Sta Cecilia Chapel - Toilet

QTY UNIT ITEM UNIT COST TOTAL


80 mts #12 THHN Stranded wire 23 1,840.00
20 mts #14 THHN Stranded wire 15 300.00
4 pcs #2 P-trap 142 568.00
3 pcs #2 PVC Pipe S,1000 600 1,800.00
1.5 kg #2 Umbrella Nails 60 90.00
2 pcs #3 Floor Drain 100 200.00
800 pcs #3/4 Hardiflex Screw (Metal) 0.8 640.00
1 pcs #4 CO, Plug 100 100.00
2 pcs #4 pvc Pipe S,1000 900 1,800.00
3 pcs #4 Socket 40 120.00
2 pcs #4 Wire 167 334.00
4 pcs 1/2 Blue Pipe 50 200.00
7 pcs 1/2 Elbow Threaded 10 70.00
30 mts 1/2 Flexible Hose 10 300.00
11 pcs 1/4 Marine Plywood 380 4,180.00
8 pcs 9mm Bars 120 960.00
54 pcs 10mm Bars 140 7,560.00
6 pcs 2x2x12 Mahogany 30 / Bd.Ft 720.00
12 pcs 2x3x10 Mahogany 30 / Bd.Ft 1,800.00
2 pcs 2x4 Tee 105 210.00
2 pcs 2x4 Wire 108 216.00
8 pcs 2x6x12 Mahogany 30 / Bd.Ft 2,880.00
6 pcs 3/4 Marine plywood 1200 7,200.00
530 pcs 4" CHB 12 6,360.00
1 pcs 45 # 4 Elbow 100 100.00
1 box 5/32 x 1/2 Rivets 290 290.00
3 pcs 9 watts LED Bulb 180 540.00
10 pcs Adjustable Stand Black 360 3,600.00
5 pcs Angle Valve 130 650.00
3 pcs Barrel Bolt 55 165.00
82 bags Cement 250 20,500.00
2 pcs Door Knob 420 840.00
1 pc Electrical Tape big 43 43.00
1/2 ltr Epoxy 150 150.00
5 pcs Flexible Hose 160 800.00
8 pcs GA24 G.I. Corr Sht 12' 330 2,640.00
150 pcs Glazed Tiles 75 11,250.00
3 m3 Gravel 1400 4,200.00
4 pcs Hinges 220 880.00
3 pcs Junction Box 30 90.00
2 sets Lavatory 500 1,000.00
2 sets PVC Door 1600 3,200.00
6 m3 Sand 1400 8,400.00
15 pcs Side Bracket 240 3,600.00
3 pcs Single switch Flush Type 65 195.00
1/4 ltr Solvent 70 70.00
6 pcs Tile Trim Big 50 300.00
80 pcs Unglazed Tilaes 75 6,000.00
2 sets Urinal 2000 4,000.00
3 pcs Utility Box 50 150.00
3 sets Water Closet 5000 15,000.00
Jalousie window 1,000.00

TOTAL MATERIAL COST 130,101.00

LABOR COST 60,000.00

TOTAL PROJECT COST: 190,101.00

PREPARED BY:

Loloy Prado