08
Descripcin unidad precio P Total Observac.
ACEROS
Fierro construccin 1/4" (6mm) kg 1.00 0.12
Fierro construccin 5/16" (8mm) kg 8.13 1.01
Fierro construccin 3/8" (10mm) kg 4.50 0.56
Fierro construccin 1/2" (12mm) kg 3.50 0.43
Fierro construccin 5/8" (16mm) kg 3.50 0.43
Fierro construccin 3/4" (20mm) kg 3.50 0.43
Fierro construccin 1" (25mm) kg 3.50 0.43
OJO
Fierro construccin Liso 1/4" (6mm) kg 3.50 0.43
Fierro construccin Liso 5/16" (8mm) kg 3.50 0.43
Fierro construccin Liso 3/8" (10mm) kg 3.50 0.43
Fierro construccin Liso 1/2" (12mm) kg 3.50 0.43
Fierro construccin Liso 5/8" (16mm) kg 3.50 0.43
Fierro construccin Liso 3/4" (20mm) kg 3.50 0.43
Fierro construccin Liso 1" (25mm) kg 3.50 0.43
0.00
Tubos de fe D= 1" ml 0.00
Tubos de fe D= 11/2" ml 0.00
Tubos de fe D= 2" ml 0.00
Tubos de fe D= 21/2" ml 0.00
Angular 3/4" x 1/8" kg 7.20 0.89
Angular 1" x 3/16" kg 7.20 0.89
Angular 1" x 1/8" kg 7.20 0.89
Angular 1 1/4" x 1/8" kg 7.20 0.89
Angular 1 1/2" x 1/8" kg 7.20 0.89
Angular 1 1/2" x 3/16" kg 7.20 0.89
Angular 1 1/2" x 1/4" kg 7.20 0.89
Angular 2" x 1/8" kg 7.20 0.89
Angular 2" x 3/16" kg 7.20 0.89
Angular 2" x 1/4" kg 7.20 0.89
Angular 2 1/2" x 3/16" kg 7.20 0.89
Angular 2 1/2" x 1/4" kg 7.20 0.89
Angular 3" x 1/4" kg 7.20 0.89
Angular 3" x 3/8" kg 7.20 0.89
ADHESIVOS 0.00
Carpicola Monopol glb 63.00 7.80
Pega alfombras glb 80.00 9.90
Sikadur 31 adhesivo epoxico kg. 120.00 14.85
Binda pasta impermeable p/sup. kg 14.00 1.73
ADITIVOS 0.00
Sika 1 impermeabilizante kg 20.00 2.48
Retardador kg 6.50 0.80
Sikacem 810 reactivo p/mortero lt 75.00 9.28
Curado antisol lt 7.00 0.87
ADOQUINES 0.00
Adoquines rectangulares 50*50*06 pza 14.00 1.73
Adoquines rectangulares 50*50*08 pza 18.00 2.23
Adoquines rectangulares 40*40*06 pza 9.00 1.11
AISLANTE TERMICO Y ACUSTICO
Plancha tecnopor 100*50 E=0,5cm m2 3.00 0.37
Plancha tecnopor 100*50 E=5,0cm m2 22.00 2.72
Lana de vidrio 25 mm.espesor m2 14.00 1.73
ALIGERANTES
Casetn 50*50*12 cm. pza 8.00 0.99
Casetn 40*40*12 cm. pza 7.00 0.87
Plastofor tira 100*40*12 cm. pza 13.00 1.61
Plastofor tira 100*40*16 cm. pza 21.00 2.60
Plastofor tira 100*50*12 cm. pza 16.00 1.98
Plastofor tira 100*50*20 cm. pza 26.00 3.22
ALAMBRES Y MALLAS
Alambre de Amarre kg 8.50 1.05
Alambre Galvanizado N 8 kg 7.00 0.87
Alambre Galvanizado N 10 kg 8.00 0.99
Alambre Galvanizado N 12 kg 10.00 1.24
Alambre Tejido (malla) m2 2.45 0.30
Alambre Tejido R/40 x 0,90 rollo 80.90 10.01
Alambre c/puas Galv. Simple ml 0.27 0.03
Alambre c/puas Galv. Triple kg 0.31 0.04
Malla Milemetrica Plastico kg 11.00 1.36
Alambre Cu N 14 (nacional) ml 0.80 0.10 OJO
Malla Olmpica Galvanizado m2 150.00 18.56
Cable d/suspension de 3/8". ml 15.00 1.86
ARIDOS
Arena o Arenilla m3 65.00 8.04
Arena Comn m3 55.00 6.81
Arena fina m3 60.00 7.43
Grava Comn m3 55.00 6.81
Grava Clasificada m3 70.00 8.66
Ripio Chancado m3 70.00 8.66
Ripio Lavado m3 60.00 7.43
Ripio Bruto m3 55.00 6.81
Piedra Manzana m3 60.00 7.43
Piedra p/Cimiento m3 55.00 6.81
Piedra Cortada pza 1.90 0.24
Piedra Tarija c/negro m2 60.00 7.43
Piedra Laja m2 35.00 4.33
Piedra Tarija m2 30.00 3.71
Piedra Tarija Cortada y Pulida m2 65.00 8.04
Piedra Pizarra Cortada y Pulida m2 65.00 8.04
ALFOMBRAS Y EMPAPELADOS
Tapizn m2 25.00 3.09
Alfombra m2 68.50 8.48
Alfombra de alto trafico m2 75.00 9.28
Alfombra americana m2 130.00 16.09
Alfombra tipo persa 240*340 pza 1020.00 126.24
AZULEJO Y CERAMICOS
Azulejo Blanco NACIONAL 0,15X0,15 m2 35.00 4.33
Azulejo color NACIONAL 0,15X0,15 m2 36.00 4.46
Azulejo decorado NACIONAL 0,15X0,15 m2 38.00 4.70
Azulejo color Brasilera 0,15X0,15 m2 42.00 5.20
Azulejo ELIANE decorado 20*20 m2 46.00 5.69
Piso ceramico ELIANE 20*20 m2 65.00 8.04
Ceramica esmaltada Brasilero 30*30 m2 72.00 8.91
Ceramica Kaiser 23,50*11,50 m2 49.00 6.06
Revest. CAPRI clasica 20*25 m2 40.00 4.95
Ceramica Espaola PAMESA 31*31 m2 98.00 12.13
BOMBAS DE AGUA
Bomba de Agua 0,8 HP ITALIANA unid 1550.00 191.83
Bomba de Agua 1 HP ITALIANA unid 1600.00 198.02
Bomba de Agua 1,5 HP ITALIANA unid 2700.00 334.16
Bomba de Agua 2,2 HP ITALIANA unid 2850.00 352.72
Bomba de Agua 5,5 HP ITALIANA unid 3800.00 470.30
CALEFONES
Calefon a Gas ARISTON 50 Lt. pza 880.00 108.91
Calefon a Gas ARISTON 80 Lt. pza 1000.00 123.76
Calefon a Gas ARISTON 100 Lt. pza 1200.00 148.51
CAOS Y ACCESORIOS GALVANIZADO
Caeria Galvanizada 1/2" ml 12.00 1.49
Caeria Galvanizada 3/4" ml 15.00 1.86
Caeria Galvanizada 1" ml 17.50 2.17
Caeria Galvanizada 1 1/4" ml 22.00 2.72
Caeria Galvanizada 1 1/2" ml 27.50 3.40
Caeria Galvanizada 2" ml 38.50 4.76
Caeria Galvanizada 2 1/2" ml 50.00 6.19
Caeria Galvanizada 3" ml 65.00 8.04
Caeria Galvanizada D=4" ml 75.00 9.28
Caeria Galvanizada D=6" ml 85.00 10.52
Caeria Galvanizada D=8" ml 90.00 11.14
Codo Galvanizado 1/2" pza 4.00 0.50
Codo Galvanizado 3/4" pza 5.90 0.73
Codo Galvanizado 1" pza 7.80 0.97
