems up to 1993 is presented in [4]. Fig. 1 is a
statistical demonstration of the number of the published
research papers where IP methods were applied to different
areas of electrical power systems after 1993 (based on Figure 2 Number of papers published in different power
IEEE/IET/Elsevier databases). system areas where IP methods were applied

Power system optimisation problems can be classied in that deal with more than one of the problems are reported
terms of their objective functions and constraints. The areas in only one category.
of active research in the electrical power systems in which
the IP methods are applied include the following: optimal 2.1 Economic dispatch
power ow, reactive power optimisation, voltage collapse
The economic dispatch (ED) problem is designed to
and reliability evaluation, maximum loadability, state
determine the optimum loading of all committed units to
estimation, electricity market, economic dispatching, unit
optimise an objective function as follows [1]
commitment (UC) and hydrothermal coordination.
X
N

Fig. 2 illustrates the number of publications and the min FT (ai bi Pi (t) ci Pi2 (t))
i1
research areas in which IP methods were applied. In this
survey we focus our attention on the application of IP
Subject to satisfying the following two general types of
methods to solve three important power system
constraints:
optimisation problems, namely, economic dispatching, UC
and hydrothermal coordination (HTC). Fig. 3 shows the Equality constraint representing the load balance equation
number of the published papers per year for the application with the losses included
of IP methods to the three optimisation problems after1993.
X
N
Pi (t)  PL (t)  PD (t) 0
In this coverage we included, to the best of our knowledge
i1
(based on IEEE/IET/Elsevier databases), almost all of the
papers that have been published since 1994. The year 1994 Inequality constraints representing the generating unit
is selected as our starting point to build on the capacity limits
comprehensive survey presented by Momoh et al. [4] and
other earlier ones. The three problems considered in this Pimin  Pi (t)  Pimax
review are closely related. Hence, some of the references
For consistency purposes, in some cases branch ow
constraints, that is a network model, need to be incorporated
in the formulation.

where N is the number of power plants, ai , bi and ci are cost


function coefcients of the ith generating unit, Pi (t) the
power generation of the ith generating unit at hour t, PD(t)
the total system load demand at hour t, PL(t) the system
total real power losses at hour t, Pimin the minimum power
generation for unit i and Pimax the maximum power
generation for unit i.

Figure 1 Number of papers published in each year on the Many formulations were introduced to solve the ED
subject of applying IP methods in power systems problem by considering different factors and constraints.

IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029 1021
doi: 10.1049/iet-gtd.2008.0573 & The Institution of Engineering and Technology 2009
www.ietdl.org

Figure 3 Number of papers published in each year for IP methods applied in ED, UC and hydrothermal coordination problems

However, the objective of the problem is still, as expressed ramp-rate limits extending over plural time slices and
above, computing the optimal allocation of the power transmission capacity limits. The algorithm solved the
demand among the running thermal units [1]. Yan and problem in 800 ms using 100 MIPS EWS noting that the
Quintana [20] implemented a predictor corrector IP problem size was limited by ten transmission capacity
method to solve the security constrained ED problem. constraints. This was because only the overloaded branches
They linearised the non-linear optimisation problem and were considered in order to reduce the number of
focused on adjusting the barrier parameters and the constraints. In [23 25] Jabr et al. presented a homogenous
determination of the initial point. A successive linear IP (HIP) method to solve the ED problem. Compared to
programming technique was used instead of non-linear the predictor corrector and the primal dual IP methods,
methods in order to achieve two advantages. Firstly, to the HIP method required one more additional step per
reduce the computational burden as there was no need to iteration to obtain the solution of the Newton system. This
calculate the second-order derivatives Hessian matrix at added step is required to make the HIP, unlike other
each iteration. Secondly, the possibility to control the methods, reliably achieve the advantage of detecting
optimisation process as per user-specied accuracy. problem infeasibility. In [23] the second-order network
Compared with a pure primal dual IP method, the model, phase shifters and operational constraints were
proposed scheme showed better performance, from a included through formulating the problem as a convex
computational point of view, when applied on power program. Jabr et al. [24] considered not only the N security
systems of 236 2124 buses. Irisarri et al. [21] formulated problem but also the (N 2 1) and (N 2 2) network security
the barrier function added to the objective function so that conditions. However, when tests were run for the practical
the slack variables are not negative. The ED problem was 175-bus network, only the (N 2 1) security was considered.
treated as a single problem by combining the power ow It should be also noted that the application did not
and the ramping constraints. In this approach the number consider system losses in this reference but was considered
of iterations only changed slightly with the size of the in [26] by the same author. In this work, when an HIP
problem when it was tested using the IEEE 30-bus system. method was applied, (N 2 1) and (N 2 2) security were
It should be also mentioned that an auxiliary penalty still considered as well as the network losses through a
variable was used which meant that there is no need for second-order model. Again an HIP method was proposed
nding an initial dispatch. This did not lead to any further in [25] to solve the dynamic ED problem as a single
computational requirements since the penalty variable was convex problem although security constraints were not
algebraically eliminated. Power unit dynamics were taken considered. The solution was obtained through the HIP
into consideration in the ED control model presented in algorithm by solving the problems of the lack of the ability
[22]. In this unit dynamic model an IP algorithm was to detect the infeasibility and the need for a starting
implemented considering many constraints such as the solution (initial guess). A modied primal dual IP method

