Tea break
Precautions before and after RDU Installation Connecting UDA Cable
Tools required for RDU Installation Connecting GPS Cable CNT-400
Ruggedized DU Installation (Horizontal Mounting at ODC Site) Connecting GPS Cable RG-316D
Rack Layout and MCB Allocations Color Banding of CPRI Cables
Cage-Nut Jig and Marking ATP-11A Process/ATP-11B Process
Installing Support Rail Installation Pictures of RDU at ODC Site
Mounting RDU Installation Pictures of RDU at GBM Site
Ruggedized DU Installation (Vertical Mounting at GBM Site) MCB Requirement for RDU Installation
Cage-Nut Jig and Marking Electrical Precautions before MCB Replacement
Mounting RDU RJIL Approved MCB Shelfs
RFE Survey for MCB Replacements
Method 1: MCB Replacement Procedure without power off
Method 2: MCB Replacement Procedure with power off
1.2 25th October 2016 Suresh Krishnamurthy Added RACK Layout and MCB Shelf
Samsung Training Team Allocations
9
Specifications of CDU and RDU
Items CDU RDU
Weight (kg) < 15 (full configuration) < 23 kg (LMD, LCC2x1), < 34.5 kg (LMD, LCC2x3)
Number of Fan 3 6
Surge Protector External surge protector required Included (External surge protector not required)
protection)
176 mm
(4U Height)
[Rear View]
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 13
RDU Processor Boards
The 4U RDU Chassis comes with Power Module in built with SPD (Surge Protection Device)
Two Fan Modules FANM-C4C are inserted as shown in the diagram.
The improved FAN Module has 3 FAN units
The system boards are ruggedized and IP50 dust protected hence no Air Filter is needed
Two types are System Boards are available as of now
LMD1 Processor Board
LCC2 Channel Assembly Board with 4 Bands support and 3 sectors each
Dummy Units are Inserted when no Channel Assembly cards (LCC2) are fitted to prevent dust from entering
LCC2
LMD1
Dummy Unit
LCC2
Dummy Unit
LMD1
CLK0
Ground CLK1 GNSS
Terminal UDA BH 2(1G/10G)
BH 0 BH 1(1G)
ETH ALM
LMT
Legend: BH 1: Backhaul Link 1 (1G)
Ports on LMD1 BH 2: Backhaul Link 2 (1G/10G)
CLK0: Clock 0 GNSS: Global Navigational Satellite System
CLK1: Clock 1 Ports on LCC2
UDA: User Defined Alarm CPRI: Common Protocol Radio Interface from RRH
ALM: Alarm SRIO: Single Radio Input Output Port
ETH: Ethernet Main RDU Chassis
LMT: Local Management Terminal DC Power: DC -48V Power Connection
BH 0: Backhaul Link 0 Ground Terminal: Grounding Twin Terminal
RDU-RRU Interface CPRI 4.1 (Optic 4.9 Gbps) CPRI 4.1 (Optic 4.9 Gbps) CPRI 4.1 (Optic 4.9 Gbps)
Holdover (hour) 24 24 24
Heating Gun
11 50~300C Shrinking Feeder cable tube
Cable Cutter
13 6~32 mm Cable cutting
Crimping Tool
14 1.5~16 mm2 Pressure terminal for crimping
LAN Tool
17 Basic Tool RJ45 Crimper
Industrial Scissor
18 Basic Tool Cutting
Knife
19 Basic Tool Cutting
24 Rope/Pulley 50 m, 100 m/3 in. 4 in. 5 in. Pull up the Antenna & eNB Unit
25 Digital Camera over the five million pixels Take a picture all installation point
Helmet/Safety
26 Common Basic Safety Equipment
Shoes
50 2.0 1200 mm,
27 Safety Belt Basic Safety Equipment
W/Simple buckle
Post off limit signs in areas The power must not be cut off Remove any debris
where accidents are most during replacement or addition of produced during the work
expected. the channel card in operating and clean up the installation
system. site.
