Anda di halaman 1dari 56

ABPR3 Combined Cycle Cogeneration Plant Project

DATE: 12th July. 2016


SUPPLEMENTARY COMMUNICATION SHEET for

TITLE OF DOCUMENT Detailed Project Schedule

PROJECT CONTROL No ABPR3-G-T-PJ-0005 REV 1

DOCUMENT No LST-LNB-XAC03-0005 REV 1

This document was prepared for ABPR3 Project for first issue.

No. Rev. CUSTOMER COMMENTS REPLIES AND EXPLANATIONS


N/A The schedule is based on ABPR3 NTP
-
1-December 2016.
1
0 N/A Closed
1
Target Taking Over has been set one month
-
ahead of the contract Taking Over date.
2
0 N/A Closed
1
This schedule will be a baseline schedule in
Monthly Progress Report, any updates/recovery
-
schedules will be shown against this Baseline
3
schedule.
0 N/A Closed
1
The activity has developed in-line with company
standard for a better engineering, procurement,
and construction management.
-
4 Refer to Appendix-1 for summary version of
baseline schedule.

0 N/A Closed
1
Detailed project schedule has been revised based
on civil construction schedule except E&C
building construction schedule. E&C building
construction schedule is now re-scheduling based
1
5 on the latest site construction progress. E&C
building construction schedule in the details
schedule is HOLD until further update on civil
construction schedule for E&C building.
2
Page 21 of 54 & Page 47 of 54.
6 1
Typo error has been corrected.
No. Rev. CUSTOMER COMMENTS REPLIES AND EXPLANATIONS
Fire Gas Heater changed to Fuel Gas Heater.
2
Page 30 of 54
Gas Turbine On-Base date has changed as per
1
7 the contract program.
8 Feb-2017 to 9-Feb-2017.
2
Page 48 of 54
1 Typo error has been corrected.
8
DCS/UPS system to DC/UPS system.
2
For Information

OWNER

Amata B.Grimm Power (Rayong) 3 Limited


PROJECT

ABPR3 Combined Cycle Cogeneration


Plant Project
CONTRACTOR

This documentation is CONFIDENTIAL and is


TITLE
INTELLECTUAL PROPERTY of TPSC (Thailand)
Co., Ltd. It must not be copied, loaned or
transferred, nor must be disclosed to any third party
Detailed Project Schedule
without their written permission.
TPSC (Thailand) Co., Ltd. PROJECT CONTROL NO. ABPR3-G-T-PJ-0005 REV. 1

APPROVED: Kainuma JOB NO. SCALE DATE

CHECKED: Ogura XAC03 NONE Apr.12.,2016


DESIGNED: Miyasaka DRAWING NO. REV

1 12-Jul 16 For Information Kainuma Ogura Miranda LST-LNB-XAC03-0005 1


0 12-Apr 16 For Information Kainuma Ogura Miyasaka

REV DATE
ISSUE
APPROVED CHECKED DESIGNED
TPSC (Thailand) Co., Ltd.
PURPOSE
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:1 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
03PMS-BL00 ABPR3 - Project
Proje Master Schedule - BL- under revision 762 01-Dec-15 01-Jan-18 32

03PMS-BL00.1 PROFESSIONAL
PROFESSIO SERVICES 650 01-Dec-15 10-Sep-17 144

03PMS-BL00.1.1 PROJECT
PROJEC MANAGEMENT & CONTROL SERVICE 119 01-Dec-15 28-Mar-16 675

03PMS-BL00.1.1.3 Project
Projec Planning & Control 119 01-Dec-15 28-Mar-16 675

03PMS-BL00.1.1.3.01 Pr
Project Operation Establishment 20 01-Dec-15 20-Dec-15 536

XAC03-11301000 Project Operation Establishment 20 01-Dec-15 20-Dec-15 536

03PMS-BL00.1.1.3.02 Project
Pr Basic Planning 20 01-Dec-15 20-Dec-15 536

XAC03-11302000 Project Basic Planning 20 01-Dec-15 20-Dec-15 536

03PMS-BL00.1.1.3.03 Pr
Project WBS Developing 20 01-Dec-15 20-Dec-15 536

XAC03-11303000 Project WBS Developing 20 01-Dec-15 20-Dec-15 536

03PMS-BL00.1.1.3.04 Sc
Schedule Control 119 01-Dec-15 28-Mar-16 675

XAC03-11304100 Schedule Control - Milestone Schedule establishment 30 01-Dec-15 30-Dec-15 536

XAC03-11304200 Schedule Control - Detail Schedule establishment 89 31-Dec-15 28-Mar-16 675

