Draft
ISOMERISATION UNIT, Rev. A
VRCFP, HPCL VISAKH Page 1 of 231
OPERATING MANUAL
OF
ISOMERISATION UNIT
(UNIT NO.73)
PREFACE
This operating manual for Isomerization Unit of HPCL, VISAKH has been prepared by M/s
Engineers India Limited for M/s Hindustan Petroleum Corporation Limited.
This manual contains process description and operating guidelines for the unit and
is based on documents supplied by the Process Licensor (Axens). Hence the manual
must be reviewed /approved by the licensor before the start-up /operation of the
unit.
Operating procedures & conditions given in this manual are indicative. These should be
treated as general guide only for routine start-up and operation of the unit. The actual
operating parameters and procedures may require minor modifications/changes from those
contained in this manual as more experience is gained in operation of the Plant.
Table of Contents
SECTION-1 ..................................................................................................................................................6
INTRODUCTION .......................................................................................................................................6
1.1 INTRODUCTION ...........................................................................................................................6
SECTION-2 ..................................................................................................................................................8
DESIGN BASIS ...........................................................................................................................................8
2.1 INTRODUCTION ...........................................................................................................................8
2.2 UNIT CAPACITY...........................................................................................................................8
2.3 ON-STREAM FACTOR .................................................................................................................8
2.4 TURNDOWN CAPABILITY .........................................................................................................8
2.5 FEED ...............................................................................................................................................8
2.6 PRODUCTS ..................................................................................................................................11
2.7 BATTERY LIMIT CONDITIONS................................................................................................17
2.8 UTILITY CONDITION ................................................................................................................17
SECTION-3 ................................................................................................................................................21
CHEMISTRY OF THE PROCESS .........................................................................................................21
3.1 INTRODUCTION .........................................................................................................................21
3.2 ISOMER REACTIONS.................................................................................................................21
3.3 ISOMAR CATALYST ..................................................................................................................25
3.4 CATALYST CONTAMINANTS .................................................................................................27
SECTION-4 ................................................................................................................................................30
PROCESS DESCRIPTION ......................................................................................................................30
4.1 ISOMERIZATION UNIT PROCESS SYSTEM: ..........................................................................30
4.2 PROCESS DESCRIPTION ...........................................................................................................34
4.3 CHLORIDE INJECTION FACILITIES .......................................................................................41
4.4 UTILITY SYSTEM.......................................................................................................................41
4.5 WASTE EFFLUENT FROM ISOMERIZATION SECTION ......................................................45
SECTION 5 .............................................................................................................................................47
PRE-COMMISSIONING PROCEDURE ...............................................................................................47
5.1 GENERAL ....................................................................................................................................47
5.2 PRE-COMMISSIONING ACTIVITIES .......................................................................................47
5.3 INSPECTION / CHECKING ........................................................................................................47
5.4 PREPARATION FOR PRE-COMMISSIONING .........................................................................49
5.5 PRE-COMMISSIONING OPERATION ......................................................................................50
SECTION 6 .............................................................................................................................................60
COMMISSIONING PROCEDURE ........................................................................................................60
6.1 FIRST START UP.........................................................................................................................60
6.2 STATUS OF THE UNIT ..............................................................................................................60
6.3 CHRONOLOGY ...........................................................................................................................60
6.4 COMPLETE INERTISING ..........................................................................................................61
6.5 HYDROCARBON CIRCULATION AND INITIAL DRY DOWN ............................................63
SECTION-1
INTRODUCTION
1.1 INTRODUCTION
Isomerization is the conversion of low octane straight chain compounds to their higher
octane branched isomers. The purpose of this process is to saturate benzene and to
isomerise normal paraffins to improve the research and motor octane number of the light
naphtha feed (predominantly C5/C6) before blending into the gasoline pool. The light
naphtha fraction is typically high in normal isomer content resulting in a low octane
number (typically < 68). The isomerization process converts an equilibrium proportion
of these low octane normal isomers into their higher octane branched isomers.
This process developed and licensed by Axens consists of three fixed bed adiabatic
reactors, with benzene saturation carried out in the first reactor, and C5/C6 isomerization
reactions completed in the following two reactors. The isomerization reactions are
carried over a fixed chlorinated platinum catalyst bed in a hydrogen environment.
Operating conditions are not severe as reflected by moderate operating pressure, low
temperature, low hydrogen partial pressure and high catalyst space velocity. These
operating conditions promote the isomerization reaction, minimize hydrocracking and
minimize equipment capital costs.
The feedstock of the Isomerization unit is light hydrotreated naphtha coming from
Naphtha Hydrotreating Unit. Naphtha is mixed with hydrogen. A small amount of
chlorinating agent is continuously injected in to the isomerization catalyst. The mixture
enters in first stage reactor where isomerization reaction occurs. The effluent is cooled
before entering the second stage reactor. Remaining isomerization reaction occurs in
third stage reactor. The effluent is then routed to stabilizer to reduce C4 rate in the
isomerization reactor effluent. The stabilizer overhead is partially cooled and vapor
phase is routed to LPG recovery section while liquid is used as reflux. Stabilizer bottom
is routed to deisohexaniser where low octane C6- n paraffin and methyl pentane is
recycled to the reactor circuit in order to obtain a high octane product.
SECTION-2
DESIGN BASIS
2.1 INTRODUCTION
The isomer unit is required to produce an Isomerate product which is suitable for gasoline
pool.
Important content of design basis is given below.
2.5 FEED
The feedstock of the Isomerization unit is light hydrotreated naphtha coming from
Naphtha Hydrotreating Unit.
Three different feeds were considered for the design of the unit NIT CASE, AM CASE
(Arabian Mixed) and BH CASE (Bombay High).
Impurities:
The Isomerization catalyst is an activated chloride, alumina based catalyst with a
platinum promoter. It is highly sensitive to impurities in the feedstock, in particular
water or other oxygenated compounds. Feed to this unit is hydrotreated and both feed
and make-up hydrogen are passed through dryers to remove any traces of water. Some
impurities are considered to be irreversible poisons such as water and nitrogen
compounds. Others are reversible such as sulfur.
Components (Mole %)
Hydrogen quality
Impurities:
H2S
5 ppm vol max
HCl
0.5 ppm vol max
CO
6-10 ppm vol
COS
1 ppm vol max
CO + CO2
25 ppm vol max
H2O
50 vol ppm
Olefins
10 ppm wt max
N2 compounds
1 wt ppm max
2.6 PRODUCTS
There are four products. The primary product is light Isomerate i.e. deisohexaniser
distillate. The secondary product is heavy Isomerate, i.e. deisohexaniser bottom. The
third product Fuel gas comes from LPG separator drum. The fourth product is LPG
stream produced isomerization stabilizer overhead.
BENZENE 0 0 0
CYCLOHEXANE 0 0 0
NHEPATANE 0 0 0
METHYLCYCLOHEXANE 0 0 0
11DIMET-CYCLOHEXANE 0 0 0
CYCLOPENTANE 0 0 0
BENZENE 0 0 0
LPG Product
LPG is recovered at LPG stripper 73-C-04 draw-off. Estimated flowrates and
compositions are presented hereafter.
SOR NIT Case AM case BH case
Temperature Pressure
C Kg/cm2 g
Feedstock :
o Light Naphta feed 40 7.0
o H2 make-up 40 22.0
o H2 for start-up 45 20.0
o 10% caustic soda 40 3.0
Products :
o LPG 40 16.0
o Light Isomerate 40 7.0
o Heavy Isomerate 40 7.0
o Sweet Fuel gas 40 4.5
o Spent caustic soda 45 6.0
Pressure, Kg/cm2g 33 35 38 40
4 STEAM CONDENSATE
Temperature, oC -- 33 -- 65
Temperature, oC -- 44 -- 65
Pressure, Kg/cm2g 47 50 -- 71
9 DEMINERALIZED WATER
Temperature, oC -- Ambient -- 65
10 PLANT AIR
Temperature, oC -- Ambient -- 65
11 INSTRUMENT AIR
Temperature, oC -- Ambient -- 65
12 NITROGEN
Temperature, oC -- Ambient -- 65
Pressure, Kg/cm2g 7 8 11 17
Temperature, oC -- -- -- --
15 FUEL GAS
16 FLARE HEADER
Super imposed
back pressure at -- 0.1 -- --
B/L(kg/cm2g)
Built up
back pr. -- 1.5 -- --
(kg/cm2g)
Total back
pressure at PSV -- 1.7 -- --
outlet(kg/cm2g)
SECTION-3
CHEMISTRY OF THE PROCESS
3.1 INTRODUCTION
The main purpose of this process is to saturate benzene and to isomerise normal
paraffins to improve the research and motor octane number of the light naphtha feed
(predominantly C5/C6) before blending into gasoline pool. The light naphtha fraction is
typically high in normal isomer content resulting in a low octane number
(typically<68).The isomerization process converts an equilibrium proportion of these
low octane normal isomers into their higher octane branched isomers. In addition the
LPG recovery section allows separating light products (H2, C1, C2) from C3+ either from
isomerization or reformer stabiliser column.
This process consists of three fixed bed adiabatic reactors, with benzene saturation
carried out in the first reactor, and C5/C6 isomerization reactions completed in the
following two reactors. The isomerization reactions are carried over a fixed chlorinated
catalyst bed in a hydrogen environment. Operating conditions are not severe as reflected
by moderate operating pressure, low temperature, low hydrogen partial pressure and
high catalyst space velocity. These operating conditions promote the isomerization
reaction, minimize hydrocracking and minimize equipment capital costs.
General process variables will be presented and discussed first and process performance
will then be discussed with respect to these variables. Finally, the Isomar kinetic model
will be discussed. This model helps to define the operation of the unit and provides
insight into monitoring and adjusting plant operation.
This reaction is highly exothermic and occurs in a separate reactor, namely the
Benzene Saturation Reactor. This allows carrying out the isomerization reactions
separately at lower temperatures in the downstream isomerization reactors.
C6H6 + 3H2 C6H12
3.2.2 Isomerization:
Isomerization is the conversion or rearrangement of the structure of a compound
to its more branched, higher octane structure. These rearrangements are depicted
by the following formula:
CH3
CH 3 - CH 2 - CH 2 - CH 2 - CH 2 - CH 3 CH 3 - CH - CH 2 - CH 2 - CH 3
CH 3
n-hexane 2 methylpentane
(RON = 30) (RON = 74 )
CH 3 - CH 2 - CH - CH 2 - CH 3
CH 3
3 methylpentane
(RON = 75 )
CH 3
CH 3 - C - CH 2 - CH 3
CH 3
2,2 dimethylbutane
(RON = 92)
CH 3
CH 3 - CH - CH - CH 3
CH 3
2,3 dimethylbutane
(RON = 104)
These reactions, as shown, are reversible and the final distribution of the isomers is
based on the equilibrium composition which is dictated by the reactor process conditions
and kinetics.
In addition to the isomerization reactions, there are other side reactions taking place as
well, and some of them are not desirable.
+ H2 C 5 H 12
C 5 H 10
(cyclopentane)
+ H2 C 6 H 14
C 6 H 12
(cyclohexane)
CH 3
+ H2 C 6 H 14
C 6 H 12
(methyl cyclopentane)
Naphthenic or cyclic components tend to inhibit the isomerization reactions and are
therefore undesirable in large quantities. The cyclic components are absorbed on the
catalyst and reduce the active sites available for paraffin isomerization. They also
consume hydrogen, produce exothermic heat which is undesirable from the
isomerization equilibrium standpoint. However undesirable as they are, they are a
natural fraction of C5/C6 cut naphtha and are difficult to eliminate without also
eliminating other desirable components.
3.2.4 Hydrocracking
Operating at the low severity reactor conditions, very little C5/C6 hydrocracking occurs
in the isomerization reactors. C7 paraffins however hydrocrack readily to produce C3 and
C4 components. Much of the hydrocracking occurs in the first reactor which typically
operates at a higher temperature. Hydrocracking reactions consume hydrogen, and hence
it is recommended to restrict the C7+ content of the isomerization feedstock.
C7 H16 + H2 C3 H8 + C4 H10
The metallic function of the catalyst, in this case platinum, catalyses the formation of an
olefin intermediate by dehydrogenation of the paraffin. The olefins are then converted
into carbonium ions by the addition of a proton during adsorption onto the acidic surface
of the catalyst.
+H+
CH3 - CH2 - CH2 - CH = CH2 CH3 - CH2 - CH2 - CH - CH3
C3
CH3 - CH2 - CH2 - CH - CH3 CH3 - CH2 - C - CH3
C3 C 3
Pt
CH3 - CH2 - C = CH2 + H2 CH3 - CH2 - CH - CH3
+
CH3 - CH2 - CH2 - CH2 - CH3 + H A CH3 - CH - CH2 - CH2 - CH3 + H2 + A
After rearrangement, isopentane is formed and the chain is propagated by the generation
of a new acid site.
