PRESUPUESTO DE MANO DE OBRA

CISTERNA MORILLAS

DESCRIPCION CANTIDAD UNIDAD PRECIO SUB- TOTAL


UNITARIO

EXCAVACION DE CISTERNA Y ELIMINACION


DE DESMONTE. 148 m3 x S/. 25.00 = S/. 3,700.00

DEMOLICION DE LOSA DE CONCRETO. 40 m2 x S/. 12.00 = S/. 480.00

ENCOFRADO Y DESENCOFRADO DE CISTERNA 105 m2 x S/. 35.00 = S/. 3,675.00

ARMADO DE ACERO EN CISTERNA.. 4800 KG x S/. 0.60 = S/. 2,880.00

PISO PULIDO EN CISTERNA. 40 m2 x S/. 15.00 = S/. 600.00

TARRAJEO DE PAREDES PULIDAS EN CISTERNA 105 m2 x S/. 15.00 = S/. 1,575.00

TOTAL EN MANO DE OBRA.. S/. 12,910.00


PRESUPUESTO DE MATERIALES
CISTERNA MORILLAS

DESCRIPCION CANTIDAD UNIDAD PRECIO SUB- TOTAL


UNITARIO

2 3
CONCRETO ARMADO PACASMAYO( 210 kg/m ) 148 m x S/. 248.30 = S/. 36,748.77

FIERRO DE 1/2 " 530 Varil. x S/. 24.00 = S/. 12,720.00

ALAMBRE N 16 30 KG x S/. 4.00 = S/. 120.00

ALAMBRE N 8. 30 KG x S/. 4.00 = S/. 120.00

CLAVOS.. 10 KG x S/. 4.00 = S/. 40.00

ARENA GRUESA. 6 m3 x S/. 20.00 = S/. 120.00

GRAVILLA DE 1/2 " . 6 m3 x S/. 30.00 = S/. 180.00

ARENA FINA.... 6 m3 x S/. 20.00 = S/. 120.00

CEMENTO ( BOLSA AZUL ) 45 Bol. x S/. 25.00 = S/. 1,125.00

TOTAL EN MANO DE OBRA.. S/. 51,293.77