TAMILNADU TRANSMISSION CORPORATION LIMITED

110 KV SC line on SC towers with Panther conductor.


Sl. No. QTY UNIT DESCRIPTION Rate in Rs. Per Amount in Rs.
1 Galvanised steel tower materials with
extension part wherever necessary, and
bolts and nutsetc.,

a 114.72 MT a. MS 100% 74453.00 MT 8541248.16


b 7.58 MT b. Ordinary Bolts & nuts 121543.00 MT 921295.94
2 600 No. 90 KN Disc Insulators 420.00 No. 252000.00
3 1029 No. 120 KN Disc Insulators 578.00 No. 594762.00
Conductor & Earth wire accessories
4 60 Set Single Suspension fittings for ACSR
Panther 1299.00 Set 77940.00
5 12 Set Sus.fittings for Jumper 1299.00 Set 15588.00
6 120 Set Single Tension fittings for ACSR
Panther 1850.00 Set 222000.00
7 6 Set Double Tension Fittings for Panther 2246.00 Set 13476.00
8 120 Set Vibration Damper for Panther 814.00 Set 97680.00
9 15 Set Mid span comp.joint for ACSR Panther
525.00 Set 7875.00
10 10 Set Repair sleeve for ACSR Panther 420.00 Set 4200.00
11 60 Set PA rod for Panther 840.00 Set 50400.00
12 20 Set Suspension clamp for Earth wire
7/3.55mm 545.00 No. 10900.00
13 40 Set Tension Clamp for Earth wire 7/3.55mm
539.00 Set 21560.00
14 5 Set Mid span comp.joint for GS Earth wire
7/3.15mm 0.3 No. per 1 KM RL 226.00 Set 1130.00
15 60 Set Alu.Earthbond 231.00 No. 13860.00
16 30.3 KM ACSR PANTHER conductors 1.0% sag
155917.00 KM 4724285.10
17 10.15 KM GI EARTH WIRE 7/3.55mm 1.5% sag 76514.00 KM 776617.10
Earthing materials
18 40 No. Pipe type earthing 4112.00 No. 164480.00
19 2 No. Counter poise earthing (120m length) 12800.00 No. 25600.00
Tower Accessories
20 40 No. Number plate 327.00 No. 13080.00
21 40 No. Danger Board 437.00 No. 17480.00
22 20 No. Phase plate( Set of three) 447.00 No. 8940.00
23 20 No. Circuit plate 397.00 No. 7940.00
24 TOTAL COST OF MATERIALS 16584337.30
TOWER FOUNDATIONS
25 20 No. PA type tower 51884.14 No. 1037682.72
0 to 2 Suspension tower
26 8 No. PB type tower 71371.20 No. 570969.60
2 to 30 Medium angle tower
27 12 No. PC type tower 119902.80 No. 1438833.60
TAMILNADU TRANSMISSION CORPORATION LIMITED
110 KV SC line on SC towers with Panther conductor.
Sl. No. QTY UNIT DESCRIPTION Rate in Rs. Per Amount in Rs.
30 to 60 High angle & Dead end tower
28 Tower protection works 500000.00
29 TOTAL COST OF FOUNDATION WORKS 3547485.92
30 Erection charges(10% on Item 24 & 29) 2013182.32
(10% on Item 24)
31 10 KM Tree/Crop compensation 1000000 KM 10000000.00
32 Service Tax 5.8 % on Foundation & 14.5
% Erection Charges 497665.62