CH 3 CH 3
+
CH 3 - C - CH 2 - CH3 + A + H2 CH 3 - CH - CH 2 - CH 3 + H A
Another principal theory of initiation and propagation is that based on the Friedel-Crafts
theory. Friedel-Crafts isomerization is believed to require the presence of traces of
olefins or alkyl halides as carbonium ion initiators with the reaction thereafter
proceeding through chain propagation. The initiator ion, which needs to be present only
in small amounts, may be formed by the addition of HCl to an olefin which is present as
an impurity in the paraffin or is formed by paraffin hydrocracking.
After skeletal rearrangement, isopentane is formed and the chain is propagated by the
generation of a new normal carbonium ion.
C3 C3
reduces the metallic function of the catalyst affecting the hydrogen transfer mechanism.
This decrease in activity is temporary and recovery is normally rapid once the sulfur has
been removed. However, an increase in reactor temperature and a higher make-up
hydrogen rate will assist in purging the sulfur from the catalyst more rapidly. While
sulfur is present in the feed, an increase in temperature may help to partially compensate
for the reduced catalyst activity.
b) Water / Oxygenates:
The deactivation which results from water or other oxygenates breakthrough is
permanent. The oxygenated compounds react chemically with the active chloride on the
catalyst, which is chemically bound into the alumina structure during manufacture. The
water, once it reacts with the catalyst is chemically bound as hydroxyl to the alumina
and the chloride is removed as HCl. Approximately one kilogram of oxygen in any form
will deactivate 100 kg of catalyst. If breakthrough occurs, the catalyst deactivation will
occur in a piston-like fashion moving down the first catalyst bed. In addition to the loss
of product quality, a clear sign is the lack of reactor T in the top portion of bed and this
inactivity slowly moving down the bed. Once the catalyst is deactivated, it must be
removed for platinum recovery and replaced with fresh catalyst.
c) Nitrogen Compounds:
This refers to organic nitrogen or ammonia, not to molecular nitrogen N2. Nitrogen
compounds react to form ammonia which in turn reacts with the chloride in the catalyst
or the HCl to form ammonium chloride salt. This leads to a permanent deactivation of
the catalyst by a coating of the catalyst active sites, loss of chloride and possibly
inactivity due to maldistribution from salt deposits.
d) Fluoride Compounds:
This is also a permanent catalyst poison caused by the fluoride bonding to catalyst active
sites affecting the catalyst acidity. Again one kilogram of fluoride will deactivate
100 kilograms of catalyst.
Maximum Allowable Contaminant Levels in
a) Hydrogen Make-up :
SECTION-4
PROCESS DESCRIPTION
Benzene hydrogenation:
This reaction takes place in the superior part of the first reactor 73-R-01. Benzene
hydrogenation is an exothermic reaction (16660 kcal/kmole of consumed hydrogen).
Isomerization
Isomerization is the conversion of hydrocarbons to their isomers, which have the same
molecular formula but a different arrangement of molecules. C5 /C6 Isomerization
section specifically converts normal C5 / C6 paraffins to their isomers, i.e. to a higher
octane branched arrangement, over a proprietary platinum catalyst in presence of
hydrogen. The conversion of normal paraffins to their isomers is determined by the
reaction equilibrium at reactor operating conditions.
The term isomer refers to compound which have the same molecular formula but
different structural formula or a different arrangement of molecules. In general any
compounds that are linear or straight chain are termed normals, if they are in a
different arrangement, i.e. branched, they are termed isomers.
Examples:
n-pentane C5 H12:
H H H H H
H C C C C C H
H H H H H
Pentane has five carbon atoms. When in a straight chain as shown, this is called normal
pentane or n-pentane. The Research Octane Number (RON) of n-pentane is 62.
i-pentane C5 H12:
H H H H
H C C C C H
H H H
H C H
This is isopentane, one of the isomers of n-pentane; it has the same molecular formula
but a different arrangement or structure. Isopentane or i-pentane has a Research Octane
Number (RON) of approximately 93.
Isomerization is simply the conversion of compounds to their isomer, i.e., to a higher
octane branched arrangement.
Similarly with hexane:
n-hexane C6 H14:
H H H H H H
H C C C C C C H
H H H H H H
Hexane has six carbon atoms. When in a straight chain as shown, this is called normal
hexane or n-hexane. The Research Octane Number (RON) of n-hexane is 30.
i-hexane C6 H14:
H
H C H
H H H
H C C C C H
H H H
H C H
This is isohexane, one of the isomers of n-hexane; again it has the same molecular
formula but a different arrangement or structure. This is called 2,2 Dimethylbutane
(2,2,DMB) and has a Research Octane Number (RON) of approximately 92.
Not all n-pentane and n-hexane will convert to their isomer but a certain percentage or
equilibrium amount will exist at given operating conditions. This is then the measure of
the performance of an Isomerization unit, i.e. the percentage of the isomer in the reactor
effluent.
The conversion of n-pentane to isopentane and n-hexane to 2,2,DMB are only two of the
many reactions occurring simultaneously in the Isomerization process. These reactions
take place in the 73-R-02 and 73-R-03 reactors.
The rate of diluent recycle must be adjusted by operator in order not to exceed 35C of
exothermicity in the hydrogenation reactor.
4.2.5. Deisohexaniser
Deisohexaniser (called DIH) 73-C-02 is fed with stabilizer bottom which preheat the
DIH pump around through DIH feed/recycle exchanger 73-E-07. Deisohexaniser
recovers stabilized isomerate product and recycles low octane methyl-pentanes and n-
hexane to the reactors. This is done via the DIH recycle drum 73-V-07, which is fed on
level control. Recycle is pumped, by pump 73-P-07 A/B as a recycle to the reactor
section after being cooled successively in the deisohexaniser recycle/reactor feed
exchanger 73-E-02 and recycle trim cooler 73-E-08.
Remaining liquid from 73-P-07 A/B is fully vaporized by heat exchange with DIH feed
in 73-E-07, and is recycled to the DIH column, in order to reduce the heat load required
for reboiling of the column.
Overhead vapor of the column is totally condensed through deisohexaniser air condenser
73-A-03 and is routed to the deisohexaniser reflux drum 73-V-08. Reflux is pumped by
deisohexaniser reflux pump 73-P-06 A/B under flow control. Isomerate product is
pumped, under flow control reset by 73-V-08 level control, by pumps 73-P-09 A/B and
is further cooled in sea water cooler 73-E-09 and routed to storage.
The Deisohexaniser reflux drum pressure is controlled by split range pressure controller
at column overhead.
Deisohexaniser bottom is reboiled by medium pressure steam in exchanger 73-E-10.
Steam flow controller to the reboiler is reset by temperature control at the sensitive tray
of the column.
The bottom stream is concentrated in C7+ and C6 Naphthenes. It is pumped by
Deisohexaniser bottoms pumps 73-P-08 A/B to the LPG recovery section, where it is
used as lean oil make-up. The lean oil is under flow control cascaded by the column
level control.
The rich oil containing the absorbed LPG is pump from the cold separator drum through
73-P-14 A/B, underflow control cascaded with level control of separator drum 73-V-11,
to stripper 73-C-04. The stripper feed is preheated through heat exchangers 73-E-14 and
73-E-15, in order to optimize the recovery.
LPG stripper reboiler with HP steam as in 73-E-17 allows recovering the LPG product
which is produced as side stream liquid draw-off below pasteurization zone. Draw off is
cooled in LPG trim cooler 73-E-18 A/B and pumped by LPG product pumps 73-P-16
A/B to the battery limit. The LPG product is on flow control cascade by column top
temperature control.
Stripper overhead is partially condensed in LPG stripper condenser 73-E-19 A/B. The
stripper off gas is recycled and mixed with the dry scrubber off gas. The stripper
overhead is under pressure control.
The stripper bottoms stream is routed, under flow control cascade with the level control,
to feed/bottom heat exchangers of LPG stripper via 73-P-15 A/B. then lean oil is
combined with DIH bottom stream. The mixture is cooled down through LPG stripper
feed/bottom exchanger 73-E-15 and through water cooler 73-E-16 A/B. Part of this
stream is sent to export via storage. The other part is fresh lean oil (to be cooled down
before absorption of LPG) and is recycled to packed zone of the LPG separator drum.
Reboiler duty is under temperature control at the sensitivity tray of column.
In case LPG recovery is in shut down, facility is provided to by-pass completely this
section and route scrubber off gas directly to Fuel gas or to flare.
maintained at the 55 oC through the caustic recycle heater 73-E-12, in order to keep the
caustic a few degrees warmer than the feed gas to avoid potential foaming problems due
to any hydrocarbon condensation.
Both the scrubber section are packed with raschig rings. The caustic inventory
requirement is stored in the tower bottom section and feed gas is bubbled through this
caustic inventory. A portion of the circulating caustic is sprayed on to the column walls
below the caustic wash packed section to avoid any wet hydrogen chloride corrosion in
this part of the scrubber.
When the concentration of circulating caustic has been decreased to about 2% wt, the
caustic inventory is drained through pump 73-P-11 A/B discharge and tower bottom is
filled up with 10% wt fresh caustic. Spent caustic is sent to the spent caustic system.
Fresh 10% wt is made up through pumps 73-P-10 A/B.
The gas leaving the caustic wash section is washed with water in the top packed section,
to remove any entrained caustic. Water is collected in the chimney tray below the water
wash packed section, and is circulated using the pumps 73-P-13 A/B. water loss to the
vent gas leaving the scrubber is made-up periodically by fresh de-mineralized water
addition (via pump 73-P-12 A/B and de-mineralized water drum 73-V-10), and once
every several days the water inventory is drained and replaced.
The return water is collected from all the equipments through cooling water return header
and sent to B/L.
Cooling water regularly PH, Chlorine, turbidity and conductivity to be monitored regularly.
In this PH and chlorine are most important parameters. Due to this, chances of exchanger
shell or tube damage increases.
4.4.9. Nitrogen
A 3 header supplies N2 to the ISOM unit. N2 is used for various purposes in equipment,
line etc. for inertisation, blanketing, purging etc. In addition to that following permanent
connections are provided for N2 in the ISOM unit.
- Hydrogen make up compressor (73-K-01 A/B)
- Isomerisation feed surge drum (73-V-01)
- Close Blow Down system (73-V-16)
- Stabiliser bottom chloride guard bed(73-V-06)
- Deisohexaniser reflux drum (73-V-08)
- Stabiliser (73-C-01)
- Stabiliser reflux drum( 73-V-05)
- Hydrogenation reactor flush drum (73-V-04)
- Isomerization reactors (73-R-02 / 03)
- Hydrogenation reactor (73-R-01)
- LPG separator drum (73-V-11)
- LPG stripper (73-C-04)
- ISOM feed dryers (73-DR-01 A/B)
Quantity, Tons/week 23
Temperature, oC 45-50
Water 87.3
Also, a small amount of spent water that is purged periodically from the scrubber water
wash section is combined with the spent caustic. This purge water contains entrained
caustic and dissolved light hydrocarbons.
SECTION 5
PRE-COMMISSIONING PROCEDURE
5.1 GENERAL
As the new unit nears completion, there is a large amount of preparatory work, which
should be performed by the operating crew. A planned check of the unit will not only set
the foundation of a smooth start-up, but will also provide a firm basis for acquainting
operators with the equipment. Start-up is a critical period and the operator must know
exactly the operation of all equipments.
Some of the pre-commissioning works can be carried out simultaneously along with
construction. But, care in the organisation of this work is necessary so that it will not
interfere with construction work. It is most important to plan schedule and record with
checklists and test schedules all the preliminary operation and to co-ordinate the
construction programme.
- Exchangers
- Pumps
- Compressors
- Instrumentation
- Catalyst/Chemical Inventory
b) Instruments
All instrument tapings for pressure, level and flow should be clear and thermo wells should
not foul with the internals. These should be checked prior to box up of the equipment.
Instruments will be checked, starting from the controller and proceeding logically through
the control loop. Cascade control system will be checked from the impulse point of
primary loop. Operating crew should check proper mounting of control valves. Control
valves responses should be checked for controller outputs. The shutdown systems of the
equipments should be checked by simulating the various conditions in the control circuits.
c) Relief Valves
Relief valves will be set in the shop and mounted before the system pressure test. Block
valves ahead and after relief valves will be checked for lock open or lock close position as
per P&ID. Relief valves will be checked against specifications.
d) Rotary Equipment
All rotary equipment such as pumps, compressors, turbines etc. are to be checked for
bearings, internals and free movement. The auxiliaries, control systems on this equipment
should be thoroughly inspected.
e) Drainage System
Check the OWS and blow down system against drawings. Check for free flow.
- Check that communication between units, control room, offsites and utilities are
complete and in working condition.
