TRAZO INICIAL , NIVELACION Y REPLANTEO PARA CERC PERIMETRICO (CON EQUIPO) M 48.80
REPLANTEO FINAL DE LA OBRA PARA CERCO PERIMETRICO(CON EQUIPO) M 48.80
EXCAV. TERR ROCOSO PULSO HASTA 1.00m prof. M3 26.10
EXCAV. TERR ROCOSO A PULSO HASTA 1.50m prof. M3 8.50
REFINE , NIVELACION, Y COMPACTACION EN TERRENO NORMAL M2 16.00
RELLENO CON MATERIAL PROPIO M3 2.00
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 10 KM CON MAQ M3 32.60
CONCRETO 1:10 C.H + 30 P.G < Max 4 " > PARA CIMIENTO CORRIDO CP-V M3 16.00
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 24.00
CONCRETO 1 : 8 C.H + 25 % PM < 3 " > PARA SOBRECIMIENTO CP-V M3 6.20
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO CORRIDO T / CARA VISTA M2 73.50
CONCRETO FC 210 KGR / CM2 PARA COLUMNAS CP V M3 5.50
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 63.10
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,278.00
CONCRETO FC210 K GR / CM2 PARA VIGA CP V M3 3.60
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA TIPO CARA VISTA M2 40.00
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 281.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 176.60
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 130.50
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 624.00
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 261.00
PUERTA CON MARCO DE TUBO FIERRO GALVANIZADO 2 " Y 4 " Y PKLANCHA LAC 3/ 16 M2 13.50
PICAPORTES UNIDAD 3.00
CERROJO O PESTILLOS UNIDAD 1.00
PICAPORTES DE FOGDO + ALDABA UNIDAD 1.00
CANDADO QUE INCLUYE ALDAVAS UNIDAD 1.00
CERRADURA PARA EXTERIOR C/ LLAVE INTERY EXTERIOR DE 2 GOLPES UNIDAD 1.00
PINTADO DE MURO EXTERIOR CON PINTURA LATEX ACRILICO M2 243.50
PINTADO DE PUERTA METALICAS LAC ( 2 MANOS ANTICORROSIVA + 2 ESMALTES ) M2 27.00
PROVISION Y COLOCADO DE ALAMBRE PUAS EN PUERTA M 31.50
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO UNIDAD 4.00
CONCRETO 1:10 + 30% P.G. PARA CIMIENTO CORRIDO (Cemento P-I) M3 18.50
91.1 X 45.50 X
0,25X 0,30 0,55X 0,25 =
6,83M3 6,256 M3 13,086 M3
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 4,014.00
C-1 C-2
TRAMO A-B 6,20+6,20 12.40 7.10
TRAMO B-C 7,10+6,20+7,00 20.30
7.00 7.00 7.10
TRAMO C-D 7,40+7,00 14.40 7.50
TRAMO D-E 6,30+ 6.30 7.30
TRAMO E-F 7,50+6,10 13.60 7.10
TRAMO F- G 6,80+6,50 13.30 7.00
6,10+7,10 13.20
TRAMO G-H 6,20+6,20 12.40 7.50
TRAMO H-A 6,50+6,50 13.00 6.00
125.90 56.60
COLUMNAS C-1 ESTRIBOS
5/ 8 = 125,90X 4X 1,55 = 780,58 K 3/ 8 = 94 X 1,20 X 0,56 X 7 = 442,18 K
1/ 2 = 125,90X 2 X 0,99 =249,28 K 3/ 8 = 52 X 1,20 X 0,56 X 12 = 419,33 K
COLUMNAS C-2 ESTRIBOS
5/ 8 = 56,60 X 4X 1,55 = 526,38 K 3/ 8 = 94 X 1,25X2X0,56X8 = 1052,80 K
1/ 2 = 56,60 X 6 X 0,99 =336,20 K
ENCOFRADO( INC. HABITACION DE MADERA )P/VIGA RECTAS Y DINTELES TIPO CARA M2 46.50
VISTA
VIGA - VC-1
V= 0,50 X 51,62 = 25.81,M2
VIGA - VC-2
V= 0,20 X 2 X 51,62 = 20,65 ,M2
46,46 m2
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 360.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 4,50 X 4 X 2 X 0,56 = 20.16 26.00 26.00
TRAMO B-C 3/ 8 = 11,00 X 4 X 2 X 0,56 = 49.28 56.00 56.00
TRAMO C-D 3/ 8 = 5,50 X 4 X 2 X 0,56 = 26.64 28.00 28.00
TRAMO D-E 3/ 8 = 6,00 X 4 X 2 X 0,56 = 26.88 28.00 28.00
TRAMO E-F 3/ 8 = 5,00 X 4 X 2 X 0,56 = 22.40 24.00 24.00
TRAMO F- G 3/ 8 = 12,60 X 4 X 2 X 0,56 = 56.44 24.00 24.00
TRAMO G-H 3/ 8 = 5,00 X 4 X 2 X 0,56 = 22.4 20.00 20.00