Codo Galvanizado 1 1/4" pza 16.00 1.98
Codo Galvanizado 1 1/2" pza 18.30 2.26
Codo Galvanizado 2" pza 26.20 3.24
Codo Galvanizado 2 1/2" pza 40.10 4.96
Codo Galvanizado 3" pza 90.20 11.16
Codo Galvanizado 4" pza 135.00 16.71
Copla Galvanizada 1/2" pza 3.30 0.41
Copla Galvanizada 3/4" pza 3.90 0.48
Copla Galvanizada 1" pza 5.10 0.63
Copla Galvanizada 1 1/4" pza 8.20 1.01
Copla Galvanizada 1 1/2" pza 11.30 1.40
Copla Galvanizada 2" pza 16.60 2.05
Copla Galvanizada 2 1/2" pza 37.50 4.64
Copla Galvanizada 3" pza 92.00 11.39
Copla Galvanizada 4" pza 175.00 21.66
Tee Galvanizado 1/2" pza 5.50 0.68
Tee Galvanizado 3/4" pza 6.80 0.84
Tee Galvanizado 1" pza 12.50 1.55
Tee Galvanizado 1 1/4" pza 20.40 2.52
Tee Galvanizado 1 1/2" pza 24.50 3.03
Tee Galvanizado 2" pza 30.90 3.82
Tee Galvanizado 2 1/2" pza 79.90 9.89
Tee Galvanizado 3" pza 110.20 13.64
Tee Galvanizado 4" pza 175.90 21.77
Cruz Galvanizada 1/2" pza 7.80 0.97
Cruz Galvanizada 3/4" pza 13.20 1.63
Cruz Galvanizada 1" pza 18.90 2.34
Cruz Galvanizada 1 1/4" pza 18.50 2.29
Cruz Galvanizada 1 1/2" pza 33.40 4.13
Cruz Galvanizada 2" pza 43.90 5.43
Cruz Galvanizada 2 1/2" pza 88.40 10.94
Cruz Galvanizada 3" pza 123.20 15.25
Cruz Galvanizada 4" pza 186.20 23.04
Niple Hexagonal 1/2" pza 4.20 0.52
Niple Hexagonal 3/4" pza 5.10 0.63
Niple Hexagonal 1" pza 6.90 0.85
Niple Hexagonal 1 1/4" pza 9.80 1.21
Niple Hexagonal 1 1/2" pza 14.30 1.77
Niple Hexagonal 2" pza 18.50 2.29
Niple Hexagonal 2 1/2" pza 25.30 3.13
Niple Hexagonal 3" pza 49.80 6.16
Niple Hexagonal 4" pza 59.60 7.38
Unin Universal Galvanizado 1/2" pza 8.90 1.10
Unin Universal Galvanizado 3/4" pza 11.20 1.39
Unin Universal Galvanizado 1" pza 13.50 1.67
Unin Universal Galvanizado 1 1/4" pza 28.60 3.54
Unin Universal Galvanizado 1 1/2" pza 31.30 3.87
Unin Universal Galvanizado 2" pza 45.90 5.68
Unin Universal Galvanizado 2 1/2" pza 79.80 9.88
Unin Universal Galvanizado 3" pza 110.50 13.68
Unin Universal Galvanizado 4" pza 235.20 29.11
Reduccin galvanizada 3/4 a 1/2" pza 8.50 1.05
Reduccin galvanizada 1 a 1/2" pza 8.00 0.99
Reduccin galvanizada 1 a 3/4" pza 6.00 0.74
Reduccin galvanizada 2 a 1" pza 13.00 1.61
Llave de paso tipo cortina D=3/4" FG pza 30.00 3.71
Llave de paso tipo cortina D=2" FG pza 89.00 11.01
Llave de paso tipo cortina D=3" FG pza 180.00 22.28
Llaves de paso tipo globo D= 1/2" FG pza 25.00 3.09
Llaves de paso tipo globo D= 1" FG pza 45.00 5.57
Llaves de paso tipo globo D= 2" FG pza 90.00 11.14
CARPINTERIA DE ALUMINIO
Ventana Corrediza 1,00X1,20 de 2 hojas pza 430.00 53.22
Ventana Corrediza 2,00X1,20 de 3 hojas pza 0.00
Ventana Corrediza 3,00X1,20 de 4 hojas pza 0.00
Ventana Corrediza 2,40X2,00 de 2 hojas pza 0.00
CEMENTOS
Cemento Portland Fancesa IP-30 kg 0.82 0.10
Cemento Portland Fancesa IP-40 kg 0.86 0.11
Cemento Portland Fancesa IP-NEGRA kg 0.82 0.10
Cemento Blanco Especial kg 4.50 0.56
Cemento Viacha Estandar kg 0.64 0.08
Cemento Viacha Especial kg 0.69 0.09
Cemento Warnes kg 0.64 0.08
Cemento Camba kg 0.64 0.08
Cemento Coboce kg 0.64 0.08
Cemento Ocre kg 18.00 2.23
ELECTRIFICACION RURAL
B C D E F
FORMATO DE PRECIOS
CONSTRUCTORA ZAMBRANA ESTRADA NIT 1319093015
N personal hora precio PRECIO $US
5 1 Ingeniero hrs 12.50 1.564
6 2 Topografo hrs 15.2 1.902
7 3 Capatas hrs 7.5 0.939
8 4 Nivelador hrs 9.375 1.173
9 5 Mastro Albail hrs 6.875 0.860
10 6 Albail hrs 12.5 1.564
11 7 Ayudante hrs 5.625 0.704
12 8 pen hrs 6.25 0.782
13 9 Operador hrs 10 1.252
14 10 Chofer hrs 3.75 0.469
15 11 Carpintero hrs 6.25 0.782
16 12 Vidriero hrs 5 0.626
17 13 Electricista hrs 5 0.626
18 14 Pintor hrs 5.625 0.704
19 15 Plomero hrs 6.875 0.860
20 16 Soldador hrs 6.875 0.860
21 17 Especialista hrs 8.75 1.095
22
23 1 IMPUESTOS (IVA) % 14.94 1.870
24 2 IMPUESTOS (I T) % 3.09 0.387
25 3 Beneficios Sociales % 20 2.503 60.59
26 4 Mano de Obra Indirecta % 5.38 0.673
27 5 IVA sobre mano de Obra % 14.94 1.870
28 6 Gastos Generales % 5 0.626 16.57
29 7 Desgaste de Herramienta % 5 0.626
30 8 Utilidad % 10 1.252
31 0.000
32 Tipo de moneda Bs. $us.
33 tipo de cambio Dlar Americano 7.99 1.000
34
35
36
37 N EQUIPO HERRAMIENTA Remd. Precio
38 1 Mescladora 350 ltros hrs 25 3.129
39 2 Mescladora 150 ltros hrs 1.25 0.156
40 3 Bomba de Agua hrs 11.25 1.408
41 4 Motor de Luz hrs 3.75 0.469
42 5 Teodolito hrs 3.125 0.391
43 6 Nivel de Ingeniero hrs 10.625 1.330
44 7 Taquimetro hrs 12.5 1.564
45 8 Vibradora hrs 12.5 1.564
46 9 Camioneta hrs 18.75 2.347
47 10 Computadora hrs 10 1.252
48 11 Impresora hrs 6.25 0.782
49 12 Compresora hrs 18.75 2.347
50 13 Volqueta hrs 100 12.516
51 14 hormigonera hrs 10
52 15 hrs 10
Direccion y organizacionn de obras
COMPUTOS METRICOS
UNIVERSIDAD AUTONOMA GABRIEL RENE MORENO
CARRERA CONSTRUCCION CIVIL
COMPUTOS METRICOS
PROYECTO VIVIENDA TIPO 2B
UBICACION : YACUIBA DISTRITO : 8
UNV: Snchez SERRANO MARIELA FECHA :