- Ensure that the required lube oil, grease and other consumable are available in
the unit.
A. Steam Network
Network shall be blown through completely from battery limit with a strong steam flow in
order to clean the lines. The following steps are recommended:
- Check network, all equipment will be disconnected to avoid entry of flushed
material.
- Drain all the low points. If necessary open steam trap inlet flanges.
- Open slowly battery limit valve and let the temperature rise in the header, slowly
and steadily.
- Check support of fixed points and expansion loops.
- When line is hot, blow it through completely with a strong steam flow.
- Close battery limit valve and prepare another network. When the blowing is
satisfactory, reconnect all equipment and remount steam traps. Recharge header
as above.
- To gauge the effectiveness of the steam blowing (and the amount of scale left in
the lines), target plates should be installed at the blow down points. The lines
should be repeatedly blown down until virtually unmarked target plates are
obtained. Condensate lines should be continually checked and traps removed
and cleaned if plugged.
Note: The following precautions to be taken while blowing / commissioning steam header:
- To drain the low points of the lines before and during heating period in order to
avoid water accumulation, this causes hammering.
- To open drain / vent during cooling period to prevent vacuum formation
- To isolate the instruments, remove orifice plates and control valves; to re-install
the orifice plates and control valves after blowing is over.
orifice plates will be removed and re-installed, after the lines become clean. When system
has been flushed, charge the lines to the operating pressure.
The following precautions to be taken:
- To open vents at high points in order to expel air from equipment and piping
- To open the battery limit valve, slowly and steadily.
5.5.3. Flushing
After pressure test has been completed on any vessel with its connected piping,
receivers, exchangers, etc., required blanks are pulled and water is circulated for the
purpose of removing any dirt, scale, etc. Much of the dirt is picked up in the pump
screens where it is taken from the system by removing and cleaning the screen.
All possible lines and pumps should be used during the washing procedure for complete
cleanout of the system. Of course, no water circulation should be carried out in the gas
sections of the unit. Temporary water connections should be provided at convenient
locations in the system for carrying out water flushing.
The following points should be remembered during water flushing.
- Low point drains and high point vents should be purged.
- All instrument connection should be isolated, orifice plates removed, control
valves isolated and by-passed. In case there is no bypass, remove control valve
and flush the line. The valve will be installed after clean water starts coming out
and further flushing may be continued.
- If there is any heat exchanger in the line, flushing should be done up to and
around the exchanger using by-pass line. It should be ensured that dirty water
from initial flushing does not get into the exchanger. Wherever by-passes are not
available, the flanged joints at the inlet of heat exchanger should be first opened
and the line flushed till clear water starts coming out. Then reconnect flange and
flush through the exchanger.
- At each opening of the flanged joints, a thin metallic sheet should be inserted to
prevent dirty water from entering the equipment or piping.
- The flow of water should preferably be from top to bottom for flushing of heat
exchanger coolers. The bottom flange of the equipment should be opened to
permit proper flushing.
- The flushing should be carried out with maximum possible flow of water till
clear water starts coming out.
- Vertical lines which are long and rather big (say over 100 mm dia) should
preferably be flushed from top to bottom. This will ensure better flushing.
Filling the lines and releasing from bottom is also helpful. The rundown lines
can also be flushed conveniently from the unit to the respective tanks.
- It should be ensured in all flushing operation that design pressure of lines and
equipment are never exceeded. After flushing of lines and equipment, water
should be thoroughly drained from all low points. Lines and equipment
containing pockets of water should not be left idle for a long time; it is preferable
to dry these lines and equipment with air after water flushing.
Where low chloride test water is required to prevent the potential of chloride stress
corrosion cracking of austenitic stainless steel, it is especially important that all water
from low points is removed by being purged with nitrogen. Otherwise, as the remaining
water evaporates, the chloride concentration that started at lower concentration will
concentrate to levels that can (and will) crack or cause pitting of the austenitic stainless
steel. If pitting occurs, it may be discovered during a final equipment inspection (for
example, at the bottom of a fractionation column), allowing time for repairs. On the
other hand, if stress corrosion cracking occurs it will probably not be discovered until
the equipment temperature is increased for the first time, causing a delay in the start up
schedule.
i) Motors
Each motor should be checked and started to ensure that it has the correct direction of
rotation. The motor speed should be checked with tachometer to ensure that RPM is
correct. The manufacturers lubrication schedule should be used to ensure that all
lubrication points have been serviced. After a short run each bearing should be felt to
ensure that it is free and not overheated.
ii) Pumps
Prior to unit start up, all centrifugal pumps should be thoroughly checked and run in
properly (after pressure testing and water flushing) as indicated in the following outline:
The pumps will be started and operated according to the manufacturers instructions.
CAUTION: Many high head pumps are not designed to pump water. To do so can
result in damage to the pump internals. Check the vendors specifications before
attempting to run in pumps with water.
subjected to test pressures above its range. Also, never pull a vacuum on a pressure
instrument or gauge unless it is specifically designed for it.
All instrument air piping should be tested at 7kg/cm2g (100 psig), with compressed air.
Soap solution should be used on all joints to check for leakage. Care should be taken to
ensure that this high air pressure is not put on any instruments or control valve
diaphragms. Likewise, when pressure testing of the unit is done, care must be taken that
the fuel gas pressure balance valves are blinded off to keep high pressure off the
diaphragm. Before starting up, all instruments should be serviced and calibrated. This
includes carefully measuring all orifice plate bores with a micrometer. The following
guidelines may be adopted for checking and calibration of all instruments.
i) Orifice Plates
Before each orifice plate is installed the orifice taps should be blown clear. The orifice
plate should be callipered to check, if the correct size orifice plate is installed. The plate
should then be installed after checking for the correct direction.
ii) Differential pressure Transmitters and Receivers
Ordinarily these should be calibrated locally against a manometer. The calibration
should be checked at the receiver, which may be board or locally mounted, recorder or
indicator.
iii) Pressure Transmitters and Receivers
These should be checked in place. The calibration of the receiver should be checked at
the same time.
iv) Alarms
All alarms, auto start and cut off systems should be checked by simulating the
conditions.
- Hydrogen Dryers
- Scrubber off-gas dryers
- Reactor (support material)
- Caustic scrubber (Raschig Ring)
- Chloride guard bed (stabiliser bottom)
Before loading ensure that the vessels are clean and dry. They have previously been
pressure tested and water washed, ensure there are no water pockets in the piping loops
(not critical for the scrubber). Brush and vacuum the inside of the vessel if necessary and
ensure they are completely isolated and flanges or manways are open, top and bottom.
The inside must be thoroughly vented with air.
v) Scrubber section:
Scrubber 73-C-03
Caustic Recycle Heater 73-E-12
SECTION 6
COMMISSIONING PROCEDURE
6.3 CHRONOLOGY
The first start up sequence is as follows:
- Complete inerting of
the dryer section, reactor section and regeneration section
the stabilizer, deisohexaniser, LPG recovery section
- Hydrogen sweep
- Oil circulation and stabilizer / deisohexaniser / LPG recovery section start-up.
- Reactor oil in
- Acidizing and final dry-out
- Hydrogenation / Isomerization catalyst loading
- Isomerisation unit start-up
- Lining out the isomerisation unit at design conditions
- LPG recovery start-up
- Lining out LPG recovery section at design conditions
- Set in service the pressure controllers on the stabilizer feed and overhead, the
scrubber, LPG stripper and the LPG separator drum. Route any excess gas first to
flare, then to fuel gas.
- Survey the unit for leaks. Set the hydrogen make-up flow at 40% of design rate.
- Switch the flow pattern around the dryers and ensure all possible dead legs are
adequately purged.
Hydrogen sweep:-
a) Reaction section :-
b) Stabiliser Section :-
Start up line
73-DR-02 A/B 73-V-05 73-E-06 A/B 73-A-02
(2-P-73-1514)
73-PV-2001 73-C-01
73-C-04
- Slowly fill each Feed Dryers separately using the globe valves and venting the
nitrogen to flare through the pressure safety valves bypass. Dryers filling and
nitrogen displacement is to be monitored through the level glasses on the PSV
bypasses.
- Once both dryers are full, the start-up line by passing the dryers is closed and the oil
circulation is continued to the stabilizer through the reactor bypass line.
- Commission the stabilizer overheads air condenser.
- As the level appears in the stabilizer, commission the reboiler.
- Slowly bring the stabilizer up to operating temperature. As the level appears in the
reflux drum 73-V-05 start the reflux pumps 73-P-05A/B and reflux back to the
column.
- Adjust the flow on the reactors by-pass line to reach a circulation rate of 60% of
design throughput.
- Once the circulation is steady, line up the regeneration circuit to by-pass the dryers.
- Crack open the flow controller on the regeneration loop and flush the loop free of
foreign material, back to rundown to storage.
- Adjust the flow to design rate, hold for 4 hours and then stop the circulation through
the regeneration loop. Close the by-pass line and re-establish the flow through the
dryers.
- Calibrate the moisture analyzers on the feed and hydrogen dryers. Commission them
to monitor dryer performance.
- During the circulation, switch the flow pattern around the dryers and ensure all
possible dead legs are adequately purged.
Start-up line
4-P-73-1321
8-P-73-1908
(LV-2101 close)
2nd Step:-
4-P-73-1615)
4-P-73-2101
73-V-01
6-P-73-1105
From 73-V-01 73-DR-01 A/B
6-P-73-1303
Reflux
Commission 73-E-05 & A02
reboiler & condenser
after level appears
Note: Enclosed start up circuits will be detailed by process licensor during Pre-
commissioning/Commissioning and shall be submitted accordingly by the licensor.
Procedure
- Line-up the internal circuit between 73-V-11 (LPG separator drum) and 73-C-04
(LPG stripper).
- Slowly introduce heavy product from DIH bottom through FV-2202 at 73-P-08
discharge to 73-V11 upto 100 % at LG-2802 (LPG separator drum).
- Start the pump 73-P-04 and through FV 2801 introduce liquid to 73-C-04 (LPG
stripper)
- Commission VHP steam to 73-E-17 (LPG stripper reboiler) and bring 73-C-04 at
total reflux conditions. Make-up heavy product to 73-V-11 and restart 73-P-14 as
necessary to maintain LPG stripper levels.
- Commission the PIC-2801 at the LPG separator drum overhead. When PIC has
reached normal operating pressure set point, open UV 2501.
- During the hydrogen and hydrocarbons circulation, it will be necessary to switch the
flows through the different reactors circuits as discussed previously. It is imperative
that all piping sections are exposed to this dry out step. Also, line-up sulfur
stripping line.
- Continue drying until the water content is below 10 ppm at the reaction section
outlet. The water content in the heavy product to storage must also be lower than 10
ppm.
- Regenerate the dryers (feed and hydrogen and) on a regular basis.
- Commission the chloride absorber on stabilizer bottoms only when water content is
below 10 ppm.
Note 1: During this step all efforts should be made to get all moisture analyzers working
properly and most specially those down stream reactors, which will be used during
acidizing.
Note 2: The moisture analyzer installed downstream the reactor, which will be used
during acidizing should have its sampling system equipped with separator liquid / gas.
The liquid sample only will be send to the moisture analyzer cell.
The analyzer measure repeatability should be checked carefully at this stage as the
acidizing step follow-up will rely only on the good operation of this analyzer.
73-E-02
73-E-03
73-V-06 bypass
(4-P-73-1902)
NOTE: Enclosed start up circuits will be detailed by process licensor during Pre-
commissioning/Commissioning and shall be submitted accordingly by the licensor.
Acidizing Step :
With hydrogen flow at design rate, C5 / C6 feed at 60% of design, and the unit steady
with the reactors inlet temperature set at 160C.All hydrogenation reactor, recycle
section equipments, isomerization reactors and equipments are including in this
acidizing step.
Through out the HCl injection period, monitor the caustic strength in the scrubber
bottoms. Replenish as necessary. Do not allow NaOH concentrate decrease below 3%
wt. Check HCl content in the scrubber off gas with dragger tubes (HCl-1ppm vol)
1st Step:-
- Inject 5 kg of HCl into the hydrogen line going to hydrogenation reactor (1st
hydrogen make up line) at a steady rate over a 5 minute period.
Note: the first injection should take into account the volume of the injection line
(the quantity injected to be adjusted).
- Wait for one hour or until the reactor effluent sample pot vapour contains less
than 10 ppm HCl.
- Reconnect the moisture analyzer and obtain a reading on the sample pot liquid,
then disconnect. Record the moisture level, HCl addition and sample time (see
typical injection table data report attached).
- Continue HCl injecting in the same manner until the moisture level peaks start to
decline. During this period continue draining all low points, purging instrument
lead lines, flushing bypasses around control valves and switching the reactors
flow pattern.
- Continue HCl injection until no further response is noted by the moisture
analyzer.
- Check that the moisture analyzer is operating correctly and that the readings are
correct.