1022 IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029
& The Institution of Engineering and Technology 2009 doi: 10.1049/iet-gtd.2008.0573
www.ietdl.org

to solve the optimal power ow dispatching was implemented 2.2 Unit commitment
by Jabr et al. [27]. Two modications were introduced to
improve convergence by controlling the step length and the The UC optimisation problem deals with determining which
search direction to ensure convergence to minimising of the generating units will be running each hour of operation
stationary points. In spite of the good performance of the period at minimum cost [1]. This is to decide which of the
modied algorithm, a failure in one of the test cases was units will be committed, shut down or in a hot reserve state
reported because of a high diagonal perturbation at the [2]. The objective of the solution to this is to minimise the
beginning of the iterations and this could be overcome by operation cost while satisfying certain system planning and
selecting another starting point. The power transactions and operational constraints. The problem can be formulated
the power traded in the spot market were taken into mathematically as follows [33]
consideration by Fernandes and Almeida [28] where a
primal dual IP method was used to solve the ED problem X Nt
N X

under a pool-bilateral market. The utilised model min FT [Ii (t)Fi (Pi (t)) Si (t)]
i1 t1
considered a transactions matrix, which consisted of
bilateral contractors, to represent the security region of the
model. Among the constraints considered in the model This objective function is subject to satisfying several
were transmission losses though they were not allocated to constraints including the following:
the participants. A 5-bus and the IEEE 118-bus systems Load balance
were used to implement the proposed method and present
the results and emphasise the inuence of each transaction X
N
and spot market on the system voltage and current. In order Ii (t)Pi (t)  PD (t) 0, t 1, 2, . . . , Nt
to achieve a better computational time, the linear system i1
was to be reduced. However, results did not show any
information regarding computational time nor convergence Spinning reserve requirements of the system
characteristics. In [29] an investigation of the use of the
primal dual IP methods in solving the power generation X
N

dispatching problem by formulating them in a symmetric Pimax (t)Ii (t)  PD (t)  PR (t)  0, t 1, 2, . . . , Nt
i1
form was conducted. It was shown that when the problem
is expressed in a symmetric form (i.e. the constraints are Unit generation limits
Bx  b; x  0), there exist two mathematically equivalent
forms for the search direction. The results showed that the
primal form is better applied to the unconstrained problems Pimin  Pi (t)  Pimax , i 1, 2, . . . , N and
whereas the dual is more suitable for the constrained t 1, 2, . . . , Nt
problems, even though no comparison with other models
was conducted. A primal dual IP method was used in [30] Thermal unit minimum start up/shut down times
to implement a price-based model with the transmission
constraints and contingencies considered. The (Xion (t  1)  Ti on )(Ii (t  1)  Ii (t))  0
contingencies were regarded as a subproblem wheras
the master problem was the ED problem. In this work, the (Xioff (t  1)  Tioff )(Ii (t)  Ii (t  1))  0
problem was not modelled as a cost based for vertically
integrated power systems but as a price based for restricted Transmission line capacity limits
power markets. The primal dual IP method was
implemented to solve the security constrained ED problem Pmmin (t)  Pm (t)  Pmmax (t)
in [31] where it was tested on the IEEE 6- and 30-bus
systems. The problem was formulated using the real power where N is the total number of units, Nt the total time in
equations that were then linearised through a linearisation hours, M the total number of transmission lines, Pi (t) the
algorithm. The approach was compared to the simplex power output of unit i at hour t, Ii(t) the commitment state
method and obtained the same results with less (1 or 0) of unit i at hour t, Fi (Pi(t)) the fuel cost of unit i
computational time and better convergence characteristics. when generating power is Pi(t), Si(t) the start up cost of
Using an IP method, Han and Gooi [32] proposed a unit i at hour t, PD(t) the system load demand at hour t,
decoupled solution model with a look-ahead-based Pimax the rated upper generation limit of unit i, Pimin the
technique to reduce the solution size of the problem. In this rated lower generation limit of unit i, PR(t) the system
reference the problem was formulated to take into account spinning reserve requirement at hour t, Xion/off (t) the time
the spinning reserve and the network ow constraints in duration for which unit i has been on/off at hour t, Tion/off(t)
addition to the unit ramp rate limits. The model was tested the minimum up/down time of unit i, Pm(t) the power
under different cases with different constraints. It was found ow of transmission line m, Pmmax(t) the power ow upper
that the system costs and time required increased by the limit of transmission line m and Pmmin(t) the power ow
increase of the number of constraints taken into account. lower limit of transmission line m.

IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029 1023
doi: 10.1049/iet-gtd.2008.0573 & The Institution of Engineering and Technology 2009
www.ietdl.org

The UC problem has been solved using various optimisation problem can be formulated, in general, as follows [1]
techniques including the IP methods. Madrigal and Quintana
[34] used the IP method to solve this problem. An IP/cutting- X
T X
N
plane method was introduced to solve the non-differentiable min FT Fj (PS ( j, t))
t1 j1
optimisation problems that go together with the Lagrangian
relaxation approaches. The advantages of this method were
to overcome the problem of parameter-tuning and to gain a where FT is the total production cost function, PS( j, t) the
better convergence. Unlike other cutting-plane methods, in power generation of thermal unit j at time interval t,
IP/cutting-plane methods the improved point is not taken Fj (PS( j, t)) the production cost for (PS( j, t)), N the
from the point that maximises the stabilised cutting plane of number of thermal units and T the number of time intervals.
the dual function. Alternatively, what is so-called a
localisation set is used to substitute stabilisation schemes and The cost function of the thermal power production is
the centre of the set is analytically considered as the expressed as follows
improved dual solution. The solution of short-term hydro
scheduling using IP methods was the subject of [35]. The Fj (PS ( j, t)) aj bj PS ( j, t) cj PS2 ( j, t)
optimal or near-optimal solution of the problem was
proposed by employing a combined modelling language with The input output characteristic of a hydro plant is presented
the optimisation tool. Followed by the branch and bound by modelling the discharge rate as a function of the output
algorithm, the IP method-based solver used in this approach hydro power and the net head. Several hydro plant
was employed to improve the solution of the linear performance models have been proposed in the literature,
programming problem. The proposed solution technique was these could be found in [41, 43]. Among these models is
reported to solve the problem in an acceptable time, although Glimn Kirchmayer model [43 45] which expresses the
there was no comparison with other methods offered to discharge rate as follows
support this conclusion. Santo et al. [36] applied IP method-
based procedure to solve the UC and ED problem as a non- q( j, t) K c(h( j))f(PH ( j, t))
convex non-linear optimisation problem. A heuristic genetic
algorithm was also applied and compared to the IP method. where q( j, t) is the water discharge rate for the hydro unit j at
Their idea was to perform the iterative process while adding time interval t, c and f are two independent functions, K the
an inequality constraint at each iteration to enforce the constant of proportionality, h( j) the effective head for the
objective function to converge to a better local minimum. unit j and PH( j, t) the power generation of hydro unit j at
Reaching a better local minimum after each iteration should time interval t.
guarantee avoiding local minima at the end. While the
maximum up and down ramps were considered among the The functions c and f are expressed as quadratic functions
problem constraints in the proposed algorithm, the system and so is input output characteristic for hydro plants
losses were not included in the power balance equality. The
two algorithms were applied to both small and realistic size q( j, t) aj P 2 ( j, t) bj P( j, t) gj
systems to assess and compare their performance. Results
showed that the IP proposed method was faster than the where aj , bj and gj are the discharge coefcients for the
genetic algorithm with better feasibility of the solution. A hydro unit j.
Lagrangian relaxation and a bundling method were presented
in [3740] and used with the IP method to implement the The objective function is subject to many constraints
UC and ED problems. The IP method in this work was including the following:
employed to initialise the multipliers of the Lagrangian
relaxation approach. Results were reported to show a reduced 1. Load balance
total operating cost and a faster computation time based on
different numbers of generating units. These results were X
M X
N
stated with no comparative evidence to support them. PH ( j, t) PS ( j, t)  PD (t)  PL (t) 0
j1 j1

where M is the number of hydro units, PD(t) the system load


2.3 Hydrothermal coordination demand at time interval t and PL(t) the system total losses at
The objective in the HTC problem is to determine the time interval t.
optimal amount of hydro and thermal energy to be
generated in the scheduled period [1, 41, 42]. To solve 2. Thermal and hydro generation capacity
the HTC problem the UC and ED problems should
be optimally solved. The HTC problem is a large-scale PS ( j)min  PS ( j, t)  PS ( j)max
non-linear and complicated constrained power system
optimisation problem. Mathematically, the HTC optimisation PH ( j)min  PH ( j, t)  PH ( j)max