OBRA GRUESA
1 letrero de obras pza 1 1
2 INSTALACION DE FAENAS GLB 1 1
3 REPLANTEO Y TRAZADO DE OBRA m2 1 61.2 61.2
4 EXCAVACIN MANUAL PARA FUNDACIONES Y SOBRECI M3 #REF!
ZAPATAS 11 0.512 5.63
4 ZAPATAS DE H A M3 5.63
11 0.8 0.8 0.8 5.632
5 COLUMNAS DE H A M3 11 0.15 0.2 3.4 1.122 1.122
6 SOBRECIMIENTO DE H A (0,20m x 0,30m) M3 1.54
S 55.60
PLANTA BAJA
LOSA 1 1 4.65 3.13 0.2 2.91
LOSA 2 1 6.6 1.94 0.2 2.56
LOSA 3 1 5.67 4.13 0.2 4.68
LOSA 4 1 4.1 3.12 0.2 2.56
LOSA 5 1 2.6 1.4 0.2 0.73
LOSA 6 1 6.35 3.3 0.2 4.19
LOSA 7 1 3.42 2.9 0.2 1.98
LOSA 8 1 4.4 2.9 0.2 2.55
PLANTA ALTA
LOSA 1 1 4.65 3.13 0.2 2.91
LOSA 2 1 6.6 1.94 0.2 2.56
LOSA 3 1 5.67 4.13 0.2 4.68
LOSA 4 1 4.1 3.12 0.2 2.56
LOSA 5 1 2.6 1.4 0.2 0.73
LOSA 6 1 6.35 3.3 0.2 4.19
LOSA 7 1 3.42 2.9 0.2 1.98
LOSA 8 1 4.4 2.9 0.2 2.55
S 44.34
18 ESCALERA DE H A M3 4.37
GRADA INTERIOR
TRAMO 1-2 4 2.2 2 0.1 1.76
DESCANSO 2 2.2 0.9 0.1 0.40
PELDAOS (b*h*/1/2) 32 1 0.3 0.175 0.84
GARADA EXTERIOR
TRAMO 1-2 4 2.9 2 0.1 1.16
PLANTA GARZONIER
EJE A(6,7) 1 10 2.1 21.0
EJE B,D,G(6,7) 3 3.32 2.1 20.9
EJE C(2,3) 1 2.1 1.35 2.8
EJE E(2,5) 1 3.03 2.4 7.3
DESCUENTO PUERTAS -2 2.1 -0.9 3.8
EJE H(2,5) 1 3.08 2.1 6.5
EJE I(1,2) 1 4.6 2.1 9.7
EJE 1(A,I) 1 10 0.9 9.0
EJE 2(A,K) 1 9.27 2.1 19.5
EJE 3(C,E) 1 2.1 1.4 2.9
EJE 4(A,C) 1 3.87 2.1 8.1
DESCUENTO COLUMNAS -1 2.1 0.35 -0.7
EJE 5(E,H) 1 3.23 2.1 6.8
DECUENTO VENTANA -1 1.8 1.8 -3.2
EJE 6(A,G) 1 0.6 2.4 1.4
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
EJE 7(A,G) 1 6.92 2.4 16.6
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
S 113.2
PLANTA GARZONIER
V1 2 1.8 1.8 6.48
V2 1 0.8 0.8 0.64
V3 2 1.8 0.9 3.24
S 10.36
V6 1 0.8 0.80
V7 1 1.8 1.80
9.80
PLANTA ALTA
V1 2 0.8 1.60
V2 1 2.4 2.40
V3 2 1.8 3.60
V4 2 1.8 3.60
11.20
PLANTA GARZONIER
V1 2 1.8 3.60
V2 1 0.8 0.80
V3 2 1.8 3.60
S 8.00
INSTALACION SANITARIA
TUBO DE 2" 1 9
INSTALACION ELECTICA
PLANTA ALTA
INTERUPTORES 8
PLANTA GARZONIER
INTERUPTORES 7
24
PLANTA ALTA
TOMA CORRIENTES 16
PLANATA GARZONIER
TOMA CORRIENTES 11
41
35 CIRCUITO DE CONMUTADORES PTO 3.00
PLANTA BAJA
COMUTADORES 3
PLANAT ALTA
S 6
OBRA FINA
PLANTA ALTA
EJE I(A,K) 1 10 2.4 24.0
DESCUENTO VENTANAS -1 1 2.4 -2.4
DESCUENTO VENTANAS -1 1.8 2.4 -4.3
DESCUENTO VENTANAS -1 0.8 0.8 -0.6
DESCUENTO VENTANAS -1 2.4 1.8 -4.3
EJE 2(F,J) 2 3.91 2.4 18.8
EJE 3,4(A,D) 4 4 2.4 38.4
DESCUENTO COLUMNA -2 2.4 0.35 -1.7
EJE5(F,I) 2 3.23 2.4 15.5
DESCUENTO DE VENTANA -1 1.8 1.5 -2.7
EJE 6(A,I) 1 6.6 2.4 15.8
DESCUENTO PUERTA -2 2.1 0.9 -3.8
DESCUENTO PUERTA -1 2.1 0.8 -1.7
DECUENTO DE COLUMNA -1 2.4 0.35 -0.8
EJE 7(B,C E,F) 2 0.6 2.4 2.9
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
EJE 8(B,C E,F) 2 0.6 2.4 2.9
EJE 9(A,I) 1 6.92 2.4 16.6
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
EJE A(1,8) 1 13.1 2.4 31.4
EJE B(1,3) 2 4.1 2.4 19.7
DECUENTO DE PUERTA -1 2.1 0.9 -1.9
EJE C,E (6,8) 4 2.89 2.4 27.7
EJE D(1,2) 2 2.4 2.4 11.5
EJE D(3,6) 2 4.56 2.4 21.9
DESCUENTO PUERTA -1 2.1 1.2 -2.5
EJE F(2,5) 2 3.05 2.4 14.6
DECUENTO DE PUERTA -1 2.1 0.9 -1.9
DECUENTO DE PUERTA -1 2.1 0.8 -1.7
EJE H(5,7) 1 3.05 2.4 7.3
PLANTA GARZONIER
EJE A(2,6) 1 5.47 2.1 11.5
EJE B,D,G(6,7) 6 3.32 2.1 41.8
EJE C(2,3) 2 2.1 1.35 5.7
EJE E(2,5) 2 3.03 2.4 14.5
DESCUENTO PUERTAS -2 2.1 -0.9 3.8
EJE H(2,5) 1 3.08 2.1 6.5
EJE I(1,2) 1 4.6 2.1 9.7
EJE 2(A,K) 1 9.27 2.1 19.5
EJE 3(C,E) 2 2.1 1.4 5.9
EJE 4(A,C) 2 3.87 2.1 16.3
DESCUENTO COLUMNAS -1 2.1 0.35 -0.7
EJE 5(E,H) 1 3.23 2.1 6.8
DECUENTO VENTANA -1 1.8 1.8 -3.2
EJE 6(A,G) 2 0.6 2.4 2.9
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
EJE 7(A,G) 1 6.92 2.4 16.6
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
S 138.2
MUROS PARA TECHOS
EJE 4/A,G) 2 6.5 1.56 20.3
EJE 5(F,I) 1 2 1.56 3.1
EJE 5(F,I) 2 3.67 1.56 5.7
EJE F(4,6) 2 3.08 0.81 2.5
EJE A(6,7) 2 3.32 1.56 5.2
S 36.8
S 740.7
41 MEZON DE HA M2 14.5
3 2.97 1.63 14.52
S 14.52
PLANTA GARZONIER
P1 1 5.92 4.48 26.52
P2 1 4 4 16.00
P3 1 4.12 3.27 13.47
P4 1 2.76 1.4 3.86
P5 1 2.8 2.47 6.92
P6 1 4 3.34 13.36
P7 1 7 3.3 23.10
S 168.1
PLANTA GARZONIER
Z1 23.3
DESCUENTO PUERTA -4 0.9
DESCUENTO PUERTA -1 0.8
Z2 1 20.38
DESCUENTO PUERTA -3 0.9
DESCUENTO PUERTA -1 0.8
Z3 1 10.38
DESCUENTO PUERTA -1 0.9
Z4 1 10.22
GRADA INTERIOR
TRAMO 1-2 4 2.2 2 17.6
DESCANSO 2 2.2 0.9 3.96
PELDAOS (b*h*/1/2) 32 1 0.3 9.6
GARADA EXTERIOR 0
TRAMO 1-2 4 2.9 2 23.2
PELDAOS (b*h*/1/2) 8 1 0.3 2.4
S 56.76
TOTAL 218.4
48 ACERAS M2 15.00
1 10 1.5 15.000
ARTEFACTOS SANITARIOS
PLANATA ALTA
5 0.9 2.1 9.5
2 0.8 2.1 3.4
12.8
PLANAT GARZONIER
5 0.9 2.1 9.5
2 0.8 2.1 3.4
12.8
TOTAL 40.5
PLANTA ALTA
EJE I(A,K) 1 10 2.4 24.0
DESCUENTO VENTANAS -1 1 2.4 -2.4
DESCUENTO VENTANAS -1 1.8 2.4 -4.3
DESCUENTO VENTANAS -1 0.8 0.8 -0.6
DESCUENTO VENTANAS -1 2.4 1.8 -4.3
EJE 2(F,J) 2 3.91 2.4 18.8
EJE 3,4(A,D) 4 4 2.4 38.4
DESCUENTO COLUMNA -2 2.4 0.35 -1.7
EJE5(F,I) 2 3.23 2.4 15.5
DESCUENTO DE VENTANA -1 1.8 1.5 -2.7
EJE 6(A,I) 1 6.6 2.4 15.8
DESCUENTO PUERTA -2 2.1 0.9 -3.8
DESCUENTO PUERTA -1 2.1 0.8 -1.7
DECUENTO DE COLUMNA -1 2.4 0.35 -0.8
EJE 7(B,C E,F) 2 0.6 2.4 2.9
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
EJE 8(B,C E,F) 2 0.6 2.4 2.9
EJE 9(A,I) 1 6.92 2.4 16.6
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
EJE A(1,8) 1 13.1 2.4 31.4
EJE B(1,3) 2 4.1 2.4 19.7
DECUENTO DE PUERTA -1 2.1 0.9 -1.9
EJE C,E (6,8) 4 2.89 2.4 27.7
EJE D(1,2) 2 2.4 2.4 11.5
EJE D(3,6) 2 4.56 2.4 21.9
DESCUENTO PUERTA -1 2.1 1.2 -2.5
EJE F(2,5) 2 3.05 2.4 14.6
DECUENTO DE PUERTA -1 2.1 0.9 -1.9
DECUENTO DE PUERTA -1 2.1 0.8 -1.7
EJE H(5,7) 1 3.05 2.4 7.3
DESCUENTO MARCO VENTANA 1 2.8 1.8 5.0
EJE I(3,5) 1 3.05 2.4 7.3
PLANTA GARZONIER