- Add another 10 kg of HCl over a 10 minute period. When the HCl content has
decreased below 10 ppm, recheck the moisture content. If a response is noted
2nd Step:-
- Swing the HCl line injection into the hydrogen line going to the isomerisation
section (2nd hydrogen make up line)
- Inject 5 kg of HCl at steady rate over a 5 minute period.
- Repeat same operation as 1st (regular HCl injections) until the moisture content is
1 ppm at the reactor outlet.
Remark : in case of vaporisation of all dissolved HCl in the separator drum, an
additional HCl injection point is foreseen at the separator outlet.
3rd Step:-
- Reduce the first isomerisation reactor inlet temperature to 100C over a one hour
period.
- When the reactors have cooled to 100C, slowly open the reaction section bypass
and route the naphtha around the reactors to the stabilizer.
- Reduce the steam flow to the Reactor Feed Heater until closed.
- The naphtha feed flow to the stabilizer can be stopped at this stage.
- Shut-off steam to the reboiler and shutdown the reflux pump.
- Reduce the stabilizer bottoms level to 30% and block in the stabilizer on standby
mode until ready for restart. The deisohexaniser and LPG recovery section
remain in standby mode.
- The stabilizer off gases are sent to the scrubber.
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
exothermic reaction; this phenomenon will be short in duration, the magnitude of the
temperature increase will depend very much on the feed quality. Under no
circumstance the hydrogenation reactor should be above 200C. If it occurs, follow
the emergency procedure for high reactor temperature.
- Slowly pressurize with hydrogen the hydrogenation reactor flash drum.
- Repeat the hydrogen batch injection until there is no benzene in the recycle loop and
no temperature increase in the hydrogenation reactor.
- Start the isomerization reactor feed pump 73-P-04 A/B and line-up the
hydrogenation reaction section to the stabilizer 73-C-01, the isomerization reaction
section is still bypassed.
- With the stabilizer in normal operation, route the feed to the isomerization feed surge
drum 73-V-01. Close the loop from the feed surge drum 73-V-01, through the dryers
73-DR-01 A/B and the hydrogenation reaction section to the stabilizer 73-C-01 and
the chloride guard bed 73-V-06.
- Pressurize with hydrogen at design flowrate the isomerization section using the 2nd
hydrogen make-up line.
- Adjust the feed dryers inlet at 50% of design flowrate using fresh naphtha make-up.
- Adjust the hydrogen at the hydrogenation reactor inlet at 50% of the design flowrate.
- If necessary, rundown the excess of stabilizer product to off-spec storage.
- When there is no benzene in the recycle loop and no temperature increase in the
hydrogenation reactor 73-R-01, reduce the feed heater temperature down to 75C.
- Check the quality of the hydrogenation reactor outlet.
H2 through 8-P-73-1503
6-P-73-1303
73-V-01 Hydro treated naphtha 73-DR-01A/B 73-E-02
6-P-73-1105
73-E-03
4-P-73-1322
73-E-04
73-A-01
73-R-01
73-V-08
73-P-03A/B 73-V-04
73-P-06A/B
6-P-73-1705
73-C-01 73-P-04A/B
73-C-02 73-V-06
73-P-08A/B 3-P-73-2212
Off-spec isomerate through 73-E-11
3-P-73-3306 / 3310
(through 73-E-11)
NOTE: Enclosed start up circuits will be detailed by process licensor during Pre-
commissioning/Commissioning and shall be submitted accordingly by the licensor.
- Allow the operation to stabilize, adjust conditions where necessary, ensure all
instrumentation is working and in the proper range. The first isomerization reactor
should operate alone for at least two days in steady state operation before the second
isomerization reactor is brought on-line.
73-P-04A/B
6-P-73-1706
73-R-02
73-E-03
Offgas to scrubber
8-P-73-1805
73-C-01
73-C-02 73-V-06
Isomerate to storage
(4-P-73-3308)
NOTE: Enclosed start up circuits will be detailed by process licensor during Pre-
commissioning/Commissioning and shall be submitted accordingly by the licensor.
Procedure:
- Slowly increase the C5/C6 isomerization unit feed rate to design in increments of
10% per hour. Monitor the catalyst bed temperatures for higher than normal
exotherms. Allow the unit to stabilize after each change.
- Record all operating data at each 10% increment, i.e., flows, temperatures,
conversion levels out of each reactor.
- At design capacity and steady temperatures, sample the isomerate product for
analysis.
- Adjust temperatures as necessary to improve the conversion ratios of the isomers.
The first reactor temperature should be adjusted to maximize isomerization in the
first reactor, and the second reactor temperature adjusted to take the advantage of the
higher equilibrium isomer content at lower temperatures. A sample point is located
at the first reactor outlet to allow an analysis of the conversion in the first reactor.
- Check the scrubber off-gas H2 analyzer to ensure that H2/HC ratio is above 0.06.
- Adjust the temperature and reflux on the stabilizer to meet the product RVP
requirements and to minimize the loss of C5+ in the overheads. Also, the stabilizer
should completely strip-out the HCl from the reactor effluent.
- PC 2501 to be reset (PC 2501 and PV 2501 to remain in control mode in normal
operation of the unit.
For example during the unit life, there will be instances when the lead isomerization
reactor will need to be taken out of service for catalyst replacement with other reactor
remaining in service. Restart procedure at this situation begins at the point for series
flow operation in the initial start-up procedure. Except in this case this reactor will be
under a low pressure nitrogen atmosphere.
As the freshly loaded catalyst will be cold, the reactor can be re-pressurized using the in-
service reactor feed through the bypass globe valve. As soon as the freshly loaded
reactor is up to operating pressure follow the series flow start-up procedure to align this
reactor in the tail position of the flow configuration.
SECTION 7
NORMAL OPERATING PROCEDURES
7.1 INTRODUCTION
After the unit has been started up and lined out, the focus shifts to reaching and
maintaining a state of optimum operation. This state of optimum operation can be
achieved by establishing a few general operating rules and being aware of potential
problems which can occur. First, a means of judging performance must be defined.
Secondly, a list of operating variables is established. Using these operating variables, an
approach to operating the Isomar unit is outlined with respect to the performance
indicators. This procedure establishes a logical method for operating the plant,
increasing yields and ensuring longer catalyst cycles.
Reaction Section:
- The set point of hydrogen make-up going to the hydrogenation reactor is adjusted by
the operator according to the amount of benzene in the feed (on line analyzer).
- Hydrogen make-up gas going to the isomerization section is under flow ratio control
with the total liquid feed to the reactors.
- First isomerization reactor inlet temperature is controlled by steam flow to the
Reactor Feed Heater and by split range on the recycle air cooler and its by-pass.
- Second isomerization reactor inlet temperature is controlled through a by-pass of the
First stage reactor Feed / Effluent Exchanger.
- The reactor section pressure is controlled directly by a back-pressure controller on
the stabilizer feed.
Stabilizer
- Stabilizer bottom is supplied to the Deisohexaniser on flow-control reset by level
control of the stabilizer tower.
- Reboiling is under steam condensate flow control reset by a sensitive tray
temperature.
- Pressure is controlled by a pressure controller on the stabilizer off gas.
- Reflux is under flow control reset by the Stabilizer Reflux Drum level.
Deisohexaniser
- Feed from the stabilizer bottoms is supplied on flow control reset by the stabilizer
bottoms level.
- Reflux to the Deisohexaniser is on flow control.
- Distillate product is withdrawn on flow control reset by level control of the reflux
drum.
- Side-draw is on level control of the Deisohexaniser Recycle Drum.
- Side-draw pump around is on flow control.
- Reboiling is under flow control reset by a sensitive tray temperature.
- Column pressure is controlled by a split range controller.
- Deisohexaniser bottom is supplied to the LPG recovery section on flow-control reset
by level control.
- LPG separator drum bottom is routed to the LPG stripper on flow-control reset by
level control.
- Lean oil is on flow control.
- LPG stripper pressure is controlled by a pressure controller on the overhead gas.
- Reboiling is under flow control reset by sensitive tray temperature.
- LPG stripper bottom is routed to the storage on flow-control reset by level control.
- Side-draw is under flow control reset by sensitive tray temperature.
- LPG side stripper bottom is fed to storage on flow control reset by level control.
- LPG stripper reflux is on flow control reset by level control.
Neutralization
- The scrubbed off gas is withdrawn under pressure control.
- Temperature control of the caustic circulation is achieved through the Caustic
Recycle Heater.
Dryers
- The dryers will be in series flow for the feed, the make-up H2 services. Once the
moisture content in the lead dryer effluent, reaches 1 ppm wt, it must be taken out of
service for regeneration.
- The regeneration flow is flow controlled into the regeneration loop.
- A pressure controller maintains a backpressure in the loop prior to re-blending with
the isomerate product after the pressure control valve.
- A Degasser is required in the loop to purge off gas leakage from the dryers and to
separate water from the regenerant. Gas purging is under level control of the
Degasser which is maintained almost full of liquid.
- The regeneration temperature is controlled by electrical power of the Regenerant
Superheater.
temperature at lower space velocity to control hydrocracking and preserve catalyst cycle
length.
b) Scrubber
- Check the scrubber operation for caustic losses and caustic strength in the circulating
caustic wash. The stabilizer off-gases are first scrubbed with 10% caustic solution
then water washed before routing to fuel gas. Check the exiting gas for HCl content
and caustic entrainment.
- The caustic inventory is replaced once the concentration drops to 2 to 3 wt. %, and
the caustic concentration should not be allowed to fall below 2 wt %. The circulating
caustic temperature should be maintained a few degrees above the off gas inlet
temperature in order to avoid condensation which can cause foaming and operating
problems in the scrubber.
c) Deisohexaniser:
- Deisohexaniser fractionates the isomerate product from the reactor recycle liquid,
and the octane number of the isomerate product is dependant on recycling the low
octane C6 components to the reactor.
- The recycle liquid also serves as a diluent for controlling the exotherm in the
benzene saturation reactor, especially when processing benzene rich feed streams
only.
- The recycle liquid in addition helps in diluting the C7+ components in the total
reactor feed to avoid excessive cracking of these heavy components in the
isomerization reactors.
Design
Design Diff.
Discharge
Item No. Item Description Capacity Head
Pressure
(m/hr) (m)
(Kg/cmg)
REACTOR RECYCLE
PUMP
ISOMERIZATION
73-P-04 A/B REACTOR FEED 121.2 78.0 406.3
PUMP
STABILIZER REFLUX
73-P-05 A/B 50.2 23.5 95.4
PUMP
DEISOHEXANIZER
73-P-06 A/B 176.1 14.0 129.5
REFLUX PUMP
DEISOHEXANIZER
73-P-07 A/B 97.9 15.0 127.2
RECYCLE PUMP
DEISOHEXANIZER
73-P-08 A/B 24.3 28.0 290.0
BOTTOM PUMP
ISOMERATE
73-P-09 A/B 40.8 22.0 239.8
STORAGE PUMP
73-P-10 A/B CAUSTIC PUMP 30.9 21.0 159.1
CAUSTIC
73-P-11 A/B 36.0 23.0 46.3
CIRCULATION PUMP
DEMINIERALISED
73-P-12 A/B 100 lph 17.5 154.2
WATER PUMP
WATER
73-P-13 A/B 24.0 21.0 25.0
CIRCULATION PUMP
Design
Design Diff.
