BLOK PODIUM DI ATAS LOT 266, 349 DAN TANAH KERAJAAN, JALAN TUN SAMBANTHAN, SEKSYEN 72,
DALAM BANDARAYA KUALA LUMPUR, WILAYAH PERSEKUTUAN. Works Package Contract: The
Execution And Completion Of Site Clearance, Earthworks, Bored Piling, Diaphragm Wall And Substructure Work
Package No. : 113/P001
___________________________________________________________________________
METHOD STATEMENT
FOR
RAFT SLAB CASTING
4 Casting
4.1 750mm Basement Slab
4.2 3000mm Basement Slab
5 Curing
7 Appendixes
Project
LOT 349 SENTRAL SUITES ref. : AJ143
METHOD STATEMENT Revision : 00
FOR
Date : 31 MAY 2017
RAFT SLAB CASTING
Page : 1 of 7
1.0 INTRODUCTION
The following method statement describes the construction procedures that need to be
taken throughout the raft slab construction period. The quality control of the work will
be highlighted in this Method Statement to ensure best quality of work can be
achieved.
The raft slab will be divided into 16 zones for 750mm thick slab, 3 tower areas (3m
thick) and 3 lift core area (1.6m thick). The 3m thick raft slab casting shall be focus
because it involves the uses of low heat concrete and concrete temperature control.
The method statement described in the following sections is subject to review during
the sub-structure construction period, and may be amended if so required. Any
amendment to this method statement shall be submitted to the Engineer for review
and approval prior to the commencement of the work at site.
In order to control the rising temperature within the allowable limit, low heat concrete
is used to maintain the peak temperature below the maximum allowable limit.
The cementitious content involved in this concrete mix is combination of Cement and
PFA as per design mix are enclosed in Appendix A.
Moreover, to ensure the above predicted temperature is well mitigated, the procedure
for the concrete temperature control is enclosed in Appendix B.
Project
LOT 349 SENTRAL SUITES ref. : AJ143
METHOD STATEMENT Revision : 00
FOR
Date : 31 MAY 2017
RAFT SLAB CASTING
Page : 2 of 7
50-mm thick of lean concrete of Grade 15 concrete shall be applied to the soffits
of basement slab.
Pressure relief valve and subsoil drain shall be provided as per drawing (ref to
Appendix C). Temporary pump pit shall also be provided for dewatering purpose..
Side formworks will be using conventional formwork from timber and plywood
with built in 50mm thick polystyrene at the internal side of formwork (between
eventual vertical concrete surface and vertical formwork plywood (which enable
the vertical formwork to dismantle after 24 hours of casting while remain the
insulation (50mm thick polystyrene) to confine the temperature. The schematic
diagram on the method of installation of 50mm thick polystyrene is enclosed in
Appendix D.
4.0 CASTING
750mm basement slab area are mainly podium area, which further divided into 16
zones (as per Appendix E). The division on casting zoning is based on our target
to complete the big cast within 12 hours, so there shall be at least 2 pumps truck
employed to perform and finish the job within the limited time.
Assuming,
Thus, 2 pump trucks are sufficient to achieve the targeted pour volume of 100m3/
hr.
Therefore, in order to ensure the continuity supply of concrete, there must have at
least 15 concrete trucks available to deliver the concrete to site and with 2 pump
trucks to pump the concrete.
Our aim is to complete casting a 3m thick raft slab in a single cast. Thus, sufficient
numbers of concrete pump shall be employed to ensure continuity of concrete pouring
and to ensure that casting will be completed in certain targeted timeframe. Number of
concrete pump to be employed shall be based on calculation taking into account
volume of casting, concrete pump capacity, targeted concreting period, and site
condition in term of space available for concrete pump and maneuver of the concrete
truck mixer. At least one (1) unit concrete pump shall be stand by for back up at any
location enabling it to replace main concrete pump in short time in case there is any
breakdown.