1024 IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029
& The Institution of Engineering and Technology 2009 doi: 10.1049/iet-gtd.2008.0573
www.ietdl.org

where PS( j)min is the minimum power generation for algorithm was tested and compared with the standard
thermal unit j, PS( j)max the maximum power generation for predictor corrector and standard log-barrier algorithms.
thermal unit j, PH( j)min the minimum power generation The tests and the comparison were performed on three
for hydro unit j and PH( j)max the maximum power medium hydrothermal coordination problems using a
generation for hydro unit j realistic power system. Results showed that the
implemented algorithm had fewer ops and better
3. Total water discharge convergence characteristics. This technique was one of the
various procedures that were implemented in many
X
T algorithms and codes such those presented in [49]. In this
Qtot ( j) q( j, t) reference, a study and comparison of the performance of
t1
various IP optimisation codes used for the optimal HTC
4. Hydraulic continuity equation were presented. The performances of the studied codes
were compared using both a small size and a realistic size
V ( j, t) V ( j, t  1) [r( j, t)  q( j, t)  s( j, t)]nt problem. The comparison was conducted based on the
solution times whereas the various codes proved to be faster
where V( j, t) is the storage volume of the reservoir i at the than the simplex-based methods. However the authors
end of time interval t, q( j, t) the water discharge rate for could not come to a conclusion regarding which of the
the hydro unit i during time interval t, r( j, t) the inow codes would be superior. The solution to the medium-term
rate into reservoir i during time interval t, s( j, t) the HTC problem in [50] was performed using both
spillage discharge rate of the reservoir i during time interval Lagrangian relaxation technique and IP method. A
t, and nt the length of time interval t. comparison of the two methods was presented and both
were found to reach to equal feasible solutions, however,
5. Water storage limits the Lagrangian relaxation algorithm was reported to be
faster. For the sake of modelling simplicity, the
Volume limits V min  V ( j, t)  V max transmission network was not taken into consideration and
all the generation units and the customer demand were
Starting volume V ( j, t)jt0 Vs assumed to be placed at a single node. In [51] the
inuence of the bilateral contracts and spot market on the
Ending volume V ( j, t)jtT VE optimal short-term HTC was considered. A primal dual
IP method was implemented to calculate the transmission
6. Water discharge rate: losses of each power transaction and to emphasise the
inuence of the loading order on the transmission losses
Flow limits q min  q( j, t)  qmax allocated to the pool and bilateral loads. Two test systems
were employed to present the results; a 6-bus system and a
Fixed discharge q( j, t) Q( j, t) 27-bus system which was assumed to be equivalent to a
specic real system. Various thermal and hydraulic
IP methods have been powerfully used to implement and constraints were considered, but yet some were not
deal with this problem. It seems that Christoforidis et al. addressed such as the down and up ramp rates. Combining
[46] were the rst who used the IP method to solve the a genetic algorithm with a primal dual IP method was the
HTC problem. They proposed a model using a commercial methodology used in [52]. In fact, in this reference the
package but there was no details presented on the determination of the on/off status of the thermal units was
methodology. However, this opened the door for applying performed using the genetic algorithm while the IP
the IP method in this area. The model implemented method was employed to solve the ED problem in order to
consisted of hydro plants, energy accounts, energy work out the short-term HTC problem. The algorithm was
transactions, frequency converters and transmission systems. tested using several realistic cases of a practical system
The transmission losses of the system were not included in consisting of 49 thermal generation units and a one
the power balance equations. The run-of-river units in the equivalent hydraulic unit. Results showed that the total
hydro plant assumed to have no accumulations and available hydraulic energy could not be used because of the
considered as storage units. A detailed modelling of the hydraulic and generation constraints. Inter-temporal
system components considered a multi-scenario approach constraints caused by cascaded reservoirs and maximum up
for random inows. A user-controlled process was and down ramps were among the considered constraints
implemented to enable selecting inow scenarios instead of while the transmission system losses were not. Including
random sampling. In [47, 48] a log-barrier primal dual IP ramps directly resulted in a higher operating cost which
algorithm which employed a clipping-off technique was was an expected impact. Genetic algorithms were also used
presented. The clipping-off technique was based on recently by Troncoso et al. [53] to compute the optimal
relaxing the bounds of the control variables in the problem. short-term HTC problem and compare its performance to
The power balance constraint considered by the algorithm that of the IP method. Improving the feasibility of the
included the unserved power but not the system losses. The solution was an important concern of the paper and the

IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029 1025
doi: 10.1049/iet-gtd.2008.0573 & The Institution of Engineering and Technology 2009
www.ietdl.org

feasibility of the constraints was secured by including some not involved. These included costs of start up and shut
heuristics. The algorithm was applied on a small size down of thermal generating units and the minimum up
system as well as a realistic generation system consisting of and down ramp rates. For simplicity, the model used only
49 thermal units and one equivalent hydro generation unit. pure quadratic cost functions for generation considering the
It was found that the genetic algorithm reached better same quadratic coefcients for all units. In a conclusion on
feasible minima while the IP method achieved better the convergence issues, the results showed that the number
performance in CPU time. It was also shown that the IP of iterations required was increased by the active bounds,
algorithm including the constraints converged without while the generation costs found to be more critical than
difculty when the problem was solved only to obtain an the transmission costs and therefore led to a faster
initialisation point. On the other hand, when the same convergence. The objective of the short-term HTC
problem was solved using the former solution, the stopping problem in [57] was to minimise the difference between
criteria needed more iterations. It should be mentioned also the generation costs and the consumer benet in a
that the constraints did not include the system power predominantly hydroelectric system. This approach
losses. As a conclusion on the results, the need to decrease considered the dynamic restrictions of the consumer energy
the computational cost of the genetic algorithm was constraints. In order to achieve that, a primal dual IP
expressed as an important issue for the real systems and as method was used and the HTC problem was treated as a
a future work to be conducted. In [54] the medium-term single problem. In the formulation, the problem was
HTC problem was solved by implementing a primal dual expressed as a HTC in the presence of price-responsive
IP method with a semi-denite programming, which is a loads to be differentiated from the usual HTC problem.
convex programming method with polynomial solution Quadratic functions were formulated to represent the
time. In this approach hydro generation was not included thermal generation costs as well as consumer benets
in the objective function as it was measured much less than together within dispatch intervals allowing cross effects
the thermal generation. The hydro characteristics of the between them. The method was rstly applied to the
system were assumed linear to help formulising the problem concentrating on the impact of price-responsive
problem as a semi-denite programming problem when loads on the system with applying a penalty term in the
included by the hydro constraints. The problem objective function to represent the energy targets. Secondly,
formulation did not, entirely, consider all the constraints it was applied using a future cost function to consider the
such as the ramp limitations and the losses effect in midterm target. Two realistic systems were used to
addition to some hydro constraints. To make it simple, the demonstrate the inuence of the price-responsive loads on
number of sub-periods for all the test cases was selected to the load distribution and the possibility of enhancing the
be 12 h, which was much shorter than the time horizon for utilisation of the available energy resources. Results showed
the typical medium-term HTC problem. In this work, only also that when the price-responsive load increased, the
non-sparse objective and constraint matrices were hydro generation consequently increased and as a result the
considered by the solver which affected the algorithm thermal generation decreased which reduced the generation
efciency when applied on larger problem sizes. Oliveira costs. Although it was mentioned that the high
et al. [55] included the transmission cost tariff in the computation time resulted by the solution of existing high-
objective function of the HTC problem. The proposed dimensional linear systems was tackled by applying some
approach was to apply a non-linear primal dual IP method measures, computational time as well as convergence
and a Benders decomposition technique. The series characteristics were not illustrated in the results. As in [51],
compensation amount and allocation problem were also the authors in [58] proposed a short-term HTC model in
considered in order to study its effect on the total cost. It which the spot market trades and the bilateral transactions
was noted that the operational cost should be considered in were discriminated. They employed a standard primal dual
the planning period in order to justify the installation of IP method to solve the hydro and thermal subproblem
series compensation. The algorithm was tested using both a whereas the dual problem was solved using a bundle
simple case study and an equivalent of a realistic system. method. An augmented Lagrangian was employed to
Results showed that the series compensation amount and achieve a better convergence for the bundle method. The
allocation were affected by considering the transmission algorithm assumed that UC status was known. Considering
tariff in the objective function. Although it was mentioned 1.0 per unit voltage magnitudes of the system, an
that the proposed methodology considered an average approximation of transmission losses was obtained from the
inow to reduce the time of computation, but neither there active power injections and included in the power balance
was information illustrated about this reduction nor about equations. The hydro power was modelled as a function of
the convergence properties of the solution. The robustness the forebay elevation and the afterbay elevation but did not
and speed of convergence of primal dual and predictor consider the ow losses and the effect of the net head and
corrector IP methods were studied in [56]. The two IP the discharge rate on the joint efciency of the turbine
methods were implemented to solve the short-term HTC generator. Jimenez and Paucar [59] used a two-step IP
problem and both reported to be robust and fast when method to solve the long-term HTC problem taking into
tested. The model considered a predominant hydro system; consideration the characteristics of multi-reservoir basins
consequently, the thermal system-related constraints were and the transmission system. The method was tested using