Discharge
Item No. Item Description Capacity Head
Pressure
(m/hr) (m)
(Kg/cmg)
BOTTOM PUMP
LPG STRIPPER
73-P-15 A/B 6.82 28.0 130.4
BOTTOM PUMP
73-P-16 A/B LPG PRODUCT PUMP 6.0 25.0 122.8
LPG STRIPPER
73-P-17 A/B 13.3 23.0 107.7
REFLUX PUMP
VESSELS
Internal Design Design
TL-TL
Tag No. Item Description Diameter Temp Pressure
(mm)
(mm) C Kg/cmg
ISOMERISATION
73-V-01 FEED SURGE 2500 6500 80 6.0+FV
DRUM
HYDROGEN
73-V-02 600 1800 80 26.0+FV
MAKE UP KOD
CHLORIDING
73-V-03 AGENT 1100 3300 80 10.5
INJECTION DRUM
HYDROGENATIO
73-V-04 N REACTOR 2800 7300 210 21.0
FLASH DRUM
STABILIZER 80
73-V-05 1900 5600 17.0
REFLUX DRUM (-)25
COLUMNS
Internal Design Design
Tag No. Height
Item Description Diameter Temp. Pressure
(mm)
(mm) (C) (Kg/cm2g)
1400/ 2100/
3000 195
73-C-01 STABILIZER 31150 17.5
(top/mid/bot (-25)
tom)
DEISOHEXANISE
73-C-02 3400 45350 155 5+FV
R
1300/
CAUSTIC 2400
73-C-03 18850 80 16.0
SCRUBBER (top/
bottom)
650/ 1200
73-C-04 LPG stripper 27300 230 16.0
(top/bottom)
DRYER
Internal Design Design
Tag No. Item Height
Diameter Temp. Pressure
Description (mm)
(mm) (C) (Kg/cm2g)
80 /
73-DR-01 FEED
1800 6850 325 37.0+FV
A/B DRYERS
(REGEN)
135 /
73-DR-02 HYDROGEN
900 9250 325 46.0+FV
A/B DRYERS
(REGEN)
SCRUBBER 80 /
73-DR-03
OFFGAS 1100 10150 325 15.0
A/B
DRYER (REGEN)
COMPRESSOR
Design Design
Item DELTA P Design Press
Tag No. Capacity Temp
Description (Kg/cm2g) (Kg/cm2g)
(NM3/HR) (C)
73-K-01 H2 MAKE UP
14038 18.1 46.0 135
A/B COMPRESSOR
REACTOR
Internal Design
Tag No. Height Design
Item Description Diameter Pressure
(mm) Temp. (C)
(mm) (Kg/cm2g)
210
HYDROGENATIO
73-R-01 1450 4650 325 24+FV
N REACTOR
(regen)
Internal Design
Tag No. Height Design
Item Description Diameter Pressure
(mm) Temp. (C)
(mm) (Kg/cm2g)
1st STAGE
73-R-02 ISOMERIZATION 1400 21510 210 41+FV
REACTOR
2nd STAGE
73-R-03 ISOMERIZATION 1400 21510 210 41+FV
REACTOR
HEAT EXCHANGER
Design Press Design Temp
Tag No. Design Duty
Item Description Shell/Tube Shell/Tube
(Mkcal/HR)
(Kg/cm2g) (C)
73-E-01 H2 MAKE UP
2*0.28 46.0/36.5 150/65
A/B COOLER
DIH RECYCLE/
73-E-02 REACTOR FEED 0.65 37.0/29.0 135/120
EXCHANGER
FIRST REACTOR
73-E-03 FEED/ EFFLUENT 1.56 31/40 135/210
EXCHANGER
HYDROGENATIO
73-E-04 N REACTOR 4.89 31/40+FV 210/400
FEED HEATER
STABILIZER
73-E-05 3.32 40+FV /31.0 400/195
REBOILER
73-E-06 STABILIZER 80(-25)/
2*0.54 17.0/13.5
A/B TRIM OOLER 65
DIH FEED/ 14.0+FV/
73-E-07 2.02 140/195
RECYCLE 18.0+FV
73-E-08 DIH TRIM
2*0.16 15.0/11.5 120/65
A/B COOLER
73-E-09 ISOMERATE
2*0.114 22.0/17.0 80/65
A/B TRIM COOLERS
12.5+FV/
73-E-10 DIH REBOILER 6.66 300/155
10+FV
Chloride injection
3 73-PSV-1202 A/B On hold
pump
73-DR-01 A/B
4 73-PSV-1301 A/B 36.5 Fire case
outlet
5 73-PSV-1401 73-V-02 26.0 Fire case
6 73-PSV-1402/1403 73-K-01A/B 46.0 Operational failure
7 73-PSV-1404/1405 Sea cooling water 7.6 Thermal expansion
8 73-PSV-1501A 73-DR-02 A 46.0 Fire case
9 73-PSV-1501B 73-DR-02 B 46.0 Fire case
10 73-PSV-1601 DIH recycle 15.0 Tube rupture
11 73-PSV-1602 73-V-18 40.0 Fire case
12 73-PSV-1603 73-R-01 24.0 Fire case
73-PSV-1701A / Operational failure,
13 73-V-04 21.0
1701B Fire case
73-P-04 A/B
14 73-PSV-1703/1704 21.0 Blocked outlet
discharge
15 73-PSV-1801 73-R-02 inlet 39.8 Fire case
16 73-PSV-1802 73-R-03 39.8 Fire case
17 73-PSV-1901 73-V-19 40.0 Fire case
18 73-PSV-1902 Stabilizer bottom 21.0 Fire case
7.9 ANALYZERS
Sr.
Tag No. Type Location/Service
No.
1 73-AE-1101 Benzene On isom feed line to 73-DR-01 A/B
2 73-AE-1301 A/B Moisture 73-DR-01A/B outlet
3 73-AE-1501 A/B Moisture 73-DR-02 A/B outlet
4 73-AE-1901 Moisture Across 73-PV-1901
Sr.
Tag No. Type Location/Service
No.
5 73-AE-2601 Moisture 73-DR-03 A/B outlet
SECTION - 8
SHUTDOWN PROCEDURES
8.1 GENERAL
While shutting down the unit due to maintenance or emergency, care must be taken not to
admit air into the system until all hydrocarbon vapours have been removed. Operators
should be thoroughly familiar with shutdown procedures and understand the reasons for
each work. Good judgement must be exercised as no written procedure can completely
cover all details or problems that can arise in an emergency. Judgement is more likely to
be exact if prior thought and planning have been made.
In this section the activities related to the normal as well as emergency shutdown
procedures have been briefly outlined.
check the atmosphere in the vessels before entering or starting repairs. Rigorously
observe all safety precautions.
The general procedure to be followed for a total shutdown is:
- To lower the severity
- To lower the capacity
- To switch the product to off-spec. or raw naphtha storage
- To shutdown the reaction section
- To drain all hydrocarbons
- To depressurize and purge.
- Reduce the reactors inlet temperatures to 90C over a one hour period and allow the
beds to cool. When isomerization reactors temperatures reach 105C approximately,
stop the chloride injection. Maintain these conditions for one hour (i.e. at 90C) to
sweep chloride from the feed circuit upstream of the reactors.
- Open the reactors bypass to bypass the C5/C6 feed directly to the stabilizer and close
the reactor feed valve. Cut the feed out as quickly as possible to minimize the low
liquid flow period over the catalyst.
- Continue sweeping the reactors with make-up hydrogen at design rate. Reduce the
reactors inlet temperatures at 20C/hour until the reactor feed heater is shutdown.
- When reactors have cooled below 60C, stop the hydrogen flow.
- Reduce the stabilizer temperature but as this is a short duration shutdown, leave the
stabilizer in operation at a low reflux rate.
- Maintain pressure in the reaction section, stabilizer and LPG stripper. If necessary
use the hydrogen make-up through the start-up line.
The unit is now considered to be on standby with C5/C6 feed bypassing the reactors, the
Deisohexaniser fed at 75% capacity with distillate and bottoms routed to off-spec
storage, the stabilizer on a low rate total reflux. The unit is under normal pressure with
hydrogen make-up as required. The reactors have cooled to below 60C.
- Stabilizer circuit is also shutdown gradually. If the stabilizer needs to be opened for
inspection, a purge of make-up hydrogen should be sent to the tower to strip any HCl
in the overheads. This can be stopped after there is no measurable HCl in the gas
sample.
- Stop the LPG recovery section.
- Block in and isolate the reactors.
- With the unit still under pressure drain all the major vessels, first to storage then to
slop.
- Depressurize all sections to fuel gas first if desired then to flare. Avoid
depressurizing the stabilizer below the scrubber pressure as there is a risk of caustic
entrained gas backing up into the stabilizer.
- Depressurize all the reactors to flare through the hydrocarbon drain lines.
- Depressurize the LPG recovery section if required.
- Shutdown both the caustic and water washes in the scrubber.
- Shutdown all air coolers and water coolers.
- When the unit is considered totally depressurized and all the utilities e.g. water,
steam have been drained and isolated from their respective equipment, the reactors
can be blocked.
- Isolate the stabilizer section from the reaction section.
- Isolate with blinds the feed lines, hydrogen make-up, product lines and fuel gas
headers. Isolate all PSV's lines to flare and instruments not suitable for vacuum
service.
- Remove one of the blinds from the reactors to the ejector and pull a vacuum in the
reaction and dryer sections (the dryers can be evacuated separately if desired) down
to 0.2 bar abs.
- Break with dry nitrogen and pressure up 1.0 bar g.
- Depressurize through all low points, dead legs, vents etc
- Repeat the evacuation breaking with nitrogen steps until the hydrocarbon level has
decreased below 0.5 vol. %.
- Note the porous catalyst and adsorbent will require time to displace the
hydrocarbons inside the pores. Proceed with caution around the reactors and dryers
by allowing one hour before pulling the sample for testing.
- Leave a residual nitrogen pressure of 0.5 bar g.
- Purge scrubber with steam and if desired leave in it a positive nitrogen pressure.
- Purging the stabilizer and all items in LPG recovery section with steam is prohibited
(except for the initial start-up) as chloride traces in presence with water are
excessively corrosive.
- As a safety precaution block and blind reactors from the reaction circuit.
Depending upon the extent and reason for shutdown the various pieces of equipment can
be isolated and air purged for entry.
The following special considerations are highlighted for operator awareness of the
isomerization process.
- The unit contains benzene and tetrachloroethylene which are known health hazards.
- The unit contains HCl downstream of the first isomerization reactor inlet. The
concentration is particularly high in the stabilizer overhead and in the LPG separator
drum. For this reason, operator shall bypass LPG recovery section, for any upstream
upsets, such as loss of H2, loss of feed, upset in stabilizer operation.
- The reactions are highly exothermic, mostly due to the benzene saturation and the
C7+ components hydrocracking. If the levels of these components in the feedstock
increase significantly, the hydrogenation reactor temperature could raise beyond a
controllable range.
- A reactor temperature excursion could occur if the flow of liquid through a hot
reactor is too low or if the reactor temperatures are too high. Reactor feed rate should
not decrease below 75% of design capacity (FT 1101).
- During an emergency situation in the stabilizer section, the stabilizer must not
depressurize below the pressure of the scrubber. There is a check valve in the
stabilizer overheads gas line to the scrubber and a static height to overcome but
despite this water and caustic could back up into the stabilizer causing a potential
corrosion problem.
- In the event a reactor temperature excursion occurs and the reactor temperatures
increase above 190C, the reactors must be depressurized to avoid excessive
hydrocracking reactions and to prevent mechanical damage. If for some reason the
reactors cannot be depressurized through the stabilizer, only as a last resort should
they be depressurized to the flare through the hydrocracking drain lines. It is
recommended to block the reactors in prior to depressurizing and to start a cold
nitrogen purge if necessary. Depressurization is started once the LPG recovery
section has been bypassed on off gas side (bypass is activated by I-101 emergency
shut down interlock).
The following procedures include all the actions to be undertaken by the operator
assuming no action by the automatic shutdown devices.
Actions:
- Cut steam immediately from the reactor feed heater.
- Cut the feed to unit.
- Increase ti maximum the recycle flowrate in the recycle air cooler. Close the recycle
air cooler bypass line. Start all fans at the air cooler.
- Bypass LPG recovery section on off gas side.
- Stop C2Cl4 injection when the isomerization lead reactor reaches 105C.
- Stop the isomerization reactor pump at the hydrogenation reactor flash drum.
- Slowly depressurize the hydrogenation reactor via the associated flash drum.
- Slowly depressurize the reaction section to the Stabilizer to keep the back pressure
control valve open and cold feed flowing through the reactors.
- Reduce the stabilizer pressure as necessary to maintain pressure control on the
column and flow of bottom to Deisohexaniser column.
- If the reactor temperatures cannot be controlled and increase above 190C during
this procedure, interlock I-101 must be activated (emergency shut down).
- Increase to maximum the recycle flow rate in the recycle air cooler. Close the
recycle air cooler bypass line. Start all fans at air cooler.
- Maximum hydrogen make-up flow in the isomerization reaction section (2nd
hydrogen make up line)
- Stop C2Cl4 injection when the isomerization reactor reaches 105C.
- Hold the reactor inlet temperatures at 100C if conditions are stable.
- Modify the fractionation towers upstream of the unit to restore the design quantities
of benzene and C7+ in the feed.
- Or check out the controllers to determine the cause of the poor control.
- When the faults have been corrected, increase the reactor temperatures slowly back
to normal operating point.
- If any of the reactor temperatures exceeds 190C, cut the liquid feed and make-up
hydrogen. Activate I-102 / 103, emergency shut-down interlock in order to
depressurize the reaction section.
If the reactor temperature excursion is due to low liquid feed rate and this cannot be
corrected quickly, cut out the remaining feed and follow the procedures for loss of feed.
- When the isomerization lead reactor reaches 105C, cut the C2Cl4 injection.
- Reduce steam to deisohexaniser reboiler, stabilizer reboiler and LPG stripper
Reboiler, but maintain the pressures.
- Follow the procedure as above for steam failure.
Incase of fire, depressurization of the reactors shall be actuated as per API 521
3.19. As the safety valves at the reactors have set pressure corresponding to
supercritical conditions, protection against fire exposure by safety valves is not
sufficient. It is mandatory to depressurize the corresponding vessels whenever a
fire is detected.