With guardrails or fences, block Be careful not to damage or
open areas such as connecting scratch the boards mounted on the
parts, roof, and scaffold. system and the cables among the
boards when the system is
transported or installed.
No of Shelfs N/A ODC Location Ground Shelter Location N/A Site incharge's Name Sanjay Sawant
( 1U Gap)
Aligning the Cage Nut Jig Marking 6 Locations for Cage Nuts
(6 Left + 6 Right = 12)
M6 SEMS
1 3
5 7
8 6
4 2
Support Rail
Power
Height 4U
LCC2
1 U Gap
1 U Gap
RDU (4U)
Cage Nut
2 6 7 4
M6 SEMS
A. Mount Ruggedized DU
3 8 5 1
Power
Air IN Connector
Bottom
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 33
Ruggedized DU (RDU)
Connecting Cables
UDA Cable
GPS Receiver
[GPS Arrestor]
2) GPS Arrestor
Ground Cable
Rectifier External
(DCDBPanel) Alarm Device [Switch/Router]
1) Ground Cable
From To Cable
Category Details
Terminal IGB/MGB and RDU Grounding Terminal
Ground Cable
Specifications and F-GV 4 mm2 2 to 5 meters approximate
approx. length
IGB/MGB
Pressure Terminal
M6 SEMS(Hex. +)
Ground Cable
IGB/MGB
Ground Cable
GPS Arrestor
6 mm2 Pressure
Terminal GPS Arrestor Ground Cable
RDU, to
Power Cable 4 mm2, 2C
(DCDB Panel) Black Cable RTN
A1 (White) -48 V DC
Connector RDU Standard Connector fits in RDU Power Port
A2 (Black) RTN
Hand Tools Cable Cutter, Wire Stripper, Crimping tool, Heating Gun, Nipper
Power Connector
Category Details
Optical modules and cables used in flows to the laser beam emitting light and
when the eyes are exposed to the laser beam of the optical fiber so it causes
serious injury to eyes, be handled with extreme caution.
Backhaul Connector
(DLC/UPC)
Latch of
Connector Backhaul Cable
(Single Mode)
Category Details
850MHz/1.8GHz/2.3 GHz RRU~RDU_LCC2_ Ports L0~L8
Ports
[Note: Ports L9~L11 is for 2.5 GHz]
Cable Type Optic Cable (Single Mode,Outdoor Type)
RDU_LCC2_L0~L8 Port DLC/UPC
Cable/Port 850MHz RRU PDLC, DLC/PC (JONHON, PDLC03J-02)
Specifications 1.8GHz RRU PDLC, DLC/PC (JONHON, PDLC03J-02)
2.3GHz RRU PDLC, DLC/PC (JONHON, PDLC03J-02)
Hand Tools Optic Connector Cleaner
Dust
Cap
CPRI Connector
(DLC/UPC)
Latch of
Connector
CPRI Cable
(Single Mode, Outdoor)
CPRI Cable
1800 MHz RRUs
(// Sectors)
Dust
Cap
CPRI Port
(1.8 GHz RRU : L3~L5)
CPRI Connector
(DLC/UPC)
Latch of
Connector
CPRI Cable
(Single Mode,
Outdoor)
CPRI Cable
2300 MHz RRUs
(// Sectors)
Dust
Cap
CPRI
Connector
(DLC/UPC)
Latch of
Connector
CPRI Cable
(Single Mode,