33 Labour Welfare Fund 1.0% on


Foundation & Erection Charges 55606.68

34 Transportation charges (5% on Item 24)


829216.87
35 Insurance at 1%, Central & State Sales

Tax at 4%-(Total 5% on materials) 829216.87


36 Contingencies (1% on item 24, 29 & 30)
221450.06
37 Total Cost of materials & Foundation
and Erection charges but excluding
CST, Service tax & LWF 33195672.46
38 Establishment & Supervision Charges
at 15.0% on item 37 4979350.87
39 Total Cost of materials & Foundation
and Erection charges including CST,
Service tax & LWF 34578161.63
TOTAL COST (Item 38 & 39) 10 KM 39557512.50
TOTAL COST PER 1 KM 3955751.25
(Rounding to nearest 1000) SAY 3956000.00
TOTAL COST PER 1 KM IN LAKHS 39.56
TAMILNADU TRANSMISSION CORPORATION LIMITED
110 KV SC line on DC towers with Panther conductor.
Sl. No. QTY Unit DESCRIPTION Rate in Rs. Per Amount in Rs.
1 Galvanised steel tower materials with
extension part wherever necessary,
and bolts and nutsetc.,
a 244.95 MT b) MS 100% 74453.00 MT 18237262.35
b 15.17 MT c) Ordinary Bolts & nuts 121543.00 MT 1843953.16
2 686 No. 90 KN Disc Insulators 420.00 No. 288120.00
3 1029 No. 120 KN Disc Insulators 578.00 No. 594762.00
Conductor & Earth wire accessories
4 60 Set Single Suspension fittings for ACSR
Panther 1299.00 Set 77940.00
36 Set Suspension fitting for jumper 1299.00 Set 46764.00
5 120 Set Single Tension fittings for ACSR
Panther 1850.00 Set 222000.00
6 6 Set Double Tension Fittings for Panther 2246.00 Set 13476.00
7 120 Set Vibration Damper for Panther 814.00 Set 97680.00
8 15 Set Mid span comp.joint for ACSR Panther
525.00 Set 7875.00
9 10 Set Repair sleeve for ACSR Panther 420.00 Set 4200.00
10 60 Set PA rod for Panther 840.00 Set 50400.00
11 20 Set Suspension clamp for Earth wire
7/3.55mm 545.00 No. 10900.00
12 40 Set Tension Clamp for Earth wire
7/3.55mm 539.00 Set 21560.00
13 5 Set Mid span comp.joint for GS Earth wire
7/3.55mm 0.3 No. per 1 KM RL
226.00 Set 1130.00
14 60 Set Aluminium earth bond 231.00 No. 13860.00
15 30.3 KM ACSR PANTHER conductors 1.0%
sag 155917.00 KM 4724285.10
16 10.15 KM GI EARTH WIRE 7/3.55mm 1.5% sag
76514.00 KM 776617.10
Earthing materials
17 40 No. Pipe type earthing 4112.00 No. 164480.00
18 Counter poise earthing (120m length)
2 No. 12800.00 No. 25600.00
Tower Accessories
19 40 No. Number plate 327.00 No. 13080.00
20 40 No. Danger Board 437.00 No. 17480.00
21 20 No. Phase plate( Set of three) 447.00 No. 8940.00
22 20 No. Circuit plate 397.00 No. 7940.00
23 TOTAL COST OF MATERIALS 27270304.71
TOWER FOUNDATIONS
24 20 No. GC type tower 78267.02 No. 1565340.36
TAMILNADU TRANSMISSION CORPORATION LIMITED
110 KV SC line on DC towers with Panther conductor.
Sl. No. QTY Unit DESCRIPTION Rate in Rs. Per Amount in Rs.
0 to 2 Suspension tower
25 8 No. HC type tower 187512.25 No. 1500098.00
2 to 30 Medium angle tower
26 12 No. KC type tower 240120.70 No. 2881448.40
30 to 60 High angle & Dead end
tower
27 Tower protection works 500000.00
28 COST OF FOUNDATION 6446886.76
29 Total Cost of materials & Foundation
33717191.47
(adding Item 23 & 28)
30 Erection charges(10% on item 29) 3371719.15
31 10 KM Tree/Crop compensation 1000000.00 KM 10000000.00
32 Service Tax 5.8 % on Foundation &
14.5 % Erection Charges 862818.71
(Adding item 27 to 28)
33 Labour Welfare Fund 1.0% on
Foundation & Erection Charges 98186.06
(Adding item 27 to28)
34 Transportation charges (5% on Item
23) 1363515.24
35 Insurance at 1%, Central & State
Sales Tax at 4%-(Total 5% on Item
29) 1363515.24
36 Contingencies (1% on materials &
erection charges) 484524.26
37 Total Cost of materials & labour but
excluding taxes 48936950.11
38 Establishment & Supervision
Charges at 15.0% on item 37 7340542.52
TOTAL COST PER 10 KM 58602012.63
TOTAL COST PER 1 KM 5860201.2632886
(Rounding to nearest 1000) SAY 5861000.00
TOTAL COST PER 1 KM IN LAKHS 58.61
TAMILNADU TRANSMISSION CORPORATION LIMITED
110 KV DC line on DC Towers with Panther conductor
Sl. Amount in Rs.
Quantity DESCRIPTION Rate in Rs. Per
No.
1 Galvanised steel tower materials
with extension part wherever
necessary, and bolts and nuts etc.,
a 244.95 MT b) MS 100% 74453.00 MT 18237262.35
b 15.47 MT c) Ordinary Bolts & nuts 121543.00 MT 1880270.21
2 1111.00 No. 90 KN Disc Insulators 420.00 No. 466620.00
3 2057.00 No. 120 KN Disc Insulators 578.00 No. 1188946.00