Actions:
- Shut off both C5/C6 feed and hydrogen make-up to the unit and block in the product
lines.
- Shut off steam to the Reactor Feed Heater, Stabilizer Reboiler, deisohexaniser
reboiler and LPG stripper reboiler.
- Immediately bypass LPG recovery on off gas side and simultaneously begin
depressurizing the reactors to flare, through the stabilizer and scrubber.
- If it is possible, isolate the problem area and block in the reactors and purge with
nitrogen to flare.
- The objectives of the following steps which should be developed by the
client/engineering contractor are to drain hydrocarbons from all the vessels, purge
the unit with inert gas in particular the reactors if they cannot be accessed. Leaving
the reactors with hydrocarbon inside and no flow will eventually lead to a
temperature excursion and mechanical failure, so all effort must be made to purge
these vessels.
SECTION-9
PROCESS VARIABLE
Process variables that affect the isomerization process are discussed below.
9.1 BENZENE SATURATION
There are six process variables which have an effect on the reactor performance:
- Reactor temperature.
- Reactor pressure
- Hydrogen make-up flow
- Liquid diluents recycle
- Space velocity.
- Feed composition
9.2 ISOMERIZATION
There are six primary process variables which have a direct effect on the reactors
performances:
- Reactor temperature.
- Space velocity.
- Hydrogen / hydrocarbon ratio.
- Feed composition.
- Reactor outlet pressure
- Chloride Injection.
Decreasing the feed rate decreases the space velocity. At constant temperature this
increases activity and therefore the approach to equilibrium. The operator can therefore
reduce the reactor inlet temperature while maintaining catalyst optimum performance.
Figure 1
ISOPENTANE/ISO + NORMAL PENTANE EQUILIBRIUM PLOT
MOLE % ISOPENTANE/ISO + n-PENTANE
100
80
60
40
20
0
100 150 200 250 300
TEMPERATURE C
Figure 2
iC5/C5 Paraffin equilibrium ratio
85
83
81
79
77
IC5/C5P
75
73
71
69
67
65
60 80 100 120 140 160 180 200
TEMPERATURE C
Figure 3
C6 Fraction equilibrium Plot
100
MCP/MCP + CH
80
60
2-MP+3MP/ C6 PARAFFINS
40
n-HEXANE/ C6 PARAFFINS
20 2,2 DMB/ C6 PARAFFINS
0
100 150 200 250 300
TEMPERATURE C
Figure 4
2.2 DMB / C6 equilibrium ratio
52
50
48
46
44
42
22 DMB/C6P
40
38
36
34
32
30
28
26
24
22
60 80 100 120 140 160 180 200
TEMPERATURE C
SECTION-10
TROUBLE SHOOTING
The main concern for the isomerization unit operation is water breakthrough through a
malfunction of the dryers or major water upset in the upstream hydrotreater.
Two other concerns are:
- Sulfur poisoning which is reversible and poor de-nitrification in the upstream units
leading to chloride stripping off the catalyst.
- Chloride breakthrough in isomerate/LPG products.
The operator must be knowledgeable and experienced enough to make the proper
corrective actions immediately and to know if he should cut feed to the unit before any
catalyst activity loss occurs. The ultimate safe rule is to cut feed from the unit if a
breakthrough is suspected and follow carefully the necessary procedures for total unit
shutdown. Remember this unit produces a gasoline component for blending; it does not
produce any feedstock for other units and can therefore be shutdown with relatively little
disruption to the other refinery operations. The upset seriousness and the contaminant
breakthrough level will dictate the necessary course of action to take.
In this chapter we will highlight some of the potential problems which the operator may
have to face.
A sudden irregular indication of water breakthrough in the lead dryer analyzer indicates
either a malfunction of the analyzer or water upset upstream.
Operator action is to immediately cut out the feed indicating the high-water content i.e.
C5/C6 feed, make-up hydrogen.
After this, the corresponding emergency procedure for shutdown and purging can be
followed.
After the unit has been secured, the dryers which experienced the water breakthrough
should be regenerated and the dryer checked for water removal capability. The feed, the
make-up gas should be tested for moisture content and the source of the problem
corrected.
Then only a unit restart should be considered.
Remark: Water breakthrough from other sources
Chloride is not corrosive with dry hydrocarbons, but becomes very corrosive when
traces of water are present.
Stabilizer and equipment in LPG recovery section are made of carbon steel as reactor
effluent is water free.
However water ingress may occur with a leaking (cooling water exchanger or steam
reboiler). If water is detected in a stabilizer or LPG recovery section stream, unit shall be
shut down, for exchanger maintenance, in order to avoid extensive chloride corrosion.
b. Off-Gas Dryer
Water breakthrough will lead to purging of 73-E-13 (ice / LPG hydrates formation) and
ultimately to LPG recovery section bypass and shutdown. Incase of water breakthrough
Immediate action must be taken.
Also note that performance of the dryers is poor when process fluid temperature exceeds
50 oC. Therefore stabilizer overhead temperature and scrubber operating temperature
shall be closely monitored, in order to have a stable off-gas temperature at dryer inlet.
- At this point the stripping operation is considered complete. Stop the chloride
injection, shutdown the reactor feed heater and the superheater and cool the reactor
catalyst beds to 65C.
- Follow the normal start-up procedures.
Caution:
When a new load of C2Cl4 is required check that the purchase order indicates C2Cl4
unstabilized or catalytic grade. The stabilized C2Cl4 will not decompose in the reactors
and will end up with product in the Stabilizer leading to some problems with the
isomerate used to dryers regeneration.
SECTION -11
SPECIAL PROCEDURES/INSTRUCTION/INFORMATION
- Sufficient dry nitrogen (less than 1 ppm wt H2O). If not available provide temporary
piping to route nitrogen through the hydrogen dryers.
- Provide emergency nitrogen storage in case of refinery nitrogen failure.
- Make available several nitrogen flexible hoses. They must be specified for nitrogen
service, must be new and perfectly dry.
- One telescopic crane capable of lifting a drum 3 m above the reactor upper flange
(see Figure 6).
- One standing hopper (see Figure 9).
- One forklift to handle the drum pallets.
- Tarpaulins should be available in case of rain or interruption during loading.
- One structure (scaffolding) disposed on the top of the reactor adapted to receive the
drums and to fill them into the reactor through the special device (see Figure 7).
- One safety harness, portable oxygen analyzer, air packs and dust masks.
- The oxygen analyzer will be used when reactors are open for catalyst loading to
make sure that no air is entering.
- Set down on the top man hole the stationary steel cover, the standing hopper and
pipe catalyst loading.
- At the same time, care must be taken to ensure that the sock penetrates in the center
of CATAPAC device. Look it through the little hole drilled on the steel cover
(figure 7).
- Then load, drum by drum the required quantity of catalyst.
- After the catalyst has been loaded install the top bed inert alumina balls layer
Note: At no time should a person enter a reactor having a nitrogen purge on it without
full instruction and experience with a fresh air mask, safety harness, safety clothes and
life line.
- Cover the manway again with plastic. Remove all the loading devices off the top
platform.
- Install the inlet distributor tray, reactor cover and inlet removable elbow as quickly
as possible after the loading is complete.
- Continue the nitrogen purge at the bottom of the reactor out through the inlet PI.
Check that the purge out through the PI is oxygen free.
- Pressure the reactor back up to 0.5 bar g. Check for flange leaks.
- Record all loading data, number of catalyst drums, inert balls, etc
- Repeat loading procedure for the second then third reactor.
Note: The opening, loading and closing procedure of the reactors should be a
continuous operation without break. During this operation a positive nitrogen
pressure should be maintained in the reactor at all times.
Figure 5
Preparation of the Drums
Figure 6
DRUM LIFTING CATALYST DENSE LOADING
Figure 7
Catalyst Handling with Catapac
Figure 8
Catalyst DENSE LOADING (part 1)
Figure 9
Catalyst DENSE LOADING (part 2)
The reactor to be unloaded has to be depressurized, isolated with blinds, evacuated and
swept with cold dry nitrogen to a hydrocarbon level of less than 0.5 vol %. The reactor
is kept under a positive nitrogen pressure of 0.1 bar g with a nitrogen bleed entering at
the reactor bottom and exiting through the inlet PI.
- Close the nitrogen vent through the top PI and remove the blind flange on the
catalyst withdrawal nozzle.
- Attach the catalyst unloading sock. The bottom end of this sock must have a solid
metal section in order to clamp the catalyst bag.
- The spent catalyst can be loaded into the original catalyst drums and liners to protect
against corrosion during shipment.
- Place an empty drum on a scale, then put the inner plastic bag with the unloading
neck inside the outer heavy plastic bag. Purge the inner bag with nitrogen.
- Clamp the plastic unloading neck of the inner bag over the end of the unloading
sock.
- Partially detach the unloading spout, crimp the sock to stop any catalyst flow and
quickly remove the catalyst draw-off cover, reattaching the unloading spout.
- Uncrimp the loading sock and load into the drums. The first material will be inert
material followed by catalyst. If possible segregate the first few drums of inert
material for screening.
- The catalyst is dropped in the original catalyst drums.
- Load catalyst into each drum. Wire clamp the plastic unloading neck in two places
then wire clamp the outer heavy plastic bag.
- Close the drum tightly, record the weight and label the drum.
- A small amount of spent catalyst and inert material will be left in the bottom of the
reactor. This must be removed manually with a person inside the reactor to sweep
the catalyst toward the withdrawal spout.
- All the precautions previously listed for personnel entry during catalyst loading and
inspection should be followed here.
- With the reactor empty, an inspection can be carried out on the internals, and then
prepared for immediately catalyst reloading.
- Catalyst spillage should be minimized using the above procedure.
- However the concrete pad at the base of the reactors should be swept clean prior to
unloading. Any spillage during unloading can then be swept and placed in one of the
drums.
- The catalyst can then be shipped for platinum recovery including any catalyst
retrieved from screening of the initial drums of inert balls.
b) Isomerization catalyst:
73-R-02 & 73-R-03 IS 614 A (1)
Supplier Axens
Shape Cylindrical extrudates
Nominal Particle Diameter 1.6 mm
Catalyst volume, m3 56.22 m3 (28.11x2) (2) (4)
Catalyst Cycle First reactor : 4 years (3)
Length(estimated) Second reactor : 4 years (3)
Catalyst Life(estimated) 10 years
(1)Reduced and activated platinum on high purity alumina
(2)Dense catalyst loading method
(3)Ex-situ regeneration / reduction required at the end of cycle
(4)Total requirement for both reactors
The 73-R-02/03 were designed to have provision in the reactor for a future loading.
Total future catalyst amount will be 61.46m3 (30.73*2)
c) Dryers Adsorbents
Manufacturer AXENS
Type Molecular Sieve4A
Volume, m3 (1) (2) 37.56 m3
Estimated cycle length 30 hours (per bed)
Manufacturer AXENS
Type Molecular Sieve 5A
3
Volume, m (1) (2) 13.7 (6.85x2) m3
Estimated cycle length 30 hours (per bed)
Life period 3 years (estimated)
Notes: (1) Total requirement for: 73-DR-01 A/B.
Manufacturer will advise on contingency to consider for this material.
(2) Sock catalyst loading method.
Manufacturer AXENS
Type Molecular sieve 13X
Volume, m3 (1) (2) 3.38 (1.69x2) m3
Estimated cycle length 30 hours (per bed)
Life period 3 years (estimated)
Notes:- (1) one time requirement , used during initial start-up of the reaction section,
removing water and oxide scales from reaction circuit.
SECTION-12
UTILITY CONSUMPTION SUMMARY
Start up requirement
The estimated consumptions are based on a normal start-up sequence.
Intermittent operation can be assumed to occur once every 24 months.
Start-up nitrogen
Nitrogen gas is necessary to get the unit free of oxygen.
Estimated consumption: Isomerization section: 3200 Nm3.
Start up hydrogen
At start-up, after 1st leak test, the reaction section is pressurized with hydrogen make-up.
Estimated consumption: Isomerization section: 4350 Nm3.
Remark for Isomerization section: Hydrogen is needed during initial start-up to perform
acidizing at 60% of normal H2 flowrate. Moreover, in case of sulfur catalyst poisoning,
it is necessary to strip catalyst with hydrogen. In order to ensure a good hydrogen
distribution through the catalyst bed, it is recommended to process at a minimum
flowrate of 1000 Nm3/h.
MP Steam
MP steam will be used as driving fluid of the start-up ejector 73-J-01 to inert reactor
section at the start-up.
LP Steam
LP steam will be used for steam purge out of the equipments and also as snuffing steam
on the flanges.
