ANALISA HARGA SATUAN

KODE ANALISA : J.027


JENIS PEKERJAAN : Pasang pipa beton U, diameter 40
SATUAN PEMBAYARAN : m

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja Biasa L17 Org/hr 0.3800 63,000.00 23,940.00


2 Tukang Batu L07 Org/hr 0.1900 68,500.00 13,015.00
3 Kepala Tukang Batu L02 Org/hr 0.0190 80,000.00 1,520.00
4 Mandor L01 Org/hr 0.0190 84,000.00 1,596.00

JUMLAH HARGA TENAGA 40,071.00

B. BAHAN

1 Buis Beton U Dia 0,3 m M053 bh 1.1000 70,000.00 77,000.00


2 Bata Merah M022 bh 123.7500 800.00 99,000.00
3 Portland Cement (PC) M037 kg 5.1500 1,500.00 7,725.00
4 Pasir Pasang M002 m 0.0305 200,000.00 6,100.00
5 Pasir Urug M001 m 0.0345 125,000.00 4,312.50

JUMLAH HARGA BAHAN 194,137.50

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A+B+C) 234,208.50