The ASTM A470 Class 7 steel T13 stage manufactured and the diaphragms were
disk of the turbine's low-pressure either repaired or manufactured anew.
integral rotor suffered a catastrophic Other work included minor repairs on
failure. The low-pressure rotor is of a the high-pressure rotor, generator, field
double-flow design, with the steam inlet installation, and startup monitoring of
at the midspan of the rotor, as shown in the unit.
figure 1. The failure occurred as a blade The T13 disk failure included cracks
CRACK
separated from the rotor during opera- in the blade hooks, so, at Sulzer's
tion, causing extensive damage to down- recommendation, the customer agreed
stream stationary and rotating compo- to remove blades from the generator end 2 Typical crack in the blade root
nents along with heavy rubs on the rotor of the rotor to permit evaluation of those (around the entire wheel).
max.
stresses
was achieved that would reduce the stress
magnitudes by almost 50% of their
original values 5. However, the final 6 Stresses also reduced by using elliptical fillets (right)
3 High stresses in the original disk blade design did not fit within the envelope instead of straight fillets (left).
roots. of the original disk geometry, so a portion
of the disk was then widened to keep
the outside loading rim in proportion to disks had to be preheated and the heat
its original configuration. The original had to be carefully controlled through-
clearance of the stationary components out the entire operation in order to
was kept intact by relocating the achieve proper weld quality. Due to the
diaphragms. tight repair schedule, both ends of the
Stress magnitudes were also reduced rotor were welded simultaneously. Figure
through the use of generous, elliptical 8 shows a detail of the weld overlay.
Stage T13 Stage T13 fillet radii instead of the standard straight Immediately after the welding was
Original two Final three-hook
hook design. design. fillets as shown in figure 6. A more completed, the disks had to be heated
generous fillet helps distribute the stress, for dehydrogenation, or hydrogen
4 Original two blade hooks (left) in stage T13 decreasing the incidence of high local- removal. This procedure causes the
was increased to three (right), which reduced ized stress magnitudes and lowering the hydrogen trapped in the weld to migrate
the stress to 81% of its original value.
generalized stress magnitudes. to the surface.
5 Final design of stage T15 (right) reduced At the same location of the cut, on
stresses by almost 50% of the original (left). either side of the rings, weld-off rings
were welded in place. These rings helped
the initial disk failure was localized to contain the weld overlay profiles to be
stage T13, stress distributions for stages used for the reconstruction of the disk.
T14, T15, G13, G14, and G15 were deter- Figure 7 shows stages T12, T14, and T15
mined as well. The model geometry was being prepared for welding, with weld-
acquired from the actual disk and blade off rings partially installed and thermo-
samples and then drawn in a CAD couples for temperature monitoring.
(computer-aided design) program. The
CAD models were imported into the Welding
finite element solver, from which stress The welding method employed was sub-
distributions were calculated 3 . merged arc. During the procedure, the
8 Weld overlay detail. 9 Stress relieving in the horizontal position while slowly rolling.
While slowly rolling, the rotor was The last steps of the repair procedure underway. Additionally, welding and
stress relieved in the horizontal position. were the final machining of the redesigned induction heating both rotor ends
Induction heating was used to bring the root profiles, reloading of the blades on simultaneously provided substantial
stress relief areas to the correct temper- the rotor, and balancing 0. time savings.
ature. Induction heating maximizes the
efficiency of this procedure, since it allows Summary
Fernando Romero
localized treatment of only the areas The shop repair work, which included
Sulzer Turbo Services Argentina S.A.
affected by the welding. It also elimi- the weld reconstruction of the forging, Talcahuano 736 2do B
Ciudad Autonoma de Buenos Aires, C1013AAP
nates the problem of having to stress the blade manufacturing and installation, Argentina
relieve a rotor of this size vertically and rotor balancing were accomplished Phone +54 11 4373 6327 224
fernando.romero@sulzer.com
in a furnace. The power supplies used in under 18 weeks. This time frame
for heat induction were controlled via included the engineering analysis which Luis Rodriguez
Sulzer Turbo Services Inc.
thermocouples located on the disks and was completed in 4 weeks. It was possible 11518 Old La Porte Rd.
data was transmitted wirelessly to a to finish this repair quickly because the La Porte, TX 77571
USA
stationary control module as shown in weld preparation process was started Phone +1 713 567-2776
figure 9. while the engineering work was still luis.e.rodriguez@sulzer.com
0 Balancing of
the repaired rotor.