Anda di halaman 1dari 5

Britten Pears Archive

Stanton Williams Architects


Annotated Drawings

David Caetano Ambrosio

13015530

Technology 2
2015/2016
1:100
Plan

N
1:100
Sectional prespective
1:20
1 AV Strong room section
7 2
8 3
4
5
6 1 PPC aluminium coping
2 Pre-weathered standing seam zinc roof
3 PPC metal profile
9
4 PPC aluminium gutter
10
5 Timber packer to create gutter falls
11 6 Steel structure
12
7 80mm foam glass insulation
8 Structural steel profiled roof deck
9 328-440mm porous clay brickwork (stan-
13 dard metric English bond)
Hydraulic lime mortar (resilient lime mortar
used below DPC level)
10 Pre-cast structural RC planks spanning
between steel beams, with structural mass
concrete topping layer
11 Cavity closer
12 Air gap
18
14 15 16 17 13 Insulated cold room panel system
14 Floating screed
15 Rigid glass insulation
16 In-situ reinforced concrete slab
17 Breathable soffit insulation
18 440mm medium density concrete block-
work
19 Free draining gravel pit
20 Ground
19 20
21 Columns
In-situ RC columns bearing on in-situ RC
pile caps over pre-cast micro piles
21
22 Footings
In-situ RC ground beams spanning be-
tween pile caps
Pre-cast micro piles
22
1:5
Roof coping detail
Aluminium coping
Extruded Aluminium
Bracket
EDPM membrane
Timber fix bracket
DPM
PPC metal profile
Brickwork