For example: Concrete volume = 7000 m3 by using 1 number of pump truck with
average speed of 50m3 per hour, hence concreting duration is approx. 140 hours. If 3
pump trucks are deployed, concreting duration is approx. 47 hours. Client
representatives shall be informed 3 days in advance the actual pump truck to be
deployed and concreting schedule for them to plan the supervising team.
calculation considering certain factors i.e. number and capacity of concrete pump,
traveling period from batching plant to project site, etc.
For instance:
- Batching time = 10 minutes,
- Travelling time per trip = 35 minutes,
- Estimated turnaround time = 70 minutes,
- Discharging time = 10 minutes,
- Concrete Truck Capacity = 10m3
Thus, 3 pump trucks are sufficient to achieve the targeted pour volume of 150m3/ hr.
Hence, the minimum concrete truck provided by Concrete Supplier shall be at least 23
trucks to ensure the flow is uninterrupted and with 3 pump trucks to operate.
However, the actual provision of concrete truck shall always suit to actual concreting
speed and shall be increased whenever is necessary.
Project
LOT 349 SENTRAL SUITES ref. : AJ143
METHOD STATEMENT Revision : 00
FOR
Date : 31 MAY 2017
RAFT SLAB CASTING
Page : 6 of 7
5.0 CURING
Any selected method of insulation must assure that the internal differential temperature
of concrete does not exceed 27.7 degrees Celsius as explained in Appendix B.
2. To provide the built in/cast in 50mm thick polystyrene attach to the internal side
of formworks (this shall enable the vertical formworks to dismantle and reuse)
until insulation period is finished.
In case of internal differential temperature exceeding 27.7 degrees Celsius, action must
be taken with the insulation such as adding more layers of polystyrene.
For normal slab other than 3m thick raft slab, curing shall be carried out by applying
approved curing compound on the final surface of concrete.
Project
LOT 349 SENTRAL SUITES ref. : AJ143
METHOD STATEMENT Revision : 00
FOR
Date : 31 MAY 2017
RAFT SLAB CASTING
Page : 7 of 7
The temperature monitoring shall continue until the difference between maximum
temperature of the concrete and the ambient temperature is less than 27.7 degree
Celsius.
Temporary perimeter drain shall be provided around the casting zone and channel to
temporary pump pit and discharged to the silt trap, to prevent excessive runoff to
contaminate the concrete during pouring.
Temporary cover over the 3m raft slab casting zone shall be provided as measure to
divert the rain to the temporary perimeter drain and temporary pump pit before
discharge from the site. The detail of temporary cover shall be provided at later stage.
Project
LOT 349 SENTRAL SUITES ref. : AJ143
METHOD STATEMENT Revision : 00
FOR
Date : 31 MAY 2017
RAFT SLAB CASTING
Page : 8 of 7
7.0 Appendixes
QUANTITIES PER M
CEMENT WATER FINE AGG. COARSE AGG. ADMIXTURE
350 Kg 155 Kg 898 Kg 973 Kg 1750 Ml RS233
2450 Ml RPF3G
METHOD OF STATEMENT
THE SUPPLY AND DELIVERY OF READY MIXED
CONCRETE FOR SENTRAL SUITESS PROJECT
KUALA LUMPUR
MAY 2017
TABLE OF CONTENT
1. Introduction
2. Objective
10. Attachments
i. Mix Designs and Temperature Calculations
ii. Product Data Sheet
iii. Contact List for Personnel
iv. Temperature Monitoring Arrangement Plan
CEMEX CONCRETE (MALAYSIA) SDN BHD
ANEKA JARINGAN SENTRAL SUITES
1.0 Introduction
The client Aneka Jaringan Sdn Bhd has undertaken the construction of Sentral Suites
Towers Raft Foundation. The project consists of 3 main towers. It is estimated that a
total of 6,000 7,000 cubic meters (m3) of Grade 35 Mass will be discharged for the raft
( 3).
foundation of each tower. Estimated total volume is 20,000 cubic meters (m
This Method Concrete is
Method Of Statement for the Delivery and Supply Of Ready Mixed Concrete
submitted by Cemex Concrete (Malaysia) Sd Sdn.
n. Bhd. who is proposing to undertake the
supply of Ready Mixed Concrete to this project.
project
The proposed mix design calculations and the temperature calculation, compliance with
the British Standards, the allocation of supply to the respective plants, the logistics
lo
involved in the supply and transportation of raw materials and concrete are mentioned.
