Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019

WBS Name Duration Start Finish Predecessors Successors


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 Engineering Project Design Process 356 days 1/2/18 8:00 AM 5/14/19 5:00 PM
2 Draft Contract Work Authorization Documents 10 days 1/2/18 8:00 AM 1/15/18 5:00 PM 3
3 Submit Contract Work Authorization Documents 0 days 1/15/18 5:00 PM 1/15/18 5:00 PM 2 4 1/15
4 Notice to Proceed 10 days 1/16/18 8:00 AM 1/29/18 5:00 PM 3 6;10;59
5 1.0 Preliminary Engineering 20 days 1/30/18 8:00 AM 2/26/18 5:00 PM
6 1.1 Document Collection 5 days 1/30/18 8:00 AM 2/5/18 5:00 PM 4 7
7 1.2 Site Walk-Down and Drawing Verification 5 days 2/6/18 8:00 AM 2/12/18 5:00 PM 6 8
8 1.3 Document Review 5 days 2/13/18 8:00 AM 2/19/18 5:00 PM 7 9
9 1.4 Preliminary Engineering Investigation 5 days 2/20/18 8:00 AM 2/26/18 5:00 PM 8
10 1.5 Establish Design Criteria 10 days 1/30/18 8:00 AM 2/12/18 5:00 PM 4 11
11 1.7 PacifiCorp Review of Preliminary Engineering 5 days 2/13/18 8:00 AM 2/19/18 5:00 PM 10 12
12 1.8 Project Discussions 5 days 2/20/18 8:00 AM 2/26/18 5:00 PM 11 14;15
13 2.0 Procurement Engineering 101 days 2/27/18 8:00 AM 7/17/18 5:00 PM
14 2.1 Prepare Data Sheets 10 days 2/27/18 8:00 AM 3/12/18 5:00 PM 12 15
15 2.2 Procurement Specification 5 days 3/13/18 8:00 AM 3/19/18 5:00 PM 12;14 16
16 2.3 Review Procurement Documentation 5 days 3/20/18 8:00 AM 3/26/18 5:00 PM 15 17
17 2.4 Finalize Procurement Documents 5 days 3/27/18 8:00 AM 4/2/18 5:00 PM 16 22;23
18 2.5 Prepare Construction Specifications 5 days 6/27/18 8:00 AM 7/3/18 5:00 PM 34 19
19 2.6 Review Construction Specifications 5 days 7/4/18 8:00 AM 7/10/18 5:00 PM 18 20
20 2.7 Finalize Construction Specifications 5 days 7/11/18 8:00 AM 7/17/18 5:00 PM 19
21 3.0 Procurement 15 days 4/3/18 8:00 AM 4/23/18 5:00 PM
22 3.1 EquipmentProcurement 15 days 4/3/18 8:00 AM 4/23/18 5:00 PM 17 25
23 3.3 Engineering Support of Procurement 15 days 4/3/18 8:00 AM 4/23/18 5:00 PM 17 25
24 4.0 Equipment Manufacture 110 days 4/24/18 8:00 AM 9/24/18 5:00 PM
25 4.1 Equipment Design (By Vendor) 30 days 4/24/18 8:00 AM 6/4/18 5:00 PM 22;23 34;26;27;28
26 4.2 Equipment Submittal Review 20 days 6/5/18 8:00 AM 7/2/18 5:00 PM 25 27;28;29
27 4.3 EquipmentManufacturing 60 days 7/3/18 8:00 AM 9/24/18 5:00 PM 25;26 32
28 4.4 Equipment Manufacturing Support 60 days 7/3/18 8:00 AM 9/24/18 5:00 PM 25;26 32
29 4.5 Vendor Meeting 5 days 7/3/18 8:00 AM 7/9/18 5:00 PM 26 30
30 4.6 Shop Test Procedures 10 days 7/10/18 8:00 AM 7/23/18 5:00 PM 29 31