Outdoor)
UDA Cable
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 54
8. UDA Cable Connection Pin Details
Port Index Label Name Pin-Map Port Index Label Name (Input) Pin-Map
(Input)
ALARM_IN0_CO
1 ALARM_IN6_COM 13
RX0 M RX6 (Door Open)
ALARM_IN0_NC 36 ALARM_IN6_NC 48
ALARM_IN1_CO
3 ALARM_IN7_COM 15
RX1 M RX7 (AC/DC SPD)
ALARM_IN1_NC 38 ALARM_IN7_NC 50
ALARM_IN2_CO
5 ALARM_IN8_COM 17
RX2 M RX8 (FAN Fault)
ALARM_IN2_NC 40 ALARM_IN8_NC 52
ALARM_IN3_CO
RX3 (AC input 7 E_UDA_NO_OUT2 26
M
Fail)
ALARM_IN3_NC 42 TX0 E_UDA_C_OUT2 27
ALARM_IN4_CO
RX4 (Rectifier 9 E_UDA_NC_OUT2 28
M
Fail)
ALARM_IN4_NC 44 E_UDA_NO_OUT3 60
ALARM_IN5_CO
RX5 (Battery 11 TX1 E_UDA_C_OUT3 61
M
Low)
ALARM_IN5_NC 46 E_UDA_NC_OUT3 62
UDA Cable
External Alarm Device
UDA
Connector
UDA Cable
Assembly
Category Deatils
Cable Connections between RDU ~ GPS Arrestor ~GPS
CABLES
Antenna
RDU ~ GPS Arrestor RG-316D
Types of Cables
GPS Arrestor ~ GPS Antenna CNT-400
RDU SMA-Male
GPS Arrestor N Type-Male
Connector Types
Line Amplifier N Type-Male
GPS Antenna TNC-Male
SMA-Male 6 kgfcm
Torque for fixing N Type-Male 20 kgfcm
TNC-Male 9 kgfcm
Cable Cutter, Wire Stripper, Nipper, Torque Wrench
Hand Tools (4~20kgfcm), Torque Wrench Spanner head (Hex. Bolt Head:
8, 19mm), Spanner(8, 19mm), Knife
If you do not comply with the minimum cable bending radius and length restrictions, failure
to receive a GPS signal system can smoothly this does not work properly. Therefore, the
minimum distance radius of curvature GPS cables and limits must comply
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 60
9. GPS Cable: GPS Antenna to Arrestor : CNT-400
RDU
GPS Antenna
GPS Arrestor
GPS Cable
(CNT-400)
1 2 3
GPS Antenna
TNC-Female Port Clamp
Fixing Screw GPS Mounting
TNC-Male Connector Bracket
Clamp
GPS Cable
(Antenna~Arrestor)
GPS Antenna
Fixing Pipe GPS Cable
GPS Mounting
(CNT-400) Bracket Clamp
M6 SEMS
RDU
GPS Antenna
GPS Arrestor
GPS Cable
(CNT-400)
4 5
200mm or more
Steel Band
Steel Band
RTT/GBT
Angle
Steel Band
Angle: Scenario 1
Nut/Screw
Assembly RTT/GBT
Angle
Steel Band
Angle: Scenario 2
Nut/Screw
Assembly
RTT/GBT
Angle
RDU
GPS Antenna
GPS Arrestor
GPS Cable
(CNT-400)
GPS Arrestor
Grounding
GPS Cable(CNT-400)
GPS Cable(RG-316D)
GPS Arrestor
GPS Cable from GPS Antenna
(CNT-400)
Grounding
GPS Cable
(RG-316D) to RDU
GPS Connector
(SMA-Male)
GPS Cable(RG-316D)
X LMD1
X LCC2
X FANM-C4C
X 2
X Not Required
X 1
X 9
X
LMD1 Sl. No.