2.0 Objective
The purpose of this Method Of Statement is to detail out all the factors and
parameters involved and to fine tune the processes to ensure that alall the criteria are
met; from the mix designs and trial mixes, the smooth delivery of the raw materials for
this pour and supporting logistics.
Water used will be underground water / SYABAS and in accordance with BS EN 1008 :
2002 Methods of test for water for making concrete (includi
(including
ng notes on the suitability
of the water)
Admixtures used will be in accordance with BS EN 408-1:2006
1:2006 Concrete admixtures.
Specification for accelerating admixtures, retarding admixtures and water reducing
admixtures. Fosroc admixture will be used
used; CONPLAST R-22 (retarder) and AURAMIX
450SR (PCE admixture).
Table 3.2 of BS 8110: Part 2: 1985 had indicated the estimating limiting temperature
changes to avoid cracking according to the aggregate type. The limit of temperature
differential relates the type of aggregate to its thermal expansion coefficient, its tensile
te
strain capacity and the limiting temperature differential for different values of the
restraint factor. Table 3.3 of BS 8110: Part 2: 1985 provides indicative value of the
restraint factor for different pour configuration.
CEMEX CONCRETE (MALAYSIA) SDN BHD
ANEKA JARINGAN SENTRAL SUITES
ii. Aggregate
Stockpile shall be stored at shaded compartment.
iii. Sand
Stockpile shall be stored at shaded compartment.
iv. Ice
Tube ice / crushed ice shall be used to reduce the fresh concrete temperature to the
desired temperature. Ice to be weighted to the correct amount required and convey
direct into the mixer. Mixing time to be adjusted appropriately to ensure it melts
completely
tely prior to the completion of mixing concrete.
Dry sand will be used for batching or moisture 5 %. Dry aggregate will be used for
batching or moisture 1 %
For every 50m3, 1 set of 12 cubes shall be taken with Site Engineers instruction, to be
tested for 7, 28 and 56 days and 3 for spare. Cubes will be casted via vibrating table or
hand tamped.
ii. Batching Plants 3 units of batching plant located at Jalan Dua (CSL plant), Jalan Tiga
(KLP plant), Jalan Lima (Sg.Besi plant) all wet type units with a capacity to produce 70m3
of concrete per hour and a back up plant (PJ Sentral) with a capacity to produce 70m3 of
concrete per hour which will back up from 8PM to 8AM the following day.
iii. Trucking Estimated trucks to be allocated for this pour is 12 units per plant carrying a
range of 8m3 to 12m3 per load
iv. Machineries For each plant there will be 2 units of loader, 2 units of 275kVa generator
sets will be available for back up supply of electricity in case of TNB black out.
vi. Materials
Cement will be stored in 4 silos each silo capacity 100 tons,
Loads of Cement tankers will be standby for stocking up,
Coarse Aggregate
Will ill be stocked up at 1500 tons
Internal grading test will be carried out prior to supply
Dry aggregate will be used or moisture <= 1%
Stockpile will be stored in shaded compartment
iv. Fine Aggregate
Will
ill be stocked up at 1500 tons
Organic and silt content will be check prior to supply
Moisture checking 3 times a day via oven dry method
Dry sand will be use or moisture <= 5%
Stockpile will be stored in shaded compartment
vii. Ice Enough Stock will be available and stored in cooler at plants
Uses
concrete with no adverse effect on subsequent stiffening
To improve the effectiveness of the water content of a and strength gain.
concrete mix. Technical Support
To extend the setting time of concrete, extending
The company provides a technical advisory service
working times and minimising delay problems.
supported by a team of specialists in the field.
