Simulation services
HIL simulation
BoHleneck analysis
Plant op+misa+on
Throughput calcula+on
Material ow calcula+on
Increase of produc+vity
Material flow simulation
Virtual reality
2
So9ware op+misa+on
Operator training Time op+misa+on
Cost reduc+on HIL test enviroment
Hydraulics simulation
Hydraulics calcula+on
Process analysis
Energy balance
Fault analysis
Control
Customer presenta+on
Stereoscopy 3D visualisa+on
Collision analysis
3
Plant Simulation
HIL simulation
Virtual test environment for effective
software development and commissioning
The real controller with the programmed automation software is linked to the
simulation computer via the dedicated field bus interface following the Hardware-
In-The-Loop (HIL) approach. The outputs from the PLC are read out and input
into the simulation model. Depending on the signals, the model performs virtual
actions, such as e.g. the switching of a solenoid valve, that can lead to a cylinder
being extended. The movement is displayed in the 3D model and resulting signal
changes, such as the tripping of a limit switch (here: cylinder is extended), are
written back to the controller by the model (PLC inputs). The programmer is
therefore able to operate and test the machine in real-time even before com-
missioning. Thanks to this innovative virtual commissioning approach, expensive
collisions can be recognised and prevented in good time, and numerous problems
and time-consuming work on the customers site can be avoided. Programming
errors can thus be detected and remedied much faster and more easily.
4
Highly complex production lines
The virtual test environment allows even highly complex systems to be tested in
combination. The communication between host computer, transport systems and
machining centres and the respective programs can be analysed and developed
further using the HIL approach. Benefits are gained when individual systems are
already integrated into the production process and a production standstill has to
be avoided.
The final machine movements generally take place during commissioning in the
customers works. The goal of the programmer here is to avoid collisions and to
fulfil the required function. Due to a lack of time and a shortage of the necessary
tools, machine movements are seldom optimised. A simulation opens up a wide
range of possibilities for optimisation here, particularly for the PLC software.
Machine movements can then be designed so that extreme vibrations from the
system are reduced. This protects the material and the expected service life is
prolonged, and even an increase in material throughput can be achieved in this
way, so that simple modifications to the software alone allow an increase in
productivity.
5
Plant Simulation
Virtual Commissioning
6
Virtual commissioning offers a wide range of benefits that become particularly
apparent in project management and the integrated time management. Internati-
onal teams often work together on a project, and the project manager is ultima-
tely responsible for ensuring that commissioning is smooth and on schedule. In
order to avoid the programmer turning up in the customers works with software
that is not yet finished, testing in advance as part of a virtual commissioning is
absolutely essential. This approach is indispensable today, as the continuous
increase in software complexity means that you can no longer see from the
outside whether or not a program is complete and fault-free.
7
Plant Simulation
Not only new developments present a company with major challenges; the re- Incorporation of original design data
vamping, expansion or optimisation of existing machines and plants is becoming
The integration of the 3D CAD data allows the
more and more commonplace. Plant simulation is a very powerful tool especially
whole production process to be analysed very
here. No-one wants the production processes standing still for longer than ab-
precisely. As a result, design errors or collision
solutely necessary, or wants to worry about the machine no longer being pro-
risks can be recognised and eliminated in good
ductive after the revamping. A high-quality plant simulation allows these risks to
time. Technical processes and safety functions
be minimised in advance.
can be observed in quasi-reality and improved, if
necessary.
8
Virtual HMI
The HIL test environment offers the possibility of linking real control desks to the
simulation system. Functions and links between the control links can therefore be
tested in advance. For organisational reasons, however, it is often not possible to
make the control desks available for the virtual tests.
The solution to this problem is virtual HMI. Thanks to the virtual simulation of
the control desks it is possible to adopt the design and all the functions of the
control desks. This ensures that the machine can be fully tested and realistic
control of the machine is assured.
Particularly in the virtual world, no-one has to be concerned that the machine
could be damaged due to an operator error. This advantage is frequently used by
customers to train their staff in advance before they are allowed to operate the
real machine. The simulation enables special error scenarios to be called up at
the press of a button in order to study important operating routines without risk.
Training directly at the virtual machine is well received by the operators, as they
can safely control the machine and test out all the functions. The operator quickly
gets to know his machine using the virtual model and can thus be gradually pre-
pared for his new duties.
The benefits at a glance
It is also possible to transfer special situations from the real production machine
to the digital twin in order to virtually simulate and analyse fault scenarios that
Remedying of faults in the engineering
data in good time
may be attributable to an error in the programming. The situation can therefore
be analysed without stress and the pressure of time while production continues Error detection and remedying in the PLC
to run in parallel. software
9
Plant Simulation
Process simulation
Physics models in Matlab SIMULINK
10
Linking of HIL real-time simulation and physics simulation
The Simulation department of the SMS group has gone one step
further than the conventional applications of physics models. A
method has been developed by means of which physics models can be
integrated into a real-time simulation. This approach is unique and
offers a large number of benefits. The programmer is thus able not
only to initiate and observe individual movements of the machine,
but can also draw on the calculation results for physical parameters
calculated parallel to the real-time simulation. The programmer can
then see, for example, the material deformation resulting from posi-
tions and speeds and can set his control parameters using the virtual
model.
11
Plant Simulation
Virtual reality
Interactive realistic perception
12
Convincing customers of a product is always a great Further benefits are the savings in cost and time
challenge particularly when the product is still in the achieved through the substitution of expensive and
development phase. Presenting the customer with time-consuming production of prototypes or samples.
something tangible here generally involves consider- The optimum communication with the customer from
able expense and requires special techniques. More the outset helps to avoid errors in interpretation,
and more companies are now following new paths and and hence costs and delays in the later delivery and
taking advantage of the very impressive and varied commissioning. Many companies also make use of this
possibilities offered by virtual reality. Here you enter technique at international trade fairs to strengthen
an interactive virtual environment and gain a realistic their competitiveness.
impression of a product or a whole plant. This enables
the customer to get a very quick but thorough over-
view so that he is able to discuss his wishes with the
developers.
13
Plant Simulation
Material flow simulation is an analysis tool for examining logistics processes in Material flow simulation of a wheel rolling line
14
Boost productivity
Many machine and plant owners are faced with the great challenge of operating
their production facilities with the highest possible productivity. Just-in-time pro-
duction, in particular, is difficult to manage. When quantities vary widely and differ-
ent product types are produced in parallel on one line, plant operation becomes a
real challenge. Thanks to its many years of experience in material flow simulation
for industrial-scale plants, the Simulation department of the SMS group has found
an effective way of precisely describing a plant mathematically in order to analyse
the productivity.
The findings are then assessed together with the customer in order to identify the
most appropriate optimisation steps for him in the plant.
Waiting for
discharge Machining
1 3
PortalRobot 1 PortalRobot 2
travel empty travel loaded travel empty travel loaded
offset travel empty offset travel loaded offset travel empty offset travel loaded
idle idle
36.49% 42.54%
Waiting for
infeed
2 4
4 2
5 1
15
SE-354E Published on 06.10.2016 Circulation 500 Printed in Germany KD
The information provided in this brochure contains a general description of the performance characteristics of the products concerned. The actual products may not always have these
characteristics as described and, in particular, these may change as a result of further developments of the products. The provision of this information is not intended to have and will not
have legal effect. An obligation to deliver products having particular characteristics shall only exist if expressly agreed in the terms of the contract.