PROYECTO AMAUTA3

CERCO PERIMETRICO PARA EL RESERVORIO RAP 01 V= 100 M


2/28/2015
PARTIDA DESCRIPCION UNIDAD METRADOS
TRAZO Y REPLANTEO INICIAL PARA CERCO PERIMETRICO CON EQUIPO M 54.07
REPLANTEO FINAL DE LA OBRA, PARA CERCO PERIMETRICO CON EQUIPO M 54.07
EXCAV. TERR ROCOSO C/COMPRENSORA HASTA 1.00m prof. Sin emplear explosivo M3 21.65
REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 21.65
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 19.90
RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.70
CONCRETO 1:10 + 30% P.G PARA CIMIENTO CORRIDO CEMENTO P-I M3 18.50
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 32.50
CONCRETO 1 : 8 + 25 % PM P/ SOBRECIMIENTO (Cemento P-I)P-V M3 6.10
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 81.10
CONCRETO FC 210 KG / CM2 PARA COLUMNAS (cemento P-I) M3 13.10
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 140.00
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 4,014.00
CONCRETO FC210 KG / CM2 PARA VIGAS (Cemento P-I) M3 4.20
ENCOFRADO ( INCLUYE HABILITACION DE MADERA ) PARA VIGAS RECTAS Y DINTELES y/caravista M2 46.50
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 360.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 267.50
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 166.46
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 654.00
SOLAQUEADO DE MURO CARAVISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 322.00
PUERTA CON MARCO DE TUBO FIERRO GALVANIZADO 2 " Y 4 " Y PLANCHA LAC 1/ 16" M2 6.00
PICAPORTES UNIDAD 1.00
CERROJO O PESTILLOS UNIDAD 1.00
PICAPORTES DE FO GDO + ALDABA UNIDAD 1.00
CANDADO, INCLUYENDO ALDABAS UNIDAD 1.00
PINTADO DE MURO EXTERIOR CON TEKNOMATE O SUPERMATE (SIMILAR) M2 281.00
PINTADO DE PUERTA METALICAS LAC ( 2 MANOS ANTICORROSIVA + 2 ESMALTES ) M2 12.00
PROVISION Y COLOCADO DE ALAMBRE PUAS EN PUERTA M 14.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO (prueba a la compresion) UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 02 V= 100 M


2/28/2015
PARTIDA DESCRIPCION UNIDAD METRADOS
TRAZO Y REPLANTEO INICIAL PARA CERCO PERIMETRICO CON EQUIPO M 52.82
REPLANTEO FINAL DE LA OBRA PARA CERCO PERIMETRICO CON EQUIPO M 52.82
CERCO DE MALLA HDP DE 1 m altura para limite de seguridad de obra -SEDAPAL M 50.00
EXCAV. TERR ROCOSOC/COMPRESORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 21.50
REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 21.10
RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.70
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 18.80
CONCRETO 1:10 + 30% P.G. PARA CIMIENTO CORRIDO CEMENTO P-I M3 19.10
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 32.50
CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P-I M3 5.80
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 76.50
CONCRETO FC 210 KG / CM2 PARA COLUMNAS Cemento P-I M3 10.50
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 112.00
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 3,949.60
CONCRETO FC210 K GR / CM2 PARA VIGA Cemento P-I M3 4.10
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO CARA VISTA M2 46.00
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 358.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 268.00
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 164.50
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 657.00
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 329.00
PUERTA CON MARCO DE TUBO FIERRO GALVANIZADO 2 " Y 4 " Y PLANCHA LAC 1/ 16 M2 6.00
PICAPORTES UNIDAD 1.00
CERROJOS O PESTILLOS UNIDAD 1.00
PICAPORTES DE FOGDO + ALDAVA UNIDAD 1.00
CANDADO QUE INCLYE UNIDAD 1.00
PINTADO DE MURO EXTERIOR CON PINTURA TEKNOMATE O SUPERMATE SIMILAR M2 279.50
PINTADO DE PUERTA METALICAS LAC ( 2 MANOS ANTICORROSIVA + 2 ESMALTES ) M2 12.00
PROVISION Y COLOCADO DE ALAMBRE DE PUAS M 14.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO A LA COMPRESION UNIDAD 4.00
CERCO PERIMETRICO PARA EL RESERVORIO CP-01 V= 20 M3
11/30/2011
PARTIDA DESCRIPCION UNIDAD METRADOS

TRAZO INICIAL , NIVELACION Y REPLANTEO PARA CERC PERIMETRICO (CON EQUIPO) M 48.80
REPLANTEO FINAL DE LA OBRA PARA CERCO PERIMETRICO(CON EQUIPO) M 48.80
EXCAV. TERR ROCOSO PULSO HASTA 1.00m prof. M3 26.10
EXCAV. TERR ROCOSO A PULSO HASTA 1.50m prof. M3 8.50
REFINE , NIVELACION, Y COMPACTACION EN TERRENO NORMAL M2 16.00
RELLENO CON MATERIAL PROPIO M3 2.00
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 10 KM CON MAQ M3 32.60
CONCRETO 1:10 C.H + 30 P.G < Max 4 " > PARA CIMIENTO CORRIDO CP-V M3 16.00
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 24.00
CONCRETO 1 : 8 C.H + 25 % PM < 3 " > PARA SOBRECIMIENTO CP-V M3 6.20
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO CORRIDO T / CARA VISTA M2 73.50
CONCRETO FC 210 KGR / CM2 PARA COLUMNAS CP V M3 5.50
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 63.10
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,278.00
CONCRETO FC210 K GR / CM2 PARA VIGA CP V M3 3.60
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA TIPO CARA VISTA M2 40.00
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 281.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 176.60
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 130.50
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 624.00
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 261.00
PUERTA CON MARCO DE TUBO FIERRO GALVANIZADO 2 " Y 4 " Y PKLANCHA LAC 3/ 16 M2 13.50
PICAPORTES UNIDAD 3.00
CERROJO O PESTILLOS UNIDAD 1.00
PICAPORTES DE FOGDO + ALDABA UNIDAD 1.00
CANDADO QUE INCLUYE ALDAVAS UNIDAD 1.00
CERRADURA PARA EXTERIOR C/ LLAVE INTERY EXTERIOR DE 2 GOLPES UNIDAD 1.00
PINTADO DE MURO EXTERIOR CON PINTURA LATEX ACRILICO M2 243.50
PINTADO DE PUERTA METALICAS LAC ( 2 MANOS ANTICORROSIVA + 2 ESMALTES ) M2 27.00
PROVISION Y COLOCADO DE ALAMBRE PUAS EN PUERTA M 31.50
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 03 V= 150 M