To extend the working life of semi-dry concrete Typical dosage
screeds.
The optimum dosage of Conplast R-2 to meet specific
Particularly suitable for use in mixes having fly ash
requirements should always be determined by trials using
and also improve the working life of semi dry concrete
the materials and conditions that will be experienced in
mixes, specifically RCC (Roller Compacted Concrete)
use. This allows the optimisation of admixture dosage and
type of mixes.
mix design and provides a complete assessment of the
Advantages concrete mix. A starting point for such trials is to use a
dosage within the normal typical range of 0.25 to 0.60
Water reduction significantly improves compressive
litres / 100 kg of cementitious material, including PFA,
strengths at all ages and enhances durability through
GGBFS or microsilica.
the production of low permeability concrete.
Use at other dosages
Controlled retardation extends working life and
stiffening time for ease of construction. Dosages outside the typical range quoted above may be
used if necessary and suitable to meet particular mix
Control of stiffening improves slip forming and assists
requirements, provided that adequate supervision is
in preventing the formation of cold joints in large
available. Compliance with requirements must be
pours.
assessed through trial mixes. Fosroc shall be contacted
Allows specified strength grades to be met at reduced for advice in these cases.
cement content or increased workability.
Properties
Chloride free, safe for use in pre stressed and
Appearance : Clear liquid
reinforced concrete.
Specific gravity : Typically 13 - 1.15 at 27C
Standards compliance
Chloride content : Nil to BS:5075
Conplast R-2 complies with BS 5075 Part 1 and with
ASTM C494 as Type B and Type D. Air entrainment : Typically slightly less air will
Conplast R-2
together prior to addition. The resultant properties of may cause segregation and bleeding, particularly in high
concrete containing more than one admixture should be workability mixes. The degree of this effect will depend on
assessed by the trial mix to ensure that effects such as the particular mix design and overdose level.
unwanted excessive retardation C494 as Type B and
Curing
Type D. brown solution which instantly disperses in water
effectively. Technical support cementitious material, As with all structural concrete, good curing practice should
including PFA, GGBFS or microsilica. Properties typically be maintained, particularly in situations where an overdose
slightly less air will normal concrete mix. Typically less has occurred. Water spray, wet hessian or a Concure spray
than 55.0g do not occur. applied curing membrane should be used.
Conplast R-2 is suitable for use with all types of ordinary Estimating
Porland cements and cement replacement materials such Packaging
as PFA, GGBFS and silica fume. Further information on
such usage is provided elsewhere on this datasheet. Conplast R-2 is available in 210 litre drums.
Dispensing Storage
The correct quantity of Conplast R-2 should be measured Conplast R-2 has a minimum shelf life of 12 months
provided the temperature is kept within the range of 2C to
by means of a recommended dispenser. The admixture
50C. Should the temperature of the product fall outside this
should then be added to the concrete with the mixing range then Fosroc shall be consulted.
water to obtain the best results. Fosroc shall be contacted
for advice regarding suitable equipment and its Freezing point : Approximately - 4C.
installation. Precautions
Effects of overdosing Health and safety instructions
An overdose of double the intended amount of Conplast Conplast R-2 should not be swallowed or allowed to come
R-2 will result in a significant increase in retardation as into contact with skin and eyes. Suitable protective gloves
compared to that normally obtained at the intended and goggles should be worn.
dosage. Provided that adequate curing is maintained, the
Splashes on the skin should be removed with water. In case
ultimate strength of the concrete will not be impaired by
of contact with eyes it shall be rinsed immediately with
increased retardation and will generally be increased. The
plenty of water and medical advice sought immediately. If
effects of overdosing will be further increased if sulphate
swallowed, medical attention shall be sought immediately.
resisting cement or cement replacement materials are
Vomiting should not be used.
used.