1026 IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029
& The Institution of Engineering and Technology 2009 doi: 10.1049/iet-gtd.2008.0573
www.ietdl.org

a practical power system. Transmission losses were included [6] FORSGREN A., GILL P.E., WRIGHT M.H. : Interior methods
in the systems demand which caused the total produced for nonlinear optimization, SIAM Rev., 2002, 44,
energy to appear rising above the systems demand. Results pp. 525 597
also showed that the system generation and the reservoir
depletion were extremely correlated with the water inow. [7] FRISCH K.R. : The logarithmic potential method of
It should be noted that there was no information offered convex programming (Institute of Economics, Oslo,
regarding the convergence properties and the time required Norway, 1955)
for the solution. In [60] a HIP method was applied to
solve the problem. The long-term bilateral contracts and [8] FIACCO A.V. , MCCORMICK G.P.: Nonlinear programming:
the forecasted market hourly prices for day-ahead auction sequential unconstrained minimization techniques, in
were integrated in the model. Many constraints were Classics Appl. Math. (SIAM, Philadelphia, PA, 1990,
considered in the model assuming that there existed a local vol. 4), reprint of the 1968 original
large reservoir for each hydro generation unit so that the
head variations were ignored. Market competition was [9] GILL P.E., MURRAY W., SAUNDERS M.A., TOMLIN J., WRIGHT M.H.:
assumed perfect and clearing prices were considered xed On projected Newton barrier methods for linear
since it was not an objective of this work to achieve programming and an equivalence to Karmarkars
maximum benets in the spot markets. Alternatively, the projective method, Math. Program., 1986, 36,
main goal of this paper is to acquire an optimal response to pp. 183 209
transactions of spot markets with day-ahead auction. The
approach was tested using both medium-size and large-size [10] QUINTANA V.H., TORRES G.L., MEDINA-PALOMO J.: Interior-point
case studies performing a comparison with simplex method. methods and their applications to power systems:
Results showed that the proposed homogeneous IP method a classication of publications and software codes, IEEE
performed faster than the simplex method. Trans. Power Syst., 2000, 15, pp. 170 176

[11] MEGIDDO N.: Pathways to the optimal set in


3 Conclusion linear programming, On progress in mathematical
programming: interior-point and related methods,
This paper presents a review of the work published on the (Springer-Verlag Inc., New York, 1989), pp. 131 158
different applications of IP methods in power system
planning and operation areas. The survey covers the period [12] MEHROTRA S.: On the implementation of the primal
from 1994 up to date. Papers dealt with optimisation dual interior point method, SIAM J. Optim., 1992, 2,
techniques using IP methods to solve the ED, UC and pp. 575 601
hydrothermal coordination problem were looked over. The
paper offers a broad-based survey of literature in order to [13] BARNES E.R.: A variation on Karmarkars algorithm for
highlight the guidelines for this ongoing eld of research. solving linear programming problems, Math. Prog., 1986,
36, pp. 174 182

4 References [14] GONZAGA C.C.: Path following methods for linear


programming, SIAM Rev., 1992, 34, pp. 167 224
[1] WOOD A.J., WOLLENBERG B.F.: Power generation operation
and control (John Wiley & Sons, Inc., New York, USA, [15] MARSTEN R.E., SALEZMAN M.J.: Implementation of a dual
1996, 2nd edn.) afne interior point algorithm for linear programming,
ORSA J. Comp., 1989, 1, pp. 287 297
[2] DEBS A.S. : Modern power systems control and
operation (Kluwer Academic Publishers, 1988) [16] SAIGAL R.: Linear programming: a modern integrated
analysis (Kluwer Academic Publishers, New York, NY, USA,
[3] MOMOH J.A., ADAPA R., EL-HAWARY M.E.: A review of selected 1995)
optimal power ow literature to 1993. I Nonlinear and
quadratic programming approaches, IEEE Trans. Power [17] TODD M.: Potential reduction methods in mathematical
Syst., 1999, 14, pp. 96 104 programming, Math. Prog., 1997, 76, pp. 3 45

[4] MOMOH J.A., EL-HAWARY M.E., ADAPA R.: A review of selected [18] WRIGHT S.J. : Primal dual interior-point methods
optimal power ow literature to 1993. II. Newton, linear (SIAM, Philadelphia, USA, 1997)
programming and interior point methods, IEEE Trans.
Power Syst., 1999, 14, pp. 105 111 [19] CLEMENTS K.A., DAVIS P.W. , FREY K.D.: An interior
point algorithm for weighted least absolute value
[5] KARMARKAR N.: A new polynomial-time algorithm for power system state estimation. IEEEPES Winter Meeting,
linear programming, Combinatorica, 1984, 4, p. 373 1991

IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029 1027
doi: 10.1049/iet-gtd.2008.0573 & The Institution of Engineering and Technology 2009
www.ietdl.org