EJE A(2,6) 1 5.47 2.1 11.5
EJE B,D,G(6,7) 6 3.32 2.1 41.8
EJE C(2,3) 2 2.1 1.35 5.7
EJE E(2,5) 2 3.03 2.4 14.5
DESCUENTO PUERTAS -2 2.1 -0.9 3.8
EJE H(2,5) 1 3.08 2.1 6.5
EJE I(1,2) 1 4.6 2.1 9.7
EJE 2(A,K) 1 9.27 2.1 19.5
EJE 3(C,E) 2 2.1 1.4 5.9
EJE 4(A,C) 2 3.87 2.1 16.3
DESCUENTO COLUMNAS -1 2.1 0.35 -0.7
EJE 5(E,H) 1 3.23 2.1 6.8
DECUENTO VENTANA -1 1.8 1.8 -3.2
EJE 6(A,G) 2 0.6 2.4 2.9
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
EJE 7(A,G) 1 6.92 2.4 16.6
DESCUENTO VENTANAS -1 1.7 1.5 -2.6
DESCUENTO VENTANAS -1 1.8 0.8 -1.4
DESCUENTO VENTANAS -1 1.8 1.7 -3.1
DESCUENTO DE COLUMNAS -3 2.4 0.35 -2.5
S 138.2
MUROS PARA TECHOS
EJE 4/A,G) 2 6.5 1.56 20.3
EJE 5(F,I) 1 2 1.56 3.1
EJE 5(F,I) 2 3.67 1.56 5.7
EJE F(4,6) 2 3.08 0.81 2.5
EJE A(6,7) 2 3.32 1.56 5.2
S 36.8
S 740.7
TOTAL 218.4
PLANTA GARZONIER
COSTO MATERIALES
B MANO DE OBRA
Albail hr 5.00
1 Pen hr 2.70
FECHA: 30-Dec-99
N DESCRIPCION UND. CANTIDAD
A MATERIALES
COSTO MATERIALES
B MANO DE OBRA
1 Pen hr 4.00
ITEM: ZAPATAS DE H A
6 clavos kg 0.20
7 alambre de amarre kg 1.00
8
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 12.00
2 ayudante hr 18.00
3 encofrador hr 10.00
4 armador hr 10.00
SUB TOTAL MANO DE OBRA
E Beneficios Sociales % 20.00
COSTO MANO DE OBRA
C EQUIPO Y HERRAMIENTA
1 mezcladora hr 1.00
2 vibradora hr 0.80
ITEM: COLUMNAS DE HA
COSTO MATERIALES
B MANO DE OBRA
Albail hr 4.50
1 Pen hr 4.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 115.00
2 arena m3 0.25
3 grava m3 0.25
3 piedra m4 0.60
4 Clavos kg 0.50
7 Madera de encofrado p2 25.00
5 Alambre de amarre kg 0.20
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 6.00
Pen hr 6.00
J IMPUESTOS (I T) % 3.00
COSTO DE APLICACIN DEL ITEM
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 alquitran Kg 0.20
2 Politileno de 200mcr ml 0.50
3 Varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
Pen hr 2.50
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 1.50
2 ayudante hr 1.75
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 7.50
2 arena m3 0.03
3 ladrillo Gambote Pza 33.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 2.00
Pen hr 2.00
J IMPUESTOS (I T) % 3.00
COSTO DE APLICACIN DEL ITEM
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 340.00
2 arena m3 0.50
3 grava m3 0.70
4 Clavos kg 1.00
Fierro de construc. Kg 60.00
4 Madera de encofrado p2 70.00
5 Alambre de amarre kg 1.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 22.00
Pen hr 22.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 340.00
2 arena m3 0.50
3 grava m3 0.70
4 Fierro de Construc. Kg 45.00
5 Elementos Plastoform pza 10.00
6 Clavos kg 1.00
7 Madera de encofrado p2 70.00
8 Alambre de amarre kg 1.00
9 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 22.00
Pen hr 22.00
ITEM: ESCALERA DE H A
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 340.00
2 arena m3 0.50
3 grava m3 0.70
3 Fierro de Construc. kg 60.00
4 Clavos kg 1.00
7 Madera de encofrado p2 68.00
5 Alambre de amarre kg 1.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 25.00
Pen hr 25.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 340.00
2 arena comun m3 0.50
3 grava clasificada m3 0.70
4 Fierro de construccion Kg 1.05
5 madera de construccion pie2 70.00
6 Alambre de amarre kg 1.60
7 Clavos kg 1.60
8 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 3.50
Pen hr 3.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 11.50
2 arena m3 0.05
3 Ladrillo ceramico 6h m3 35.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 1.50
Pen hr 1.75
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Madera Pie2 13.00
2 Pernos Kg 0.65
3 Plancha de 1/16" M2 0.02
3 Clavos Kg 0.04
4 Teja Colinial col 50 cm Kg 19.00
7 Cemento portlamnd kg 1.00
Arena m3 0.02
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 3.50
Pen hr 4.50
COSTO MATERIALES
B MANO DE OBRA
1 Carpintero hr 7.00
Ayudante hr 7.00
Albail hr 0.50
Peon hr 0.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 4.70
2 arena m3 0.01
3 grava m3 0.01
4 Madera de encofrado p2 0.75
5 Fierro de const. kg 0.75
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 1.60
Pen hr 2.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 65.00
2 arena m3 0.12
3 grava m3 0.07
3 piedra m4 0.10
4 Ladrillo Gambote pza 150.00
7 Fierro de Construcion kg 6.00
5 Alambre de amarre kg 0.10
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 16.00
Pen hr 16.00
G Utilidad % 10.00
H SUB - TOTAL
I IMPUESTOS (IVA) (B+C) % 13.00
J IMPUESTOS (I T) % 3.00
COSTO DE APLICACIN DEL ITEM
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Tubo de Hormigon D=6" pza 1.10
2 Cemento Portland kg 2.50
3 Arena m3 0.01
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 0.40
Pen hr 0.40
J IMPUESTOS (I T) % 3.00
COSTO DE APLICACIN DEL ITEM
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Tubo PVC D=4" ml 1.05
2 Pegamento kg 0.15
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Plomero hr 0.50
2 Pen hr 0.50
J IMPUESTOS (I T) % 3.00
COSTO DE APLICACIN DEL ITEM
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Tuvo PVC D=2" ml 1.05
2 Pegamento Kg 0.80
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Plomero hr 0.35
Ayudante hr 0.35
G Utilidad % 10.00
H SUB - TOTAL
I IMPUESTOS (IVA) (B+C) % 13.00
J IMPUESTOS (I T) % 3.00
COSTO DE APLICACIN DEL ITEM
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Caeria Galv. 1/2" ml 1.03
2 Codo Tupy 1/2 pza 0.40
3 Tee Tupy 1/2" pza 0.40
3 Cinta teflon pza 0.60
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Plomero hr 0.50
Ayudante hr 0.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Caja de medidor Pza 1.05