Fire
An overdose will tend to increase the plasticising effect of
the admixture. As concrete is normally batched to a target Conplast R-2 is water based and non-flammable.
workability, increased plasticising will allow an increased
Cleaning and disposal
water reduction. This will have the effect of increasing
ultimate strength and partially or fully offsetting the effect Spillages of Conplast R-2 should be absorbed onto sand,
of any increased air entrainment. If no increase in water earth or vermiculite and transferred to suitable containers.
reduction is taken, and a significant rise is workability is
The disposal of excess or waste material should be carried
allowed, the chance of segregation may be higher.
out in accordance with local legislation under the guidance
Increased initial workability will tend to extend the working
of the local waste regulatory authority.
life of the concrete, which will delay finishing and stiffening
times to some extent.
constructive solutions
Conplast R-2
Important note
Fosroc products are guaranteed against defective materials and manufacture and are sold subject to its standard Conditions for the
Supply of Goods and Services, copies of which may be obtained on request. Whilst Fosroc endeavours to ensure that any advice,
recommendation, specification of information it may give is accurate and correct, it cannot, because it has no direct or continuous
control over where or how its products are applied, accept any liability either directly or indirectly arising from the use of its products,
Fosroc Sdn. Bhd. whether or not in accordance with any advice, specification, recommendation of information given by it.
www.fosroc.com
Fosroc*
Auramix 450SR constructive solutions
One type of PCE based admixture specially Auramix 450SR combines the properties of high water
reduction and workability retention. It allows the production
designed for superplasticizer with long slump
of high performance concrete and/or concrete with high
retention concrete without retardation and ultra workability.
high performance concrete (UHPC)
Auramix 450SR is a particularly strong superplasticizer
Uses allowing production of consistent concrete properties
around the required dosage.
Auramix 450SR is a high performance superplasticizer
intended for applications where increased early and ultimate
Properties
compressive strengths and slump retention are required.
Auramix 450SR has been developed for use in;
SCC, high flowing concrete Appearance : Light yellow coloured liquid
Ultra high performance concrete (UHPC)
Specific gravity : 1.09 0.02, @ 20C
Pumping concrete for high rising skyscrapers
Chloride content : < 0.1%
Long slump retention
: Typically less than 1.5% Na2O
Alkali content
Advantages Equivalent / litre of admixture.
Specially developed for ready mix concrete and good
surface finishing Dosage
Especially developed for long slump retention concrete
Improved adhesion to reinforcing and stressing steel The optimum dosage of Auramix 450SR to meet specific
Improved resistance to carbonation requirements should always be determined by trials using
Reduced water permeability the materials and conditions that will be experienced in use.
Resistance to aggressive atmospheric conditions
Reduced shrinkage and creep The typical dosage range is between 0.5 to 2.5 kg/100 kg of
Increased workability retention without affecting setting cementitious material.
time
Increased concrete durability Use at other dosages
Enhanced pumpability with low viscosity Dosages outside the typical range quoted above can be
Resistance to bleeding and segregation used to meet particular mix requirements. Contact Fosroc
for advice in these cases.
Standards compliance
Auramix 450SR conforms with BS 5075, BS:EN 934 and with Effects of overdosing
ASTM C494 as Type F & G depending on the dosage used. Overdosage may promote delays in setting time,
segregation and excessive bleeding of the concrete mix.
Advantages
Auramix 450SR is differentiated from conventional Technical support
superplasticizers in that it is based on a unique carboxylic Fosroc provides a technical advisory service for on-site
polymer with long lateral chains. This greatly improves assistance and advice on mix design, admixture selection,
cement dispersion. At the start of the mixing process, evaluation trials and dispensing equipment.
electrostatic dispersion occurs but the presence of the lateral
chains, linked to the polymer backbone, generate a steric
hindrance which stabilizes the cement particles capacity to
separate and disperse. This mechanism considerably
reduces the water demand in flowable concrete.
