Fortificacin
Perno helicoidal US$/perno 25
Malla biscocho US$/m2 6.4
Shotcrete US$/m3 320
Insumos varios
Petrleo US$/Lt 0.7
Lubricantes US$/Lt 7.3
Energa elctrica US$/Kwh 0.14
Agua industrial US$/m3 1.1
Explosivos
Cordn detonante 5gr/m Mts 0.37
Softron C/U 2.1
Nonel MS/LP avance C/U 3.1
Nonel MS/LP banqueo C/U 3.5
Buster 225 gr 4.1
Fulminante n8 C/U 0.28
Mecha lenta Mts 0.35
Anfo Kg 1.6
Emulsin 1 1/4 x 8" C/U 0.8
VALOR HORARIO JUMBO DE AVANCE DE 1 BRAZO
Valor US$ Vida/Rendto. US$/Hr
Neumticos (US$/cu) 1100 2500 1.76
Energa (US$/Kwh) 0.14 77.8 10.89
Lubricantes (US$/Lt) 7.3 2 14.60
Mantencin Jumbo (US$/equipo) 750000 16000 23.44
Mantencin Perforadora (US$/perf.) 60000 7500 4.00
Agua (US$/Lt) 1.1 20 22.00
Otros (%) 7.67
TOTAL COSTO (US$/Hr) 84.36