TRAMO H-A 3/ 8 = 5,50 X 4 X 2 X 0,56 = 24.64 28.00 28.00
248,84 KILOS 234 M 234M
SOBRECIMIENTO 81.1
COLUMNAS 140.00
VIGAS 46.50
267.6
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 166.46
TRAMO A-B 11.100 M2
TRAMO B-C 38.520 M2
TRAMO C-D 14.760 M2
TRAMO D-E 19.700 M2
TRAMO E-F 14.920 M2
TRAMO F- G 40.320 M2
TRAMO G-H 10.860 M2
TRAMO H-A 16.280 M2
166.460 M2
EXCAV. TERR ROCOSO C/COMPRESORA HASTA 1.00m prof. Sin emplear explosivo M3 21.50
CONCRETO 1:10 + 30% P.G. PARA CIMIENTO CORRIDO CEMENTO P-I M3 19.10
68.6 X 37.80 X
0,25X 0,30 0,55X 0,25 =
5,145 M3 5,20 M3 10,34M3
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 3,949.60
C-1 C-2
TRAMO A-B 6.20 6.20 6.50
TRAMO B-C 6,20+7,00+7,50 20.70 6.70
TRAMO C-D 6,20+5,50 11.70 7.50
TRAMO D-E 6,20+ 6.20 6.20
TRAMO E-F 6,2+6,70 12.90 6.70
TRAMO F- G 7,00+7,00+6,20 20.20 6.80
TRAMO G-H 6.50 6.50 7.00
TRAMO H-A 6.00 60.00 6.00
144.40 53.40
COLUMNAS C-1 ESTRIBOS
5/ 8 = 144,40X 4X 1,55 = 895,28 K 3/ 8 = 94 X 1,20 X 0,56 X 7 = 442,18 K
1/ 2 = 144,40X 2 X 0,99 =285,91 K 3/ 8 = 52 X 1,20 X 0,56 X 12 = 419,33 K
COLUMNAS C-2 ESTRIBOS
5/ 8 = 53,40 X 4X 1,55 = 331,08 K 3/ 8 = 94 X 1,25X2X0,56X8 = 1052,80 K
1/ 2 = 53,40 X 6 X 0,99 =317,20 K
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA rectas y dinteles T/ CARA VIST M2 46.00
VIGA - VC-1
V= 0,50 X 50,82 = 25.41,M2
VIGA - VC-2
V= 0,20 X 2 X 50,82 = 20,33,M2
45.73
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 358.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 4,00 X 4 X 2 X 0,56 = 17.92 26.00 26.00
TRAMO B-C 3/ 8 = 12,00 X 4 X 2 X 0,56 = 53.76 56.00 56.00
TRAMO C-D 3/ 8 = 5,50 X 4 X 2 X 0,56 = 24.6 28.00 28.00
TRAMO D-E 3/ 8 = 6,00 X 4 X 2 X 0,56 = 26.88 28.00 28.00
TRAMO E-F 3/ 8 = 5,00 X 4 X 2 X 0,56 = 22.4 24.00 24.00
TRAMO F- G 3/ 8 = 12,60 X 4 X 2 X 0,56 = 56.44 24.00 24.00
TRAMO G-H 3/ 8 = 4,00 X 4 X 2 X 0,56 = 17.92 20.00 20.00
TRAMO H-A 3/ 8 = 6,00 X 4 X 2 X 0,56 = 26.88 28.00 28.00
246.8 234.00 234.00
SOBRECIMIENTO 81.1
COLUMNAS 140.00
VIGAS 46.85
267.95
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 164.50
TRAMO A-B 14.200 M2
TRAMO B-C 33.180 M2
TRAMO C-D 15.420 M2
TRAMO D-E 17.760 M2
TRAMO E-F 15.200 M2
TRAMO F- G 39.600 M2
TRAMO G-H 14.400 M2
TRAMO H-A 14.600 M2
164.360 M2
TRAZO INICIAL , NIVELACION Y REPLANTEO PARA CERC PERIMETRICO CON EQUIPO M 48.80
TRAMO C-D
V = 0,40 X 1,00 X 6,34 = 2,53 M3
TRAMO C - D
V = 0,40 X 1,50 X 4,90 = 2,94M3
TOTAL = 8,426 M3
TRAMO D-A
V = 0,4 X 1,50 X 1,61 = 0,966 M3
V = 0,4 X 1,50 X 2,55 = 1,53 M3
CONCRETO 1:10 C.H + 30 P.G < Max 4 " > PARA CIMIENTO CORRIDO CP- V M3 16.00
15.98
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,278.00
C-1
TRAMO A-B 6,00+6,00+6,00+ 18.00
6,00+6,00+6,00 18.00
TRAMO B-C 7,00+6,20+6,50 19.70
6,50+8,50 15.00
TRAMO C-D 7,00+7,50+7,50 22.00
TRAMO D-A 7,50+7,70 15.20
107.90 X
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA TIPO CARA VISTA M2 40.00
VIGA - VC-1
V= 0,50 X 44,30 = 22,15,M2
VIGA - VC-2
V= 0,20 X 2 X 44,30 = 17,72,M2
39.87
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 281.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 11,70 X 4 X 2 X 0,56 = 52.42 26.00 26.00
TRAMO B-C 3/ 8 = 15,00 X 4 X 2 X 0,56 = 67.20 56.00 56.00
TRAMO C-D 3/ 8 = 8,50 X 4 X 2 X 0,56 = 38.08 28.00 28.00
TRAMO D-A 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 28.00 28.00
213,70 KILOS 138,00M 138,M