03PMS-BL00.1.2 BASIC ENGINEERING


EN SERVICE 592 01-Dec-15 14-Jul-17 202

03PMS-BL00.1.2.2 Basic Design 592 01-Dec-15 14-Jul-17 202

03PMS-BL00.1.2.2.03 Plant
Pla Basic Design Concept 56 01-Dec-15 25-Jan-16 64

XAC03-12203000 Plant Basic Design Concept 56 01-Dec-15 25-Jan-16 64

03PMS-BL00.1.2.2.04 Pla
Plant Plot Plan Study 85 01-Dec-15 23-Feb-16 169

XAC03-12204000 Plant Plot Plan Study 85 01-Dec-15 23-Feb-16 169

03PMS-BL00.1.2.2.05 Heat
He Balance Diagram 110 26-Jan-16 14-May-16 64

XAC03-12205000 Heat Balance Diagram 110 26-Jan-16 14-May-16 64

03PMS-BL00.1.2.2.06 Wa
Water Balance Diagram 56 19-Mar-16 13-May-16 629

XAC03-12206000 Water Balance Diagram 56 19-Mar-16 13-May-16 629

03PMS-BL00.1.2.2.07 Plant
Pla Performance Test work 50 26-May-17 14-Jul-17 160

XAC03-12207000 Plant Performance Test work 50 26-May-17 14-Jul-17 160

03PMS-BL00.1.2.2.08 Equipment
Eq Redundancy Concept 56 23-Feb-16 18-Apr-16 165

XAC03-12208000 Equipment Redundancy Concept 56 23-Feb-16 18-Apr-16 165

03PMS-BL00.1.2.2.09 Equipment
Eq Design Concept 56 23-Feb-16 18-Apr-16 165

XAC03-12209000 Equipment Design Concept 56 23-Feb-16 18-Apr-16 165

03PMS-BL00.1.2.2.11 General
Ge arrangement Study 92 01-Dec-15 01-Mar-16 588

XAC03-12211100 Power block area 56 01-Dec-15 25-Jan-16 624

XAC03-12211200 Switchyard Area 56 01-Dec-15 25-Jan-16 414

XAC03-12211300 Mechanical BOP area 92 01-Dec-15 01-Mar-16 222

XAC03-12211400 Electrical BOP area 56 01-Dec-15 25-Jan-16 200

XAC03-12211500 Panel Layout 87 01-Dec-15 25-Feb-16 169

03PMS-BL00.1.2.2.12 P&
P&ID 125 23-Jan-16 26-May-16 291

XAC03-12212600 CW/ACW System 56 23-Jan-16 18-Mar-16 196

XAC03-12212700 CCCW System 56 23-Jan-16 18-Mar-16 196

XAC03-12212800 Boiler Feedwater System 56 23-Jan-16 18-Mar-16 196

XAC03-12212C00 Steam Supply System 56 23-Jan-16 18-Mar-16 196

XAC03-12212100 GT and Auxiliary 56 02-Feb-16 28-Mar-16 129

XAC03-12212300 Boiler(HRSG) and Auxiliary 56 02-Feb-16 28-Mar-16 164

XAC03-12212400 Condensate Water System 56 02-Feb-16 28-Mar-16 186

XAC03-12212900 Fuel Gas System 56 02-Feb-16 28-Mar-16 186

XAC03-12212A00 Fuel Oil System 56 02-Feb-16 28-Mar-16 186

XAC03-12212B00 Compressed Air System 56 02-Mar-16 26-Apr-16 213

XAC03-12212200 ST and Auxiliary 56 01-Apr-16 26-May-16 291

03PMS-BL00.1.2.2.13 System
Sy Design Description 424 20-Jan-16 18-Mar-17 320

03PMS-BL00.1.2.2.13.1 Arrangement 58 10-Feb-16 07-Apr-16 315

XAC03-12213120 Fire Protection System 56 10-Feb-16 05-Apr-16 291

XAC03-12213110 HVAC System 56 12-Feb-16 07-Apr-16 315

03PMS-BL00.1.2.2.13.2 Process 62 26-Mar-16 26-May-16 291

XAC03-12213210 GT and Auxiliary 56 26-Mar-16 20-May-16 76

XAC03-12213220 NST and Auxiliary 56 01-Apr-16 26-May-16 291

03PMS-BL00.1.2.2.13.4 Mechanical 124 23-Jan-16 25-May-16 344

XAC03-12213420 Condensate Water System 56 23-Jan-16 18-Mar-16 196

XAC03-12213430 CW/ACW System 56 23-Jan-16 18-Mar-16 196

XAC03-12213450 Boiler Feedwater System 56 23-Jan-16 18-Mar-16 196

XAC03-12213490 Steam Supply System 56 23-Jan-16 18-Mar-16 196

XAC03-12213440 CCCW System 56 02-Feb-16 28-Mar-16 186

XAC03-12213460 Fuel Gas System 56 26-Mar-16 20-May-16 76

XAC03-12213470 Fuel Oil System 56 26-Mar-16 20-May-16 349

XAC03-12213480 Compressed Air System 56 26-Mar-16 20-May-16 76

XAC03-12213410 Boiler(HRSG) and Auxiliary 56 31-Mar-16 25-May-16 106

03PMS-BL00.1.2.2.13.6 Instruments 217 10-Mar-16 12-Oct-16 266

XAC03-12213600 Instruments 217 10-Mar-16 12-Oct-16 266

03PMS-BL00.1.2.2.13.7 Electrical 56 28-Jul-16 21-Sep-16 87

XAC03-12213700 Electrical 56 28-Jul-16 21-Sep-16 87

03PMS-BL00.1.2.2.13.8 Electrical Bulk 56 22-Jan-17 18-Mar-17 320

XAC03-12213800 Electrical Bulk 56 22-Jan-17 18-Mar-17 320

03PMS-BL00.1.2.2.13.A Civil Construction 56 20-Jan-16 15-Mar-16 688

XAC03-12213A00 Civil Construction 56 20-Jan-16 15-Mar-16 688

03PMS-BL00.1.2.2.14 Eq
Equipment Design Determination (Capacity Calculation) 413 23-Jan-16 10-Mar-17 328

03PMS-BL00.1.2.2.14.1 Arrangement 56 06-Apr-16 31-May-16 261

XAC03-12214110 HVAC System 56 06-Apr-16 31-May-16 261

XAC03-12214120 Fire Protection System 56 06-Apr-16 31-May-16 235

03PMS-BL00.1.2.2.14.4 Mechanical 95 23-Jan-16 26-Apr-16 646

XAC03-12214490 Steam Supply System 56 23-Jan-16 18-Mar-16 685

XAC03-12214460 Fuel Gas System 56 02-Feb-16 28-Mar-16 675

XAC03-12214470 Fuel Oil System 56 02-Feb-16 28-Mar-16 675

XAC03-12214420 Condensate Water System 56 23-Feb-16 18-Apr-16 654

XAC03-12214430 CW/ACW System 56 23-Feb-16 18-Apr-16 654

XAC03-12214440 CCCW System 56 23-Feb-16 18-Apr-16 654

XAC03-12214450 Boiler Feedwater System 56 23-Feb-16 18-Apr-16 654

XAC03-12214480 Compressed Air System 56 02-Mar-16 26-Apr-16 646

03PMS-BL00.1.2.2.14.7 Electrical 205 19-Feb-16 10-Sep-16 234

XAC03-12214720 Unit Aux Transformer Sizing Calculation 56 19-Feb-16 14-Apr-16 357

XAC03-12214760 Auxiliary Transformer Sizing Calculation 56 19-Feb-16 14-Apr-16 357

XAC03-12214710 Generator Setup Transformer Sizing Calculation 56 19-Feb-16 14-Apr-16 357

XAC03-12214770 HV/MV SWGR Logic Diagram 56 09-Jun-16 03-Aug-16 239

XAC03-12214780 LV SWGR Logic Diagram 56 09-Jun-16 03-Aug-16 246

XAC03-12214730 Battery Sizing Calculation 56 23-Jun-16 17-Aug-16 122

XAC03-12214740 Emergency D/G Sizing Calculation 56 17-Jul-16 10-Sep-16 234

03PMS-BL00.1.2.2.14.9 Switchyard 56 03-Jun-16 28-Jul-16 170

XAC03-12214900 Switchyard 56 03-Jun-16 28-Jul-16 170

03PMS-BL00.1.2.2.14.A Civil Construction 373 03-Mar-16 10-Mar-17 328

XAC03-12214A00 Civil Construction 373 03-Mar-16 10-Mar-17 328

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:2 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
03PMS-BL00.1.2.2.15 Eq
Equipment Specification 307 24-Mar-16 24-Jan-17 373

03PMS-BL00.1.2.2.15.1 Arrangement 94 07-Apr-16 09-Jul-16 572

XAC03-12215110 HVAC System 56 07-Apr-16 01-Jun-16 610

XAC03-12215120 Fire Protection System 56 15-May-16 09-Jul-16 572

03PMS-BL00.1.2.2.15.4 Mechanical 117 17-Apr-16 11-Aug-16 539

XAC03-12215420 Condensate Water System 56 17-Apr-16 11-Jun-16 600

XAC03-12215480 Compressed Air System 56 17-Jun-16 11-Aug-16 539

03PMS-BL00.1.2.2.15.6 Instruments 269 01-May-16 24-Jan-17 373

XAC03-12215610 DCS 56 01-May-16 25-Jun-16 586

XAC03-12215630 Steam and Water Analysis System 56 09-Oct-16 03-Dec-16 425

XAC03-12215660 Primary Energy Saving System 56 05-Nov-16 30-Dec-16 398

XAC03-12215640 Plant Communication System, CCTV & Clock 56 30-Nov-16 24-Jan-17 373

03PMS-BL00.1.2.2.15.7 Electrical 206 24-Mar-16 15-Oct-16 474

XAC03-12215710 Transformers 56 24-Mar-16 18-May-16 624

XAC03-12215720 SWGRs / MCCs / DBs 88 08-Jun-16 03-Sep-16 516

XAC03-12215730 DC & UPS 56 28-Jul-16 21-Sep-16 498

XAC03-12215740 EDG / BSDG 56 21-Aug-16 15-Oct-16 474

03PMS-BL00.1.2.2.15.9 Switchyard 56 15-May-16 09-Jul-16 572

XAC03-12215900 Switchyard 56 15-May-16 09-Jul-16 572

03PMS-BL00.1.2.2.16 RFQ
RF (Request for Quotation) 335 01-Dec-15 30-Oct-16 459

03PMS-BL00.1.2.2.16.1 Arrangement 30 09-Dec-15 07-Jan-16 201

XAC03-12216110 RFQ Preparation - HVAC System 30 09-Dec-15 07-Jan-16 201

XAC03-12216120 RFQ Preparation - Fire Protection System 30 09-Dec-15 07-Jan-16 164

03PMS-BL00.1.2.2.16.2 Process 1 01-Dec-15 01-Dec-15 266

XAC03-12216210 RFQ Preparation - GT and Auxiliary 1 01-Dec-15 01-Dec-15 0

XAC03-12216220 RFQ Preparation - ST and Auxiliary 1 01-Dec-15 01-Dec-15 266

03PMS-BL00.1.2.2.16.3 Civil design 14 01-Dec-15 14-Dec-15 780

XAC03-12216300 RFQ Preparation - Civil design 14 01-Dec-15 14-Dec-15 780

03PMS-BL00.1.2.2.16.4 Mechanical 152 01-Dec-15 30-Apr-16 642

XAC03-12216430 RFQ Preparation - Boiler(HRSG) and Auxiliary 1 01-Dec-15 01-Dec-15 0

XAC03-12216440 RFQ Preparation - Condensate Water System 45 01-Dec-15 14-Jan-16 247

XAC03-12216470 RFQ Preparation - Boiler Feedwater System 45 01-Dec-15 14-Jan-16 352

XAC03-122164B0 RFQ Preparation - Steam Supply System 3 01-Dec-15 03-Dec-15 791

XAC03-122164A0 RFQ Preparation - Compressed Air System 30 03-Dec-15 01-Jan-16 281

XAC03-12216480 RFQ Preparation - Fuel Gas System 30 15-Dec-15 13-Jan-16 294

XAC03-12216490 RFQ Preparation - Fuel Oil System 30 15-Dec-15 13-Jan-16 294

XAC03-12216450 RFQ Preparation - CW/ACW System 30 08-Jan-16 06-Feb-16 228

XAC03-12216460 RFQ Preparation - CCCW System 63 13-Feb-16 15-Apr-16 187

03PMS-BL00.1.2.2.16.4.Z Other System


03PMS-BL00.1.2.2.16.4 152 01-Dec-15 30-Apr-16 212

XAC03-122164Z1 RFQ Preparation - Others System (CT Make Up Storage Water Tank) 30 01-Dec-15 30-Dec-15 218

XAC03-122164Z2 RFQ Preparation - Others System (Waste Water Treatment) 1 01-Dec-15 01-Dec-15 169

XAC03-122164Z3 RFQ Preparation - Others System (Service Water & Fire Water Storage Tank) 30 09-Dec-15 07-Jan-16 172

XAC03-122164Z4 RFQ Preparation - Others System (Raw Water Buffer Tank) 30 09-Dec-15 07-Jan-16 255

XAC03-122164Z5 RFQ Preparation - Others System (DM Water Storage Tank) 30 10-Dec-15 08-Jan-16 182

XAC03-122164Z6 RFQ Preparation - Others System (Cooling Tower) 30 16-Dec-15 14-Jan-16 182

XAC03-122164Z7 RFQ Preparation - Others System (STG Overhead Crane) 30 16-Dec-15 14-Jan-16 294

XAC03-122164Z8 RFQ Preparation - Others System (Condenser) 30 01-Jan-16 30-Jan-16 183

