Introduction
This article is intended to throw light on the differences between pipeline engineering and piping engineering, which are important
organs of any engineering firm active in oil and gas sector. Pipeline and piping engineering do not only sound similar but share a lot
of common activities. Both the engineering department belong to mechanical disciplines and deals primarily with pipes. Various
codes have defined the battery limits for pipeline and piping activities, however, there has always been a contest between Pipeline
and piping disciplines regarding the division of scope in various types of projects. Therefore we have tried to highlight the
differences between both the engineering disciplines for onshore systems and offshore systems separately.
Note:We do not claim that all companies follow the exact division of activities between pipeline and piping disciplines. However, we are trying to
broadly differentiate between the two.
Onshore System
1 Design Codes
2 Scope
http://allaboutpipelines.com/Article/PipelineVsPiping 1/6
3/10/2017 Pipeline vs Piping - all about pipelines
3 Type of pipe
Line pipes as per following code: Assorted pipes as per following code:
API Spec 5L: Specification for Line Pipes ASTMs
BS
API 5L
4 Valves
Valves are procured as per following code: Valves are procured as per following code:
BS
API 6D: Specification for Pipeline and API Standard
Piping Valves
Full bore (FB) and Reduced bore (RB) both types of valves are used
as per respective valve standards. There is no requirement for
Full Bore (FB) Ball Valves are used for smooth pigging.
passage of pigs.
5 Welding
100% by Automatic UT or RT (by using X- 5% to 100% (mostly by using gamma ray source)
Ray)
7 Analyses
- Wall Thickness Analysis - Piping wall thickness calculation [as input to Piping Material
(../ASMEB31/ASMEB31.aspx) Specification (PMS)]
- Elastic Bend Radius Analysis - Piping Stress Analysis (by Caesar II). Following analyses are
- Stability Analysis for Water Bodies/ Marshy performed on CAESAR II
Areas Static Analysis
- Horizontal directional drilling design analysis Dynamic Analysis
(../HDD_Calculation/HDD_Input.aspx) Wind Analysis
- Railroad/ Highway Crossing Analysis Flange Leakage Analysis
- Casing Pipe Analysis for Crossings Seismic Analysis
- Seismic Analysis
8 Installation
9 Special Installations
http://allaboutpipelines.com/Article/PipelineVsPiping 2/6
3/10/2017 Pipeline vs Piping - all about pipelines
10 Special Equipments
11 Survey
14 Hydrostatic testing
http://allaboutpipelines.com/Article/PipelineVsPiping 3/6
3/10/2017 Pipeline vs Piping - all about pipelines
Gauge Plate run of 95% of ID of highest No gauge plate run is done. Generally card-board blasting is done to
thickness of pipes clean the piping.
15 Preservation
16 Communication System
17 Pigging
Offshore System
1 Design Codes
2 Installation
Subsea (in water on seabed or buried in seabed) Deck Platform Piping (similar to plant)
3 Survey (Subsea)
http://allaboutpipelines.com/Article/PipelineVsPiping 4/6
3/10/2017 Pipeline vs Piping - all about pipelines
Geophysical survey/ Bathymetric Survey by using side scan sonar, Not Applicable
sub-bottom profiler and echo-sounder
Met-Ocean data collection
Geo-technical data of the pipeline route
4 Pipes
Lines pipes are utilized as per following specs: Assorted Pipes are utilized as per
following specs:
API Spec 5L : Specification for Line Pipes
DNV-OS-F101 : Submarine Pipeline Systems ASTM Standards
5 Valves
Full bore Valves for smooth passage of intelligent pigs are utilized as per Reduced bore valves are utilised (as there
spec: is no requirement for pigging) as per spec:
API 6D SS : Specification on Subsea Pipeline Valves BS/API standards
6 Analyses
Wall thickness Analysis (../DNV-OS-F101 code check/Input_DNV- Deck piping stress analysis using
OS-F101 Code check.aspx) CAESAR II
On-bottom Stability
Span Analysis
Global Buckling Lateral and Upheaval
Pipeline Expansion Analysis
Riser Design (Span , Stress & Flexibility Analysis)
Riser Clamp Design
Pipeline Crossing Design and Analysis
Installation Analyses such as :- Pipelay Analyses in OFFPIPE,
Shore approach installation design & Analyses, Riser/ Expansion
Spool installation analyses, Hoses lifting & installation analyses
10 Welding
API Std. 1104 : Welding of Pipelines and Related Facilities ASME Sec. IX : Standard for
(http://www.api.org/publications-standards-and- Welding and Brazing Procedures,
statistics/standards/whatsnew/publication-updates/new-pipeline- Welders, Brazers and Welding and
publications/api_std_1104) Brazing Operators
Mostly automatic welding on pipelay barge. Manual welding at fabrication yard.
http://allaboutpipelines.com/Article/PipelineVsPiping 5/6
3/10/2017 Pipeline vs Piping - all about pipelines
12 Special Equipments
13 Installation Equipment
14 Installation Methods
S-lay Method (for shallow water installation) Along with deck structure
J-Lay Method (for deep water installation)
Shore pull/ barge pull near Land Fall Point (LFP)
15 Hydrostatic testing
16 NDT requirements
17 Intelligent Pigging
Home (/Default.aspx) | Write for Us (/Terms and conditions/Write for us.aspx) | About us (/About.aspx) | Contact Us (/Contact.aspx)
Copyright 2017 NT Technologies - Terms of Use (/Terms and conditions/Terms of Use.aspx) - Privacy Policy (/Terms and conditions/Privacy Policy.aspx)
http://allaboutpipelines.com/Article/PipelineVsPiping 6/6