SECTION-13
SAMPLING PROCEDURE AND LABORATORY ANALYSIS REQUIREMENT
13.1 GENERAL
Control tests provide the information to the operating staff for making necessary
adjustments to get the maximum output and on-spec quality products. The control
tests are to be made at all steps to monitor the intermediate and final products whether or
not they are at the desired specification. Samples are taken and analyzed at regular
intervals such that the operation of the plant are monitored and any deviation (from
specification will indicate some maloperation / malfunction of the plant which can be
spotted and rectified in time without undue loss of time and product. Sometimes,
samples are taken to find out the effect of certain changes brought about in the operating
conditions. The samples are to be taken with great care so that the samples are
representative samples. The frequency of sampling, the type of analysis and points
where samples are to be taken are generally specified by t he process licensor. During
guarantee tests some additional samples can be taken at higher frequencies, which will
be specified, in the technical procedures prior to test run. The following guidelines
should be followed while collecting samples.
gate. Then again open the globe valve and drain the hold up between the gate
and globe valve in case of congealing liquid.
iv) Sample valve should be slowly opened, first slightly to check for plugging. If the
plugging is released suddenly, the liquid will escape at a dangerously
uncontrolled rate. Never tap the line to release the plugging. Call the
maintenance gang to properly unplug the line. In case of congealing type
samples, sample point should be equipped with copper coil type steam tracer. It
should be ensured that steam-tracing line is functioning normally.
v) The operator taking the sample should be careful to stand in a position such that
the liquid does not splash on him and he has unobstructed way out from the
sample point in case of accident.
vi) While taking dangerous toxic material for sampling, it will act as an observer for
safety. Proper gas mask is to be used. It is advisable to stand opposite to wind
direction in case of volatile toxic liquid.
vii) Sample should be collected in clean, dry and stoppered bottle. In case of
congealing samples use clean dry ladle.
viii) Rinsing of the bottle should be thorough before actual collection.
ix) Before collecting, ensure that the line content has been drained and fresh sample
is coming.
x) Gradually warm up the sample bottle / metallic can by repeated rinsing before
collecting the sample.
xi) Stopper the bottle immediately after collection of sample.
xii) Attach a tag to the bottle indicating date, time, and name of the product and tests
to be carried out.
xiii) A few products suffer deterioration with time.
xiv) For example, the color of the heavier distillates slowly deteriorates with time. So
these samples should be sent to laboratory at the earliest after collection.
The samples after collection should be kept away from any source of ignition to
minimize fire hazard.
Volatile samples (e.g. naphtha) should be collected in bottles and kept in ice particularly
for some critical test like RVP.
vi) Allow liquid hydrocarbon to fill the bomb. When the bomb is full up to the
specified level, close both the valves on sample point. Close inlet valve on the
sample point.
vii) Carefully disconnect the hose from the sample bomb. To allow for some vapor
space in the bomb for thermal expansion in case of overfilling, crack open the
outlet valve of bomb and discharge a small part of the liquid. Close outlet valve.
viii) Closed sampling facilities are provided at some locations where it is not
desirable to waste the costly product or if the material is toxic. For filling the
sampling bomb, pressure drop across a control valve is usually utilized or across
pump discharge & suction. Air is expelled from the bomb after it is connected to
upstream of control valve or pump discharge side. The sample is then collected
and bomb is detached after closing valves on both sides.
ix) Send sample bomb to laboratory for analysis. Protect the bomb from heat
exposure.
c) Gas Sample
For collection of gas sample, which are not under high pressure and temperature, rubber
bladders are used. For the operations under vacuum or low pressure, aspirator is used.
For representative sample, purge the bladder 3 to 4 times with the gas and then take t he
final sample. Use of 3 ways valve with bladder / aspirator will facilitate purging and
sampling.
Sample bombs are to be used for taking gas samples from high pressure and high
temperature source. Procedure mentioned under high-pressure liquid sampling (flashing
type) is to be used.
** PANAMETRICS is selling this kind of analyzer with the defined range of detection.
Isomerate Product
Specific Gravity ASTM D 1298 1 per day
Stabilizer Off-Gas
Hydrogen Sulfide Dragger (tube CH 298) 1 per day
LPG product
Property Method Frequency
Chemical Composition ISO 7941 1 per day
Chloride Content IFP 9316 1 per day
Circulating Caustic
NaOH Wt % pH meter (lab) 1 per day
Catalyst
Carbon ASTM D 3178 As required
Specific surface Brunauer, Emmett and As required
Teller method
Metals content IFP 9315 As required
Stabilizer bottoms
Chloride content IFP 9316 1 per day
LPG product
Chloride content IFP 9316 1 per day
SECTION -14
SAFETY PROCEDURE
14.1 INTRODUCTION
Safety of personnel and equipment is very important. Ignorance of the details of the unit or
the techniques of safe and efficient operation reduces the margin of safety of personnel and
subjects the equipment to more hazardous conditions. All the operating and maintenance
crew therefore must be fully familiar with the equipment and materials being handled in the
unit, and recognize the hazards involved in handling them and the measures taken to ensure
safe operations.
Since the unit handles with one of the most potential source of fire and explosion, H2,
Naphtha and chemical like caustic, therefore adherence of safety rules should be given
uphill importance.
c) Entry permits
Entry permits are required for entering enclosed spaces such as vessels, sewer, pits,
trenches, etc.
The use of any tool or machinery, which could provide a source of ignition, is forbidden.
Also, prior to entry it should be ensured that area is well ventilated and the oxygen
content in air is about 21% by volume. Fresh air flow is to be ensured in the enclosed
space through out the duration of work. A gas test for H2S and flammable gases should
also be performed before entry. A person should also be on alert outside the enclosed
space for rescue in case of emergency. Procedure for carrying out work and rescue plan
shall be formulated before commencement of work.
- The validity of the permit can be cancelled at any moment by the operator or by
safety officer; in case they deem that the conditions are not safe.
- The conditions to be complied with shall include special precautions, such as the use
of protective clothing, breathing apparatus, safety equipment and the tools to be used
etc.
- No one shall be allowed to enter the vessel or other enclosed spaces without suitable
protective clothing and until the vessels or the enclosed spaces become safe for entry
by means of proper isolation, proper ventilation and suitable check of the
atmosphere inside and availability of rescue person outside the enclosed equipment.
Note: Open a vent on the upper part of the vessel to allow gases to escape during filling
and to allow air inside the vessel during draining. Ensure proper ventilation inside
the vessel by opening all manholes. For hydrocarbon or other gases, pressurise the
vessel with N2 or gas and fill in the liquid and drain under pressure. This is to avoid
hydrocarbon going to atmosphere.
After the above operations have been made, a safety permit should be issued for carrying
out the work. A responsible operating supervisor should be personally present at the place
of hot work till the first torch is lighted. Hot work should be immediately suspended if
instructed by the supervisor or on detecting any unsafe condition.
When people have to enter a vessel for inspection or other work, one person should stand
outside near the manhole of the vessel for any help needed by the persons working inside.
The person entering the vessel should have tied on his waist a rope to enable pulling him
out in case of urgency. Detail procedure for preparation for vessel entry is given in next
sub-section.
The precautions apply equally to entry into all forms of vessels, including those enclosed
areas which might not normally be considered vessels.
Examples include:
The area around the vessel manways should also be surveyed for possible sources of
dangerous gases which might enter the vessel while the person is inside. Examples
include acetylene cylinders for welding and process vent or drain connections in the
same or adjoining units. Any hazards found in the survey should be isolated or
removed.
Vessel Access
Safe access must be provided both to the exterior and interior of the vessel to be entered.
The exterior access should be a solid, permanent ladder and platform or scaffolding
strong enough to support the people and equipment who will be involved in the work to
be performed.
Access to the interior should also the strong and solid. Scaffolding is preferred when the
vessel is large enough. The scaffolding base should rest firmly on the bottom of the
vessel and be solidly anchored.
If the scaffolding is tall, the scaffolding should be supported in several places to prevent
sway. The platform boards should be sturdy and capable of supporting several people
and equipment at the same time and also be firmly fastened down. Rungs should be
provided on the scaffolding spaced at a comfortable distance for climbing on the
structure.
If scaffolding will not fit in the vessel a ladder can be used. A rigid ladder is always
preferred over a rope ladder and is essential to avoid fatigue during lengthy periods of
work inside a vessel. The bottom and top of the ladder should be solidly anchored. If
additional support is available, then the ladder should also be anchored at intermediate
locations. When possible, a solid support should pass through the ladder under a rung,
thereby providing support for the entire weight should the bottom support fail. Only one
person at a time should be allowed on the ladder.
When a rope ladder is used, the ropes should be thoroughly inspected prior to each new
job. All rungs should be tested for strength, whether they be made of metal or wood.
Each rope must be individually secured to an immovable support. If possible, a solid
support should pass through the ladder so that a rung can help support the weight and the
bottom of the ladder should be fastened to a support to prevent the ladder from
swinging. As with the rigid ladder, only one person should climb the ladder at a time.
normal. The auxiliary supply should have an alarm which alerts the user that he is on
backup supply and it should be sufficiently large to give the user 5 minutes to escape
from danger.
process line into the vessel which is being entered. For these reasons vessel entry
procedures must still be rigorously followed during the checkout of a new unit.
The oxygen content of the atmosphere inside of the vessel should be checked before
every entry and the vessel should be blinded. Independent blinds at each vessel nozzle
are preferred. However, in the event that many vessels are to be entered in a new unit
which is separate from the rest of the plant, the entire unit can be isolated by installing
blinds at the battery limits rather than by individually isolating every vessel nozzle.
case, the period of time spent working inside of the vessel should be limited and
frequent breaks should be taken outside of the vessel.
At low concentrations (small amounts) H2S has an offensive odour similar to rotten eggs.
At slightly higher concentrations (small amounts), H2S may have a sick-sweet odour. At
high concentrations no smell can be detected, because H2S rapidly deadens the sense of
smell by paralysis of the Olfactory-Nerve. Consequently the sense of smell cannot be
depended upon to detect H2S.
Characteristics of H2S
Hydrogen sulphide has the following characteristics:
- Deadly-extremely toxic gas.
- Colourless.
- Heavier than air tends to settle in low lying areas.
- Readily dispersed by wind movement of air currents.
- Burns with a blue flame, producing Sulphur Di-oxide (SO2), which is also a toxic gas.
- Odour of rotten eggs. Only in low concentrations rapidly deadens the sense of smell.
Do not depend on the sense of smell to detect H2S
- Highly corrosive to certain metals.
- More deadly than Carbon Monoxide (CO), and almost as toxic as Hydrogen Cyanide
(HCN) gas.
- When approaching the work area it is necessary to take the following precautions to
insure safe entry
1. Observe Condition signs and observe for audio/visual alarms.
2. Check for wind direction.
3. Look for personnel and their activity.
4. Enter work area slowly.
- Maintain mental image of two (at least) escape routes preferably cross wind.
- Continuous atmosphere monitoring or detecting equipment is required along with an
adequate audio/visual alarm warning system. Portable detectors and combustible gas
meters give an additional degree of safety.
Maintenance Procedure:
There are two basic areas of maintenance operations which are inherently dangerous from
the standpoint of H2S exposure. These are venting / draining of piping and confined space
entry.
- Depressurisation of piping, valves, fittings, strainers, etc. in H2S service represents a
safety hazard in the unit, since the vent and drain valves are not hard-piped to a
closed vent or drain header.
Without exception, breathing air respirators are to be worn when opening piping, removing
valves or performing any operation which might permit vapours to enter the immediate
area. When valves are removed, install blind flanges.
- Confined space entry is entrance into areas such as tanks, vessels, etc. This is one of
the most dangerous activities of the unit and should be avoided whenever possible.
When it is absolutely necessary that a confined entry be made, entry should be made only
after the following safety conditions have been met.
- Entry permit form has been filled out and signed.
- Space contains at least 19.5% of oxygen by volume.
- Sample does not contain combustible vapours above L.E.L.
- Space does not contain toxic gas contaminants above the limit of appropriate threshold
values for the substance.
- Even if the above mentioned conditions are met, personnel entering such enclosed
spaces shall be equipped with self contained breathing apparatus (SCBA) pressure
demand type.
- Rescue equipment must be in close vicinity of the confined space.
- All personnel entering the confined space must wear safety harness and reflective tape.
- An adequate number of personnel must be stationed outside for emergency assistance.
- Communications must be clearly established and a system of safety signs and signals
understood by all.
- Any battery operated or electrical communications system such as hand-held walkie-
talkie or throat type microphone, if used in a hazardous environment must be
intrinsically safe.
- There are a number of other safety precautions and equipment to be considered when a
confined space entry must be made such as:
Resuscitation equipment, litter, safety lanterns or chemical lights, tripped for hoisting over
hatches, instrument calibration, mechanical ventilation, cascade systems, continuous
monitoring, houseline units, separate means of access where possible, emergency team and
plan and proper training.