XAC03-122164Z9 RFQ Preparation - Others System (Raw Water Pump) 30 16-Jan-16 14-Feb-16 182

XAC03-122164ZA RFQ Preparation - Others System (CT Make UP Water Pump) 30 16-Jan-16 14-Feb-16 193

XAC03-122164ZB RFQ Preparation - Others System (Service Water Pump) 30 16-Jan-16 14-Feb-16 283

XAC03-122164ZC RFQ Preparation - Others System (DM Water Pump) 30 16-Jan-16 14-Feb-16 197

XAC03-122164ZD RFQ Preparation - Others System (Chemical Dosing for HRSG) 30 17-Mar-16 15-Apr-16 227

XAC03-122164ZE RFQ Preparation - Others System (Chemical Dosing for CT) 30 17-Mar-16 15-Apr-16 186

XAC03-122164ZF RFQ Preparation - Others System (Sump Pump) 30 01-Apr-16 30-Apr-16 205

03PMS-BL00.1.2.2.16.6 Instruments 335 01-Dec-15 30-Oct-16 459

XAC03-12216650 RFQ Preparation - Chemical Laboratory 1 01-Dec-15 01-Dec-15 619

XAC03-12216690 RFQ Preparation - Meteorological System 15 01-Dec-15 15-Dec-15 779

XAC03-12216610 RFQ Preparation - DCS 15 30-Dec-15 13-Jan-16 52

XAC03-12216660 RFQ Preparation - Primary Energy Saving System 15 14-Apr-16 28-Apr-16 278

XAC03-1221668A RFQ Preparation - Turbine Bypass 15 17-Apr-16 01-May-16 110

XAC03-1221668B RFQ Preparation - Control Valves 15 17-Apr-16 01-May-16 139

XAC03-12216630 RFQ Preparation - Steam and Water Analysis System 15 02-May-16 16-May-16 305

XAC03-12216620 RFQ Preparation - Continuous Emission Monitoring System 15 12-May-16 26-May-16 176

XAC03-12216640 RFQ Preparation - Plant Communication System, CCTV & Clock 15 25-Aug-16 08-Sep-16 131

XAC03-1221667A RFQ Preparation - C&I Bulk Material 15 29-Aug-16 12-Sep-16 91

XAC03-1221667B RFQ Preparation - Cabling Bulk for C&I Cable 15 16-Oct-16 30-Oct-16 100

03PMS-BL00.1.2.2.16.7 Electrical 112 10-Dec-15 30-Mar-16 232

XAC03-1221671A RFQ Preparation - Transformers 5 10-Dec-15 14-Dec-15 238

XAC03-1221671B RFQ Preparation - Unit Aux Transformer with remote OLTC panel 5 10-Dec-15 14-Dec-15 285

XAC03-1221671C RFQ Preparation - Auxiliary Transformer 5 27-Jan-16 31-Jan-16 290

XAC03-1221672A RFQ Preparation - LV SWGR 5 10-Feb-16 14-Feb-16 226

XAC03-1221672B RFQ Preparation - HV/MV SWGR 5 17-Feb-16 21-Feb-16 205

XAC03-12216730 RFQ Preparation - DC & UPS 5 23-Feb-16 27-Feb-16 106

XAC03-12216740 RFQ Preparation - EDG / BSDG 5 23-Feb-16 27-Feb-16 264

XAC03-1221672C RFQ Preparation - MCCs / DBs 5 26-Mar-16 30-Mar-16 189

03PMS-BL00.1.2.2.16.9 Switchyard 6 01-Dec-15 06-Dec-15 91

XAC03-12216900 RFQ Preparation - Switchyard 6 01-Dec-15 06-Dec-15 91

03PMS-BL00.1.2.2.17 Te
Technical Evaluation of Vendor Quotation 367 01-Dec-15 01-Dec-16 313

03PMS-BL00.1.2.2.17.1 Arrangement 52 08-Jan-16 28-Feb-16 201

XAC03-12217110 Technical Evaluation of Vendor Qutation - HVAC System 52 08-Jan-16 28-Feb-16 201

XAC03-12217120 Technical Evaluation of Vendor Qutation - Fire Protection System 52 08-Jan-16 28-Feb-16 164

03PMS-BL00.1.2.2.17.2 Process 31 01-Dec-15 31-Dec-15 266

XAC03-12217210 Technical Evaluation of Vendor Qutation - GT and Auxiliary 1 01-Dec-15 01-Dec-15 0

XAC03-12217220 Technical Evaluation of Vendor Qutation - ST and Auxiliary 30 02-Dec-15 31-Dec-15 266

03PMS-BL00.1.2.2.17.4 Mechanical 214 01-Dec-15 01-Jul-16 205

XAC03-12217430 Technical Evaluation of Vendor Qutation - Boiler(HRSG) and Auxiliary 1 01-Dec-15 01-Dec-15 0

XAC03-122174A0 Technical Evaluation of Vendor Qutation - Compressed Air System 60 02-Jan-16 01-Mar-16 281

XAC03-12217440 Technical Evaluation of Vendor Qutation - Condensate Water System 152 08-Jan-16 07-Jun-16 209

XAC03-12217470 Technical Evaluation of Vendor Qutation - Boiler Feedwater System 67 08-Jan-16 14-Mar-16 314

XAC03-12217480 Technical Evaluation of Vendor Qutation - Fuel Gas System 48 14-Jan-16 01-Mar-16 294

XAC03-12217460 Technical Evaluation of Vendor Qutation - CCCW System 81 14-Feb-16 04-May-16 186

XAC03-12217450 Technical Evaluation of Vendor Qutation - CW/ACW System 46 15-Feb-16 31-Mar-16 220

03PMS-BL00.1.2.2.17.4.Z Others
03PMS-BL00.1.2.2.17.4 213 02-Dec-15 01-Jul-16 205

XAC03-122174Z1 Technical Evaluation of Vendor Qutation - Others System (Water treatment Plant) 60 02-Dec-15 30-Jan-16 169

XAC03-122174Z2 Technical Evaluation of Vendor Qutation - Others System (CT Make Up Water Storage 40 31-Dec-15 08-Feb-16 218
Tank)
XAC03-122174Z3 Technical Evaluation of Vendor Qutation - Others System (Service and Fire Water 32 08-Jan-16 08-Feb-16 172
Storage Tank)
XAC03-122174Z4 Technical Evaluation of Vendor Qutation - Others System (Raw Water Buffer Tank) 32 08-Jan-16 08-Feb-16 255

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:3 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-122174Z5 Technical Evaluation of Vendor Qutation - Others System (DM Water Storage Tank) 32 09-Jan-16 09-Feb-16 182

XAC03-122174Z6 Technical Evaluation of Vendor Qutation - Others System (Cooling Tower) 45 15-Jan-16 28-Feb-16 182

XAC03-122174Z7 Technical Evaluation of Vendor Qutation - Others System (STG Overhead Crane) 47 15-Jan-16 01-Mar-16 294

XAC03-122174Z8 Technical Evaluation of Vendor Qutation - Others System (Condenser Ball Cleaning) 121 31-Jan-16 30-May-16 183

XAC03-122174Z9 Technical Evaluation of Vendor Qutation - Others System (Raw Water Pump) 47 15-Feb-16 01-Apr-16 182

XAC03-122174ZA Technical Evaluation of Vendor Qutation - Others System (CT Make Up Water Pump) 46 15-Feb-16 31-Mar-16 193

XAC03-122174ZB Technical Evaluation of Vendor Qutation - Others System (Service Water Pump) 46 15-Feb-16 31-Mar-16 283

XAC03-122174ZC Technical Evaluation of Vendor Qutation - Others System (DM Water Pump) 46 15-Feb-16 31-Mar-16 197

XAC03-122174ZD Technical Evaluation of Vendor Qutation - Others System (Chemical Dosing for HRSG) 46 16-Apr-16 31-May-16 227

XAC03-122174ZE Technical Evaluation of Vendor Qutation - Others System (Chemical Dosing for CT) 46 16-Apr-16 31-May-16 186

XAC03-122174ZF Technical Evaluation of Vendor Qutation - Others System (Sump Pump) 62 01-May-16 01-Jul-16 205

03PMS-BL00.1.2.2.17.6 Instruments 366 02-Dec-15 01-Dec-16 313

XAC03-12217650 Technical Evaluation of Vendor Qutation - Chemical Laboratory 60 02-Dec-15 30-Jan-16 619

XAC03-12217610 Technical Evaluation of Vendor Qutation - DCS 48 14-Jan-16 01-Mar-16 52

XAC03-12217660 Technical Evaluation of Vendor Qutation - Primary Energy Saving System 31 29-Apr-16 29-May-16 278

XAC03-1221768A Technical Evaluation of Vendor Qutation - Tur bine Bypass 46 02-May-16 16-Jun-16 110

XAC03-1221768B Technical Evaluation of Vendor Qutation - Control Valves 45 02-May-16 15-Jun-16 139

XAC03-12217630 Technical Evaluation of Vendor Qutation - Steam and Water Analysis System 62 17-May-16 17-Jul-16 305

