Anda di halaman 1dari 5

White Paper

Does Better Scheduling


Drive Execution Success?
Contents Introduction Approach
1 Introduction Both the failure and cost/schedule overruns of In order to prove or disprove the hypothesis, a
major CapEx projects receive a high degree of quantitative analysis approach was adopted. So
1 Hypothesis public and stakeholder scrutiny and publicity. as to establish true quantitative measures for
1 Approach However, rarely is the corresponding planning the analysis, the objective of the modeling was to
quality and project management maturity given quantify two primary attributes of a project:
1 Schedule Quality the same level of detailed investigation. Arguably,
Measurement Quality of the plan
focus is generally given to the result of failure
Quality of the execution
2 Project Execution without also considering the root cause.
Measurement As such, this white paper is the result of a If these two core entities can be successfully
research project that was carried out during the quantified, then any correlations between
3 The Projects Used for
Assessment summer of 2011 to investigate the relationship, if them can be determined easily using standard
any, between project planning quality and project statistical correlation techniques. To describe
3 Results & Discussion execution success. In other words, this project set this in a more qualitative manner: objectively
4 Does Complex Logic out to determine if poor planning results in project determine the quality of the plan and compare
Result in Unnecessary cost and schedule overruns and conversely, against the quality of the execution to determine
Redundancy? does sound planning help ensure on time and any relationship between the two.
successful project completion?
5 Next Steps
Schedule Quality Measurement
5 Conclusions Hypothesis Within the discipline of project management,
The null hypothesis for this research exercise is techniques for quantitative tracking of project
that there is no measurable relationship between execution performance are reasonably well
quality of planning and quality of execution. established. Accepted approaches such as
Instead, the success of execution is driven largely performance tracking, earned value, earned
by the contractors ability to execute to a plan schedule and progress relative to a baseline
irrespective of its realism or achievability. are all commonplace today. However, it has
The alternate hypothesis is that there is indeed only been in recent years that the project
a positive correlation between sound project management community has recognized the
scheduling and successful on-time project value of applying similar analysis to determine
execution completion, or, the better the plan, the the quality of planning. Through the use of metric
higher the chance of on-time or early completion analysis (looking at the likes of quality of logic;
and the lesser quality of the plan, the higher the consistency of detail; appropriate use of activity
chance of a project overrun. constraints; use of leads/lags and the resultant
impact on float), we now have a means of actually
quantifying the quality of a project schedule.

1
The research project was carried out by Acumen with analysis conducted by Jin Ouk Choi and Dr. Dan Patterson. All rights
to the results of this project are the property of Deltek | Acumen.

1
White Paper Does Better Scheduling Drive Execution Success?

Today, there exists several industry standards Using this approach, individual metrics are
for schedule metric analysis such as the DCMA combined into a Schedule Index. This index is a
14-Point Assessment as well as thought leaders combination of the listed metrics weighted based
recommended best practices (see Acumen white on their contribution to the structural integrity of a
paper on metric analysis). sound project plan. The Schedule Index is based
For this exercise, Acumens extensively used on a 1 to 100% scale with 1% being the lowest
and well-established standard schedule check quality and 100% being a perfect quality score.
metric library was used to score the quality of the
project plan. These metrics include: Project Execution Measurement
When selecting a measurement technique
Metric Description
for execution performance, there are several
Open-ended Logic Total number of
choices. Earned value is a sound measure of value
activities that are
missing a predecessor, created relative to effort/time/cost expended but
a successor, or both. for the purpose of this research project, the focus
This number should is around schedule rather than project cost and
not exceed 5%
so a more schedule-centric method is needed.
Logic DensityTM Average number of Traditional performance metric analysis
logic links per activity.
uses simple comparisons such as number
Critical Number of critical of activities that started or finished relative to
activities their corresponding baseline dates. However, a
Soft Constraints Number of activities recent white paper determined that this type of
with soft or one-way measurement is not suitable for CPM schedules.
constraints
The reason being: the measurement is a binary
Hard Constraints Number of activities measure that does not take into account
with hard or two-way how large a slip or acceleration the activity is
constraints
experiencing. A small one-day slip at the start of
High Float Number of activities the project could cause a domino effect along
with total float greater
the critical path causing an erroneous report that
than 2 months. The
number should not all activities on the critical path have slipped. In
exceed 5% short: there is no control of granularity using this
Negative Float Total number of
type of measurement.
activities with total Instead a measurement known as Baseline
finish float less than 0 Compliance has been developed and is the basis
working days
of measurement for this investigation. Baseline
Number of Lags Total number of Compliance is a measure of how many activities
activities that have lags fall within the period that they were expected to
in their predecessors.
This number should fall within. A period is defined by the project
not exceed 5% based on a standard reporting calendar e.g.,
weekly or monthly. In the case of weekly reporting,
Redundancy IndexTM The amount of
redundant or an activity that slips from a planned completion
unnecessary logic in a of Wednesday to Friday is not deemed to be
schedule late. Fall into the following week however, and its

2
ref. D. Patterson, Oct 2009, Project Simplification through Metric Analysis, www.projectacumen.com/resources/
whitepapers

2 deltek.com
White Paper Does Better Scheduling Drive Execution Success?

flagged as a slipped activity. This approach is an are completed. The majority of the schedules
excellent balance between detailed execution were developed by the contractor and then
insight and reasonableness of reporting on multi- subsequently bought into by the owner going into
year projects. Two baseline compliance metrics execution with the schedule as a basis for tracking
Start are available to us: Start and Finish Compliance. performance. Projects were modeled in a variety