[20] YAN X., QUINTANA V.H.: An efcient predictor corrector [33] WANG S.J. , SHAHIDEHPOUR S.M. , KIRSCHEN D.S. , MOKHTARI S. ,
interior point algorithm for security-constrained economic IRISARRI G.D. :
Short-term generation scheduling with
dispatch, IEEE Trans. Power Syst., 1997, 12, pp. 803 810 transmission and environmental constraints using an
augmented Lagrangian relaxation, IEEE Trans. Power Syst.,
[21] IRISARRI G., KIMBALL L.M., CLEMENTS K.A., BAGCHI A., DAVIS P.W.: 1995, 10, pp. 1294 1301
Economic dispatch with network and ramping constraints
via interior point methods, IEEE Trans. Power Syst., 1998, [34] MADRIGAL M., QUINTANA V.H.: An interior-point/cutting-
13, pp. 236 242 plane method to solve unit commitment problems, IEEE
Trans. Power Syst., 2000, 15, pp. 1022 1027
[22] TANIMOTO M., IZUI Y., HIROSE K. , NAKAMURA S.: Advanced
economic dispatching control algorithm using dynamic [35] CHANG G.W., AGANAGIC M., WAIGHT J.G., ET AL .: Experiences
unit model and interior point method. Fourth Int. Conf. with mixed integer linear programming based
on Advances in Power System Control, Operation and approaches, IEEE Trans. Power Syst., 2001, 16, pp. 743 749
Management, 1997, APSCOM-97 (Conf. Publ. no. 450),
1997, vol. 2, pp. 79 801 [36] SANTOS J.R., RAMOS J.L.M., LORA A.T., GOMEZ-EXPOSITO A. :
Finding improved local minima of power system
[23] JABR R.A. , COONICK A.H.: Homogeneous interior point optimization problems by interior-point methods, IEEE
method for constrained power scheduling, IEE Proc. Power Eng. Rev., 2002, 22, pp. 60 60
Gener. Transm. Distrib., 2000, 147, pp. 239 244
[37] HAMDAN N., AHMED M.M., HASSAN I.: New concepts of costs
[24] JABR R.A., COONICK A.H., CORY B.J.: A homogeneous linear optimization for thermal scheduling. Proc. National Power
programming algorithm for the security constrained and Energy Conf., 2003 (PECon 2003), 2003, pp. 200 204
economic dispatch problem, IEEE Trans. Power Syst.,
2000, 15, pp. 930 936 [38] HAMDAN N., AHMED M.M., HASSAN I.: Costs optimization for
unit commitment and economic load dispatch in large scale
[25] JABR R.A., COONICK A.H., CORY B.J. : A study of the power systems. Proc. National Power and Energy Conf.,
homogeneous algorithm for dynamic economic dispatch 2004 (PECon 2004), 2004, pp. 190 194
with network constraints and transmission losses, IEEE
Trans. Power Syst., 2000, 15, pp. 605 611 [39] HAMDAN N., AHMED M.M., HASSAN I.: New costs
optimization concepts for unit commitment and economic
[26] JABR R.A.: Homogeneous cutting-plane method to solve load dispatch in large scale power systems. 2004 IEEE
the security-constrained economic dispatching problem, Region 10 Conf., 2004 (TENCON 2004), vols. C and 3,
IEE Proc. Gener. Transm. Distrib., 2002, 149, pp. 139 144 pp. 480 483

[27] JABR R.A., COONICK A.H., CORY B.J.: A primal-dual interior [40] AHMED M.M., HASSAN I. , HAMDAN N. : New concepts of
point method for optimal power ow dispatching, IEEE optimizing unit commitment and economic load dispatch
Trans. Power Syst., 2002, 17, pp. 654 662 costs in large scale power systems. Proc. Student Conf.
on Research and Development, 2003 (SCORED 2003),
[28] FERNANDES T.S.P., ALMEIDA K.C.: A methodology for optimal 2003, pp. 407 412
power dispatch under a pool-bilateral market, IEEE Trans.
Power Syst., 2003, 18, pp. 182 190 [41] EL-HAWARY M.E., CHRISTENSEN G.S.: Optimal economic
operation of electric power systems (Academic Press,
[29] JABR R.A.: Exploiting special structure in interior-point New York, 1979)
algorithms for power generation dispatching, Int. J. Electr.
Power Energy Syst., 2004, 26, pp. 65 71 [42] CHRISTENSEN G.S., EL-HAWARY M.E., SOLIMAN S.A.: Optimal
control application in electric power systems (Springer,
[30] YAMIN H. , AL-AGTASH S. , SHAHIDEHPOUR M.: Security- 1987)
constrained optimal generation scheduling for GENCOs,
IEEE Trans. Power Syst., 2004, 19, pp. 1365 1372 [43] KOTHARI D.J., DHILLON J.S.: Power system optimization
(Prentice-Hall of India Pvt. Ltd, New Delhi, India, 2004)
[31] KIM K.S., JUNG L.H., LEE S.C., MOON U.C.: Security constrained
economic dispatch using interior point method. Int. Conf. [44] EL-HAWARY M.E., TSANG D.H.: The hydrothermal optimal
on Power System Technology, 2006 (PowerCon 2006), load ow, a practical formulation and solution techniques
2006, pp. 1 6 using Newtons approach, IEEE Trans. Power Syst., 1986,
1, pp. 157 166
[32] HAN X.S., GOOI H.B.: Effective economic dispatch model
and algorithm, Int. J. Electr. Power Energy Syst., 2007, 29, [45] EL-HAWARY M.E., RAVINDRANATH K.M.: Optimal operation
pp. 113 120 of variable head hydro-thermal systems using the