XAC03-12217620 Technical Evaluation of Vendor Qutation - Continuous Emission Monitoring System 62 27-May-16 27-Jul-16 176

XAC03-12217640 Technical Evaluation of Vendor Qutation - Communication & Clock System 30 09-Sep-16 08-Oct-16 131

XAC03-1221767A Technical Evaluation of Vendor Qutation - C&I Bulk Materials 77 13-Sep-16 28-Nov-16 91

XAC03-1221767B Technical Evaluation of Vendor Qutation - Cabling Bulk for C&I Cable 32 31-Oct-16 01-Dec-16 100

03PMS-BL00.1.2.2.17.7 Electrical 143 15-Dec-15 05-May-16 257

XAC03-1221771A Technical Evaluation of Vendor Qutation - Transformers 36 15-Dec-15 19-Jan-16 238

XAC03-1221771B Technical Evaluation of Vendor Qutation - Unit Aux Transformer with remote OLTC panel 36 15-Dec-15 19-Jan-16 285

XAC03-1221771C Technical Evaluation of Vendor Qutation - Auxiliary Transformer 40 01-Feb-16 11-Mar-16 290

XAC03-1221772A Technical Evaluation of Vendor Qutation - LV SWGR 44 15-Feb-16 29-Mar-16 226

XAC03-1221772B Technical Evaluation of Vendor Qutation - HV/MV SWGR 37 22-Feb-16 29-Mar-16 205

XAC03-12217730 Technical Evaluation of Vendor Qutation - DC & UPS 61 28-Feb-16 28-Apr-16 106

XAC03-12217740 Technical Evaluation of Vendor Qutation - EDG / BSDG 61 28-Feb-16 28-Apr-16 264

XAC03-1221772C Technical Evaluation of Vendor Qutation - MCCs / DBs 36 31-Mar-16 05-May-16 189

03PMS-BL00.1.2.2.17.8 Electrical Bulk 154 15-Apr-16 15-Sep-16 162

XAC03-12217800 Technical Evaluation of Vendor Qutation - Electrical Bulk 154 15-Apr-16 15-Sep-16 162

03PMS-BL00.1.2.2.17.9 Switchyard 110 07-Dec-15 25-Mar-16 91

XAC03-12217900 Technical Evaluation of Vendor Qutation - Switchyard 110 07-Dec-15 25-Mar-16 91

03PMS-BL00.1.2.2.18 List
Lis 457 26-Jan-16 26-Apr-17 281

03PMS-BL00.1.2.2.18.1 Equipment List 156 26-Jan-16 29-Jun-16 582

XAC03-12218100 Equipment List 156 26-Jan-16 29-Jun-16 582

03PMS-BL00.1.2.2.18.3 CCCW List 56 12-Feb-16 07-Apr-16 665

XAC03-12218300 CCCW List 56 12-Feb-16 07-Apr-16 665

03PMS-BL00.1.2.2.18.4 Lubricant List 364 28-Apr-16 26-Apr-17 281

XAC03-12218400 Lubricant List 364 28-Apr-16 26-Apr-17 281

03PMS-BL00.1.2.2.18.7 Special Tool List 457 26-Jan-16 26-Apr-17 281

XAC03-12218770 Electrical 56 26-Jan-16 21-Mar-16 682

XAC03-12218740 Mechanical 56 02-Mar-17 26-Apr-17 281

03PMS-BL00.1.2.2.19 Electrical
Ele Load List 300 31-Dec-15 25-Oct-16 464

03PMS-BL00.1.2.2.19.1 Draft Electrical Load List (70% accuracy) 204 05-Apr-16 25-Oct-16 464

XAC03-12219140 Mechanical 204 05-Apr-16 25-Oct-16 464

03PMS-BL00.1.2.2.19.2 Update Electrical Load List (90% accuracy) 300 31-Dec-15 25-Oct-16 464

XAC03-12219270 Electrical 56 31-Dec-15 24-Feb-16 708

XAC03-12219240 Mechanical 204 05-Apr-16 25-Oct-16 464

03PMS-BL00.1.2.2.19.3 Final Electrical Load List (Freez) 300 31-Dec-15 25-Oct-16 464

XAC03-12219370 Electrical 56 31-Dec-15 24-Feb-16 708

XAC03-12219340 Mechanical 204 05-Apr-16 25-Oct-16 464

03PMS-BL00.1.2.2.20 Single
Sin Line Diagram 56 13-Feb-16 08-Apr-16 664

03PMS-BL00.1.2.2.20.1 Draft Single Line Diagram 56 13-Feb-16 08-Apr-16 664

XAC03-12220110 Load Flow Study 56 13-Feb-16 08-Apr-16 664

XAC03-12220130 Motor Starting Study 56 13-Feb-16 08-Apr-16 664

XAC03-12220120 Short Circuit Study 56 13-Feb-16 08-Apr-16 664

03PMS-BL00.1.2.2.20.2 Update Single Line Diagram 56 13-Feb-16 08-Apr-16 664

XAC03-12220210 Load Flow Study 56 13-Feb-16 08-Apr-16 664

XAC03-12220230 Motor Starting Study 56 13-Feb-16 08-Apr-16 664

XAC03-12220220 Short Circuit Study 56 13-Feb-16 08-Apr-16 664

03PMS-BL00.1.2.3 Plant O
Operation Engineering 176 02-Feb-16 26-Jul-16 555

03PMS-BL00.1.2.3.01 Plant
Pla Operation philosophy 56 02-Feb-16 28-Mar-16 186

XAC03-12301000 Plant Operation philosophy 56 02-Feb-16 28-Mar-16 186

03PMS-BL00.1.2.3.02 Pla
Plant Automation Operation philosophy 56 13-Feb-16 08-Apr-16 197

XAC03-12302000 Electrical Operation Philosophy 56 13-Feb-16 08-Apr-16 197

03PMS-BL00.1.2.3.03 Ele
Electrical Operation Philosophy 56 01-Jun-16 26-Jul-16 555

XAC03-12303000 Plant Automation Operation philosophy 56 01-Jun-16 26-Jul-16 555

03PMS-BL00.1.2.3.04 Ele
Electrical Plant Interlock 56 02-May-16 26-Jun-16 585

XAC03-12304000 Electrical Plant Interlock 56 02-May-16 26-Jun-16 585

03PMS-BL00.1.3 DETAIL E
ENGINEERING DOCUMENT 649 02-Dec-15 10-Sep-17 144

03PMS-BL00.1.3.1 Arrang
Arrangement Detail Engineering 208 25-Mar-16 18-Oct-16 471

03PMS-BL00.1.3.1.01 HVAC
HV System 99 22-Apr-16 29-Jul-16 552

XAC03-13101000 HVAC System 99 22-Apr-16 29-Jul-16 552

03PMS-BL00.1.3.1.02 Fire
Fir protection System 208 25-Mar-16 18-Oct-16 471

XAC03-13102000 Fire protection System 208 25-Mar-16 18-Oct-16 471

03PMS-BL00.1.3.2 Civil D
Detail Design 506 31-Jan-16 19-Jun-17 227

03PMS-BL00.1.3.2.01 Ci
Civil General 506 31-Jan-16 19-Jun-17 227

XAC03-13201200 Site development 56 31-Jan-16 26-Mar-16 677

XAC03-13201300 Subsoil improvement 56 31-Jan-16 26-Mar-16 677

XAC03-13201100 Site investigation 56 01-Feb-16 27-Mar-16 676

XAC03-13201400 Piling 113 10-Feb-16 01-Jun-16 610

XAC03-13201500 Earthing structure 56 02-Mar-16 26-Apr-16 646

XAC03-13201600 Drainage 56 18-Aug-16 12-Oct-16 477

XAC03-13201700 Road & Paving 56 18-Aug-16 12-Oct-16 477

XAC03-13201800 Fence & Gate 56 22-Sep-16 16-Nov-16 442

XAC03-13201Z00 Others 56 25-Apr-17 19-Jun-17 227

03PMS-BL00.1.3.2.02 Concrete
Co Structure 449 05-Mar-16 27-May-17 250

XAC03-13202400 Concrete Trench 243 05-Mar-16 02-Nov-16 456

XAC03-13202600 Pipe sleeper 216 26-Mar-16 27-Oct-16 462

XAC03-13202100 Elevated Structure 339 06-Apr-16 10-Mar-17 328

XAC03-13202500 Pit & pond 141 29-Jun-16 16-Nov-16 442

XAC03-13202300 Foundation 286 15-Aug-16 27-May-17 250

03PMS-BL00.1.3.2.03 Steel
St Structure 173 26-Mar-16 14-Sep-16 505

XAC03-13203100 Pipe Rack 173 26-Mar-16 14-Sep-16 505

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:4 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-13203300 Steel Shed 142 26-Mar-16 14-Aug-16 536

XAC03-13203200 Platform & access way 114 11-May-16 01-Sep-16 518

03PMS-BL00.1.3.2.04 Bu
Building 270 06-Apr-16 31-Dec-16 397

XAC03-13204700 Control Building 100 06-Apr-16 14-Jul-16 567

XAC03-13204900 WTP building 56 07-Apr-16 01-Jun-16 610

XAC03-13204500 STG building 56 12-Aug-16 06-Oct-16 483

XAC03-13204600 HRSG building 56 06-Nov-16 31-Dec-16 397

03PMS-BL00.1.3.3 Mecha
Mechanical Equipment Detail Engineering 431 02-Dec-15 04-Feb-17 156