2 Medidor de luz Pza 1.05
3 Cable N8 Pza 1.05
4 Ternico de 30A Pza 0.50
5 Cinta Aislante Pza 0.30
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Electricista hr 0.50
Ayudante hr 0.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Almabre cobre N 14 AWG ml 20.00
2 Interuptor sencillo Pza 1.00
3 Ductos de 5/8 ml 9.00
3 Cinta Aislante 2*4 pza 0.05
4 Caja plastica pza 2.00
7 Canoa de 2*40 pza 1.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Electricista hr 3.50
2 Ayudante hr 3.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Almabre cobre N 12 AWG ml 20.00
2 Toma corriente doble Pza 1.00
3 Ductos de 5/8 ml 7.00
3 Cinta Aislante 2*4 pza 0.05
4 Caja plastica pza 2.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Electricista hr 3.50
2 Ayudante hr 3.50
3 Otros % 3.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Almabre cobre N 14 AWG ml 20.00
2 Conmutador doble Pza 1.00
3 Ductos de 5/8 ml 9.00
3 Cinta Aislante 2*4 pza 0.05
4 Caja plastica pza 2.00
7 Araa de 3 focos pza 1.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Electricista hr 3.50
2 Ayudante hr 3.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Almabre cobre N 14 AWG ml 20.00
2 Termico de 30 Amp Pza 1.00
3 Ductos de 5/8 ml 9.00
3 Cinta Aislante 2*4 pza 0.05
4 Caja plastica pza 2.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Electricista hr 3.50
2 Ayudante hr 3.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Yeso Kg 17.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 1.00
Pen hr 1.10
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Madera Verdolago Pie2 5.20
2 Malla de Alambre m2 1.00
3 Clavos kG 0.15
3 Estuco Kg 16.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 2.20
Pen hr 2.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Estuco Kg 16.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 2.00
Pen hr 2.00
C EQUIPO Y HERRAMIENTA
3 Otros % 3.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Pedra Manzana M3 0.12
2 cemento portland Kg 17.10
3 arena m3 0.05
4 grava m3 0.05
5 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 2.10
Pen hr 2.40
ITEM: MEZON DE HA
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 30.00
2 arena m3 0.04
3 grava m3 0.06
3 Fierro de Construccion Kg 8.00
4 Madera de encofrado Pie2 20.00
Clavos Kg 0.20
Alambre de amarre Kg 0.20
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 3.00
Pen hr 3.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento cola Kg 17.70
2 Ceramica Esmaltada m2 0.04
3 Cemento Blanco Kg 0.05
4 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 2.50
Pen hr 2.80
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 0.50
Pen hr 0.50
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 12.60
2 arena m3 0.03
3 Ceramica m2 0.30
3 Cemento Blanco Kg 0.25
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 2.90
Pen hr 2.90
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 4.00
2 arena m3 0.04
3 Cal Viva Kg 6.00
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 2.00
Pen hr 2.20
COSTO MATERIALES
B MANO DE OBRA
1 Carpintero hr 13.00
2 Ayudante 13.00
3 Albail 0.60
4 Pen hr 0.60
ITEM: ACERAS
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 cemento portland Kg 165.00
2 arena m3 0.25
3 grava m3 0.35
3 piedra m3 0.50
4 Clavos kg 0.50
7 Madera de encofrado p2 25.00
5 Alambre de amarre kg 0.20
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Albail hr 6.00
Pen hr 6.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
COSTO MATERIALES
B MANO DE OBRA
1 Plomero hr 2.00
2 Ayudante hr 2.00
3 Albail hr 2.00
4 Pen hr 2.20
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Lavamanos C/Pedestal pza 1.00
2 Chicotillo de 1/2" pza 1.00
3 Sifon sencillo Pza 1.00
4 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Plomero hr 2.00
2 Ayudante hr 2.00
3 Albail hr 2.00
4 Pen hr 2.20
FECHA: 30-Dec-99
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Pie de Ducha pza 1.00
2 Cemento Kg 0.20
3 Arena M3 0.05
4 Ducha electrica Pza 1.00
5 Cemento Blanco Kg 0.07
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Plomero hr 2.00
2 Ayudante hr 2.00
3 Albail hr 2.00
4 Pen hr 2.20
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Lavaplatos Inox. Pza 1.00
2 Sifon Sencillo Lavapl Pza 1.00
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Plomero hr 2.00
2 Ayudante hr 2.00
3 Albail hr 2.00
4 Pen hr 2.20
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Puerta de madera Pza 1.00
2 Bisagra de 4" Pza 3.00
3 Picaporte de 6" Pza 2.00
4 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Carpintero hr 13.00
2 Ayudante hr 0.60
3 Albail hr 13.00
4 Pen hr 0.60
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Pintura Latex Gal 0.07
2 Lija de Pared m3 0.25
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Pintor hr 0.45
2 Ayudante hr 0.45
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Pintura Latex Gal 0.09
2 Lija de Pared m3 0.30
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Pintor hr 0.45
2 Ayudante hr 0.45
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Vidrio Doble de 3mm P2 1.10
2 Silicona Pza 0.10
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
1 Vidriero hr 0.10
2 Ayudante hr 0.10
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
1 Tubo cuadrado Kg. 65.00
2 fierro de 1/4 m3 0.50
3 soldadura m2 0.1
4 pintura anticorrosiva lt 0.11
5 Varios gbl 0.003
COSTO MATERIALES
B MANO DE OBRA
3 Especialista (soldador) hr 0.08
Ayudante hr 0.08
SUB TOTAL MANO DE OBRA
E Beneficios Sociales % 20.00
COSTO MANO DE OBRA
C EQUIPO Y HERRAMIENTA
1 Otros % 5.00
FECHA: 30-Dec-99
N DESCRIPCION UND. REND.