11/30/2011
PARTIDA DESCRIPCION UNIDAD METRADOS

TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 41.69


REPLANTEO FINAL DE LA OBRA PARA CERC PERIMETRICO CON EQUIPO M 41.69
CERCO DE MALLA HDP de 1 m altura para limite de Seguridad de obra -SEDAPAL M 50.00
Demolicion de muro ladrillo con refuerzo estructural - cerco M 19.00
EXCAV. TERR ROCOSO C/ COMPRESORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 16.76
REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 16.76
ELIMINACION DE DESMONTE PROVENIENTO DE DEMOLICION DE ESTRUCTURAS CON CARGADOR Y VOLQ M3 7.40
RELLENO CON MATERIAL PROPIO M3 2.10
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 14.66
CONCRETO 1:10 + 30 % p.g. PARA CIMIENTO CORRIDO Cemento P-I M3 16.72
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 25.10
CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P-I M3 4.70
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 62.60
CONCRETO FC 210 KGR / CM2 PARA COLUMNAS Cemento P-I M3 7.10
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 56.50
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 2,008.70
CONCRETO FC210 KG / CM2 PARA VIGA Cemento P-I M3 3.50
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO CARA VISTA M2 37.60
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 156.70
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 156.00
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 585.00
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 312.00
PINTADO DE MURO EXTERIOR CON TEXNOMATE O SUPERMATE SIMILAR M2 209.00
PINTADO DE PUERTAS METALICAS LAC (2 manos anticorrosiva + 2 esmalte) M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 3.75
PRUEBA DE CALIDAD DE CONCRETO PRUEBA A LA COMPRESION UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 04 V= 100 M


12/1/2011
PARTIDA DESCRIPCION UNIDAD METRADOS
TRAZO y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 40.50
REPLANTEO FINAL DE LA OBRA PARA CERC PERIMETRICO CON EQUIPO M 40.50
CERCO DE MALLA HDP DE 1 m ALTURA PARA LIMITE DE SEGURIDAD DE OBRA - SEDAPAL M 50.00
DEMOLICION DE MURO DE LADRILLO CON REFUERZO ESTRUCTURAL-CERCO M 18.00
EXCAV. TERR ROCOSO C/COMPRESORA HASTA 1.00 m PROF. SIN EMPLEAR EXPLOSIVO M3 16.20
REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 16.20
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R=20 KM. CON MAQUINARIA M3 14.20
RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.00
ELIMINACION DE DESMONTE PROVENINTE DE LA DEMOLICION ESTRUCTURAS CON CARGADOR Y VOLQU M3 7.40
CONCRETO 1:10 + 30 % P.G PARA CIMIENTO CORRIDO CEMENTO P-I M3 16.20
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 24.30
CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P-I M3 4.60
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 60.70
CONCRETO FC 210 KG / CM2 PARA COLUMNAS CEMENTO P-I M3 6.00
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 51.00
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,750.50
CONCRETO FC210 K GR / CM2 PARA VIGA CEMENTO P-I M3 3.30
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO CARA VISTA M2 36.50
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 148.50
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 154.00
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 624.00
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 308.00
PINTADO DE MURO EXTERIOR CON TEKNOMATE O SUPERMATE SIMILAR M2 202.50
PINTADO DE PUERTAS METALICAS LAC 2MANOS ANTICORROSIVA + 2 ESMALTE M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 3.75
PRUEBA DE CALIDAD DE CONCRETO PRUEBA A LA COMPRENSION UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 05 V= 100 M


12/1/2011
PARTIDA DESCRIPCION UNIDAD METRADOS
TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 39.11
REPLANTEO FINAL DE LA OBRA PARA CERC PERIMETRICO CON EQUIPO M 39.11
CERCO DE MALLA HDP DE 1 M ALTURA PARA LIMITE DE SEGURIDAD DE OBRA SEDAPAL M 40.00
DEMOLICION DE MURO DE LADRILLO CON REFUERZO ESTRUTURAL CERCO M 21.60
EXCAV. TERR ROCOSO C/COMPRESORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 16.20
REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 16.20
ELIMINACION DE DESMONTE PROVENIENTO DE DEMOLICION DE ESTRUCTURAS CON CARGADOR Y VOLQ M3 9.40
RELLENO CON MATERIAL PROPIO M3 2.00
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 14.20
CONCRETO 1:10 + 30% P.G. PARA CIMIENTO CORRIDO CEMENTO P-I M3 16.20
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 24.30
CONCRETO 1:8 + 25 % PM PARA SOBRECIMIENTO Cemento P-I M3 4.60
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 60.70
CONCRETO FC 210 KGR / CM2 PARA COLUMNAS Cementp P-I M3 6.00
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 51.00
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,750.50
CONCRETO FC210 KG / CM2 PARA VIGA CEMENTO P-I M3 3.30
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO CARA VISTA M2 36.50
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 148.50
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 154.00
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 624.00
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K. SOGA CON MORTERO 1:3 M2 308.00
PINTADO DE MURO EXTERIOR CON TEKNOMATE O SUPERMATE SIMILAR M2 202.50
PINTADO DE PUERTAS METALICAS LAC 2 MANOS ANTICORROSIVAS+ 2 ESMALTE M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 3.75
PRUEBA DE CALIDAD DE CONCRETO PRUEBA A LA COMPRESION UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 06 V= 100 M


12/1/2011
PARTIDA DESCRIPCION UNIDAD METRADOS
TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 52.43
REPLANTEO FINAL DE LA OBRA PARA CERC PERIMETRICO CON EQUIPO M 52.43
CERCO DE MALLA HDP DE 1 M ALTURA PARA LIMITE DE SEGURIDAD DE OBRA -SEDAPAL M 52.00
DEMOLICION DE MURO DE LADRILLO CON REFUERZO ESTRUCTURAL CERCO M 31.64
EXCAV. TERR ROCOSO C/COMPRENSORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 21.60
REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 21.10
ELIMINACION DE DESMONTE PROVENIENTO DE DEMOLICION DE ESTRUCTURAS CON CARGADOR Y VOLQ M3 14.40
RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.70
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 18.80
CONCRETO 1:10 + 30 %P.G PARA CIMIENTO CORRIDO CEMENTO P-I M3 19.10
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 32.50
CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P-I M3 5.80
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 76.50
CONCRETO FC 210 KGR / CM2 PARA COLUMNAS Cemento P-I M3 10.50
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 112.00
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 3,949.60
CONCRETO FC210 KG / CM2 PARA VIGA CEMENTO P-I M3 4.10
ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO CARA VISTA M2 46.00
ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 358.00
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 268.00
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 164.50
ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 657.00
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K. SOGA CON MORTERO 1:3 M2 329.00
PINTADO DE MURO EXTERIOR CON TEKNOMATE O SUPERMATE SIMILAR M2 279.50
PINTADO DE PUERTAS METALICAS LAC 2 MANOS ANTICORROSIVA+2 ESMALTE M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO PRUEBA A LA COMPRESION UNIDAD 4.00
CERCO PERIMETRICO PARA EL RESERVORIO RAP 01 V= 100 M

PARTIDA DESCRIPCION UNIDAD METRADOS

TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 54.07


REPLANTEO FINAL DE LA OBRA PARA CERCO PERIMETRICO CON EQUIPO M 54.07
EXCAV. TERR ROCOSO C/COMPRENSORA HASTA 1.00m prof./sin emplear explosivo) M3 21.65