03PMS-BL00.1.3.3.01 Gas
Ga turbine & generator 379 02-Dec-15 15-Dec-16 40

XAC03-13301100 Drawing Review and Comments for Notice To Fabr icate (NTF) 247 02-Dec-15 05-Aug-16 0

XAC03-13301300 Factory Test - G TG 31 0 08-Dec-16 0

XAC03-35505140 Factory Test - G TG 32 0 15-Dec-16 40

03PMS-BL00.1.3.3.02 Bo
Boiler / HRSG & Auxilliary Equipment 351 02-Dec-15 16-Nov-16 0

XAC03-13302100 Drawing Review and Comments for Notice To Fabr icate (NTF) 282 02-Dec-15 08-Sep-16 0

XAC03-13302300 Factory Test 0 16-Nov-16 0

03PMS-BL00.1.3.3.03 St
Steam Turbine & Generator 302 18-Mar-16 13-Jan-17 59

XAC03-13303100 Drawing Review and Comments for Notice To Fabr icate (NTF) 161 18-Mar-16 25-Aug-16 200

XAC03-13303300 Factory Test 0 13-Jan-17 59

03PMS-BL00.1.3.3.05 Condenser
Co / Air cooled co ndenser 238 09-Jun-16 01-Feb-17 54

XAC03-13305100 Drawing Review and Comments for Notice To Fabr icate (NTF) 84 09-Jun-16 31-Aug-16 208

XAC03-13305300 Factory Test 0 01-Feb-17 54

03PMS-BL00.1.3.3.06 Water
Wa Pumps 311 31-Mar-16 04-Feb-17 156

03PMS-BL00.1.3.3.06.A Extract ion Pump 213 16-Apr-16 14-Nov-16 166

XAC03-13306A10 Drawing Review and Comments for Notice To Fabr icate (NTF) 103 16-Apr-16 27-Jul-16 276

XAC03-13306A30 Factory Test 0 14-Nov-16 166

03PMS-BL00.1.3.3.06.B HP Feed Water Pump 204 13-May-16 02-Dec-16 113

XAC03-13306B10 Drawing Review and Comments for Notice To Fabr icate (NTF) 78 13-May-16 29-Jul-16 239

XAC03-13306B30 Factory Test 0 02-Dec-16 113

03PMS-BL00.1.3.3.06.C LP Feed Water Pump 239 04-May-16 29-Dec-16 86

XAC03-13306C10 Drawing Review and Comments for Notice To Fabr icate (NTF) 85 04-May-16 27-Jul-16 241

XAC03-13306C30 Factory Test 0 29-Dec-16 86

03PMS-BL00.1.3.3.06.D CCCW/ACW Pump 127 05-Aug-16 09-Dec-16 64

XAC03-13306D10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 94

XAC03-13306D30 Factory Test 0 09-Dec-16 64

03PMS-BL00.1.3.3.06.E Main Cooling Water Pum p 174 20-Apr-16 10-Oct-16 110

XAC03-13306E10 Drawing Review and Comments for Notice To Fabr icate (NTF) 114 20-Apr-16 11-Aug-16 170

XAC03-13306E30 Factory Test 0 10-Oct-16 110

03PMS-BL00.1.3.3.06.F Condenser Vacuum Pump 311 31-Mar-16 04-Feb-17 156

XAC03-13306F10 Drawing Review and Comments for Notice To Fabr icate (NTF) 118 31-Mar-16 26-Jul-16 349

XAC03-13306F30 Factory Test 0 04-Feb-17 156

03PMS-BL00.1.3.3.06.G Raw Water Pump 134 04-May-16 14-Sep-16 150

XAC03-13306G10 Drawing Review and Comments for Notice To Fabr icate (NTF) 134 04-May-16 14-Sep-16 150

XAC03-13306G30 Factory Test 0 14-Sep-16 150

03PMS-BL00.1.3.3.06.H CT Make Up Water Pump 194 04-May-16 13-Nov-16 116

XAC03-13306H10 Drawing Review and Comments for Notice To Fabr icate (NTF) 150 04-May-16 30-Sep-16 160

XAC03-13306H30 Factory Test 0 13-Nov-16 116

03PMS-BL00.1.3.3.06.I Service Water Pump 132 05-Aug-16 14-Dec-16 122

XAC03-13306I10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 157

XAC03-13306I30 Factory Test 0 14-Dec-16 122

03PMS-BL00.1.3.3.06.J DM Water Pump 132 05-Aug-16 14-Dec-16 36

XAC03-13306J10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 71

XAC03-13306J30 Factory Test 0 14-Dec-16 36

03PMS-BL00.1.3.3.06.K Auxiliary Cooling Water Pump 134 05-Aug-16 16-Dec-16 57

XAC03-13306K10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 94

XAC03-13306K30 Factory Test 0 16-Dec-16 57

03PMS-BL00.1.3.3.06.L Sump Pump 67 27-Sep-16 02-Dec-16 123

XAC03-13306L10 Drawing Review and Comments for Notice To Fabr icate (NTF) 64 27-Sep-16 29-Nov-16 126

XAC03-13306L30 Factory Test 0 02-Dec-16 59

03PMS-BL00.1.3.3.07 Fu
Fuel Supply System 212 06-May-16 03-Dec-16 96

XAC03-13307100 Drawing Review and Comments for Notice To Fabr icate (NTF) 79 06-May-16 23-Jul-16 229

XAC03-13307300 Factory Test 0 03-Dec-16 96

03PMS-BL00.1.3.3.08 Cooling
Co Tower 262 17-Mar-16 03-Dec-16 66

XAC03-13308100 Drawing Review and Comments for Notice To Fabr icate (NTF) 163 17-Mar-16 26-Aug-16 165

XAC03-13308300 Factory Test 0 03-Dec-16 66

03PMS-BL00.1.3.3.09 Water
Wa Treatment System 141 15-May-16 02-Oct-16 64

XAC03-13309100 Drawing Review and Comments for Notice To Fabr icate (NTF) 141 15-May-16 02-Oct-16 64

XAC03-13309300 Factory Test 0 02-Oct-16 64

03PMS-BL00.1.3.3.ZZ Others
O 326 29-Feb-16 19-Jan-17 109

03PMS-BL00.1.3.3.ZZ.A Chemical Dosing For HRSG 110 01-Oct-16 18-Jan-17 88

XAC03-133ZZA10 Drawing Review and Comments for Notice To Fabr icate (NTF) 93 01-Oct-16 01-Jan-17 105

XAC03-133ZZA30 Factory Test 0 18-Jan-17 88

03PMS-BL00.1.3.3.ZZ.B Chemical Dosing For CT 111 01-Oct-16 19-Jan-17 59

XAC03-133ZZB10 Drawing Review and Comments for Notice To Fabr icate (NTF) 106 01-Oct-16 14-Jan-17 64

XAC03-133ZZB30 Factory Test 0 19-Jan-17 59

03PMS-BL00.1.3.3.ZZ.C Compressed Air System 151 16-Jun-16 13-Nov-16 93

XAC03-133ZZC10 Drawing Review and Comments for Notice To Fabr icate (NTF) 69 16-Jun-16 23-Aug-16 175

XAC03-133ZZC30 Factory Test 0 13-Nov-16 93

03PMS-BL00.1.3.3.ZZ.D CT Make Up Storage Water Tank 44 31-May-16 14-Jul-16 106

XAC03-133ZZD10 Drawing Review and Comments for Notice To Fabr icate (NTF) 44 31-May-16 14-Jul-16 106

XAC03-133ZZD30 Factory Test 0 14-Jul-16 106

03PMS-BL00.1.3.3.ZZ.E Service and Fire Storage Water Tank 56 02-May-16 26-Jun-16 86

XAC03-133ZZE10 Drawing Review and Comments for Notice To Fabr icate (NTF) 53 02-May-16 23-Jun-16 89

XAC03-133ZZE30 Factory Test 0 26-Jun-16 86

03PMS-BL00.1.3.3.ZZ.F DM Storage Water Tank 66 02-May-16 06-Jul-16 87

XAC03-133ZZF10 Drawing Review and Comments for Notice To Fabr icate (NTF) 53 02-May-16 23-Jun-16 100

XAC03-133ZZF30 Factory Test 0 06-Jul-16 87

03PMS-BL00.1.3.3.ZZ.G Rawa Water Buffer Water Tank 44 28-Jul-16 10-Sep-16 85

XAC03-133ZZG10 Drawing Review and Comments for Notice To Fabr icate (NTF) 44 28-Jul-16 10-Sep-16 85

XAC03-133ZZG30 Factory Test 0 10-Sep-16 85

03PMS-BL00.1.3.3.ZZ.H CCCW Heat Exchanger 134 05-Aug-16 16-Dec-16 83

XAC03-133ZZH10 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 05-Aug-16 30-Sep-16 160

XAC03-133ZZH30 Factory Test 0 16-Dec-16 83

03PMS-BL00.1.3.3.ZZ.I Feed Water Heat Exchanger 186 07-Jun-16 09-Dec-16 150

XAC03-133ZZI10 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 07-Jun-16 02-Aug-16 279