Downlink Throughput
Uplink Throughput
Internet Browsing
K-touch (LTE smartphone) with Siteforge and Net Velocity android apps installed in it,
serves this purpose of ATP11B with minimum human intervention
Space for
Additional Rack
Rack-1 MCBs
Rack-2 MCBs
RJIL Doc Reference: SLD For RT,GBT with 16kw SMPS10070-E51-XX-XXXX-XXXX-ENB-0000-209 R6-Model
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 75
Own Built: Rack 2 Exploded View of MCB-RDU-CSS
Rack-1 Rack-2
1 U Gap
Rack-2
1 U Gap
4 U RDU (BBU)
Rack-1 MCBs
Rack-2 MCBs
Rack-1 MCBs
Rack-2 MCBs
B
Rack-2
Rack-1 MCBs
Rack-2 MCBs
RJIL Doc Reference: SLD For COLO Indoor & Outdoor 10070-E51-XX-XXXX-XXXX-ENB-0000-102 R3
Rack-1
Marking to
fit cage
nuts
Front Side (Right Bracket) Rear Side (Left Bracket) Left Bracket Right Bracket
3 1
7 5
6 8
2 4
3 Support Rails 1
2 4
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 89
No Roxtec needed for New L&T Rack
New Rack
without Roxtec
LMD 1
LCC2
Dummy
LCC2
RDU Power ON
Circuit LCC2
Breaker
(32A) New Back Board
LCC2
Rectifier
supports LCC2
SPD function LMD
Current Capacity : 32A
SPD: Surge Protection Device
Existing 16A circuit breaker need to be replaced with 32A circuit breaker
Before After
Caution
Never Touch the MCB Feeder Bus Bar Touch ONLY MCB while
with Bare Hands Removing/Fixing
X
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 106
RJIL Approved MCB Shelfs
+ Ve RTN to Equipments
63A 32A 16A 16A 10A 16A 16A 6A 16A 16A 16A 16A 6A 10A 32A 63A
- 48 V to Equipments - 48 V to Equipments
-48V DC from Rectifier + Ve RTN from Rectifier -48V DC from Rectifier
63A + 32 A Input = 95 Amps Input (Left) 63A + 32 A Input = 95 Amps Input (Right)
6 MCBs Max of 16 A = 96 Amps Output (Left) 6 MCBs Max of 16 A = 96 Amps Output (Right)
DC Rectifier (SMPS)
Min 10mm Gap needed for individual MCB Removal without Power OFF Bus-Bar Comb Length
about 15 mm
Front View
X Top View X Top View
CAUTION:
Fix only Schneider MCB in Schneider MCB Shelf
Fix only L&T MCBs in L&T MCB Shelf
Samsung Electronics. All Rights Reserved. Confidential and Proprietary. 111
RFE Survey Points Related to MCB Replacement
M6 Screw
Mounting Frame
Standard MCB
MCB (16 A) ON
OFF
Lock
Plastic Notch
M6 Screw
M6 Screw
UnLock
1
OFF
Lock
Plastic Notch
2
4
UnLock M6 Screw
M6 Screw
7 3 5
Power Cable -48V Power Cable +Ve RTN
To CDU (Output -48V)
9
Mounting Frame
Mounting Frame
Standard MCB
Standard MCB
10
11
Mounting Frame
Mounting Frame
Standard MCB
Standard MCB
MCB Replacement Steps
10. Tilt the Bottom of MCB Little MORE MCB Replacement Steps
Towards You 11. Pull DOWN the MCB Completely from the MCB Assembly
13
12
Mounting Frame
Mounting Frame
Standard MCB
Standard MCB
14
Mounting Frame
Mounting Frame
Standard MCB
Standard MCB
15
MCB (32 A) ON
OFF
Lock
Plastic Notch
21
19
UnLock M6 Screw
M6 Screw
16 20
To CDU (Output -48V) 18 32 A Rating New Power Cable +Ve RTN
32 A Rating New Power Cable -48V
M6 Screw
Mounting Frame
Standard MCB
MCB (32 A) ON
OFF
Lock
Plastic Notch
M6 Screw
M6 Screw
UnLock
32 A Rating New Power Cable +Ve RTN
3. Power OFF Input -48V to MCB Shelf from Rectifier (63 A and 32 A) on both sides
128
Samsung Electronics. All Rights Reserved. Confidential and Proprietary.
Method-2 Replacing MCB with Main Feeder Power OFF
14. Push UP the MCB (32 A) Completely 19. Fix the Feeder Bus Bar Screw of all MCBs
Towards the Bus Bar
Mounting Frame
Standard MCB
23. Fix the -48 V Screw for RDU MCB (32 A) ON