Closed Sites:
Natural
Attenuation site
Built in a series of
abandoned sand
and gravel pits
Post Closure
Report completed
for the site
Oshawa creek
borders the site
to the north and
west
Operating waste
transfer station
on site
Old City landfill
on opposite side
of street
The Problem
Sediment
Control Fencing
(Looking south west)
Upper Terrace & Plantings
Geogrid Material
Willow Stakes
Sediment Control
Concrete & Brick Fencing
Debris
Seep B, Area 1
Before & After Sept 2012 repair
Before (Spring 2012) After (November 2012)
(Looking south)
Seep B, Area 1
June 2013
(Looking south east)
Matting slumped
Close up of Area 3
Live staking using native
Stream was diverted to allow a more gradual slope
willow and dogwoods were
installed on part of the
Eroded areas were filled in.
slope as a pilot to evaluate
the effectiveness of their
use up the slope.
Project Began
August 5, 2015
All work
was done
from the top
of the slope
with the use
of an
excavator
with a 60
reach, and
customized
shovel
controls.
Topsoil,
sand and
clay were
stockpiled
(Looking south east)
Seep B, Area 1
Area 1
being
completed
with only
sand
Area 2 will
use sand
and clear
stone
(Looking south)
Installing Geogrid &
FilterSoxxTM to Area 1 & 2
A blower truck is used to fill the GrowsoxxTM. The growth media and any type of
seed mixture is blown into the SoxxTM and this allows for a custom fit to the site.
(Looking south)
A layer of cobbles were applied at the base of the creek as requested by the local
Conservation Authority to protect the fish from the Geogrid
Anchors were then installed
A GrowthMediaTM blanket is then applied above the FilterSoxxTM
In Situ Pilot
Area 3
Added on to
initial Area 1
& 2 design.
Area 3 was
to be used
an in situ
test area
with no
grading at
all.
Area 3
FilterSoxxTM were
installed directly
to the slope with
a drainage layer
of HPB (High
Permeable
Bedding) blown in
behind the
SoxxTM
Area 1, 2 & 3
cassie.scobie@durham.ca info@organic-express.ca
www.durham.ca www.organic-express.ca