ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018

Mode A S O N D J F M A M J J
1 KALI PRAWAN 122 days Fri 9/15/17 Mon 3/5/18

2 PO received 0 days Fri 9/15/17 Fri 9/15/17 9/15

3 Issuance of drawings from 7 days Fri 9/15/17 Sun 9/24/17


OHI
4 Approval of drawings 7 days Mon 9/25/17Tue 10/3/17

5 US fabrication 21 days Wed 10/4/17Wed 11/1/17

6 US inspection 5 days Thu 11/2/17 Wed 11/8/17

7 Freight & handling (US-KL) 14 days Thu 11/9/17 Tue 11/28/17

8 LOCAL FABRICATION - GATES 40 days Wed Tue 1/23/18


11/29/17
9 LOCAL FABRICATION - Main 10 days Wed Tue 2/6/18
Anchors 1/24/18
10 MSIA inspection + training 14 days Wed 2/7/18 Mon 2/26/18

11 Freight & handling (KL - 5 days Tue 2/27/18 Mon 3/5/18


Jakarta)
12 CREST GATE INSTALLATION 37 days Fri 3/9/18 Mon 4/30/18
PROJECT
13 RIVER INSTALLATION (ZONE 19 days Fri 3/9/18 Wed 4/4/18
1;22 M)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: KALI PRAWAN
Summary Manual Summary Rollup Late
Date: Wed 9/6/17
Project Summary Manual Summary Progress

Inactive Task Start-only Manual Progress

Inactive Milestone Finish-only Slack

Page 1
ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018
Mode A S O N D J F M A M J J
14 Rebar ready and pass 0 days Fri 3/9/18 Fri 3/9/18 3/9
inspection
15 Main anchor installation 2 days Sat 3/10/18 Mon 3/12/18

16 Concrete ready and pass 0 days Tue 3/13/18 Tue 3/13/18 3/13
inspection
17 Abutment plate 3 days Wed Fri 3/16/18
installation 3/14/18
18 Spillway pipeline work 2 days Sat 3/17/18 Mon 3/19/18

19 Air piping pressure test 2 days Tue 3/20/18 Wed 3/21/18

20 Grouting work completion 0 days Thu 3/22/18 Thu 3/22/18 3/22


+ acceptance
21 Structure preparation 3 days Fri 3/23/18 Tue 3/27/18
work
22 Unloading of main 1 day Wed Wed 3/28/18
component 3/28/18
23 Intallation of air bladder & 1 day Thu 3/29/18 Thu 3/29/18
air connection
24 installation of gate panels 1 day Fri 3/30/18 Fri 3/30/18

25 Installation of accessories 2 days Sat 3/31/18 Mon 4/2/18

26 Complete torquing of bolts 2 days Tue 4/3/18 Wed 4/4/18


& nuts

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: KALI PRAWAN
Summary Manual Summary Rollup Late
Date: Wed 9/6/17
Project Summary Manual Summary Progress

Inactive Task Start-only Manual Progress

Inactive Milestone Finish-only Slack

Page 2
ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018
Mode A S O N D J F M A M J J
27 CONTROL HOUSE 16 days Mon 4/9/18 Mon 4/30/18
INSTALLATION
28 Structure & security ready 0 days Mon 4/9/18 Mon 4/9/18 4/9
& pass inspection
29 Install Air/instrument 1 day Tue 4/10/18 Tue 4/10/18
panel
30 Pipeline work 5 days Wed 4/11/18Tue 4/17/18
31 Install electrical panel + 5 days Wed Tue 4/24/18
wiring 4/18/18
32 Operation test for air 2 days Wed Thu 4/26/18
system 4/25/18
33 CONTROL ROOM 2 days Fri 4/27/18 Mon 4/30/18
COMMISSIONING
34 CONNECTING PIPELINE 14 days Tue 5/1/18 Fri 5/18/18
INSTALLATION
35 Pipe trenches ready 0 days Tue 5/1/18 Tue 5/1/18 5/1

36 Install complete piping 10 days Wed 5/2/18 Tue 5/15/18


between gates & control
house
37 System pipeline leakage 2 days Wed Thu 5/17/18
testing 5/16/18
38 Connecting pipes - gates & 1 day Fri 5/18/18 Fri 5/18/18
control
39 Gate Operation 1 day Fri 5/18/18 Fri 5/18/18
Commissioning

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: KALI PRAWAN
Summary Manual Summary Rollup Late
Date: Wed 9/6/17
Project Summary Manual Summary Progress

Inactive Task Start-only Manual Progress

Inactive Milestone Finish-only Slack

Page 3
ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018
Mode A S O N D J F M A M J J
40 HANDOVER 1 day Sat 5/19/18 Sat 5/19/18
41 FINAL TRAINING 3 days Sun 5/20/18 Tue 5/22/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: KALI PRAWAN
Summary Manual Summary Rollup Late
Date: Wed 9/6/17
Project Summary Manual Summary Progress

Inactive Task Start-only Manual Progress

Inactive Milestone Finish-only Slack