V = 0,40 X 1,0 X 54,07 = 21,60 M3

REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 21.65

A = 0,40 X 54,07 = 21,62

RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.70

V = 0,25 X 0,20 X 54,07 = 2,70 M3


V = 0,15 X 0,20 X 54,07 = 1,622 M3 ( ELIMINAR )
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 19.90

TOTAL = 18,266 M3 + 1,62 = 19,89 M3

CONCRETO 1:10 + 30% P.G. PARA CIMIENTO CORRIDO (Cemento P-I) M3 18.50

TRAMO A-B V = 0,40 X 1,00 X 3,99 = 1,596 M3


TRAMO B- C V = 0,40 X 0,80 X 11,50 = 3,68 M3
TRAMO C- D V = 0,40 X 0,80 X 4,79 = 1,433 M3
TRAMO D-E V = 0,40 X 0,90 X 5,83 = 2,10 M3
TRAMO E-F V = 0,40 X 0,90 X 4,79 = 1,724 M3
TRAMO F- G V = 0,40 X 0,90 X 11,50 = 4,14 M3
TRAMO G- H V = 0,40 X 1,00 X 3,99 = 1,596 M3
TRAMO H- A V = 0,40 X 1,00 X 4,99 = 1,996 M3
TOTAL = 18,266 M3
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 32.50

A = 0,30 X 54,07 X 2 = 32,44 M2

CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO (Cemento P-I) M3 6.10

V = 0,15 X 0,75 X 54,07 = 6,083 M3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 81.10

A = 0,75 X 54,07 X 2 = 81,10 M2

CONCRETO FC 210 KG / CM2 PARA COLUMNAS (Cemento P-I) M3 13.10


C-1 C-2
TRAMO A-B 4,20+4,20 8.4 5.50
TRAMO B-C 5,80+4,20+5,00 15 6.00
5,80+ 5.8
TRAMO C-D 4,30+5,00 9.3 5.40
TRAMO D-E 4,3+ 4.3 6.30
TRAMO E-F 6,20+4,20 10.4 6.00
TRAMO F- G 5,40+4,50+4,40 14.30 6.00
6.00 6.00
TRAMO G-H 4,30+4,30 8.60 5.80
TRAMO H-A 4,50+4,50 9.00 4.50

91.1 X 45.50 X
0,25X 0,30 0,55X 0,25 =
6,83M3 6,256 M3 13,086 M3

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 140.00

COLUMNAS C-1 A= 91,10 X 0,80 = 72,88 M2


COLUMNAS C-2 A= 45,50 X 1,30 = 59,15 M2
JUNTAS A= 31X 0,25 =7,75 M2
139,78 M2

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 4,014.00

C-1 C-2
TRAMO A-B 6,20+6,20 12.40 7.10
TRAMO B-C 7,10+6,20+7,00 20.30
7.00 7.00 7.10
TRAMO C-D 7,40+7,00 14.40 7.50
TRAMO D-E 6,30+ 6.30 7.30
TRAMO E-F 7,50+6,10 13.60 7.10
TRAMO F- G 6,80+6,50 13.30 7.00
6,10+7,10 13.20
TRAMO G-H 6,20+6,20 12.40 7.50
TRAMO H-A 6,50+6,50 13.00 6.00

125.90 56.60
COLUMNAS C-1 ESTRIBOS
5/ 8 = 125,90X 4X 1,55 = 780,58 K 3/ 8 = 94 X 1,20 X 0,56 X 7 = 442,18 K
1/ 2 = 125,90X 2 X 0,99 =249,28 K 3/ 8 = 52 X 1,20 X 0,56 X 12 = 419,33 K
COLUMNAS C-2 ESTRIBOS
5/ 8 = 56,60 X 4X 1,55 = 526,38 K 3/ 8 = 94 X 1,25X2X0,56X8 = 1052,80 K
1/ 2 = 56,60 X 6 X 0,99 =336,20 K

ADICIONAL 3/ 8 = 2,25 X 4 X 18 X 0,56 = 90,72 K

TOTAL =780,58 +249,29+526,38+336,20+90,72+442,18+419,33+1052,80 = 3897,48 +3%


4014,40KILOS

CONCRETO FC210 KG / CM2 PARA VIGA (cemento P-I) M3 4.20


VIGA - VC-1
V= 0,25 X 0,20 X 51,62 = 2,581,M3
VIGA - VC-2
V= 0,15 X 0,20 X 51,62 = 1,549 ,M3
4,13 M3

ENCOFRADO( INC. HABITACION DE MADERA )P/VIGA RECTAS Y DINTELES TIPO CARA M2 46.50
VISTA
VIGA - VC-1
V= 0,50 X 51,62 = 25.81,M2
VIGA - VC-2
V= 0,20 X 2 X 51,62 = 20,65 ,M2
46,46 m2

ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 360.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 4,50 X 4 X 2 X 0,56 = 20.16 26.00 26.00
TRAMO B-C 3/ 8 = 11,00 X 4 X 2 X 0,56 = 49.28 56.00 56.00
TRAMO C-D 3/ 8 = 5,50 X 4 X 2 X 0,56 = 26.64 28.00 28.00
TRAMO D-E 3/ 8 = 6,00 X 4 X 2 X 0,56 = 26.88 28.00 28.00
TRAMO E-F 3/ 8 = 5,00 X 4 X 2 X 0,56 = 22.40 24.00 24.00
TRAMO F- G 3/ 8 = 12,60 X 4 X 2 X 0,56 = 56.44 24.00 24.00
TRAMO G-H 3/ 8 = 5,00 X 4 X 2 X 0,56 = 22.4 20.00 20.00
TRAMO H-A 3/ 8 = 5,50 X 4 X 2 X 0,56 = 24.64 28.00 28.00
248,84 KILOS 234 M 234M

V-1 1/ 4 = 234 X 1,00 X 0,25 = 58,50 KGR

V-2 1/ 4 = 234 X 0,72 X 0,25 = 42,12 KGR


100.62
TOTAL= 248,84 +100,62 =349,46+3% =359,94

ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 267.50

SOBRECIMIENTO 81.1
COLUMNAS 140.00
VIGAS 46.50
267.6

MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 166.46
TRAMO A-B 11.100 M2
TRAMO B-C 38.520 M2
TRAMO C-D 14.760 M2
TRAMO D-E 19.700 M2
TRAMO E-F 14.920 M2
TRAMO F- G 40.320 M2
TRAMO G-H 10.860 M2
TRAMO H-A 16.280 M2
166.460 M2

ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 654.00

COLUMNAS C-1 L = 8 X 2,60 X 11 = 228,80 ML


L = 5 X 3,60 X 11 = 198 ML
COLUMNAS C-2 L = 8X 2,60 X 11 = 228,00 ML
654 ML
SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K. SOGA CON MORTERO 1:3 M2 322.00
PUERTA CON MARCO DE TUBO FIERRO GALVANIZADO 2 " Y 4 " Y PKLANCHA LAC 3/ 16 M2 6.00
PICAPORTES UNIDAD 1.00
CERROJOS O PESTILLOS UNIDAD 1.00
PICAPORTES DE FO GDO+ ALDABA UNIDAD 1.00
CANDADO QUE INCLUYE ALDAVAS UNIDAD 1.00
PINTADO DE MURO EXTERIOR CON TEXNOMATE O SUPERMATE (Similar) M2 281.00
PINTADO DE PUERTA METALICAS LAC ( 2 MANOS ANTICORROSIVA + 2 ESMALTES ) M2 12.00
PROVISION Y COLOCADO ALAMBRES PUAS M 14.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 02 V= 100 M