1028 IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029
& The Institution of Engineering and Technology 2009 doi: 10.1049/iet-gtd.2008.0573
www.ietdl.org

Glimn Kirchmayer model and the Newton Raphson nonlinear programming and genetic algorithms. Power
method, Electr. Power Syst. Res., 1988, 14, pp. 11 22 Tech Proc., 2001 (IEEE Porto, 2001), vol. 3, p. 6

[46] CHRISTOFORIDIS M., AGANAGIC M., AWOBAMISE B., TONG S., RAHIMI [53] TRONCOSO A., RIQUELME J.C., AGUILAR-RUIZ J.S., RIQUELME SANTOS
A.F. :
Long-term/mid-term resource optimization of a J.M.: Evolutionary techniques applied to the optimal short-
hydrodominant power system using interior term scheduling of the electrical energy production,
point method, IEEE Trans. Power Syst., 1996, 11, Eur. J. Oper. Res., 2008, 185, pp. 1114 1127
pp. 287 294
[54] FUENTES-LOYOLA R., QUINTANA V.H.: Medium-term
[47] MEDINA J., QUINTANA V.H., CONEJO A.J.: A new clipping-off hydrothermal coordination by semidenite programming,
interior-point algorithm to solve the medium-term hydro- IEEE Trans. Power Syst., 2003, 18, pp. 1515 1522
thermal coordination problem. IEEE 1997 Canadian Conf.
on Electrical and Computer Engineering, 1997, vol. 1, [55] DE OLIVEIRA E.J., PEREIRA J.L.R., JUNIOR I.C.S., PAULO A.N.G. :
pp. 285 288 Wheeling cost inuence in hydrothermal dispatch and
series compensation allocation, Int. J. Electr. Power
[48] MEDINA J., QUINTANA V.H., CONEJO A.J.: A clipping-off interior- Energy Syst., 2004, 26, pp. 97 102
point technique for medium-term hydro-thermal
coordination, IEEE Trans. Power Syst., 1999, 14, [56] OLIVEIRA A.R.L. , SOARES S., NEPOMUCENO L. : Short term
pp. 266 273 hydroelectric scheduling combining network ow and
interior point approaches, Int. J. Electr. Power Energy
[49] MEDINA J., QUINTANA V.H., CONEJO A.J., THODEN F.P. : A Syst., 2005, 27, pp. 91 99
comparison of interior-point codes for medium-term
hydro-thermal coordination, IEEE Trans. Power Syst., [57] UTURBEY W., COSTA A.S.: Dynamic optimal power ow
1998, 13, pp. 836 843 approach to account for consumer response in short term
hydrothermal coordination studies, IET Gener. Transm.
[50] FUENTES-LOYOLA R. , MADRIGAL M. , QUINTANA V.H. : A Distrib., 2007, 1, pp. 414 421
performance comparison of a primal dual interior point
method vs. Lagrangian relaxation to solve the medium [58] MEZGER A.J., DE ALMEIDA K.C.: Short term hydrothermal
term hydro-thermal coordination problem. IEEE Power scheduling with bilateral transactions via bundle method,
Engineering Society Summer Meeting, 2000, vol. 4, Int. J. Electr. Power Energy Syst., 2007, 29, pp. 387 396
pp. 2255 2260
[59] JIMENEZ R.W., PAUCAR V.L.: Long term hydrothermal
[51] PALACIO N.J.O. , ALMEIDA K.C., ZURN H.H.: Short scheduling linear programming model for large scale
term hydrothermal scheduling under bilateral contracts. power systems. 2007 Large Engineering Systems Conf. on
Power Tech Proceedings, 2001 (IEEE Porto, 2001), vol. 1, Power Engineering, 2007, pp. 96 100
p. 6
[60] BISANOVIC S. , HAJRO M. , DLAKIC M. : Hydrothermal self-
[52] RAMOS J.L.M., LORA A.T., SANTOS J.R., EXPOSITO A.G.: Short-term scheduling problem in a day-ahead electricity market,
hydro-thermal coordination based on interior point Electr. Power Syst. Res., 2008, 78, pp. 1579 1596

IET Gener. Transm. Distrib., 2009, Vol. 3, Iss. 11, pp. 1020 1029 1029
doi: 10.1049/iet-gtd.2008.0573 & The Institution of Engineering and Technology 2009

Anda mungkin juga menyukai