Instruction for use Precautions
Compatibility Storage
Auramix 450SR should not be used in conjunction with any Auramix 450SR has a minimum shelf life of 12 months
other admixtures unless prior approval is obtained from your provided the temperature is kept within the range of 2C to
local Fosroc office. 50C. Should the temperature of the product fall outside this
range then contact Fosroc for advice.
Auramix 450SR is suitable for use with all types of Portland
cements and cement replacement materials such as PFA, Health and safety
GGBS, SRC and Micro-Silica. Auramix 450SR does not fall into the hazard classifications of
current regulations. However, it should not be swallowed or
Mixing allowed to come into contact with skin and eyes. Suitable
When used at the mixing plant, Auramix 450SR should be protective gloves and goggles should be worn. Splashes on
added in the mixing water. the skin should be removed with water. In case of contact
with eyes rinse immediately with plenty of water and seek
In some instances, e.g. addition to ready mix concrete on site, medical advice. If swallowed seek medical attention
Auramix 450SR can be added directly in the truck mixer and immediately - do not induce vomiting.
mixed at maximum speed for an extra 5 minutes.
For further information consult the Material Safety Data Sheet
Dispensing available for this product.
The correct quantity of Auramix 450SR should be measured
by means of suitable dispenser. The admixture should then Fire
be added to the concrete with the mixing water to obtain the Auramix 450SR is water based and non-flammable.
best results. Contact Fosroc for advice regarding suitable
equipment and its installation. Cleaning and disposal
Spillages of Auramix 450SR should be absorbed onto sand,
Estimating packaging earth or vermiculite and transferred to suitable containers.
Auramix 450SR is available in 200 litre drums, 1000 litre IBCs Remnants should be hosed down with large quantities of
and bulk. water. The disposal of excess or waste material should be
carried out in accordance with local legislation under the
guidance of the local waste regulatory authority.
+
See separate data sheet
Important note
Fosroc SDN BHD Fosroc products are guaranteed against defective materials and manufacture and are sold subject to its standard terms and conditions of sale,
copies of which may be obtained on request. Whilst Fosroc endeavours to that any advice, recommendation, specification or information it may
give is accurate and correct, it cannot, because it has no direct or continuous control over where or how its products are applied, accept any
No. 8, Jalan Trompet 33/8 liability either directly or indirectly arising from the use of its products, whether or not in accordance with any advice, specification,
Seksyen 33 recommendation or information given by it.
40400 Shah Alam
Selangor, Malaysia Telephone: Fax: email:
+60 3 5102 5660 +60 3 5102 5668 enquirymalaysia@fosroc.com
FM/OCT/16/A
CEMEX CONCRETE (MALAYSIA) SDN BHD
ANEKA JARINGAN SENTRAL SUITES
Date TBC
Time TBC
Volume 6000m
Pump
Overrall in charges Muhammad Alif 012-2821222
Yap 012-2736503
Site Coordinator Plant Manager Rama 012-3421674 (Shift 1)
Plant Manager Lim 012-3421649 (Shift 2)
Qc Manager Azanan 012-2826605 (Shift 1)
Qc Manager Hj.Khairul 012-6030122 (Shift 2)
Qc Technician 9 Person Shift 1 (3 slump checked point)
Qc Technician 9 Person Shift 2 (3 slump checked point)
Vibrating Table 3 nos
Temperature Monitoring
Arrangement Plan
Thermal Couples
200mm
200mm
650mm
650mm
3m depth
650mm
650mm
200mm
2nd Pour
1st Pour
MEGAMIX SDN. BHD.