PARTIDA DESCRIPCION UNIDAD METRADOS

TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 52.82

REPLANTEO FINAL DE LA OBRA PARA CERCO PERIMETRICO CON EQUIPO M 52.82

CERCO DE MALLA HDP DE 1 m ALTURA PARA LIMITE DE SEGURIDAD DE OBRA M 50.00

EXCAV. TERR ROCOSO C/COMPRESORA HASTA 1.00m prof. Sin emplear explosivo M3 21.50

V = 0,40 X 1,0 X 52,82 = 21,13 M3

REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 21.10

A = 0,40 X 52,82 = 21,03 M2

RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.70

V = 0,25 X 0,20 X 52,82 = 2,64 M3


V = 0,15 X 0,20 X 52,82 = 1,59 M3 ( ELIMINAR )
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 18.80

TOTAL = 18,266 M3 + 1,62 = 19,89 M3

CONCRETO 1:10 + 30% P.G. PARA CIMIENTO CORRIDO CEMENTO P-I M3 19.10

TRAMO A-B V = 0,40 X 1,00 X 4,58 = 1,83 M3


TRAMO B- C V = 0,40 X 0,80 X 10,14 = 3,24 M3
TRAMO C- D V = 0,40 X 0,80 X 4,86 = 1,56 M3
TRAMO D-E V = 0,40 X 0,90 X 5,65 = 2,03 M3
TRAMO E-F V = 0,40 X 0,90 X 4,86 = 1,75 M3
TRAMO F- G V = 0,40 X 0,90 X 10,79 = 3,88 M3
TRAMO G- H V = 0,40 X 1,00 X 4,44 = 1,78 M3
TRAMO H- A V = 0,40 X 1,00 X 7,50 = 3,00 M3
19,07 M30,
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 32.50

A = 0,30 X 54,07 X 2 = 32,44 M2

CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P-I M3 5.80

V = 0,15 X 0,75 X 50,82 = 5,72 M3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 76.50


A = 0,75 X 50,82 X 2 = 76,23 M2

CONCRETO FC 210 KG / CM2 PARA COLUMNAS Cemento P-I M3 10.50


C-1 C-2
TRAMO A-B 4,50+4,20 8.7 5.00
TRAMO B-C 4,20+5,00+5,20 14.4 5.00

TRAMO C-D 4,30+5,00 9.3 4.30


TRAMO D-E 4,3+ 4.3 5.00
TRAMO E-F 4,70+4,30 9 5.00
TRAMO F- G 5,00+5,00+4,30+ 14.30 5.00

TRAMO G-H 4.50 4.50 4.50


TRAMO H-A 4,10+ 4.10 4.00

68.6 X 37.80 X
0,25X 0,30 0,55X 0,25 =
5,145 M3 5,20 M3 10,34M3

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 112.00

COLUMNAS C-1 A= 68,60 X 0,80 = 54,88 M2


COLUMNAS C-2 A= 37,80 X 1,30 =49,14 M2
JUNTAS A= 31X 0,25 =7,75 M2
111.77

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 3,949.60

C-1 C-2
TRAMO A-B 6.20 6.20 6.50
TRAMO B-C 6,20+7,00+7,50 20.70 6.70
TRAMO C-D 6,20+5,50 11.70 7.50
TRAMO D-E 6,20+ 6.20 6.20
TRAMO E-F 6,2+6,70 12.90 6.70
TRAMO F- G 7,00+7,00+6,20 20.20 6.80
TRAMO G-H 6.50 6.50 7.00
TRAMO H-A 6.00 60.00 6.00

144.40 53.40
COLUMNAS C-1 ESTRIBOS
5/ 8 = 144,40X 4X 1,55 = 895,28 K 3/ 8 = 94 X 1,20 X 0,56 X 7 = 442,18 K
1/ 2 = 144,40X 2 X 0,99 =285,91 K 3/ 8 = 52 X 1,20 X 0,56 X 12 = 419,33 K
COLUMNAS C-2 ESTRIBOS
5/ 8 = 53,40 X 4X 1,55 = 331,08 K 3/ 8 = 94 X 1,25X2X0,56X8 = 1052,80 K
1/ 2 = 53,40 X 6 X 0,99 =317,20 K

ADICIONAL 3/ 8 = 2,25 X 4 X 18 X 0,56 = 90,72 K

TOTAL =895,28 +285,91+331,08+317,20+90,72+442,18+419,33+1052,80 = 3834,50 +3% =


3949,54 KILOS

CONCRETO FC210 KG / CM2 PARA VIGA Cemento P-I M3 4.10


VIGA - VC-1
V= 0,25 X 0,20 X 50,82 = 2,541,M3
VIGA - VC-2
V= 0,15 X 0,20 X 50,82 = 1,525 ,M3
4,066 M3

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA rectas y dinteles T/ CARA VIST M2 46.00

VIGA - VC-1
V= 0,50 X 50,82 = 25.41,M2
VIGA - VC-2
V= 0,20 X 2 X 50,82 = 20,33,M2
45.73

ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 358.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 4,00 X 4 X 2 X 0,56 = 17.92 26.00 26.00
TRAMO B-C 3/ 8 = 12,00 X 4 X 2 X 0,56 = 53.76 56.00 56.00
TRAMO C-D 3/ 8 = 5,50 X 4 X 2 X 0,56 = 24.6 28.00 28.00
TRAMO D-E 3/ 8 = 6,00 X 4 X 2 X 0,56 = 26.88 28.00 28.00
TRAMO E-F 3/ 8 = 5,00 X 4 X 2 X 0,56 = 22.4 24.00 24.00
TRAMO F- G 3/ 8 = 12,60 X 4 X 2 X 0,56 = 56.44 24.00 24.00
TRAMO G-H 3/ 8 = 4,00 X 4 X 2 X 0,56 = 17.92 20.00 20.00
TRAMO H-A 3/ 8 = 6,00 X 4 X 2 X 0,56 = 26.88 28.00 28.00
246.8 234.00 234.00

V-1 1/ 4 = 234 X 1,00 X 0,25 = 58,50 KGR

V-2 1/ 4 = 234 X 0,72 X 0,25 = 42,12 KGR


347,42 +3 % = 357,84
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 268.00

SOBRECIMIENTO 81.1
COLUMNAS 140.00
VIGAS 46.85
267.95

MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 164.50
TRAMO A-B 14.200 M2
TRAMO B-C 33.180 M2
TRAMO C-D 15.420 M2
TRAMO D-E 17.760 M2
TRAMO E-F 15.200 M2
TRAMO F- G 39.600 M2
TRAMO G-H 14.400 M2
TRAMO H-A 14.600 M2
164.360 M2

ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 657.00

COLUMNAS C-1 L = 15 X 2,60 X 11 = 429 ML

COLUMNAS C-2 L = 8X 2,60 X 11 = 228,00 ML


657,00 ML
SOLAQUEADO DE MURO CARA VISTA DE LADRILLOS K. K. SOGA CON MORTERO 1:3 M2 329.00
PUERTA CON MARCO DE TUBO FIERRO GALVANIZADO 2 " Y 4 " Y PLANCHA LAC 1/ 16 M2 6.00
PICAPORTES UNIDAD 1.00
CERROJO O PESTILLOS UNIDAD 1.00
PICAPORTES DE FOGDO + ALDAVA UNIDAD 1.00
CANDADO QUE INCLUYE ALDAVAS UNIDAD 1.00
PINTADO DE MURO EXTERIOR CON PINTURA LATEX ACRILICO M2 279.50
PINTADO DE PUERTA METALICAS LAC ( 2 MANOS ANTICORROSIVA + 2 ESMALTES ) M2 12.00
ALAMBRES PUAS M 14.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO UNIDAD 4.00

CERCO PERIMETRICO PARA CP-01 V= 20 M

PARTIDA DESCRIPCION UNIDAD METRADOS

TRAZO INICIAL , NIVELACION Y REPLANTEO PARA CERC PERIMETRICO CON EQUIPO M 48.80

REPLANTEO FINAL DE LA OBRA PARA CERCO PERIMETRICO CON EQUIPO M 48.80

EXCAV. TERR ROCOS A PULSO HASTA 1.00m prof. M3 26.10

V = 0,40 X 1,0 X 39,95 = 15,98 M3


TRAMO A-B
V = 0,40 X 1,00 X 5,75 = 2,30 M3
TOTAL = 26,03 M3
TRAMO B -C
V = 0,40 X 1,00 X 13,05 = 5,22 M3

TRAMO C-D
V = 0,40 X 1,00 X 6,34 = 2,53 M3

EXCAV. TERR ROCOSO A PULSO HASTA 1.50m prof. M3 8.50


TRAMO A-B
V = 0,40 X 1,3 X 5,75 = 2,99 M3

TRAMO C - D
V = 0,40 X 1,50 X 4,90 = 2,94M3
TOTAL = 8,426 M3
TRAMO D-A
V = 0,4 X 1,50 X 1,61 = 0,966 M3
V = 0,4 X 1,50 X 2,55 = 1,53 M3

REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 16.00

A = 0,40 X 39,95 = 15,98 M2

RELLENO CON MATERIAL PROPIO M3 2.00

V = 0,25 X 0,20 X 39,95 = 1,998 M3


V = 0,15 X 0,20 X 52,82 = 1,59 M3 ( ELIMINAR )
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 10 KM CON MAQ M3 32.60

TOTAL = 16,00 M3 -2,00 = 14,00 M3

CONCRETO 1:10 C.H + 30 P.G < Max 4 " > PARA CIMIENTO CORRIDO CP- V M3 16.00

TRAMO A-B V = 0,40 X 1,00 X 11,50 = 4,60 M3


TRAMO B- C V = 0,40 X 1,00 X 13,05 = 5,22 M3
TRAMO C- D V = 0,40 X 1,00 X 11,24 = 4,50 M3
TRAMO D-A V = 0,40 X 1,00 X 4,16 = 1,66 M3

15.98

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 24.00

A = 0,30 X39,95 X 2 = 23,97 M2

CONCRETO 1 : 8 C.H + 25 % PM < 3 " > PARA SOBRECIMIENTO CP- V M3 6.20

V = 0,15 X 0,75 X 31,06 = 3,494 M3


V = 0,20 X 1,50 X 6,34 = 1,90 M3
V = 0,20 X 1,50 X 2,55 = 0,765 M3
6,159 M3
ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO CORRIDO T / CARA VIST M2 73.50

A = 0,75 X 31,06 X 2 = 46,59 M2


A = 1,50 X 6,34 X 2 = 19,02 M2
A = 1,50 X 2,55 X 2 = 7,65 M2
73,26 M2
CONCRETO FC 210 KGR / CM2 PARA COLUMNAS CP V M3 5.50
C-1
TRAMO A-B 4,50+4,20+4,20+ 12.60
4,20+4,20+4,20 12.60

TRAMO B-C 5,00+4,50+5,00 14.50


5,00+5,00 10.00
TRAMO C-D 4,20+4,20+4,20 12.60
TRAMO D-E 4,20+4,80 9.00
71.30 X 0,25X0,30 = 5,34 M3

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 63.10

COLUMNAS C-1 A= 71,30 X 0,80 = 57,04 M2


A = 0,25 X 6,00 X 4 = 6,00
63,04 M2

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,278.00

C-1
TRAMO A-B 6,00+6,00+6,00+ 18.00
6,00+6,00+6,00 18.00
TRAMO B-C 7,00+6,20+6,50 19.70
6,50+8,50 15.00
TRAMO C-D 7,00+7,50+7,50 22.00
TRAMO D-A 7,50+7,70 15.20

107.90 X

COLUMNAS C-1 ESTRIBOS


5/ 8 = 107,90X 4X 1,55 = 668,98 K 3/ 8 = 28X1,20 X 0,56 X 11 = 206,98 K
1/ 2 = 107,90 X 2 X 0,99 =213,64 K 3/ 8 = 33 X 1,20 X 0,56 X 5 = 110,88 K
882,62 K 317,86 K

1/ 2 = 20 X 4 X 0,99 =79,20 K ( ZONA DE CASETA )

ADICIONAL 3/ 8 = 2,25 X 4 X 8 X 0,56 = 40,32 K

TOTAL = 882,62 +317,86+40,32 = 1240,80 +3% =1278,00 KILOS

CONCRETO FC210 K GR / CM2 PARA VIGA CP V M3 3.60


VIGA - VC-1
V= 0,25 X 0,20 X 44,30 = 2,22,M3
VIGA - VC-2
V= 0,15 X 0,20 X 44,30 = 1,32 ,M3
3,54 M3

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA TIPO CARA VISTA M2 40.00

VIGA - VC-1
V= 0,50 X 44,30 = 22,15,M2
VIGA - VC-2
V= 0,20 X 2 X 44,30 = 17,72,M2
39.87

ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 281.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 11,70 X 4 X 2 X 0,56 = 52.42 26.00 26.00
TRAMO B-C 3/ 8 = 15,00 X 4 X 2 X 0,56 = 67.20 56.00 56.00
TRAMO C-D 3/ 8 = 8,50 X 4 X 2 X 0,56 = 38.08 28.00 28.00
TRAMO D-A 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 28.00 28.00
213,70 KILOS 138,00M 138,M
ESTRIBOS
V-1 1/ 4 = 138 X 1,00 X 0,25 = 34,50 KGR
V-2 1/ 4 = 138 X 0,72 X 0,25 = 24,84 KGR
273,04 + 3% = 281,23 K

ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 176.60

SOBRECIMIENTO 73,50 M2
COLUMNAS 63,10 M2
VIGAS 40,00M2
176,60 M2
MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 130.50
TRAMO A-B 37.000
TRAMO B-C 45.120
TRAMO C-D 20.720
TRAMO D-A 27.610
130.450

ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 624.00

COLUMNAS C-1 L = 15 X 2,60 X 16 =624 429 ML

SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 261.00


PUERTA CON MARCO DE TUBO FIERRO GALVANIZADO 2 " Y 4 " Y PKLANCHA LAC 3/ 16 M2 13.50
PICAPORTES UNIDAD 3.00
CERROJO O PESTILLOS UNIDAD 1.00
PICAPORTES DE FOGDO + ALDAVAS UNIDAD 1.00
CANDADO QUE INCLUYE ALDAVAS UNIDAD 1.00
CERRADURA PARA EXTERIOR C/ LLAVE INTERY EXTERIOR DE 2 GOLPES UNIDAD 1.00
PINTADO DE MURO EXTERIOR CON PINTURA LATEX ACRILICO M2 243.50
PINTADO DE PUERTA METALICAS LAC ( 2 MANOS ANTICORROSIVA + 2 ESMALTES ) M2 27.00
ALAMBRES PUAS ( ENCIMADO DE PUERTA ) M 31.50
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 03 V= 150 M

PARTIDA DESCRIPCION UNIDAD METRADOS

TRAZO y replanteo INICIAL PARA CERCO PERIMETRICO M 41.69


REPLANTEO FINAL DE LA OBRA PARA CERCO PERIMETRICO CON EQUIPO M 41.69
CERCO DE MALLA HDP DE 1 M PARA LIMITE DE SEGURIDAD DE OBRA SEDAPAL M 50.00
DEMOLICION DE MURO DE LADRILLO - CON REFUERZO ESTRUCTURAL - CERCO M 19.00
EXCAV. TERR ROCOSO C/COMPRESORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 16.76

V = 0,40 X 1,0 X 41,89 = 16,76 M3

REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 16.76

A = 0,40 X 41,89 =16,76 M2

RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.10

V = 0,25 X 0,20 X 41,79 = 2,10 M3


V = 0,15 X 0,20 X 52,82 = 1,59 M3 ( ELIMINAR )
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 14.66

TOTAL = 18,266 M3 + 1,62 = 19,89 M3

ELIMINACION DE DESMONTE PROVENIENTE DEMOLICION ESTRCTURAS CON CARGADOR Y M3 7.40


CONCRETO 1:10 + 30 %. P.G. PARA CIMIENTO CORRIDO CEMENTO P-I M3 16.72

V= 0,40 X 1,00 X 41,79 = 16,72

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 25.10

A = 0,30 X 41,79 X 2 = 25,07 M2

CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P-I M3 4.70

V = 0,15 X 0,75 X 41,69 = 4,69 M3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 62.60

A = 0,75 X 41,69 X 2 = 62,54 M2

CONCRETO FC 210 KGR / CM2 PARA COLUMNAS CIMIENTO P-I M3 7.10

COLUMNAS C-1 15X 4,30X 0,25 X 0,30 = 4,84 M3

COLUMNA C-2 3X4,30 X 0,55 X 0,25 = 1,77 M3

COLUMNA C-3 1X 4,30 X 0,45 X 0,25 = 0,48 M3

7,09 M3

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 56.50

COLUMNAS C-1 A= 0,60 X 4,30 X 15 = 38,70 M2


COLUMNAS C-2 A= 1,10 X 4,30 X 3 = 14,19 M2
JUNTAS A= 0,40 X 4,30 X 2 =3,44 M2
56,33 M2

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 2,008.70

COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 15 = 576,60 K
1/ 2 = 4 X 6,20 X 0,99 X 15 = 368,28 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 15 = 362,88 K

COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 3 = 115,32 K
1/ 2 = 4 X 6,20 X 0,99 X 3 = 73,66 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K

COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K

ADICIONAL 3/ 8 = 2,25 X 4 X 18 X 0,56 = 90,72 K

1950,19 +3% = 2008,70

CONCRETO FC210 K GR / CM2 PARA VIGA Cemento P-I M3 3.50


VIGA - VC-1
V= 0,25 X 0,20 X 41,69 = 2,09,M3
VIGA - VC-2
V= 0,15 X 0,20 X 41,69 = 1,25 M3
3.34

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS DINTELES TIPO CAR M2 37.60

VIGA - VC-1
V= 0,50 X 41,69 = 20,85,M2
VIGA - VC-2
V= 0,20 X 2 X 41,69 = 16,68,M2
37.52

ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00

V-1 1/ 4 = 297 X 1,00 X 0,25 = 74,25 KGR

V-2 1/ 4 = 297 X 0,72 X 0,25 = 53,46 KGR


333,79 + 3% = 343,80
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 156.70

SOBRECIMIENTO 62.6
COLUMNAS 56.50
VIGAS 37.60
156.7

MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 156.00

A = 4,30 X 36,19 = 155,17 M2

ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 585.00

COLUMNAS C-1 L = 15 X 2,60 X 15 = 585ML

SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 312.00


PINTADO DE MURO EXTERIOR CON TEXNOMATE O SUPERMATE SIMILAR M2 209.00
PINTADO DE PUERTAS METALICAS LAC 2 MANOS ANTICORROSIVA + 2 ESMALTE M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 3.75
PRUEBA DE CALIDAD DE CONCRETO ALA COMPRESION UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 04 V= 100 M 2/28/2015

PARTIDA DESCRIPCION UNIDAD METRADOS


TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 40.50
REPLANTEO FINAL DE LA OBRA PARA CERC PERIMETRICO CON EQUIPO M 40.50
CERCO DE MALLA HDP DE 1 m PARA LIMITE DE SEGURIDAD DE OBRA SEDAPAL M 50.00
DEMOLICION DE MURO DE LADRILLO CON REFUERZO ESTRUCTURAL CERCO M 18.00
EXCAV. TERR ROCOSO C COMPRESORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 16.20

V = 0,40 X 1,0 X 40,50 = 16,20 M3

REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 16.20

A = 0,40 X 40,50 = 16,20 M2

RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.00

V = 0,25 X 0,20 X 40,50 = 2,03 M3

ELIMINACION DE DESMONTE EN TERRENO ROCOSO R = 20 KM CON MAQ M3 14.20

TOTAL = 16,20 - 2,03 = 14,17 M3

CONCRETO 1:10 + 30 % P.G PARA CIMIENTO CORRIDO CEMENTO P-I M3 16.20

V= 0,40 X 1,00 X 40,50 = 16,20 m3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 24.30

A = 0,30 X 40,50 X 2 = 24,30 M2

CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P- I M3 4.60

V = 0,15 X 0,75 X 40,50 = 4,56 M3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 60.70