Compliance Start Compliance is a measure used to of scheduling tools including Primavera P3, P6
determine whether or not activities are able to and MS Project. All projects carried an agreed
is a measure start on time (i.e. are they getting delayed by their upon baseline schedule which was then used
used to predecessors). Finish Compliance is more a as the basis for calculating Finish Compliance.
reflection of how well activities are being executed The results shown in the following section are
determine and completed. This research project opted for presented anonymously with no reference to their
whether or not Finish Compliance as the core measurement for source.
activities are execution performance.
Results & Discussion
able to start on The Projects Used for Assessment Schedule Index was calculated for each of
time (i.e. are Thirty-five projects ranging in value from the projects along with a corresponding Finish
they getting US$15MM to US$30B were used in the Compliance Index. The results were calculated
assessment. All projects were classed as major as shown in figure 1.
delayed by their CapEx projects each involving both an owner Figure 1 shows a very interesting set of results.
predecessors). and (EPC) contractor. The projects are all recent Firstly, there is a definite positive relationship
(within the past five years) and nearly all of them between schedule quality index and Finish
Finish
Compliance
is more a
reflection
of how well
activities are
being executed
and completed.

Figure 1: Correlation Between Schedule Index & Finish Compliance Index

3
ref. D. Patterson, June 2011, Baseline Compliance Analysis, www.projectacumen.com/resources/whitepapers

3 deltek.com
White Paper Does Better Scheduling Drive Execution Success?

Compliance Index. As figure 1 shows, as the with no negative impact on the schedule. These
Schedule Index increases so does the finish can be removed to simplify the schedule without
compliance index (and vice versa) in essence any changes to CPM results i.e., dates and float
proving that the better the planning quality, the remain the same. Removal of these redundancies
more activities that finish on time. results in cleaner, more readable schedules that
Secondly, we need to understand how close also form a better basis for running risk models.
this relationship is. A trend line was plotted to give One common question being repeatedly
an accurate coefficient of determination factor asked has been, If a schedule has a high number
between the two data sets. The R2 factor shows a of logic links per activity (Logic Density), does
value of 0.603, meaning there is 60% confidence this necessarily mean that there is a high degree
that a change in the quality of the plan directly of redundancy? If the answer is yes, then it makes
drives the quality of execution. Given there are so sense to remove the redundancy. However, if
many other variables affecting project execution a high logic density does not equate to a high
(quality of labor, materials, weather, industrial degree of redundancy, then high logic density isnt
action, owner/contractor relationships etc.), this necessarily a concern.
0.603 factor is extremely high.
An analysis was conducted on the same
Does Complex Logic Result in Unnecessary project data set comparing Logic Density and
Redundancy? Redundancy Index. The results can be seen in
A recently developed schedule metric known as figure 2.
Redundancy Index, measures the amount of
redundant or unnecessary logic in a schedule. This
metric pinpoints logic links that can be removed

Figure 2: Correlation Between Logic Density and Redundancy Index

4 deltek.com
World Headquarters: From figure 2 it can be seen that there is a Conclusions
United States strong positive relationship between logic density From the research conducted, it can be
2291 Wood Oak Drive and the degree of schedule logic redundancy. The concluded that the alternate hypothesis that
Herndon, VA 20171-2823 R2 factor shows a value of 0.6 thus reflecting a there is indeed a positive correlation between
800.456.2009 very strong correlation between the two. sound project scheduling and successful on time
Secondly, from the results, it can be seen that project execution completion, is true. While a
Worldwide Locations: the majority of the Logic Density values fall within sound plan cannot be held solely responsible for
Belgium a score of 2 and 5. In theory, each activity should this driving success factor, it has been shown that
+32 (0) 2 709 2191 have at least one predecessor and one successor, it is indeed a highly significant one.
thus driving a minimum score of 2. The results are Tied very closely to this, overly complex
Denmark not only confirming this but also showing that the schedules with regards to logic definition
+45 35 27 79 00 majority of activities do not surpass an average also drive a high degree of unnecessary logic
value of 5. Those activities that do, also then carry redundancy.
Germany a high percentage of redundant logic. In summary, projects typically fail due to either
Frankfurt am Main unrealistic, poorly thought out plans or weak
+49 6967733106 Next Steps execution. This research exercise gives a strong
This initial analysis is part of ongoing research indication that by focusing on achieving a sound
The Netherlands within Acumen within the area of project plan up front; there is a much higher chance of
+31(0)30 7430014 analytics. As we continue to develop more and success during execution.
more analytics, metrics and tools to help with
Norway planning and execution, it is equally important
+47 22 01 38 00 that we continue to validate these against real life
projects. All of our metrics are continuously being
Sweden reviewed and calibrated by industry experts and
+46 (0)8 587 077 00 real-life projects. As part of this, we are actively
pursuing additional research specifically in the
United Kingdom area of logic and float analysis to help form the
London basis of further insight into CPM scheduling best
+44 (0)20 7518 5010 practices.

deltek.com
info@deltek.com

Deltek is the leading global provider of enterprise software and information solutions for professional services firms and
government contractors. For decades, we have delivered actionable insight that empowers our customers to unlock their
business potential. 16,000 organizations and 2 million users in over 80 countries around the world rely on Deltek to research
and identify opportunities, win new business, optimize resources, streamline operations, and deliver more profitable projects.
Deltek Know more. Do more. deltek.com

2014 Deltek, Inc. All rights reserved. All referenced trademarks are the property of their respective owners.
5 013014-v1

Anda mungkin juga menyukai