XAC03-133ZZI30 Factory Test 0 09-Dec-16 150

03PMS-BL00.1.3.3.ZZ.J STG Overhead Crane 155 07-Aug-16 08-Jan-17 38

XAC03-133ZZJ10 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 07-Aug-16 02-Oct-16 136

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:5 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-133ZZJ30 Factory Test 0 08-Jan-17 38

03PMS-BL00.1.3.3.ZZ.K Condenser Ball Cleaning 131 06-Aug-16 14-Dec-16 82

XAC03-133ZZK10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 06-Aug-16 10-Nov-16 116

XAC03-133ZZK30 Factory Test 0 14-Dec-16 82

03PMS-BL00.1.3.3.ZZ.L HVAC 255 29-Feb-16 09-Nov-16 99

XAC03-133ZZL10 Drawing Review and Comments for Notice To Fabr icate (NTF) 153 29-Feb-16 30-Jul-16 201

XAC03-133ZZL30 Factory Test 0 09-Nov-16 99

03PMS-BL00.1.3.3.ZZ.M Fire Fighting 164 29-Feb-16 10-Aug-16 164

XAC03-133ZZM10 Drawing Review and Comments for Notice To Fabr icate (NTF) 164 29-Feb-16 10-Aug-16 164

XAC03-133ZZM30 Factory Test 0 10-Aug-16 164

03PMS-BL00.1.3.4 Piping Detail Design 615 05-Jan-16 10-Sep-17 144

03PMS-BL00.1.3.4.01 De
Design Input Review 110 08-Jan-16 26-Apr-16 646

XAC03-13401000 Design Input Review 110 08-Jan-16 26-Apr-16 646

03PMS-BL00.1.3.4.02 De
Design Calculation 330 22-Apr-16 17-Mar-17 321

XAC03-13402000 Design Calculation 330 22-Apr-16 17-Mar-17 321

03PMS-BL00.1.3.4.03 Pip
Piping Arrangement 120 16-Jul-16 12-Nov-16 446

XAC03-13403000 Piping Arrangement 120 16-Jul-16 12-Nov-16 446

03PMS-BL00.1.3.4.04 BQ and Specification (RFQ) 566 05-Jan-16 23-Jul-17 123

03PMS-BL00.1.3.4.04.A CW Piping Material 7 16-May-16 22-May-16 81

XAC03-13404A00 BQ and Specification (RFQ) - MCW Piping 7 16-May-16 22-May-16 81

03PMS-BL00.1.3.4.04.C BOP Piping Material (Bear) 7 18-Mar-16 24-Mar-16 234

XAC03-13404C10 BQ and Specification (RFQ) - Underground Piping Materials (Stainless) 7 18-Mar-16 24-Mar-16 234

XAC03-13404C20 BQ and Specification (RFQ) - Underground Piping Materials (PVC&ABS) 7 18-Mar-16 24-Mar-16 234

03PMS-BL00.1.3.4.04.D Shop Fabrication Piping 100 07-May-16 14-Aug-16 117

XAC03-13404D20 BQ and Specification (RFQ) - BOP Piping Materials Large Bore (Alloy) 7 07-May-16 13-May-16 72

XAC03-13404D10 BQ and Specification (RFQ) - BOP Piping Materials Large Bore (Carbon & Stainless) 7 07-May-16 13-May-16 103

XAC03-13404D30 BQ and Specification (RFQ) - Shop Fabrication Piping - BOP Piping Materials Small 7 15-Jun-16 21-Jun-16 115
Bore (Galvanized Materials)
XAC03-13404D50 BQ and Specification (RFQ) - Shop Fabrication Piping - BOP Piping Materials Small 7 29-Jul-16 04-Aug-16 69
Bore (Alloy Materials)
XAC03-13404D40 BQ and Specification (RFQ) - Shop Fabrication Piping - BOP Piping Materials Small 7 08-Aug-16 14-Aug-16 117
Bore (Carbon & Stainless Materials)
03PMS-BL00.1.3.4.04.E Valve 471 05-Jan-16 19-Apr-17 218

XAC03-13404E40 BQ and Specification (RFQ) - Valve - High Pressure Valve 7 05-Jan-16 11-Jan-16 86

XAC03-13404E60 BQ and Specification (RFQ) - Valve - MCW and Non Return Butterfly Valve 7 27-Feb-16 04-Mar-16 94

XAC03-13404E70 BQ and Specification (RFQ) - Valve - General Butterfly Valve 7 10-Mar-16 16-Mar-16 202

XAC03-13404E30 BQ and Specification (RFQ) - Valve - Motor Valve 7 01-Apr-16 07-Apr-16 19

XAC03-13404E10 BQ and Specification (RFQ) - Valve - General Valve 7 10-Apr-16 16-Apr-16 72

XAC03-13404E50 BQ and Specification (RFQ) - Valve - Alloy Valve 7 23-Apr-16 29-Apr-16 19

XAC03-13404E20 BQ and Specification (RFQ) - Valve - Ball Valve 7 08-May-16 14-May-16 46

XAC03-13404E90 BQ and Specification (RFQ) - Valve - Auto Vent Valve 7 08-May-16 14-May-16 116

XAC03-13404E80 BQ and Specification (RFQ) - Valve - Temporary Valve for Steam Blow 7 13-Apr-17 19-Apr-17 218

03PMS-BL00.1.3.4.04.F Specialty Product 339 10-Apr-16 14-Mar-17 221

XAC03-13404F20 BQ and Specification (RFQ) - Strainer 7 10-Apr-16 16-Apr-16 74

XAC03-13404F10 BQ and Specification (RFQ) - Expansion & Flexible Joint 7 02-Jul-16 08-Jul-16 74

XAC03-13404F30 BQ and Specification (RFQ) - Drain Trap 7 17-Jul-16 23-Jul-16 18

XAC03-13404F40 BQ and Specification (RFQ) - Silencer 7 17-Jul-16 23-Jul-16 18

XAC03-13404F50 BQ and Specification (RFQ) - Tar get Plate for Steam Blow 7 08-Mar-17 14-Mar-17 221

03PMS-BL00.1.3.4.04.G Piping Support 108 16-Sep-16 01-Jan-17 6

XAC03-13404G30 BQ and Specification (RFQ) - Structural Beam & Plate (2nd Order) 7 16-Sep-16 22-Sep-16 90

XAC03-13404G20 BQ and Specification (RFQ) - Pipe Chair 7 28-Oct-16 03-Nov-16 21

XAC03-13404G10 BQ and Specification (RFQ) - Spring hanger 7 31-Oct-16 06-Nov-16 6

XAC03-13404G40 BQ and Specification (RFQ) - Structural Beam & Plate (3rd Order) 7 26-Dec-16 01-Jan-17 6

03PMS-BL00.1.3.4.04.H Platform for Valve 77 25-Oct-16 09-Jan-17 308

XAC03-13404H10 BQ and Specification (RFQ) - Platform for Valve - HRSG Side Pipe Rack 7 25-Oct-16 31-Oct-16 52

XAC03-13404H30 BQ and Specification (RFQ) - Platform for Valve - STG Side Pipe Rack 7 25-Oct-16 31-Oct-16 150

XAC03-13404H40 BQ and Specification (RFQ) - Platform for Valve - GTG Side Pipe Rack 7 02-Dec-16 08-Dec-16 52

XAC03-13404H20 BQ and Specification (RFQ) - Platform for Valve - Deaerator Tower Valve 7 03-Jan-17 09-Jan-17 308
OperationStage
03PMS-BL00.1.3.4.04.I Insulation 7 30-Jan-17 05-Feb-17 237

XAC03-13404I00 BQ and Specification (RFQ) - Insulation 7 30-Jan-17 05-Feb-17 237

03PMS-BL00.1.3.4.04.J Consumable Material 105 14-Dec-16 28-Mar-17 101

XAC03-13404J10 BQ and Specification (RFQ) - Consumable Materials - Paint for Support structure 7 14-Dec-16 20-Dec-16 31

XAC03-13404J20 BQ and Specification (RFQ) - Consumable Materials - Paint for Piping 7 22-Mar-17 28-Mar-17 101

03PMS-BL00.1.3.4.04.K Miscellaneous Material 332 26-Aug-16 23-Jul-17 83

XAC03-13404K60 BQ and Specification (RFQ) - Bolt, Nut and Gasket 7 26-Aug-16 01-Sep-16 90

XAC03-13404K10 BQ and Specification (RFQ) - Shop Fabrication Piping - Orifice 7 30-Sep-16 06-Oct-16 90

XAC03-13404K30 BQ and Specification (RFQ) - Shop Fabrication Piping - Fuel Gas Condensate Tank 7 28-Oct-16 03-Nov-16 47

XAC03-13404K20 BQ and Specification (RFQ) - Shop Fabrication Piping - Funnel 7 08-Dec-16 14-Dec-16 304

XAC03-13404K50 BQ and Specification (RFQ) - Shop Fabrication Piping - CCCW Head Pipe / CCCW 7 08-Dec-16 14-Dec-16 304
Chemical Pot
XAC03-13404K40 BQ and Specification (RFQ) - Shop Fabrication - Drain Flash Pipe 7 18-Dec-16 24-Dec-16 159

