This checklist provides 16 items to inspect for column concreting. It ensures proper formwork, reinforcement, placement and compaction of concrete. Key points include: verifying rebar diameter and spacing matches drawings; providing the required concrete cover; installing vibrators, working platforms and chutes; and having the necessary tools like buckets, cylinders and vibrators available on site. The checklist is to be completed, signed and dated by foreman, engineer and senior engineer to confirm all acceptance criteria are met before pouring concrete.
This checklist provides 16 items to inspect for column concreting. It ensures proper formwork, reinforcement, placement and compaction of concrete. Key points include: verifying rebar diameter and spacing matches drawings; providing the required concrete cover; installing vibrators, working platforms and chutes; and having the necessary tools like buckets, cylinders and vibrators available on site. The checklist is to be completed, signed and dated by foreman, engineer and senior engineer to confirm all acceptance criteria are met before pouring concrete.
This checklist provides 16 items to inspect for column concreting. It ensures proper formwork, reinforcement, placement and compaction of concrete. Key points include: verifying rebar diameter and spacing matches drawings; providing the required concrete cover; installing vibrators, working platforms and chutes; and having the necessary tools like buckets, cylinders and vibrators available on site. The checklist is to be completed, signed and dated by foreman, engineer and senior engineer to confirm all acceptance criteria are met before pouring concrete.
Title: Checklist For Column Concreting. Rev. , dated
Building Location Date.
Grade of concrete= M Grade of steel =
Sr. No. Activity Acceptance Criteria Observation
1. Column starter. Shall be free of honey combing, edge being not broken & laitance removed with coarse aggregate top exposed compulsorily. 2. Provision of Rebar (dia. & As per Column schedule As per RCC Drg. qty.), + dowels if No.:_______, any Rev. No.:________ 3. Position of Rebar. As per General drawing. As per RCC Drg. (Lapping, spacing of No.:_______, stirrups with 45 degree Rev. No.:________ legs & master ring). 4. Clear Cover of Rebar. Shall be provided of 55mm & 40mm, for below ground & above ground respectively, with a + 5 mm tolerance. 5. Position of topmost stirrup Shall be placed at 40mm below concreting of column. top. 6. Position of guide/master Shall be provided at Min. 600mm & Max. stirrup above 1000mm.from concrete top. concreting level. 7. Space of needle vibrator, Shall be Min. 70mm gap to suit 60mm insertion, for needle vibrator & Min 50mm gap to suit concreting works. 40mm needle vibrator 8. Binding wire knots & tail Shall not be in Clear cover zone. 9. Shuttering works Soldiers shall be provided after every panel for column length more than 750mm. 1st tie rod shall be at 125mm from bottom. Window shall be provided for column height more than 1400mm. Wedge clips shall be at 150mmc/c. back to back angle Yokes shall be provided at each tie rod level. Raker props shall be supported on firm base. 10. Provision of Empty cement No gap shall be seen, in space between bag below shuttering shuttering panel. panel bottom & slab top. 11. Starter/ Column dimension As per Drawing. Dwg No.__________ (width, length, Rev. No.:________ right angle, line & plumb). 12. Column top concreting As per Drawing. Dwg No.__________ level. Rev. No.:________ 13. Working platform. Shall be supported on H frame with atleast 27 wide platform. 14. Chute (Supda) at window Shall be provided in 45 degrees slope with level & top level. width of minimum 300mm & to be provided in alternate window panel. 15. Tools & materials for 2 G.I. buckets, 1 ltr. Cylinder,500 ml bottle making cement slurry, for & trey for plasticizer & rod for stirring concreting 16. Two nos. electrical Available near columns vibrator, one no. petrol vibrator & spare needle.
Note : All dwg numbers , to be referred should be filled in , before the Checklist is referred to , at
location , for Acceptance Criteria , by the Senior Engineer/Sector Engineer .
FOREMAN: _________________________
JR.ENGR/SITE ENGINEER: _______________
SENIOR/SECTOR ENGINEER: ______________
NB: Checklist, to be completed in all respects and signed with date by all concerned, as designated