31 4.7 Test & Startup Procedures 10 days 7/24/18 8:00 AM 8/6/18 5:00 PM 30 32
32 4.8 Factory Acceptance Test (OPTIONAL) 0 days 9/24/18 5:00 PM 9/24/18 5:00 PM 27;28;31 9/24
33 5.0 Detailed Engineering & Design 76 days 6/5/18 8:00 AM 9/18/18 5:00 PM
34 5.1 50% Design Engineering 16 days 6/5/18 8:00 AM 6/26/18 5:00 PM 25 43;35;18
35 5.1 QA/QC Review of 50% Design Package 5 days 6/27/18 8:00 AM 7/3/18 5:00 PM 34 36
36 5.1 50% Design Review 5 days 7/4/18 8:00 AM 7/10/18 5:00 PM 35 37
37 5.2 90% Design Engineering 30 days 7/11/18 8:00 AM 8/21/18 5:00 PM 36 38
38 5.2 QA/QC Review of 90% Design Package 5 days 8/22/18 8:00 AM 8/28/18 5:00 PM 37 39
39 5.2 90% Design Review 5 days 8/29/18 8:00 AM 9/4/18 5:00 PM 38 40
40 5.3 Finalize Detailed Engineering and Design 10 days 9/5/18 8:00 AM 9/18/18 5:00 PM 39 41
41 Finalize Engineering & Design (Milestone) 0 days 9/18/18 5:00 PM 9/18/18 5:00 PM 40 47 9/18
42 6.0 Miscellaneous Engineering 40 days 7/5/18 8:00 AM 8/29/18 5:00 PM
43 6.1 Description of Operations (DOO) 20 days 7/5/18 8:00 AM 8/1/18 5:00 PM 34 44
44 6.2 Test/Startup Plan Development 10 days 8/2/18 8:00 AM 8/15/18 5:00 PM 43 45
45 6.3 Quality Control Inspection Program 10 days 8/16/18 8:00 AM 8/29/18 5:00 PM 44
46 7.0 Post Design 170 days 9/19/18 8:00 AM 5/14/19 5:00 PM
47 7.1 Bill of Materials RFIs 10 days 9/19/18 8:00 AM 10/2/18 5:00 PM 41 48
48 7.2 Construction Kick-Off Meeting 5 days 10/3/18 8:00 AM 10/9/18 5:00 PM 47 49
49 7.3 Pre-Outage Construction Work 5 days 10/10/18 8:00 AM 10/16/18 5:00 PM 48 50;51;52
50 7.4 Installation Construction 90 days 10/17/18 8:00 AM 2/19/19 5:00 PM 49 53;55
51 7.5 Field Engineering Services 90 days 10/17/18 8:00 AM 2/19/19 5:00 PM 49
52 7.6 Construction Inspections 90 days 10/17/18 8:00 AM 2/19/19 5:00 PM 49
53 7.7 Testing Services 15 days 2/20/19 8:00 AM 3/12/19 5:00 PM 50 54
54 7.8 Startup Services 15 days 3/13/19 8:00 AM 4/2/19 5:00 PM 53
55 7.9 Engineering Support of Testing and Startup 20 days 2/20/19 8:00 AM 3/19/19 5:00 PM 50 56
56 7.10 As-Built Record Documentation 15 days 3/20/19 8:00 AM 4/9/19 5:00 PM 55 57
57 7.11 As-Built CAD Drafting 20 days 4/10/19 8:00 AM 5/7/19 5:00 PM 56 58
58 7.12 Administrative Closeout (Milestone) 5 days 5/8/19 8:00 AM 5/14/19 5:00 PM 57

Grace Hydroelectric Plant Relay Replacement - page1


Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019
WBS Name Duration Start Finish Predecessors Successors
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
59 8.0 Project Management 336 days 1/30/18 8:00 AM 5/14/19 5:00 PM 4

Grace Hydroelectric Plant Relay Replacement - page2