Conductor & Earth wire accessories


4 120 Set Single Suspension fittings for ACSR
Panther 1299.00 Set 155880.00
5 36 Set Sus.fittings for Jumper 1299.00 Set 46764.00
6 240 Set Single Tension fittings for ACSR
Panther 1850.00 Set 444000.00
7 12 Set Double Tension Fittings for Panther 2246.00 Set 26952.00
8 240 Set Vibration Damper for Panther 814.00 Set 195360.00
9 30 Set Mid span comp.joint for ACSR
Panther 525.00 Set 15750.00
10 10 Set Repair sleeve for ACSR Panther 420.00 Set 4200.00
11 120 Set PA Rod for Panther 840.00 Set 100800.00
12 20 Set Suspension clamp for Earth wire
7/3.55mm 545.00 No. 10900.00
13 40 Set Tension Clamp for Earth wire
7/3.55mm 539.00 Set 21560.00
14 5 Set Mid span comp.joint for GS Earth

wire 7/3.55mm 0.3 No. per 1 KM RL 226.00 Set 1130.00


15 60 Set Aluminium earth bond 231.00 No. 13860.00
16 60.6 KM ACSR PANTHER conductors 1.0%
sag 155917.00 KM 9448570.20
17 10.15 KM GI EARTH WIRE 7/3.55mm 1.5%
sag 76514.00 KM 776617.10
Earthing materials
18 40 No. Pipe type earthing 4112.00 No. 164480.00
Counter poise earthing (120m
19 2 No. length) 12800.00 No. 25600.00
Tower Accessories
20 40 No. Number plate 327.00 No. 13080.00
21 40 No. Danger Board 437.00 No. 17480.00
22 40 No. Phase plate( Set of three) 447.00 No. 17880.00
23 40 No. Circuit plate 397.00 No. 15880.00
24 Total Cost of materials 33289841.86
TOWER FOUNDATIONS
25 20 No. GC type tower 78267.02 No. 1565340.36
0 to 2 Suspension tower
TAMILNADU TRANSMISSION CORPORATION LIMITED
110 KV DC line on DC Towers with Panther conductor
Sl. Amount in Rs.
Quantity DESCRIPTION Rate in Rs. Per
No.
26 8 No. HC type tower 187512.25 No. 1500098.00
2 to 30 Medium angle tower
TAMILNADU TRANSMISSION CORPORATION LIMITED
110 KV DC line on DC Towers with Panther conductor
Sl. Amount in Rs.
Quantity DESCRIPTION Rate in Rs. Per
No.
27 12 No. KC type tower 240120.70 No. 2881448.40
30 to 60 High angle & Dead end
tower
28 Tower protection works 500000.00
29 Total Cost of Foundations 6446886.76
Erection charges(10% on item 24 &
30 29 ) 3973672.86
31 10 KM Tree/Crop compensation 1000000.00 KM 10000000.00
Service Tax 5.8 % on Foundation &
32 14.5 % Erection Charges 950102.00
Labour Welfare Fund 1.0% on
33 Foundation & Erection Charges 104206.00

Transportation charges (5% on Item


34 24) 1664492.09
Insurance at 1%, Central & State
Sales Tax at 4%-(Total 5% on Item 1
35 to 23) 1664492.09
Contingencies (1% on Materials,
36 Foundation &erection charges) 437104.01
Total Cost of materials & Foundation
and Erection charges but excluding
37 CST, Service tax & LWF 55811997.59
Establishment & Supervision
38 Charges at 15.0% on item 37 8371800.00
Total Cost of materials, Foundation
and Erection charges including
39 CST, Service tax & LWF 58530797.68

40 TOTAL COST (Item 38 & 39) 10 KM 66902597.68


TOTAL COST PER 1 KM 6690259.77
(Rounding to nearest 1000) SAY 6691000.00
TOTAL COST /KM in LAKHS 66.91