Remember the fact that any entry into a confined space is inherently dangerous.
E) Emergency Procedures
If all the above procedures have been adhered to strictly, a catastrophic release of H2S
should never occur. In the unlikely event such a release does occur, the emergency
procedures detailed in this section should be followed.
a) Egress
H2S is a dangerous, deadly gas, however serious injury or death can be avoided by simply
evacuating the contaminated area and moving to a safe area upwind. Therefore, the most
important things to remember are to Stay Claim and Get Away.
Precise emergency escape procedures will be defined by the operations management of the
complex, however the following general procedures should be followed:
- Remain Calm-Do Not Panic
- Hold your breath
- Extinguish all fires
- Alert the rest of the crew
- Make a quick, cursory check of the area to see if the source of the gas is obvious.
- Do not spend time looking for a leak
- Observe windsock to determine wind direction. Move upwind or crosswind, not
downwind, until the safe breathing area is reached.
- Active alarms if not already done.
- Once assembled at the safe briefing area, the foreman will make a head count to
determine if all personnel have evacuated safely.
importance. A natural reaction is to unthinkingly rush to the side of the downed victim,
which could be a fatal action.
Instead, before proceeding into the hazardous area to rescue a downed victim, stop, think
and:
- Put on an appropriate safe breathing apparatus.
- Move quickly, but carefully to the victim, side. Move the victim to a safe area;
either upwind or crosswind from the hazardous area. Do not evacuate in a
downwind direction.
- Begin mouth-to-mouth artificial respiration if the victim has stopped breathing.
Check the victims pulse periodically to ensure that the victims heart is still
beating. If the victims heart stops beating, administer CPR. Artificial respiration or
CPR should be continued until:
- The victim begins to breathe and, if applicable, the heart begins to beat.
- He is pronounced dead by a doctor.
- He is dead beyond any doubt.
- Seek assistance at the first opportunity and make arrangements for transportation to a
medical facility to seek medical attention by a physician.
c) Abatement Procedure
Once the safety of all personnel has been determined, the next order or business is to
determine the source of H2S and stop it, if possible.
Field Personnel
- Use breathing apparatus (Respirator).
- Establish communication with Control Room.
- Communicate with first personnel to sound alarm/notice of the H2S.
- To determine the general area of the source, slowly begin searching the source from the
upwind side.
14.6.2 HYDROGEN
Hydrogen is a colourless, tasteless, odourless and highly flammable gas and is the
lightest element. Since hydrogen is lighter than air, less danger exists of it collecting in
pockets in low areas. However, the potential danger from fire or explosion is high.
Gaseous fuels such as hydrogen can mix with air or oxygen in all proportions. However,
the proportions must be within certain limits before those mixtures will burn. The
limiting proportions are referred to as flammable limits or explosive limits and are
expressed as the percentage by volume of the fuel in the air-fuel mixture. Fuel-air
mixtures outside of the flammable range will not explode. Hydrogen has a very wide
range (4-75%) of flammability or explosive limits in air at atmospheric pressure. In
addition to, the flammability range becomes wider at higher pressure or if oxygen is
substituted for air. Thus, explosions can occur over a very wide range of hydrogen
concentrations in air. The safest approach to safeguard against possible fires or
explosions is to make sure that hydrogen leaks do not develop.
The auto ignition temperature of a substance is the lowest temperature required to
initiate or cause self-sustained combustion in the absence of a spark or flame. The auto
ignition temperature of hydrogen in air is 580C at atmospheric conditions. However,
other factors such as the nature, size, and shape of the igniting surface can affect this
temperature.
Unlike most gases, which cool when expanded or bled off, hydrogen heats up when
expanded and great care must be exercised when bleeding down lines or compressors to
the atmosphere. In its pure state, hydrogen burns with a bluish white flame (almost
invisible) that is extremely hot. Such a hot flame can weaken any support beams or lines
on which it may impinge. Any leaks should be put under a steam blanket immediately to
prevent the possibility of a fire. Be aware, however, that many leaks can auto ignite and
will be difficult to see. Replacing the source of the hydrogen with a nitrogen or steam
purge is the most effective way of combating a hydrogen fire.
Hydrogen, although a not a poisonous gas itself, is an asphyxiant (i.e. cuts off oxygen
supply to the body by displacing air in the lungs) and can cause unconsciousness and
even death if the victim falls and remains in a high hydrogen atmosphere.
Because of the small size of hydrogen molecules, a pressure check with air or nitrogen
or a hydrostatic test will not always show all leaks that will occur with hydrogen.
Head protection:
Safety helmets shall be worn by all personnel at all times in the plant for protection of the
head. They may be removed when inside rooms or buildings which do not have overhead
or other hazards.
Hand Protection
Proper hand protective gloves should be worn.
Foot protection
Safety shoes are to be worn for foot protection.
Ear protection
Whenever personnel are required to be work in noisy areas proper ear protection device
such as ear plug etc, is to be used.
Breathing apparatus
Whenever persons are required to work or enter an area of high
toxic/aromatic/hydrocarbon vapor concentration, wear appropriate respiratory
protection, such as self-contained breathing apparatus or an air mask with an external air
supply.
SECTION -15
GENERAL OPERATING INSTRUCTIONS FOR EQUIPMENT
15.1 GENERAL
This section covers the general procedure for operation and trouble shooting of commonly
used equipment like pumps, heat exchangers and furnace etc. For specific information and
more detail refer to vendor's manuals.
In some pumps a by-pass has been provided across the check valve and discharge valve to
keep the idle pump hot. In such pumps, the by-pass valve should be closed before starting
the pump. It should be ensured that casing of these pumps are heated up sufficiently prior
to starting of the pump to guard against damage of the equipment and associated piping due
to thermal shock.
15.2.2. Shutdown
- Close discharge valve fully.
- Stop the pump
a) If pump is going to remain as standby and has provision for keeping the pump hot,
proceed as follows:
- Open the valve in the by-pass line across the discharge valve and check valve.
- The circulation rate should not be so high to cause reverse rotation of idle pump
and also overloading of the running pump.
- Check the liquid level from where the pump is taking suction.
- Check pump coupling and rotation.
- Get the pump checked by a technician.
v. Unusual Vibration
- Check the foundation bolts.
- Check the fan cover for looseness.
- Stop the pump and hand over to maintenance.
v. Check that the motor shaft is reasonably free and coupling secured. Coupling guard
should be in position.
vi. Energise motor. Open discharge valve. Start the motor and check direction of
rotation. Stop and rectify if direction of rotation is wrong.
vii. Adjust the pump stroke and run the pump at different settings. Watch discharge
pressure and check the rate of pumping using the flow meter or by taking suction
from the calibration pot. In case the pumps is provided with a pressure controller
adjust it to obtain the required discharge pressure.
viii. Care should be taken to avoid dry running of pump and back flow of liquid. Bleed
if necessary to expel vapour/air.
ix. Check for unusual noise, vibrations, rise of temperature of both motor and gears.
15.3.2. Shutdown
- Stop the pump.
- Close the suction and discharge valves.
- Drain the liquid if maintenance jobs are to be carried out on the pump.
15.4.1. Start-up
i. Ensure all mechanical jobs have been completed on the compressor that is to be
started including suction line passivation.
ii. No load run of the motor to be completed before the compressor is coupled.
After no load run, de-energize the electrical supply. Couple the motor and
compressor. Check the rotating element of the compressor for free rotation
turning slowly by hand. If the rotor rubs, rotation should be stopped immediately
and the difficulty located and repaired.
iii. Check oil level in lube oil tank and refill as required bringing the oil level to the
high mark on the sight glass. Do not overfill.
iv. Line-up and start seal and lube oil circulation to make certain that bearings of the
compressor and driver are well lubricated.
v. Establish the pressure of lubricating oil in bearings and seal oil to seal.
Note: Seal system is to be in operation whenever any pressure is in the compressor, even
though the machine is idle.
vi. Bar the unit over once to be sure all moving parts are clear.
vii. Make sure that water cooler and air coolers coming in compressor circuit are in
operation.
viii. Ensure that compressor casing has also been purged with inert gas. Pressurise the
compressor with nitrogen and leak test.
ix. Open suction valve/discharge valve and line up to the system. Remove any
accumulated liquid from the casing by opening casing drain.
x. Start the drive as per the vendors recommendations and run the compressor.
xi. Allow the oil to warm up to 40o C. Watch compressor motor amperage. Listen
for unusual noise or vibration during the warm up period.
xii. Auxiliary motor driven lube oil pump will be stopped when shaft-driven pump
develops normal oil pressure and kept ready for auto start.
xiii. When the unit is warmed up and determined to be operating satisfactorily,
gradually start throttling the valve beyond surge requirements of the compressor.
xiv. Load the compressor to the required capacity in the above mentioned manner.
Note: The compressor before trial run on the actual medium may be tried on air with
suction and discharge open to atmosphere. While attempting to run the
Compressor on air, Vendor's instructions and recommendations are to be
followed. It is to be noted that scaling arrangement may be required to be
changed to suit the machine running on air.
15.4.2. Shutdown
i. Stop the drive.
ii. Start the oil pump to lubricate the bearing till required.
iii. Close the discharge valve.
iv. Close the suction valve.
v. Turn off cooling water to oil cooler as applicable.
vi. If the compressor is to be given for maintenance, isolate, depressurise and purge
with inert gas to make the compressor free of hydrocarbons.
- Bearing damage
The exchangers have been provided with draining and flushing connections. The coolers
and condensers have been provided with TSV's on the cooling water side to guard against
possible rise of pressure due to faulty operations with the safety release to atmosphere.
Temperature gauges or thermo wells have been provided at the inlet and outlet of
exchangers. Where water is the cooling medium, no temperature measurement is provided
for water inlet temperature which is the same as cooling water supply header temperature.
AIR COOLERS
The air coolers/condensers comprise of a fin tube assembly running parallel between the
inlet and outlet headers. These are of the forced draft type. The forced draft fans
provided have auto variable speed rotors in which the fan speeds are adjusted during
rotation. This allows variation in air flow as per the cooling requirements. A high
vibration switch is provided with alarm to indicate any mechanical damage.
EXCHANGERS
Shell and Tube type heat exchangers can be broadly classified into following types: -
- Water Coolers/condensers
- Steam heaters (reboiler)
- Exchangers
Start-up /shut down procedures for each unit shall vary slightly from case to case.
However, general start-up /shut-down procedures are discussed in the following
paragraphs.
15.5.1. Start-Up
After the heat exchanger has been pressure tested and all blinds removed, proceed as
follows:
i. Open cooling medium vent valve to displace non-condensable (air, fuel gas, inert
gas etc.) from the system. Ensure the drain valves are capped. For high pressure
system, drain valves should be flanged. This activity is not required if gas is the
medium.
ii. Open cooling medium inlet valve. Close vent valve when liquid starts coming
out through it, then open cold medium outlet valve and fully open the inlet valve
also. Where cold medium is also hot, warming up of cold medium side gradually
is also essential.
iii. Open hot medium side vent valve to displace non condensable (air, fuel inert gas
etc.). Check that the drain is closed and capped. This activity is not required if
gas is the medium.
iv. Crack open hot medium inlet valve. When liquid starts coming out from the vent
valve, close it. Open hot medium inlet valve and then open the outlet valve
fully. In case of steam heaters, initially the condensate shall be drained to sewer
till pressure in the system builds up to a level where it can be lined up to the
return condensate header.
v. In case by passes are provided across shells and tube side, gradually close the
bypass on the cold medium side and then the bypass across the hot medium side.
vi. Check for normal inlet and outlet temperatures. Check that TSVs are not
popping.
vii. The operation of inlet and outlet valves should be done carefully ensuring that
the exchangers are not subjected to thermal shock.
viii. In case of coolers/condensers, adjust the water flow to maintain the required
temperatures at the outlet.
ix. For avoiding fouling, velocity of water should be at least 1 m/sec in a
cooler/condenser.
15.5.2. Shutdown
Shut down of an exchanger, coolers, condenser is considered when the equipment is to be
isolated for handling over to maintenance while the main plant is in operation. The
following is the suggested procedure for isolation of the piece of equipment
i. Isolate the hot medium first. In case both hot and cold medium are from process
streams, exchanger shall remain in service till the hot stream has cooled down
enough.
ii. In case of a cooler, adjust cooling water flow to the cooler which is in line so that
product temperature is within allowable unit.
iii. Isolate the cold medium next.
iv. Drain out the shell and tube sides to OWS/Sewer/Closed blow down system as
applicable. In case flushing oil connection is given flush the exchanger to CBD.
Ensure that the CBD drum has sufficient level to receive the flushing of the
exchanger
v. Depressurize the system to atmosphere/flare/blow down system as applicable.
vi. Purge/flush if required. This is particularly important in congealing services.
vii. Blind inlet and outlet lines before handing over the equipment for maintenance.