A MATERIALES
6 varios glb 0.01
COSTO MATERIALES
B MANO DE OBRA
Pen hr 2.00
TARIOS
UNIDAD: GLB
MONEDA: Bs.
P. UNIT. TOTAL
290 290
330 330
620.00
12.50 62.50
6.25 16.88
79.38
79.38 15.88
95.25
79.38 2.38
2.38
717.63
717.63 35.88
717.63 71.76
825.28
81.76 10.63
835.90 25.08
860.98
UNIDAD: M2
MONEDA: BS
P. UNIT. IMPOR Bs.
8 2
14 0.28
15.00 0.15
0.70 0.05
2.48
18.75 0.38
12.50 0.25
20.00 0.40
1.03
1.03 0.21
1.23
1.03 0.03
0.03
4.73
4.73 0.24
4.73 0.47
5.44
1.06 0.14
5.58 0.17
5.75
UNIDAD: M3
MONEDA: Bs.
0.00
6.25 25.00
25.00
25.00 5.00
30.00
32.98 1.65
25.00 0.75
0.75
30.75
30.75 1.54
30.75 1.54
33.83
25.75 3.35
37.17 1.12
38.29
UNIDAD: M3
MONEDA: Bs.
1.16 406.00
8.07 322.80
120.00 114.00
90.00 40.50
8.00 200.00
15.00 3.00
15.00 15.00
1101.30
18.75 225.00
12.50 225.00
18.75 187.50
18.75 187.50
825.00
825.00 165.00 20 % del subtotal de mano de obra
990.00
18.00 18
15.00 12
60.00 49.50
79.50
2170.80
2170.80 108.54 5 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herramie
2170.80 217.08 10 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herrami
2496.42
904.50 117.59 13 % de la sumatoria de B + C ( mano de obra + equipo y herrameiIVA
2614.01 78.42 3% de la sumatoria de subtotal H + impuestos (materiales+mano de obra +equipo y herram
2692.43
UNIDAD: M3
MONEDA: Bs.
1.16 406.00
8.07 1008.75
90.00 40.50
120.00 110.40
8.00 640.00
15.00 30.00
15.00 30.00
2265.65
18.75 337.50
18.75 187.50
18.75 187.50
12.50 212.50
925.00
18.00 5.4
15.00 2.25
15.00 3
60.00 49.75 5% mano de obra
60.40
3436.05
3436.05 171.80 5 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herramienta)
3436.05 343.61 10 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herramienta)
3951.46
985.40 128.10 13 % de la sumatoria de B + C ( mano de obra + equipo y herrameinta)
4079.56 122.39 3% de la sumatoria de subtotal H + impuestos (materiales+mano de obra +equipo y herram
4201.95
UNIDAD: M3
MONEDA: Bs.
1.16 406.00
8.07 484.20
90.00 40.50
120.00 110.40
8.00 360.00
15.00 18.00
15.00 15.00
1434.10
10.00 65.00
6.25 40.63
6.25 0.50
106.13
106.13 21.23 20 % del subtotal de mano de obra
127.35
20.00 3
10.00 1.5
60.00 3.00
5% mano de obra
7.50
1568.95
1568.95 78.45
1568.95 156.90 5 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herramienta)
1804.29 10 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herramienta)
113.63 14.77
1819.06 54.57 13 % de la sumatoria de B + C ( mano de obra + equipo y herrameinta)
1873.64 3% de la sumatoria de subtotal H + impuestos (materiales+mano de obra +equipo y herram
UNIDAD: m2
MONEDA: Bs.
11 1.65
3.5 3.85
150.00 1.50
7.00
18.75 5.63
12.50 3.75
9.38
9.38 1.88 20 % del subtotal de mano de obra
11.25
9.38 0.47
0.47
18.72
18.72 0.94 5 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herramienta)
18.72 1.87 10 % de la sumatoria de A+B+C (materiales + mano de obra + equipo y herramienta)
21.53
9.84 1.28 13 % de la sumatoria de B + C ( mano de obra + equipo y herrameinta)
22.81 0.68 3% de la sumatoria de subtotal H + impuestos (materiales+mano de obra +equipo y herram
23.49
UNIDAD: M3
MONEDA: Bs.
0.91 89.18
80 48
120 28.8
110 39.6
300.00 3
208.58
12.50 56.25
6.25 28.13
84.38
84.38 16.88
101.25
16.88 0.84
0.84
310.67
310.67 15.53
310.67 31.07
357.27
85.22 11.08
368.35 11.05
379.40
UNIDAD: M3
MONEDA: Bs.
0.91 104.65
120.00 30.00
110.00 27.50
80.00 48.00
16.00 8.00
3.50 87.50
14.00 2.80
300.00 3.00
311.45
12.50 75.00
6.25 37.50
112.50
112.50 22.50
135.00
18.00 2.7
22.50 1.125
1.13
447.58
447.58 22.38
447.58 44.76
514.71
113.63 14.77
529.48 15.88
545.37
UNIDAD: M2
MONEDA: Bs.
9.00 1.80
2.00 1.00
300.00 3.00
5.80
6.25 15.63
15.63
15.63 3.13
18.75
3.13 0.09375
0.09
24.64
24.64 1.23
24.64 2.46
28.34
15.72 2.04
30.38 0.91
31.30
UNIDAD: M2
MONEDA: Bs.
1.16 12.76
150.00 7.50
1.40 33.60
53.86
18.75 28.13
12.50 21.88
50.00
50.00 10.00
60.00
10.00 0.5
0.50
114.36
114.36 5.72
114.36 11.44
131.51
50.50 6.57
138.08 4.14
142.22
UNIDAD: M3
MONEDA: Bs.
0.91 6.83
120.00 3.60
1.00 33.00
300.00 3.00
46.43
12.50 25.00
6.25 12.50
37.50
37.50 7.50
45.00
7.50 0.375
0.38
91.80
91.80 4.59
91.80 9.18
105.57
37.88 4.92
110.49 3.31
113.81
UNIDAD: M3
MONEDA: Bs.
0.91 309.40
120.00 60.00
100.00 70.00
16.00 16.00
13.80 828.00
3.50 245.00
14.00 14.00
300.00 3.00
1545.40
12.50 275.00
6.25 137.50
412.50
412.50 82.50
495.00
18.00 5.4
12.50 1.875
82.50 2.475
4.35
2044.75
2044.75 102.24
2044.75 204.48
2351.46
416.85 54.19
2405.65 72.17
2477.82
UNIDAD: m3
MONEDA: Bs.
0.91 309.40
120.00 60.00
100.00 70.00
13.80 621.00
5.50 55.00
16.00 16.00
3.50 245.00
14.00 14.00
300.00 3.00
1393.40
12.50 275.00
6.25 137.50
412.50
412.50 82.50
495.00
18.00 5.4
12.50 1.875
82.50 2.475
4.35
1892.75
1892.75 94.64
1892.75 189.28
2176.66
416.85 54.19
2230.85 66.93
2297.78
UNIDAD: M3
MONEDA: Bs.
