Anda di halaman 1dari 3

PANORAMA

Design modifications and repair


of a 90MW steam turbine after
a catastrophic failure
A catastrophic failure of a 90MW steam turbine occurred due to a fracture of the blade root
in one of the disks, which, in turn, caused massive damage to the rotating and stationary
parts. As cost and delivery of a new replacement rotor were prohibitive to the customer, Sulzer
offered more competitive pricing and a shorter delivery than the OEM. Sulzer was therefore
contracted to reengineer the blade root geometry and weld repair 6 of the total 12 disks.
The entire engineering analysis and repair process was completed in 18 weeks.

The ASTM A470 Class 7 steel T13 stage manufactured and the diaphragms were
disk of the turbine's low-pressure either repaired or manufactured anew.
integral rotor suffered a catastrophic Other work included minor repairs on
failure. The low-pressure rotor is of a the high-pressure rotor, generator, field
double-flow design, with the steam inlet installation, and startup monitoring of
at the midspan of the rotor, as shown in the unit.
figure 1. The failure occurred as a blade The T13 disk failure included cracks
CRACK
separated from the rotor during opera- in the blade hooks, so, at Sulzer's
tion, causing extensive damage to down- recommendation, the customer agreed
stream stationary and rotating compo- to remove blades from the generator end 2 Typical crack in the blade root

nents along with heavy rubs on the rotor of the rotor to permit evaluation of those (around the entire wheel).

body. blade roots as well. Throughout the


Sulzer Turbo Services was also con- course of the visual and magnetic particle arrival at Sulzer. Figure 2 shows the
tracted to provide an engineering inspections, additional cracks were iden- typical crack locations in the corners of
solution that would prevent a failure re- tified in the T14, T15, G13, G14, and G15 the root hooks. Magnetic particle inspec-
occurrence. The main strategy was to stages. This foresight was crucial, for tions revealed that the cracks ran circum-
redesign the blade root in order to lower severe damages would have surely ferentially around the entire disk, in both
the stress concentration on the disk hooks. occurred after the machine was rein- the upper and the lower blade hooks.
After the design was finalized, the rotor stalled.
was repaired by welding the damaged The sections of the T13 and T14 disk Analysis and design modifications
disks. New sets of rotating blades were had been removed prior to the rotors The primary strategy of the engineering
analysis was to evaluate the stress dis-
tribution on the original disk design, and
1 Low pressure then redesign the root profiles in order
turbine rotor with T16 G16
Running Speed: 3600 RPM
T15
T14 G14
G15 to reduce the stress magnitudes on the
symmetrical flow. T13 G13
T12 G12 hooks. A major requirement of the
T11 G11
redesign was to assure that the geomet-
rical modifications still permitted the
HP rotor to fit properly without casing mod-
Turbine
End ifications.
Generator Finite element analysis (FEA) was
End
performed in order to quantify the
Failure Flow
stress distribution on the disks under
normal operating conditions. Although

18 | Sulzer Technical Review 3/2010 4320


PANORAMA

Figure 4 shows the final design of the


failed T13 row. This design reduced the
min.
stress to 81% of its original value. The Standard
straight fillet. Elliptical fillet.
same engineering reviews were also per-
formed for the larger stage T15. After Original Final
T15 T15
several iterations, a root design for T15 design. design.

max.
stresses
was achieved that would reduce the stress
magnitudes by almost 50% of their
original values 5. However, the final 6 Stresses also reduced by using elliptical fillets (right)
3 High stresses in the original disk blade design did not fit within the envelope instead of straight fillets (left).
roots. of the original disk geometry, so a portion
of the disk was then widened to keep
the outside loading rim in proportion to disks had to be preheated and the heat
its original configuration. The original had to be carefully controlled through-
clearance of the stationary components out the entire operation in order to
was kept intact by relocating the achieve proper weld quality. Due to the
diaphragms. tight repair schedule, both ends of the
Stress magnitudes were also reduced rotor were welded simultaneously. Figure
through the use of generous, elliptical 8 shows a detail of the weld overlay.

Stage T13 Stage T13 fillet radii instead of the standard straight Immediately after the welding was
Original two Final three-hook
hook design. design. fillets as shown in figure 6. A more completed, the disks had to be heated
generous fillet helps distribute the stress, for dehydrogenation, or hydrogen
4 Original two blade hooks (left) in stage T13 decreasing the incidence of high local- removal. This procedure causes the
was increased to three (right), which reduced ized stress magnitudes and lowering the hydrogen trapped in the weld to migrate
the stress to 81% of its original value.
generalized stress magnitudes. to the surface.

Anatomy of the weld repair Stress relief


As part of the weld preparation process, The rotor was machined to a stress relief
the damaged sections of the disk were profile. The quality of the weld was then
RIM cut from the rotor. The FEA from the inspected using wet magnetic particle
engineering analysis determined the and ultrasonic techniques.
radial location of the cuts. Each stage
Stage T15 Stage T15
Original three Final stronger was cut at a diameter where the heat
hook design. hook design.
affected zone (HAZ) would be away from
any areas of stress concentration. 7 Stages T12, T14, and T15 being prepared for welding.

5 Final design of stage T15 (right) reduced At the same location of the cut, on
stresses by almost 50% of the original (left). either side of the rings, weld-off rings
were welded in place. These rings helped
the initial disk failure was localized to contain the weld overlay profiles to be
stage T13, stress distributions for stages used for the reconstruction of the disk.
T14, T15, G13, G14, and G15 were deter- Figure 7 shows stages T12, T14, and T15
mined as well. The model geometry was being prepared for welding, with weld-
acquired from the actual disk and blade off rings partially installed and thermo-
samples and then drawn in a CAD couples for temperature monitoring.
(computer-aided design) program. The
CAD models were imported into the Welding
finite element solver, from which stress The welding method employed was sub-
distributions were calculated 3 . merged arc. During the procedure, the

Sulzer Technical Review 3/2010 | 19


PANORAMA

8 Weld overlay detail. 9 Stress relieving in the horizontal position while slowly rolling.

While slowly rolling, the rotor was The last steps of the repair procedure underway. Additionally, welding and
stress relieved in the horizontal position. were the final machining of the redesigned induction heating both rotor ends
Induction heating was used to bring the root profiles, reloading of the blades on simultaneously provided substantial
stress relief areas to the correct temper- the rotor, and balancing 0. time savings.
ature. Induction heating maximizes the
efficiency of this procedure, since it allows Summary
Fernando Romero
localized treatment of only the areas The shop repair work, which included
Sulzer Turbo Services Argentina S.A.
affected by the welding. It also elimi- the weld reconstruction of the forging, Talcahuano 736 2do B
Ciudad Autonoma de Buenos Aires, C1013AAP
nates the problem of having to stress the blade manufacturing and installation, Argentina
relieve a rotor of this size vertically and rotor balancing were accomplished Phone +54 11 4373 6327 224
fernando.romero@sulzer.com
in a furnace. The power supplies used in under 18 weeks. This time frame
for heat induction were controlled via included the engineering analysis which Luis Rodriguez
Sulzer Turbo Services Inc.
thermocouples located on the disks and was completed in 4 weeks. It was possible 11518 Old La Porte Rd.
data was transmitted wirelessly to a to finish this repair quickly because the La Porte, TX 77571
USA
stationary control module as shown in weld preparation process was started Phone +1 713 567-2776
figure 9. while the engineering work was still luis.e.rodriguez@sulzer.com

0 Balancing of
the repaired rotor.

20 | Sulzer Technical Review 3/2010

Anda mungkin juga menyukai