by CONSTRUCTION X

Feb '18 Mar '18


TITLE % DURATION START DATE END DATE OWNER
4 8 12 16 20 24 28 4 8 12 16 20 24 28

0 40 days
CONST RUCT ION
Feb 5 - M ar 31 keiths

Sit e Est ablishment & Preparat io ns


0

Storage Setup 0

Plumbing of shaft 0

False Car / Scaffolding Installation 0

Comply with other Special Site Requirements 0

Mechanical Inst allat io n


0

Guard Rail Brackets installation


0

Car Frame installation


0

Wire Ropes installation


0

Motor Room Equipment installation


0

Door frames boxes installation


0

Car Superstructure installation


0

Car Door Operator installation completed


0

Pit Equipment installation


0

Elect rical Inst allat io n


0

Motor Room Wiring 0

Lift Shaft Wiring 0

Well Switch Gear 0

Car wiring flexes installation 0

Co mmissio ning, T est ing & Final Inspect io ns


0

Commissioning of Equipment 0

Snags/Modifications requested/NCR rectification & 0


close outs

Final Cleaning & Painting 0

Final inspection and handover to client 0

Operat io n, Maint enance and Cert if icat io n


0
Package
Obtain manuals of equipments used in the project 0

Drafting of As-built drawings and send to the 0


Document Controller

Assembly of Operation & Maintenance Manual & 0


transmit to the Client