ESTRIBOS
V-1 1/ 4 = 138 X 1,00 X 0,25 = 34,50 KGR
V-2 1/ 4 = 138 X 0,72 X 0,25 = 24,84 KGR
273,04 + 3% = 281,23 K
SOBRECIMIENTO 73,50 M2
COLUMNAS 63,10 M2
VIGAS 40,00M2
176,60 M2
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 130.50
TRAMO A-B 37.000
TRAMO B-C 45.120
TRAMO C-D 20.720
TRAMO D-A 27.610
130.450
7,09 M3
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 2,008.70
COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 15 = 576,60 K
1/ 2 = 4 X 6,20 X 0,99 X 15 = 368,28 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 15 = 362,88 K
COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 3 = 115,32 K
1/ 2 = 4 X 6,20 X 0,99 X 3 = 73,66 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K
COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS DINTELES TIPO CAR M2 37.60
VIGA - VC-1
V= 0,50 X 41,69 = 20,85,M2
VIGA - VC-2
V= 0,20 X 2 X 41,69 = 16,68,M2
37.52
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00
SOBRECIMIENTO 62.6
COLUMNAS 56.50
VIGAS 37.60
156.7
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 156.00
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,750.50
COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 14 = 538,16 K
1/ 2 = 4 X 6,20 X 0,99 X 14 = 343,73 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 14 = 338,69 K
COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 2 = 76,88 K
1/ 2 = 4 X 6,20 X 0,99 X 2 = 49,10 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 2X 2 = 100,80 K
COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO C M2 36.50
VIGA - VC-1
V= 0,50 X 40,50 = 20,25,M2
VIGA - VC-2
V= 0,20 X 2 X 40,50 = 16,20,M2
36.45
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00
SOBRECIMIENTO 60.7
COLUMNAS 51.00
VIGAS 36.50
148.2
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 154.00
5.75
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,750.50
COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 14 = 538,16 K
1/ 2 = 4 X 6,20 X 0,99 X 14 = 343,73 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 14 = 338,69 K
COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 2 = 76,88 K
1/ 2 = 4 X 6,20 X 0,99 X 2 = 49,10 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 2X 2 = 100,80 K
COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO C M2 36.50
VIGA - VC-1
V= 0,50 X 40,50 = 20,25,M2
VIGA - VC-2
V= 0,20 X 2 X 40,50 = 16,20,M2
36.45
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00
SOBRECIMIENTO 60.7
COLUMNAS 51.00
VIGAS 36.50
148.2
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 154.00
5.75
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 3,949.60
COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 14 = 538,16 K
1/ 2 = 4 X 6,20 X 0,99 X 14 = 343,73 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 14 = 338,69 K
COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 2 = 76,88 K
1/ 2 = 4 X 6,20 X 0,99 X 2 = 49,10 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 2X 2 = 100,80 K
COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO C M2 46.00
VIGA - VC-1
V= 0,50 X 40,50 = 20,25,M2
VIGA - VC-2
V= 0,20 X 2 X 40,50 = 16,20,M2
36.45
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 358.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00
SOBRECIMIENTO 60.7
COLUMNAS 51.00
VIGAS 36.50
148.2
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 164.50
OBRAS CIVILES