First-floor movable steel ladder has not been fabricated or installed (design change)
1.1.7 9/1/2017 9/30/2017 430.07A10105J006 Not finish
Ore bin E-room wall was peeled, need to touch up.
1.1.8 9/1/2017 9/30/2017 430.07A10105J001 Not finish
Ore bin E-room windows are damaged, need to be repaired.
1.1.9 10/1/2017 10/15/2017 430.07A10105J001 Not finish
Ore bin E-room stair tiles are damaged, need to be handled.
1.1.10 10/1/2017 10/15/2017 430.07A10105J001 Not finish
Some windows of central TS are damaged, need to be handled.
1.1.11 10/1/2017 10/15/2017 430.07A10103J001 Not finish
Central TS third-floor lifting hole door has not been installed.
1.1.12 10/1/2017 10/15/2017 430.07A10103J001 Not finish
Central TS enterior wall is fell off, need to be repaired.
1.1.13 10/1/2017 10/30/2017 430.07A10103J001 Not finish
Mechanical room's external ladder's cantilever concrete beam need to plaster.
1.1.14 10/7/2017 10/15/2017 430.07A10103J001 Not finish
2/13
Remaining Work Schedule of BF Ore Bin)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
The node at the end of TC101 corridor is connected by two (2) connective plates and
1.2.4 fillet is collocated; it is only connected by one (1) plate on the construction site. 8/20/2017 9/30/2107 Not finish
TC101
In the newly collocated support of TJ101 corridor, a cross beam suffers from fillet
1.2.5 leakage. 8/20/2017 9/30/2107 Not finish
TJ101
As for the sliding support in the upper part of TC101 corridor, the on-site fabrication
1.2.6 methods can not realize sliding any longer. 8/20/2017 9/30/2107 Not finish
TC101
In PTKS project, all the steel partition plates and platform plates have welding
1.2.7 changes; the welding specification is provided; intermittent welding is made. 8/20/2017 9/30/2107 Not finish
Dust removal duct inner side need to be checked and cleaned before the hole closed.
1.2.8 8/20/2017 9/10/2107 430.07A10106J031 Not finish
1.3 Equipment Total 2 2 0 0%
3/13
Remaining Work Schedule of BF Ore Bin)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
: 3
Broken coke and ore: The blanking gate fails to make commissioning.
1.3.2 9/1/2017 9/30/2107 Not finish
:
4/13
Remaining Work Schedule of BF Ore Bin)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
In TF101 belt conveyor, the tear switch SW1 fails to make commissioning.
1.5.4 9/1/2017 9/20/2017 Not finish
TF101SW1
The slide switch not
In TF101 belt conveyor, the sliding switch SS1 fails to make commissioning.
1.5.5 9/1/2017 9/20/2017 installed. Not finish
TF101SS1
TB101SMA 2
TN101SRL1 2
TN101SMA 4
5/13
Remaining Work Schedule of BF Ore Bin)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
In TQ101 belt conveyor, the error tolerance plugging unit SJ1 fails to make The chute plugging
commissioning. unit not installed.
1.5.16 9/1/2017 9/20/2017 Not finish
TQ101SJ1
TS102 3
6/13
Remaining Work Schedule of BF Ore Bin)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
Fan shaft temperature: TE101 thermal resistance is not installed; the cables fail to Currently, the
1.6.2 make wiring 9/1/2017 9/20/2017 equipment not found Not finish
TE101
Fan shaft temperature: TE102 thermal resistance is not installed; the cables fail to Currently, the
1.6.3 make wiring 9/1/2017 9/20/2017 equipment not found Not finish
TE102
Damper openness adjustment: HZ101 actuator fails to make commissioning. Mechanical fault.