A = 0,75 X 40,50 X 2 = 60,75 M2

CONCRETO FC 210 KG / CM2 PARA COLUMNAS CEMENTO P-I M3 6.00

COLUMNAS C-1 14X 4,00X 0,25 X 0,30 = 4,20 M3

COLUMNA C-2 2X4,00 X 0,55 X 0,25 = 1,10 M3

COLUMNA C-3 1X 4,00 X 0,45 X 0,25 = 0,45 M3


5.75

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 51.00

COLUMNAS C-1 A= 0,60 X 4,00 X 14 = 33,60 M2


COLUMNAS C-2 A= 1,10 X 4,00 X 2 = 14,19 M2
c-3 A= 0,80 X 4,00 X 1 = 3,20 M2
50,99 m2

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,750.50

COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 14 = 538,16 K
1/ 2 = 4 X 6,20 X 0,99 X 14 = 343,73 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 14 = 338,69 K

COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 2 = 76,88 K
1/ 2 = 4 X 6,20 X 0,99 X 2 = 49,10 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 2X 2 = 100,80 K

COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K

ADICIONAL 3/ 8 = 2,25 X 4 X 8 X 0,56 = 40,32 k

1699,21 +3% = 1750,19 k

CONCRETO FC210 KG / CM2 PARA VIGA CEMENTO P-I M3 3.30


VIGA - VC-1
V= 0,25 X 0,20 X 40,50 = 2,025 m3
VIGA - VC-2
V= 0,15 X 0,20 X 40,50 = 1,22 M3
3.24

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO C M2 36.50

VIGA - VC-1
V= 0,50 X 40,50 = 20,25,M2
VIGA - VC-2
V= 0,20 X 2 X 40,50 = 16,20,M2
36.45

ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00

V-1 1/ 4 = 297 X 1,00 X 0,25 = 74,25 KGR

V-2 1/ 4 = 297 X 0,72 X 0,25 = 53,46 KGR


333,79 + 3% = 343,80
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 148.50

SOBRECIMIENTO 60.7
COLUMNAS 51.00
VIGAS 36.50
148.2

MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 154.00

A = 4,30 X 35,70 = 153,51 M2

ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 624.00

COLUMNAS C-1 L = 15 X 2,60 X 16 = 624ML

SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 308.00


PINTADO DE MURO EXTERIOR CON TEKNOMATE O SUPERMATE SIMILAR M2 202.50
PINTADO DE puertas metalicas lac 2 manos anticorrosiva + 2esmalte M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 3.75
PRUEBA DE CALIDAD DE CONCRETO PRUEBA A LA COMPRESION UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 05 V= 100 M 2/28/2015

PARTIDA DESCRIPCION UNIDAD METRADOS


TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 39.11
REPLANTEO FINAL DE LA OBRA PARA CERC PERIMETRICO CON EQUIPO M 39.11
CERCO DE MALLA HDP DE 1 m PARA LIMITE DE SEGURIDAD DE OBRA SEDAPAL M 40.00
DEMOLICION DE MURO DE LADRILLO CON REFUERZO ESTRUCTURAL CERCO M 21.60
EXCAV. TERR ROCOSO C COMPRESORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 16.20

V = 0,40 X 1,0 X 40,50 = 16,20 M3

REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 16.20

A = 0,40 X 40,50 = 16,20 M2

RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.00

V = 0,25 X 0,20 X 40,50 = 2,03 M3

ELIMINACION DE DESMONTE PROV. DEMOLICION ESTRUCTURA CON CARGADOR Y VOLQUET M3 9.40


TOTAL = 16,20 - 2,03 = 14,17 M3

CONCRETO 1:10 + 30 % P.G PARA CIMIENTO CORRIDO CEMENTO P-I M3 16.20

V= 0,40 X 1,00 X 40,50 = 16,20 m3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 24.30

A = 0,30 X 40,50 X 2 = 24,30 M2

CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P- I M3 4.60

V = 0,15 X 0,75 X 40,50 = 4,56 M3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 60.70

A = 0,75 X 40,50 X 2 = 60,75 M2

CONCRETO FC 210 KG / CM2 PARA COLUMNAS CEMENTO P-I M3 6.00

COLUMNAS C-1 14X 4,00X 0,25 X 0,30 = 4,20 M3

COLUMNA C-2 2X4,00 X 0,55 X 0,25 = 1,10 M3

COLUMNA C-3 1X 4,00 X 0,45 X 0,25 = 0,45 M3

5.75

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 51.00

COLUMNAS C-1 A= 0,60 X 4,00 X 14 = 33,60 M2


COLUMNAS C-2 A= 1,10 X 4,00 X 2 = 14,19 M2
c-3 A= 0,80 X 4,00 X 1 = 3,20 M2
50,99 m2

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 1,750.50

COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 14 = 538,16 K
1/ 2 = 4 X 6,20 X 0,99 X 14 = 343,73 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 14 = 338,69 K

COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 2 = 76,88 K
1/ 2 = 4 X 6,20 X 0,99 X 2 = 49,10 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 2X 2 = 100,80 K

COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K

ADICIONAL 3/ 8 = 2,25 X 4 X 8 X 0,56 = 40,32 k

1699,21 +3% = 1750,19 k

CONCRETO FC210 KG / CM2 PARA VIGA CEMENTO P-I M3 3.30


VIGA - VC-1
V= 0,25 X 0,20 X 40,50 = 2,025 m3
VIGA - VC-2
V= 0,15 X 0,20 X 40,50 = 1,22 M3
3.24

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO C M2 36.50

VIGA - VC-1
V= 0,50 X 40,50 = 20,25,M2
VIGA - VC-2
V= 0,20 X 2 X 40,50 = 16,20,M2
36.45

ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 344.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00

V-1 1/ 4 = 297 X 1,00 X 0,25 = 74,25 KGR

V-2 1/ 4 = 297 X 0,72 X 0,25 = 53,46 KGR


333,79 + 3% = 343,80
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 148.50

SOBRECIMIENTO 60.7
COLUMNAS 51.00
VIGAS 36.50
148.2

MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 154.00

A = 4,30 X 35,70 = 153,51 M2

ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 624.00

COLUMNAS C-1 L = 15 X 2,60 X 16 = 624ML


SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 308.00
PINTADO DE MURO EXTERIOR CON TEKNOMATE O SUPERMATE SIMILAR M2 202.50
PINTADO DE puertas metalicas lac 2 manos anticorrosiva + 2esmalte M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 3.75
PRUEBA DE CALIDAD DE CONCRETO PRUEBA A LA COMPRESION UNIDAD 4.00

CERCO PERIMETRICO PARA EL RESERVORIO RAP 06 V= 100 M 2/28/2015

PARTIDA DESCRIPCION UNIDAD METRADOS


TRAZO Y REPLANTEO INICIAL PARA CERC PERIMETRICO CON EQUIPO M 52.43
REPLANTEO FINAL DE LA OBRA PARA CERC PERIMETRICO CON EQUIPO M 52.43
CERCO DE MALLA HDP DE 1 m PARA LIMITE DE SEGURIDAD DE OBRA SEDAPAL M 52.00
DEMOLICION DE MURO DE LADRILLO CON REFUERZO ESTRUCTURAL CERCO M 31.64
EXCAV. TERR ROCOSO C COMPRESORA HASTA 1.00m prof. SIN EMPLEAR EXPLOSIVO M3 21.60