C12/3, BLOCK C, JALAN DAGANG BESAR
PUSAT PERDAGANGAN TAMAN DAGANG, 68000 AMPANG SELANGOR
: 42703399
: 42703389
QUANTITIES PER M
CEMENT WATER FINE AGG. COARSE AGG. ADMIXTURE
350 Kg 155 Kg 898 Kg 973 Kg 1750 Ml RS233
2450 Ml RPF3G
200mm
200mm
650mm
650mm
3m depth
650mm
650mm
200mm
2nd Pour
1st Pour
Appendix C
SUMP PIT LAYOUT
Appendix D
INSTALLATION OF POLYSTYRENE
RaftSlabtoCast
Formwork
750
3000
Polystyrene ConstructionJoint
toreferCJshop
drawings
DowelBars
toEngineers
detail
1600
Swellable WS
3000
Polystyrene ConstructionJoint
toreferCJshop
drawings
DowelBars
toEngineers
detail
1600
Swellable WS
Glostrext Instrumentation Method : A novel technology empowering You to make decisions based on Facts
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
CONTENTS
Page
1. Introduction 3
Figures:
Figure 1: Temperature Probe Monitoring details
Appendixes:
Appendix A: Technical catalogues and information on Geokon Thermistor Probes,
Datalogger and Spectests Web-based Data Centre Monitoring Services
2
Spectest Sdn. Bhd. ( 236932-K)
~Leading Geotechnical Instrumentation Specialists ~
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
1. Introduction
The phenomena of temperature rise-and-fall in early-age concrete have been well recognized. It is
due to hydration and this causes expansion or contraction in the concrete mass. Concreting in a
tropical climate can be challenging, particularly in the case of a thick section. Higher ambient and
initial concrete temperatures accelerate cement hydration, affecting both fresh and hardened
concrete properties. Therefore it is important to consider aspects of temperature control, design
and implement good strategy for placement of a thick section in mass concrete pour.
It is also useful to adopt an instrumentation and monitoring scheme to obtain the temperature
profiles during placement of mass concrete pour, to assist engineers to assess various aspects of
temperature control and the use of certain construction methods.
Geokon Model 3800 Thermistor probes, consist of interchangeable thermistor bead mounted
inside a rugged PVC, are designed for remote measurement of hydration and cooling
temperatures in placement of mass concrete. Readings of the thermistor probes can be
conveniently logged automatically and continuously using Geokon Datalogger. The data can
be monitored, viewed and displayed real-time through internet via Spectests SDataCentre,
at close and short interval instructed by the consulting engineer from time to time.
3
Spectest Sdn. Bhd. ( 236932-K)
~Leading Geotechnical Instrumentation Specialists ~
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
The technical catalogues and information on Geokon Thermistor Probes, Datalogger and
Spectests Web-based Data Centre Monitoring Services are given in Appendix A for ease of
reference .
4
Spectest Sdn. Bhd. ( 236932-K)
~Leading Geotechnical Instrumentation Specialists ~
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
5
Spectest Sdn. Bhd. ( 236932-K)
~Leading Geotechnical Instrumentation Specialists ~
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
Appendix A: Technical catalogues and information on Geokon Thermistor Probes, Datalogger
and Spectests Web-based Data Centre Monitoring Services
6
Spectest Sdn. Bhd. ( 236932-K)
~Leading Geotechnical Instrumentation Specialists ~
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
7
Spectest Sdn. Bhd. ( 236932-K)
~Leading Geotechnical Instrumentation Specialists ~
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
8
Spectest Sdn. Bhd. ( 236932-K)
~Leading Geotechnical Instrumentation Specialists ~
. Your Trusted Instrumentation and Monitoring Technology Provider since 1992 .....
SDataCentre Web Monitoring Services
SDataCentre web monitoring services utilizes professional data analysis software to store logged data,
display and publish it to the Web. Our services contain everything you need to view data from any other
data text files, and easily view data in the internet.
Data from data logger is collected remotely from Spectest Data Centre using Multilogger / LoggerNet
software and the data is stored in our server's local drive. SDataCentre monitors these data files and as soon
as new data is collected from a remote datalogger the data is automatically read and imported into our
database.
As soon as the data is in the database it is accessible online using any Internet browser. The data can be
analyzed in different ways.
9
Appendix G
CURING COMPOUND
Appendix H
BONDING AGENT
Appendix I
SAFE WORK METHOD STATEMENT