0.91 309.40
120.00 60.00
100.00 70.00
13.80 828.00
16.00 16.00
3.50 238.00
14.00 14.00
300.00 3.00
1538.40
12.50 312.50
6.25 156.25
468.75
468.75 93.75
562.50
18.00 5.4
12.50 1.25
93.75 2.8125
4.06
2104.96
2104.96 105.25
2104.96 210.50
2420.71
472.81 61.47
2482.17 74.47
2556.64
UNIDAD: M3
MONEDA: Bs.
0.91 309.40
120.00 60.00
100.00 70.00
13.80 14.49
3.50 245.00
14.00 22.40
16.00 25.60
300.00 3.00
749.00
12.50 43.75
6.25 21.88
65.63
65.63 13.13
78.75
18.00 5.4
12.50 1.25
13.13 0.39375
1.64
829.39
829.39 41.47
829.39 82.94
953.80
67.27 8.74
962.55 28.88
991.42
UNIDAD: M2
MONEDA: Bs.
0.91 10.47
120.00 6.00
1.20 42.00
300.00 3.00
61.47
12.50 18.75
6.25 10.94
29.69
29.69 5.94
35.63
5.94 0.30
0.30
97.39
97.39 4.87
97.39 9.74
111.99
29.98 3.90
115.89 3.48
119.37
UNIDAD: M2
MONEDA: Bs.
3.50 45.50
3.00 1.95
50.00 1.00
16.00 0.64
18.00 342.00
0.91 0.91
120.00 2.40
300.00 3.00
397.40
12.50 43.75
6.25 28.13
71.88
71.88 14.38
86.25
14.38 0.43125
0.43
484.08
484.08 24.20
484.08 48.41
556.69
72.31 9.40
566.09 16.98
583.08
UNIDAD: M2
MONEDA: Bs.
9.00 99.00
4.00 12.00
18.00 36.00
300.00 3.00
150.00
18.00 126.00
6.25 43.75
12.50 6.25
6.25 3.13
179.13
179.13 35.83
214.95
35.83 1.79125
1.79
366.74
366.74 18.34
366.74 36.67
421.75
180.92 23.52
445.27 13.36
458.63
UNIDAD: ML
MONEDA: Bs.
0.91 4.28
120.00 1.20
100.00 1.00
3.50 2.63
13.80 10.35
300.00 3.00
22.45
12.50 20.00
6.25 12.50
32.50
32.50 6.50
39.00
6.50 0.325
0.33
61.78
61.78 3.09
61.78 6.18
71.04
32.83 4.27
75.31 2.26
77.57
UNIDAD: PZA
MONEDA: Bs.
0.91 59.15
120.00 14.40
100.00 7.00
80.00 8.00
1.00 150.00
13.80 82.80
14.00 1.40
300.00 3.00
325.75
12.50 200.00
6.25 100.00
300.00
300.00 60.00
360.00
650.00 32.5
60.00 3
3.00
688.75
688.75 34.44
688.75 68.88
792.06
303.00 39.39
831.45 24.94
856.40
UNIDAD: ML
MONEDA: Bs.
25.00 27.50
0.80 2.00
120.00 1.20
300.00 3.00
33.70
18.00 7.20
6.25 2.50
9.70
9.70 1.94
11.64
1.94 0.097
0.10
45.44
45.44 2.27
45.44 4.54
52.25
9.80 1.27
53.53 1.61
55.13
UNIDAD: ML
MONEDA: Bs.
8.00 8.40
25.00 3.75
300.00 3.00
15.15
18.00 9.00
6.25 3.13
12.13
12.13 2.43
14.55
2.43 0.12125
0.12
29.82
29.82 1.49
29.82 2.98
34.29
12.25 1.59
35.89 1.08
36.96
UNIDAD: ML
MONEDA: Bs.
5.00 5.25
25.00 20.00
300.00 3.00
28.25
18.00 6.30
6.25 2.19
8.49
8.49 1.70
10.19
18.00 2.7
12.50 1.25
1.70 0.050925
1.30
39.74
39.74 1.99
39.74 3.97
45.70
9.79 1.27
46.97 1.41
48.38
UNIDAD: ML
MONEDA: Bs.
4.10 4.22
4.00 1.60
5.00 2.00
2.00 1.20
300.00 3.00
12.02
18.00 9.00
6.25 3.13
12.13
12.13 2.43
14.55
2.43 0.12125
0.12
26.69
26.69 1.33
26.69 2.67
30.70
12.25 1.59
32.29 0.97
33.26
UNIDAD: PZA
MONEDA: Bs.
65.00 68.25
680.00 714.00
8.00 8.40
25.00 12.50
5.00 1.50
300.00 3.00
807.65
18.00 9.00
6.25 3.13
12.13
12.13 2.43
14.55
2.43 0.12125
0.12
822.32
822.32 41.12
822.32 82.23
945.67
12.25 1.59
947.26 28.42
975.68
UNIDAD: 0
MONEDA: Bs.
1.10 22.00
12.00 12.00
0.68 6.12
5.00 0.25
1.00 2.00
100.00 100.00
300.00 3.00
145.37
12.50 43.75
6.25 21.88
65.63
65.63 13.13
78.75
13.13 0.66
0.66
224.78
224.78 11.24
224.78 22.48
258.49
66.28 8.62
267.11 8.01
275.12
UNIDAD: PTO
MONEDA: Bs.
1.70 34.00
15.00 15.00
0.68 4.76
5.00 0.25
1.00 2.00
300.00 3.00
59.01
12.50 43.75
6.25 21.88
65.63
65.63 13.13
78.75
13.13 0.39
0.39
138.15
138.15 6.91
138.15 13.82
158.88
66.02 8.58
167.46 5.02
172.48
UNIDAD: PTO
MONEDA: Bs.
1.10 22.00
24.00 24.00
0.68 6.12
5.00 0.25
1.00 2.00
145.00 145.00
300.00 3.00
202.37
12.50 43.75
6.25 21.88
65.63
65.63 13.13
78.75
13.13 0.39375
0.39
281.51
281.51 14.08
281.51 28.15
323.74
66.02 8.58
332.32 9.97
342.29
UNIDAD: PTO
MONEDA: Bs.
1.10 22.00
25.00 25.00
0.68 6.12
5.00 0.25
1.00 2.00
300.00 3.00
58.37
12.50 43.75
6.25 21.88
65.63
65.63 13.13
78.75
13.13 0.65625
0.66
137.78
137.78 6.89
137.78 13.78
158.44
66.28 8.62
167.06 5.01
172.07
UNIDAD: M2
MONEDA: Bs.
0.60 10.20
300.00 3.00
13.20
12.50 12.50
6.25 6.88
19.38
19.38 3.88
23.25
3.88 0.11625
0.12
36.57
36.57 1.83
36.57 3.66
42.05
19.49 2.53
44.59 1.34
45.92
UNIDAD: M2
MONEDA: Bs.
4.50 23.40
3.50 3.50
18.00 2.70
0.50 8.00
300.00 3.00
40.60
12.50 27.50
6.25 15.63
43.13
43.13 8.63
51.75
8.63 0.43125
0.43
92.78
92.78 4.64
92.78 9.28
106.70
43.56 5.66
112.36 3.37
115.73
UNIDAD: M2
MONEDA: Bs.
0.50 8.00
300.00 3.00
11.00
12.50 25.00
6.25 12.50
37.50
37.50 7.50
45.00
7.50 0.225
0.23
56.23
56.23 2.81
56.23 5.62
64.66
37.73 4.90
69.56 2.09
71.65
UNIDAD: M3
MONEDA: Bs.