V = 0,40 X 1,0 X 40,50 = 16,20 M3

REFINE , NIVELACION, Y COMPACTACION EN TERRENO ROCOSO M2 21.10

A = 0,40 X 40,50 = 16,20 M2

ELIMINACION DE DESMONTE EN TERRENO ROCOSO R=20 KM con maquinaria m3 18.80

RELLENO COMPACTADO CON MATERIAL PROPIO M3 2.70

V = 0,25 X 0,20 X 40,50 = 2,03 M3

ELIMINACION DE DESMONTE PROV. DEMOLICION ESTRUCTURA CON CARGADOR Y VOLQUET M3 14.40

TOTAL = 16,20 - 2,03 = 14,17 M3

CONCRETO 1:10 + 30 % P.G PARA CIMIENTO CORRIDO CEMENTO P-I M3 19.10

V= 0,40 X 1,00 X 40,50 = 16,20 m3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA CIMIENTO CORRIDO M2 32.50

A = 0,30 X 40,50 X 2 = 24,30 M2

CONCRETO 1 : 8 + 25 % PM PARA SOBRECIMIENTO Cemento P- I M3 5.80

V = 0,15 X 0,75 X 40,50 = 4,56 M3

ENCOFRADO ( INCL. HABILIT. DE MADERA ) PARA SOBRE CIMIENTO M2 76.50

A = 0,75 X 40,50 X 2 = 60,75 M2

CONCRETO FC 210 KG / CM2 PARA COLUMNAS CEMENTO P-I M3 10.50

COLUMNAS C-1 14X 4,00X 0,25 X 0,30 = 4,20 M3


COLUMNA C-2 2X4,00 X 0,55 X 0,25 = 1,10 M3

COLUMNA C-3 1X 4,00 X 0,45 X 0,25 = 0,45 M3

5.75

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA COLUMNAS T/ CARAVISTA M2 112.00

COLUMNAS C-1 A= 0,60 X 4,00 X 14 = 33,60 M2


COLUMNAS C-2 A= 1,10 X 4,00 X 2 = 14,19 M2
c-3 A= 0,80 X 4,00 X 1 = 3,20 M2
50,99 m2

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS ( COSTO PROMEDIO INCL. DESPERD ) Kgr 3,949.60

COLUMNA C-1
5/ 8 = 4 X 6,20 X 1,55 X 14 = 538,16 K
1/ 2 = 4 X 6,20 X 0,99 X 14 = 343,73 K
ESTRIBOS
3/ 8 = 1,20 X 36X 0,56X 14 = 338,69 K

COLUMNA C-2
5/ 8 = 4 X 6,20 X 1,55 X 2 = 76,88 K
1/ 2 = 4 X 6,20 X 0,99 X 2 = 49,10 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 2X 2 = 100,80 K

COLUMNA C-3
5/ 8 = 5 X 6,20 X 1,55 X 1 = 48,05 K
1/ 2 = 2 X 6,20 X 0,99 X 1 = 12,28 K
ESTRIBOS
3/ 8 = 1,25 X 36X 0,56X 3X 2 = 151,20 K

ADICIONAL 3/ 8 = 2,25 X 4 X 8 X 0,56 = 40,32 k

1699,21 +3% = 1750,19 k

CONCRETO FC210 KG / CM2 PARA VIGA CEMENTO P-I M3 4.10


VIGA - VC-1
V= 0,25 X 0,20 X 40,50 = 2,025 m3
VIGA - VC-2
V= 0,15 X 0,20 X 40,50 = 1,22 M3
3.24

ENCOFRADO ( INCLUYE HABITACION DE MADERA ) PARA VIGA RECTAS Y DINTELES TIPO C M2 46.00

VIGA - VC-1
V= 0,50 X 40,50 = 20,25,M2
VIGA - VC-2
V= 0,20 X 2 X 40,50 = 16,20,M2
36.45

ACERO ESTRUCTURAL TRABAJADO PARA VIGA ( COSTO PROMEDIO INCL. DESPERD ) Kgr 358.00
V-1 V-2
1.00 0.72
TRAMO A-B 3/ 8 = 2,00 X 4 X 2 X 0,56 = 8.96 229 229
TRAMO B-C 3/ 8 = 12,50 X 4 X 2 X 0,56 = 56.00 54 54.0
TRAMO C-D 3/ 8 = 17,00 X 4 X 2 X 0,56 = 76,16
76.16 14 14
TRAMO D-E 3/ 8 = 8,00 X 4 X 2 X 0,56 = 35.84
TRAMO E-F 3/ 8 = 6,50 X 4 X 2 X 0,56 = 29.12
206,08 KILOS 297.00 297.00

V-1 1/ 4 = 297 X 1,00 X 0,25 = 74,25 KGR

V-2 1/ 4 = 297 X 0,72 X 0,25 = 53,46 KGR


333,79 + 3% = 343,80
ADITIVO DESMOLDEADOR PARA ENCOFRADO TIPO CARA VISTA M2 268.00

SOBRECIMIENTO 60.7
COLUMNAS 51.00
VIGAS 36.50
148.2

MUROS DE LADRILLOS K. K DE ARCILLA DE SOGA CARA VISTA CON MORTER 1 : 4 X 1.5 cm M2 164.50

A = 4,30 X 35,70 = 153,51 M2

ALAMBRE NEGRO N 8 PARA CONFINAMIENTO DE MUROS ( INCL DESPERDICIOS ) M 657.00

COLUMNAS C-1 L = 15 X 2,60 X 16 = 624ML

SOLAQUEO DE MURO CARA VISTA DE LADRILLOS K. K.CON MORTERO 1:3 M2 329.00


PINTADO DE MURO EXTERIOR CON TEKNOMATE O SUPERMATE SIMILAR M2 279.50
PINTADO DE puertas metalicas lac 2 manos anticorrosiva + 2esmalte M2 12.00
PROVISION Y COLOCADO DE TECNOPORT DE 1 " M2 5.00
PRUEBA DE CALIDAD DE CONCRETO PRUEBA A LA COMPRESION UNIDAD 4.00
AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO PARA NUEVAS HABILITACIONES EN EL VALLE AM

OBRAS CIVILES

CONSTRUCCION DE CISTERNA CP-01 V = 20 M3 - VALLE AMAUTA 3

CERCO PERIMETRICO PARA EL RESERVORIO RAP 01 V= 100 M


CERCO PERIMETRICO PARA EL RESERVORIO RAP 02 V= 100 M
CERCO PERIMETRICO PARA CISTERNA CP-01 DE V= 20 M
CERCO PERIMETRICO PARA EL RESERVORIO RAP 03 V= 150 M
CERCO PERIMETRICO PARA EL RESERVORIO RAP 04 V= 100 M
CERCO PERIMETRICO PARA EL RESERVORIO RAP 05 V= 100 M
CERCO PERIMETRICO PARA EL RESERVORIO RAP 06 V= 100 M
TACIONES EN EL VALLE AMAUTA -3