XAC03-13404K80 BQ and Specification (RFQ) - Name Tag Plate for Replace 7 19-Jun-17 25-Jun-17 56

XAC03-13404K70 BQ and Specification (RFQ) - Shop Fabrication Piping - Water seal for Buili ng 7 17-Jul-17 23-Jul-17 63
penetration Rain Cover
03PMS-BL00.1.3.4.04.L Steam Blow Piping 7 13-Apr-17 19-Apr-17 202

XAC03-13404L00 BQ and Specification (RFQ) - Steam Blow Piping 7 13-Apr-17 19-Apr-17 202

03PMS-BL00.1.3.4.04.M Shop Fabricated Piping 7 18-May-16 24-May-16 174

XAC03-13404M00 BQ and Specification (RFQ) - BOP Yard Pipe Prefabrication 7 18-May-16 24-May-16 174

03PMS-BL00.1.3.4.05 Dr
Drawing 312 05-Jul-16 12-May-17 265

XAC03-13405100 Drawing Preparation for Shop MCW Piping 42 05-Jul-16* 15-Aug-16 81

XAC03-13405000 Drawing 260 26-Aug-16 12-May-17 265

XAC03-13405200 Drawing Preparation for Shop Raw & CT Make Up System (1st) 29 23-Sep-16* 21-Oct-16 90

XAC03-13405300 Drawing Preparation for Shop Condensate Water,MCW Blow & SW System (2nd) 29 21-Oct-16* 18-Nov-16 81

XAC03-13405400 Drawing Preparation for Shop DM Water, IA/SA Air (3rd) 29 18-Nov-16* 16-Dec-16 113

XAC03-13405500 Drawing Preparation for Shop Ext. Steam, HP/LP Feed & Fuel Gas (4th) 28 16-Dec-16* 12-Jan-17 47

XAC03-13405600 Drawing Preparation for Shop HP/LP Steam (5th) 28 12-Jan-17* 08-Feb-17 58

XAC03-13405700 Drawing Preparation for Shop CCCW, Condensate Drain & Vacuum System (6th) 28 08-Feb-17* 07-Mar-17 175

03PMS-BL00.1.3.4.06 Pr
Procurement Support 608 12-Jan-16 10-Sep-17 144

03PMS-BL00.1.3.4.06.A CW Piping Materials 236 23-May-16 13-Jan-17 81

XAC03-13406A10 Technical Clarification - MCW Material Piping 43 23-May-16 04-Jul-16 81

XAC03-13406A20 Procurement & Manufacturing - MCW Material Piping 151 16-Aug-16 13-Jan-17 81

03PMS-BL00.1.3.4.06.C BOP Piping Materials (Bear) 70 25-Mar-16 02-Jun-16 234

XAC03-13406C10 Technical Clarification - Underground Piping Materials (Stainless) 29 25-Mar-16 22-Apr-16 234

XAC03-13406C20 Technical Clarification - Underground Piping Materials (PVC&ABS) 29 25-Mar-16 22-Apr-16 234

XAC03-13406C30 Procurement & Manufacturing - Underground Piping Materials (Stainless) 41 23-Apr-16 02-Jun-16 234

XAC03-13406C40 Procurement & Manufacturing - Underground Piping Materials (PVC / ABS) 41 23-Apr-16 02-Jun-16 234

03PMS-BL00.1.3.4.06.D Sho Fabrication Piping 252 14-May-16 20-Jan-17 85

XAC03-13406D20 Technical Clarification - BOP Pipin g Materials Large Bore (Alloy) 13 14-May-16 26-May-16 72

XAC03-13406D10 Technical Clarification - BOP Pipin g Materials Large Bore(Carbon & Stainles s) 37 14-May-16 19-Jun-16 103

XAC03-13406D70 Procurement & Manufacturing - Large Bore (Alloy) 210 27-May-16 22-Dec-16 72

XAC03-13406D60 Procurement & Manufacturing - Large Bore (Carbon & Stainless) 74 20-Jun-16 01-Sep-16 103

XAC03-13406D30 Technical Clarification - BOP Yard Piping Small Bore (Galvanized Materials) 30 22-Jun-16 21-Jul-16 115

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:6 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-13406D80 Procurement & Manufacturing - BOP Yard Piping Procurement - Small Bore (Galvanized 85 03-Aug-16 26-Oct-16 103
Materials)
XAC03-13406D50 Technical Clarification - BOP Yard Piping Small Bore (Alloy Materials) 43 05-Aug-16 16-Sep-16 69

XAC03-13406D40 Technical Clarification - BOP Yard Piping Small Bore (Car bon & Stainless Materials) 43 15-Aug-16 26-Sep-16 117

XAC03-13406DA0 Procurement & Manufacturing - BOP Yard Piping Procurement - Small Bore (Alloy 126 17-Sep-16 20-Jan-17 69
Materials)
XAC03-13406D90 Procurement & Manufacturing - Small Bore (Carbon & Stainless Materials) 84 27-Sep-16 19-Dec-16 117

03PMS-BL00.1.3.4.06.E Valves 497 12-Jan-16 22-May-17 218

XAC03-13406E40 Technical Clarification - High Pressure Valve Valve 31 12-Jan-16 11-Feb-16 86

XAC03-13406ED0 Procurement & Manufacturing - High Pressure Valve 327 12-Feb-16 03-Jan-17 86

XAC03-13406E60 Technical Clarification - MCW and Non Return Butterfly Valve 44 05-Mar-16 17-Apr-16 94

XAC03-13406E70 Technical Clarification - General Butterfly Valve 45 17-Mar-16 30-Apr-16 202

XAC03-13406E30 Technical Clarification - Motor Valve 42 08-Apr-16 19-May-16 19

XAC03-13406E10 Technical Clarification - General Valve 42 17-Apr-16 28-May-16 72

XAC03-13406EF0 Procurement & Manufacturing - MCW and Non Return Butterfly Valve 221 18-Apr-16 24-Nov-16 94

XAC03-13406E50 Technical Clarification - Alloy Valve 43 30-Apr-16 11-Jun-16 19

XAC03-13406EG0 Procurement & Manufacturing - General Butterfly Valve 5 01-May-16 05-May-16 254

XAC03-13406E20 Technical Clarification - Ball Valve 42 15-May-16 25-Jun-16 46

XAC03-13406E90 Technical Clarification - Auto Vent Valve 44 15-May-16 27-Jun-16 116

XAC03-13406EC0 Procurement & Manufacturing - Motor Valve 244 20-May-16 18-Jan-17 19

XAC03-13406EA0 Procurement & Manufacturing - General Valve 180 29-May-16 24-Nov-16 72

XAC03-13406EE0 Procurement & Manufacturing - High Temp (Alloy Mtrls.) Valve 207 26-Jun-16 18-Jan-17 19

XAC03-13406EB0 Procurement & Manufacturing - Ball Valve 180 27-Jun-16 23-Dec-16 45

XAC03-13406EI0 Procurement & Manufacturing - Auto Vent and Hoot Valve 188 28-Jun-16 01-Jan-17 116

XAC03-13406E80 Technical Clarification - Temporary valve for Steam Blow 19 20-Apr-17 08-May-17 218

XAC03-13406EH0 Procurement & Manufacturing - Temporary Valve, Pipe & Fitting for Steam Blow 14 09-May-17 22-May-17 218

03PMS-BL00.1.3.4.06.F Special Product 398 17-Apr-16 19-May-17 221

XAC03-13406F20 Technical Clarification -Special Product - Strainer 42 17-Apr-16 28-May-16 74

XAC03-13406F70 Procurement & Manufacturing - Strainer 180 29-May-16 24-Nov-16 74

XAC03-13406F10 Technical Clarification -Special Product - Expansion & Flexible Joint 44 09-Jul-16 21-Aug-16 74

XAC03-13406F30 Technical Clarification -Special Product - Drain Trap 43 24-Jul-16 04-Sep-16 18

XAC03-13406F40 Technical Clarification - Special Product - Silencer 43 24-Jul-16 04-Sep-16 18

XAC03-13406F60 Procurement & Manufacturing - Expansion & Flexible Joint 81 05-Sep-16 24-Nov-16 74

XAC03-13406F80 Procurement & Manufacturing - Drain Trap 137 05-Sep-16 19-Jan-17 18

XAC03-13406F90 Procurement & Manufacturing - Silencer 137 05-Sep-16 19-Jan-17 18

XAC03-13406F50 Technical Clarification -Special Product - Target Plate for Steam Blow 16 15-Mar-17 30-Mar-17 221

XAC03-13406FA0 Procurement & Manufacturing - Target Plate for Steam Blow 50 31-Mar-17 19-May-17 221

03PMS-BL00.1.3.4.06.G Piping Support 168 23-Sep-16 09-Mar-17 6

XAC03-13406G30 Technical Clarification - Structural Beam & Plate (2nd Order) 43 23-Sep-16 04-Nov-16 90

XAC03-13406G20 Technical Clarification - Pipe Chair 29 04-Nov-16 02-Dec-16 21

XAC03-13406G70 Procurement & Manufacturing - Structural Beam & Plate (2nd Order) 41 05-Nov-16 15-Dec-16 90

