NEC 2017 will bring some big changes to the world of PV design and permitting.
The 2017 Edition of the National Fire Protection Association (NFPA) 70 National
Electrical Code (NEC) brings a handful of additions and clarifications to the code
pertaining to the permitting and installation of solar PV. These changes will have
meaningful impacts on the design criteria of residential and commercial solar installations
alike. While NFPA 70 covers best-practice of everything from feeders circuits, to HVAC
and fiber optic cable raceways, the code most relevant to solar installations lives in Article
690.

In addition to providing clarification, the new NEC code was developed with concision in
mind. Despite building out certain sections (namely rapid shutdown requirements) to
provide manufacturers and contractors with increased guidance, overall Article 690 will see
a 20% reduction in word count over the 2014 Edition. Although the final draft of NEC
2017 has yet to be signed off by the NFPA, the changes highlighted below are sure to be
represented in the final adoption. Please note this is not an exhaustive look at all the solar-
relevant code changes coming down the pipe. The following represent changes sure to
impact a large majority of solar contractors on the most common installs. Further resources
on coming code changes can be found at the end of this article.

Section 690.12 - Rapid Shutdown of PV Systems on Buildings

Rapid shutdown (RS) was formally codified in the 2014 Edition of NFPA 70. This article
sought to control conductors beyond a specified distance of the array to ensure first
responder safety in the event of a fire-related emergency at a building with solar. As can be
seen in the figure below, PV conductors greater than 5 ft in length within the building, and
conductors greater than 10ft outside of the building must be limited to no more than 30V
and 240 volt-amperes within 10 seconds of rapid shutdown initiation. Rapid shutdown
initiation methods must be labeled in a specific manner.

Conductors impacted by NEC 2014 rapid shutdown requirments.

Most notably, NEC 2014 called for rapid shutdown equipment to be listed and identified as
serving its named purpose. In keeping with the definition provided by the NFPA, identified
allows for the use of existing equipment (contactor combiner) to satisfy RS requirements as
long as the equipments use is compliant with its stated rating. Seeking to standardize the
equipment used in RS systems, NEC 2017 calls for the use of equipment that is listed and
labeled. This labeled requirement drives the need for the development of RS-specific
product standards. As these standard have yet to be established, listed and labeled RS
requirements will not come into enforcement until January 1, 2019. We'll be on the lookout
for standardized and certified RS combiners as they hit the market.

NEC 2017 spells out 3 options for RS compliance:

Option 1: List and label or field-label PV array as a rapid-shutdown PV array.


Option 2: Limit controlled conductors within the array boundary to 80 V or less
within 30 seconds of rapid-shutdown initiation.
Option 3: Install nonmetallic PV array with no exposed wiring and array more than
8 feet from any grounded metal parts.

Options 2 and 3 will help guide the development of the certifications and standards for the
next generation of labeled RS boxes/combiners.

As RS codes evolve so must the labeling of these systems. In a post NEC 2017 adoption
world firefighters will face the possibility of encountering three different PV systems; pre-
NEC 2014 (no RS), NEC 2014 compliant (conductors de-energized according to the below-
left image), and NEC 2017 compliant (PV conductors de-energized at the array, below-
right image). To effectively communicate the safety of the array, labels must accurately
reflect which conductors will become de-energized after RS initiation. Some sample labels
can be found below.

On the left we see a label indicating a system in compliance with NEC 2014 Rapid
Shutdown. The system on the right is NEC 2017 compliant.
For a more detailed look at PV labeling in NEC 2017 (including but not limited to RS)
please see Todd Friess article in Solar Power World.

Functionally v. Solidly Grounded

In the US utilities supply grounded AC power to homes and businesses. In practice this
means a conductor that would otherwise carry current is purposely not energized and is
instead connected solidly to ground. According to Article 100 of the NFPA code a solidly
grounded system is one that is connected to ground without inserting any resistor or
impedance device. Evolution of safety guidelines in the code and technological
developments of PV inverters have rendered the solidly grounded requirement somewhat
obsolete. First, the advent and ultimate requirement of DC ground fault protection in PV
systems led to overcurrent protection (OCP) becoming a part of the system ground
connection. A system with OCP on the ground conductor is no longer in accordance with
the coded definition of a solidly grounded electrical system. In essence these systems are
functionally rather than solidly grounded.

Second, the rise of non-isolated transformerless inverters further pushed the limits of the
code by introducing ungrounded electrical systems into the grid. This led to the
introduction of Article 690.35, Ungrounded PV Systems in the 2005 Edition of the NEC.
With ungrounded and functionally grounded systems becoming the only types of systems
installed in the past decade or so, NEC 2017 sought to bring clarity and simplification to
contractors and AHJs alike. NEC 2017 introduces the definition of a functionally grounded
PV system as one that has an electrical reference to ground that is not solidly grounded.
Furthermore Article 690.35, Ungrounded PV Systems was removed from NEC 2017.
New design criteria for functionally grounded and ungrounded PV systems under NEC
2017. Note OCP on only one leg of the circuit but a disconnecting means on both poles.
Image Courtesy of SolarPro

Together these two changes have a large impact on the design criteria of modern PV
systems. Prior to this change two design criteria existed for PV systems. For solidly or
functionally grounded PV systems OCPD was required on one leg of a PV circuit. By
comparison, ungrounded PV systems required both legs of the PV circuit to have OCP. In
recognizing that no new PV system is solidly grounded we can consolidate the design
criteria for all new PV systems under NEC 2017. These changes can be summarized as
follows;

Overcurrent protection is required in only one leg of a PV circuit [690.9(C)]


Disconnecting means are required in both legs of a PV circuit [690.15]
USE-2 or PV Wire is allowed as single-conductor cable in a PV array [690.31(C)]

In practice this consolidation will simplify system design for new and experienced solar
contractors alike. The permitting and inspection of new PV systems will also become more
intuitive as both functionally grounded and ungrounded systems will be held to the same
standard of OCP. To the relief of many, ungrounded systems that require combiner boxes
will no longer require "oversized" boxes to accommodate double the number of fuses as
their are PV circuits entering the box. The code changes listed above, in particular 690.15,
will also improve the safety of technicians servicing functionally grounded systems. By
requiring a means to disconnect both legs of the PV circuit a technician can safely work on
a PV system during daylight hours. Finally, the final code change bulleted above,
690.31(C), allows for integrators to replace grounded inverters with new transformerless
inverters in an existing system without having to upgrade single conductor wiring (DC
disconnects will need to be rewired or most-likely replaced).

PV System Boundaries

To increase serviceability safety and increase clarity NEC 2017 addresses the location of
the PV disconnect and introduces new PV system boundaries. Unlike previous NEC
editions, NEC 2017 breaks out energy storage and battery-based multimode inverters from
the PV system. As energy storage systems become more prevalent in the presence of solar
it was deemed necessary to parse out the code covering these components. Moving forward
these components will be addressed in their own dedicated articles. As such, the PV
disconnect now represents the boundary of the PV system. In standard grid-tied systems
the only components located upstream of the PV disconnect include the PV array and
inverter(s). This remains the same for systems employing AC modules or microinverters.
No longer part of the PV system, battery inverters, batteries and dump loads will be located
downstream of the PV system disconnect.

Once again, please keep in mind the proposed changes above are just a small section of the
changes to Article 690 in NEC 2017. As can be seen in the table below there are many
subtle yet impactful changes sure to be coming in the newest edition of the NEC. Together
these changes promise to clarify both the design and permitting process. Stay tuned for
more NEC 2017 developments as they arise.
Summary of NEC 2017 solar-related changes.

For more information and analysis on upcoming NEC changes please see the following