80.00 9.60
0.80 13.68
120.00 6.00
110.00 5.50
300.00 3.00
28.18
12.50 26.25
6.25 15.00
41.25
41.25 8.25
49.50
8.25 0.2475
0.25
77.93
77.93 3.90
77.93 7.79
89.62
41.50 5.39
95.01 2.85
97.86
UNIDAD: M2
MONEDA: Bs.
0.91 27.30
120.00 4.80
110.00 6.60
13.30 106.40
3.50 70.00
16.00 3.20
14.00 2.80
300.00 3.00
224.10
12.50 37.50
6.25 18.75
56.25
56.25 11.25
67.50
11.25 0.3375
0.34
291.94
291.94 14.60
291.94 29.19
335.73
56.59 7.36
343.08 10.29
353.38
UNIDAD: M2
MONEDA: Bs.
1.20 21.24
45.00 1.80
30.00 1.50
300.00 3.00
27.54
12.50 31.25
6.25 17.50
48.75
48.75 9.75
58.50
9.75 0.4875
0.49
86.53
86.53 4.33
86.53 8.65
99.51
49.24 6.40
105.91 3.18
109.08
UNIDAD: ML
MONEDA: Bs.
0.80 1.44
120.00 1.20
45.00 4.95
30.00 1.50
300.00 3.00
12.09
12.50 6.25
6.25 3.13
9.38
9.38 1.88
11.25
1.88 0.05625
0.06
23.40
23.40 1.17
23.40 2.34
26.91
9.43 1.23
28.13 0.84
28.98
UNIDAD: M2
MONEDA: Bs.
0.80 10.08
120.00 3.60
45.00 13.50
30.00 7.50
300.00 3.00
37.68
12.50 36.25
6.25 18.13
54.38
54.38 10.88
65.25
10.88 0.54375
0.54
103.47
103.47 5.17
103.47 10.35
118.99
54.92 7.14
126.13 3.78
129.92
UNIDAD: M2
MONEDA: Bs.
0.80 10.08
120.00 3.60
45.00 13.50
30.00 7.50
300.00 3.00
37.68
12.50 36.25
6.25 18.13
54.38
54.38 10.88
65.25
10.88 0.54375
0.54
103.47
103.47 5.17
103.47 10.35
118.99
54.92 7.14
126.13 3.78
129.92
UNIDAD: M2
MONEDA: Bs.
0.80 3.20
120.00 4.80
0.50 3.00
300.00 3.00
14.00
12.50 25.00
6.25 13.75
38.75
38.75 7.75
46.50
7.75 0.2325
0.23
60.73
60.73 3.04
60.73 6.07
69.84
38.98 5.07
74.91 2.25
77.16
UNIDAD: PZA
MONEDA: Bs.
115.60 2196.40
45.00 270.00
135.00 135.00
35.00 70.00
300.00 3.00
2674.40
18.00 234.00
6.25 81.25
12.50 7.50
6.25 3.75
326.50
326.50 65.30
391.80
65.30 3.265
3.27
3069.47
3069.47 153.47
3069.47 306.95
3529.88
329.77 42.87
3572.75 107.18
3679.94
UNIDAD: 0
MONEDA: Bs.
0.91 150.15
120.00 30.00
110.00 38.50
80.00 40.00
16.00 8.00
3.50 87.50
14.00 2.80
300.00 3.00
359.95
12.50 75.00
6.25 37.50
112.50
112.50 22.50
135.00
18.00 2.7
22.50 0.675
0.68
495.63
495.63 24.78
495.63 49.56
569.97
113.18 14.71
584.68 17.54
602.22
UNIDAD: PZA
MONEDA: Bs.
510.00 510.00
8.00 8.00
300.00 3.00
521.00
18.00 36.00
6.25 12.50
12.50 25.00
6.25 13.75
38.75
38.75 7.75
46.50
7.75 0.3875
0.39
567.89
567.89 28.39
567.89 56.79
653.07
39.14 5.09
658.16 19.74
677.90
UNIDAD: Pza
MONEDA: Bs.
270.00 270.00
8.00 8.00
20.00 20.00
300.00 3.00
301.00
18.00 36.00
6.25 12.50
12.50 25.00
6.25 13.75
38.75
38.75 7.75
46.50
7.75 0.3875
0.39
347.89
347.89 17.39
347.89 34.79
400.07
39.14 5.09
405.16 12.15
417.31
UNIDAD: 0
MONEDA: Bs.
140.00 140.00
8.00 1.60
120.00 6.00
30.00 2.10
300.00 3.00
152.70
18.00 36.00
6.25 12.50
12.50 25.00
6.25 13.75
38.75
38.75 7.75
46.50
7.75 0.3875
0.39
199.59
199.59 9.98
199.59 19.96
229.53
39.14 5.09
234.61 7.04
241.65
UNIDAD: PZA
MONEDA: Bs.
160.00 160.00
0.80 0.16
120.00 6.00
85.00 85.00
30.00 2.10
300.00 3.00
256.26
18.00 36.00
6.25 12.50
12.50 25.00
6.25 13.75
38.75
38.75 7.75
46.50
7.75 0.3875
0.39
303.15
303.15 15.16
303.15 30.31
348.62
39.14 5.09
353.71 10.61
364.32
UNIDAD: 0
MONEDA: Bs.
350.00 350.00
35.00 35.00
300.00 3.00
388.00
18.00 36.00
6.25 12.50
12.50 25.00
6.25 13.75
38.75
38.75 7.75
46.50
7.75 0.2325
0.23
434.73
434.73 21.74
434.73 43.47
499.94
38.98 5.07
505.01 15.15
520.16
UNIDAD: M2
MONEDA: Bs.
420.00 420.00
4.00 12.00
18.00 36.00
300.00 3.00
471.00
18.00 234.00
6.25 3.75
12.50 162.50
6.25 3.75
166.25
166.25 33.25
199.50
18.00 2.7
12.50 1.25
33.25 0.9975
2.25
672.75
672.75 33.64
672.75 67.27
773.66
168.50 21.90
795.56 23.87
819.43
UNIDAD: M2
MONEDA: Bs.
77.41 5.42
2.50 0.63
300.00 3.00
9.04
12.50 5.63
6.25 2.81
8.44
8.44 1.69
10.13
1.69 0.084375
0.08
19.25
19.25 0.96
19.25 1.93
22.14
8.52 1.11
23.25 0.70
23.95
UNIDAD: M2
MONEDA: Bs.
77.41 6.97
2.50 0.75
300.00 3.00
10.72
12.50 5.63
6.25 2.81
8.44
8.44 1.69
10.13
1.69 0.084375
0.08
20.93
20.93 1.05
20.93 2.09
24.07
8.52 1.11
25.17 0.76
25.93
UNIDAD: PIE2
MONEDA: Bs.
6.05 6.66
25.00 2.50
300.00 3.00
12.16
12.50 1.25
6.25 0.63
1.88
1.88 0.38
2.25
0.38 0.019
0.02
14.42
14.42 0.72
14.42 1.44
16.59
1.89 0.25
16.83 0.51
17.34
UNIDAD: ML
MONEDA: Bs.
6.00 390.00
8.50 4.25
25.00 2.50
25.00 2.75
500.00 1.50
401.00
18.00 1.44
6.25 0.50
1.94
3.75 0.75
2.69
1.94 0.10
0.10
403.79
403.79 20.19
403.79 40.38
464.36
2.04 0.30
464.66 14.36
479.02
UNIDAD: GBL
MONEDA: Bs.
300.00 3.00
3.00
6.25 12.50
12.50
12.50 2.50
15.00
2.50 0.075
0.08
18.08
18.08 0.90
18.08 1.81
20.79
12.58 1.63
22.42 0.67
23.09
GASTOS GENERALES
UTILIDAD