1.6.4 9/1/2017 9/20/2017 Not finish
HZ101
Weighing funnel and weighing apparatus: Twenty-four (24) sets of weighing apparatus
1.6.5 fail to make calibration. 9/1/2017 9/20/2017 Not finish
7/13
Remaining Work Schedule of BF Ore Bin)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
1.6.5 9/1/2017 9/20/2017 Not finish
24
The equipment of
MIT9020 coke midbin water content analyzer is not installed; the conduit pipe is not radiation leakage risk
collocated; the cables are not collocated; they fail to make wiring. is not suitable to
1.6.6 9/1/2017 9/20/2017 installation temporarily. Not finish
MIT9020
8/13
Remaining Work Schedule of BF BF Proper)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
In the East side of blast furnace, 66.500m platform under the towing support of crown
block is collocated with channel steel beam. 430.07A10202J031-46A
2.2.1 8/15/2017 9/10/2017 Not finish
66.500m430.07A10202J031-46A
On the top of blast furnace, 70.000m foundation of even diffusion framework column in
the crude gas is collocated with stiffening ring steel structureIt suffers from design
2.2.2 leakage. The connection model is changed. 430.07A10202J031-56, 57 8/15/2017 9/30/2017 Not finish
70.000m
430.07A10202J031-5657
78.8m hole is drilled on the platform on top of the blast furnace. 430.07A10202J031
2.2.3 8/15/2017 9/30/2017 Not finish
78.8m430.07A10202J031
9/13
Remaining Work Schedule of BF BF Proper)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
50m platform and 55.995m platform beam of the blast furnace refer to the mobile
2.2.5 platform; they are not constructed according to the requirements. 8/15/2017 9/30/2017 Finish
5055.995
On 71.3m platform of the blast furnace, two (2) connective plates are collocated at the
2.2.6 end of platform; only one (1) node plate is collocated on the construction site. 8/15/2017 9/30/2017 Not finish
71.3
On 28.5m platform and 32.61m platform of the blast furnace, the full welding is made
to the node plate at the end of platform beam; intermittent welding is made on the
2.2.7 construction site. 8/15/2017 9/30/2017 Finish
28.5,32.61
Change in 38.5m platform.
2.2.8 8/15/2017 9/15/2017 Not finish
38.5
Change in 32.61m platform.
2.2.9 8/15/2017 9/15/2017 Not finish
32.61
10/13
Remaining Work Schedule of BF BF Proper)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
Date Remaining Finish Finish Ratio
The water is filled into the blast furnace until 30m; the leakage point is not treated. The
sampling valves and missing bolts and materials of the blast furnace are already
2.4.1 delivered but not installed yet. 8/20/2017 9/10/2017 430.07A10202T008 Not finish
30
The temporary water pipes for the large, medium and small tuyere flushing are not
2.4.2 intalled. 8/15/2017 9/10/2017 430.07A10202T008 Not finish
Two (2) DN65 crossing temperature measurement water pipes fail to make changes.
2.4.3 8/15/2017 9/10/2017 430.07A10202T008 Not finish
DN652
The stabilized pressure water supplementation measures are not adopted.
2.4.4 8/15/2017 9/10/2017 430.07A10202T008 Not finish
On the tuyere platform, the contact of coal pulverizing gun is not finished; the support
of coal pulverizing pipe needs to be consolidated; the anti-plugging compressed air
pipe is not finished. On the platform of coal powder distributor, the self-operated
pressure reducing valve loses its pressure guide pipe and joint; the gas source hose
2.4.5 of pneumatic valve is not delivered yet. 8/20/2017 10/10/2017 430.07A10701T003 Not finish
The steel brick, water gun and crossing temperature measurement pipe on top of the
2.4.6 blast furnace fail to make flushing or water connection. 8/15/2017 9/10/2017 430.07A10201T005 Not finish
The cooling water pipe of equipment on top of the blast furnace fails to make flushing
2.4.7 or water connection. 8/16/2017 9/10/2017 430.07A10201T005 Not finish
The primary equalizing pipe fails to make pressure test.
2.4.8 8/17/2017 9/10/2017 430.07A10201T003 Not finish
The steam trap and contact of steam pipe are not finished; the heat conservation
2.4.9 measures are not adopted; three (3) pneumatic valves pipe should be finish. 8/18/2017 9/15/2017 430.07A10201T005 Not finish
11/13
Remaining Work Schedule of BF BF Proper)
Target/Actua 9/4/2017
Target Remarks
NO Remaining Work l Finished
started Date
2.4.9 8/18/2017 Date
9/15/2017 430.07A10201T005 Remaining Not
Finish Finish Ratio
finish
3
The nitrogen valve on top of the blast furnace fails to make pressure test; the safety
2.4.10 valve is not installed. 8/19/2017 9/15/2017 430.07A10201T005 Not finish
The cooling water of hydraulic station on top of the blast furnace fails to receive
2.4.11 flushing. 8/20/2017 9/15/2017 430.07A10201T005 Not finish
12/13
Note :
1. Warna merah
muda di remarks,
pekerjaan bisa
dikerjajakan oleh KS
dan KPDP Operasi
2. Hasil koordinasi
penyamaan presepsi
dengan Pak Memed
(Structure KE)
seluruh pekerjaan
Civil dan Structure
tidak bisa dikerjakan
orang KS (selain
KPDP)
13/13