XAC03-13406G10 Technical Clarification - Spring Hanger 43 07-Nov-16 19-Dec-16 6

XAC03-13406G60 Procurement & Manufacturing - Pipe Chair 82 03-Dec-16 22-Feb-17 21

XAC03-13406G50 Procurement & Manufacturing - Spring hanger 80 20-Dec-16 09-Mar-17 6

XAC03-13406G40 Technical Clarification - Structural Beam & Plate (3rd Order) 29 02-Jan-17 30-Jan-17 6

XAC03-13406G80 Procurement & Manufacturing - Structural Beam & Plate (3rd Order) 38 31-Jan-17 09-Mar-17 6

03PMS-BL00.1.3.4.06.H Platform for Valve 160 01-Nov-16 09-Apr-17 298

XAC03-13406H10 Technical Clarification - Platform for Valve - HRSG Side Pipe Rack 25 01-Nov-16 25-Nov-16 52

XAC03-13406H30 Technical Clarification - Platform for Valve - STG Side Pipe Rack 25 01-Nov-16 25-Nov-16 150

XAC03-13406H50 Procurement & Manufacturing - Platform for Valve - HRSG Side Pipe Rack 79 26-Nov-16 12-Feb-17 52

XAC03-13406H40 Technical Clarification - Platform for Valve - GTG Side Pipe Rack 15 09-Dec-16 23-Dec-16 52

XAC03-13406H80 Procurement & Manufacturing - Platform for Valve - GTG Side Pipe Rack 67 24-Dec-16 28-Feb-17 52

XAC03-13406H20 Technical Clarification - Platform for Valve - Deaerator Tower Valve OperationStage 17 10-Jan-17 26-Jan-17 308

XAC03-13406H60 Procurement & Manufacturing - Platform for Valve - Deaerator Tower Valve 63 27-Jan-17 30-Mar-17 308
OperationStage
XAC03-13406H70 Procurement & Manufacturing - Platform for Valve - STG Side Pipe Rack 41 28-Feb-17 09-Apr-17 56

03PMS-BL00.1.3.4.06.I Insulation 124 06-Feb-17 09-Jun-17 237

XAC03-13406I00 Technical Clarification - Insulation 40 06-Feb-17 17-Mar-17 237

XAC03-214090-503 Procurement & Manufacturing - Insulation 77 25-Mar-17 09-Jun-17 237

03PMS-BL00.1.3.4.06.J Consumable Materials 151 21-Dec-16 20-May-17 101

XAC03-13406J10 Technical Clarification - Consumable Materials - Paint for Support structure 21 21-Dec-16 10-Jan-17 31

XAC03-13406J30 Procurement & Manufacturing - Consumable Materials - Paint for Support structure 33 11-Jan-17 12-Feb-17 31

XAC03-13406J12 Technical Clarification - Consumable Materials - Paint for Piping 14 29-Mar-17 11-Apr-17 101

XAC03-13406J40 Procurement & Manufacturing - Consumable Materials - Paint for Piping 39 12-Apr-17 20-May-17 101

03PMS-BL00.1.3.4.06.K Miscellaneous Materials 374 02-Sep-16 10-Sep-17 144

XAC03-13406K60 Technical Clarification - Bolt, Nut and Gasket 43 02-Sep-16 14-Oct-16 90

XAC03-13406K10 Technical Clarification - Orifice 29 07-Oct-16 04-Nov-16 90

XAC03-13406KE0 Procurement & Manufacturing - Bolt Nut and Gasket 62 15-Oct-16 15-Dec-16 90

XAC03-13406K30 Technical Clarification - Fuel Gas Condensate Tank 29 04-Nov-16 02-Dec-16 47

XAC03-13406K90 Procurement & Manufacturing - Orifice 41 05-Nov-16 15-Dec-16 90

XAC03-13406KB0 Procurement & Manufacturing - Fuel Gas Condensate Tank 82 03-Dec-16 22-Feb-17 47

XAC03-13406K20 Technical Clarification - Funnel 30 15-Dec-16 13-Jan-17 304

XAC03-13406K50 Technical Clarification - CCCW Head Pipe / CCCW Chemical Pot 28 15-Dec-16 11-Jan-17 304

XAC03-13406K40 Technical Clarification - Drain Flash Pipe 33 25-Dec-16 26-Jan-17 159

XAC03-13406KD0 Procurement & Manufacturing - CCCW Head Pipe / CCCW Chemical Pot 82 12-Jan-17 03-Apr-17 304

XAC03-13406KA0 Procurement & Manufacturing - Funnel 80 14-Jan-17 03-Apr-17 304

XAC03-13406KC0 Procurement & Manufacturing - Drain Flash Pipe 82 27-Jan-17 18-Apr-17 159

XAC03-13406K70 Technical Clarification - Water seal for Builing penetration Rain Cover 29 25-Jun-17 24-Jul-17 63

XAC03-13406K80 Technical Clarification - Name Tag Plate for Replace 20 26-Jun-17 15-Jul-17 56

XAC03-13406KG0 Procurement & Manufacturing - Name Tag Plate for Replace 36 16-Jul-17 20-Aug-17 56

XAC03-13406KF0 Procurement & Manufacturing - Water seal for Buili ng penetration Rain Cover 21 21-Aug-17 10-Sep-17 35

03PMS-BL00.1.3.4.06.L Steam Blow Piping 70 20-Apr-17 28-Jun-17 218

XAC03-13406L10 Technical Clarification - Steam Blow Piping 29 20-Apr-17 18-May-17 202

XAC03-13406L20 Procurement & Manufacturing - Support material / Steam Blow Piping 41 19-May-17 28-Jun-17 218

03PMS-BL00.1.3.4.06.M Shop Prefabricated Piping 313 25-May-16 02-Apr-17 175

XAC03-13406M10 Technical Clarification - BOP Yard Pipin g 37 25-May-16 30-Jun-16 174

XAC03-13406M20 Procurement & Pre-fabrication Raw & CT Make Up System (1st) 55 22-Oct-16 15-Dec-16 90

XAC03-13406M30 Procurement & Pre-fabrication Condensate Water,MCW Blow & SW System (2nd) 56 19-Nov-16 13-Jan-17 81

XAC03-13406M40 Procurement & Pre-fabrication DM Water, IA/SA Air (3rd) 51 17-Dec-16 05-Feb-17 113

XAC03-13406M05 Procurement & Pre-fabrication Ext. Steam, HP/LP Feed & Fuel Gas (4th) 41 13-Jan-17 22-Feb-17 47

XAC03-13406M60 Procurement & Pre-fabrication HP/LP Steam (5th) 29 09-Feb-17 09-Mar-17 58

XAC03-13406M70 Procurement & Pre-fabrication CCCW, Condensate Drain & Vacuum System (6th) 26 08-Mar-17 02-Apr-17 175

03PMS-BL00.1.3.4.07 Er
Erection Support 148 16-Dec-16 12-May-17 265

XAC03-13407000 Erection Support 148 16-Dec-16 12-May-17 265

03PMS-BL00.1.3.5 C&I Detail


De Engineering 412 02-Mar-16 17-Apr-17 265

03PMS-BL00.1.3.5.01 DCS
DC 298 02-Mar-16 24-Dec-16 52

XAC03-13501100 Drawing Review and Comments for Notice To Fabr icate (NTF) 222 02-Mar-16 09-Oct-16 52

XAC03-13501300 Factory Test 0 24-Dec-16 52

03PMS-BL00.1.3.5.02 Co
Continuous Emission Monitoring System 244 17-Aug-16 17-Apr-17 4

XAC03-13502100 Drawing Review and Comments for Notice To Fabr icate (NTF) 92 17-Aug-16 16-Nov-16 156

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:7 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-13502300 Factory Test 0 17-Apr-17 4

03PMS-BL00.1.3.5.03 Steam
St and Water Analysis System 129 07-Oct-16 12-Feb-17 153

XAC03-13503100 Drawing Review and Comments for Notice To Fabr icate (NTF) 58 07-Oct-16 03-Dec-16 224

XAC03-13503300 Factory Test 0 12-Feb-17 153

03PMS-BL00.1.3.5.04 Pla
Plant Communication System, CCTV & Clock 136 29-Nov-16 13-Apr-17 25

XAC03-13504100 Drawing Review and Comments for Notice To Fabr icate (NTF) 81 29-Nov-16 17-Feb-17 80

XAC03-13504300 Factory Test 0 13-Apr-17 25

03PMS-BL00.1.3.5.05 Ch
Chemical Laboratory 142 19-Nov-16 09-Apr-17 273

XAC03-13505100 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 19-Nov-16 14-Jan-17 358

XAC03-13505300 Factory Test 0 09-Apr-17 273

03PMS-BL00.1.3.5.06 Primary
Pr Emergency Saving System 106 26-Oct-16 08-Feb-17 89

XAC03-13506100 Drawing Review and Comments for Notice To Fabr icate (NTF) 66 26-Oct-16 30-Dec-16 129

XAC03-13506300 Factory Test 0 08-Feb-17 89

03PMS-BL00.1.3.5.07 C&
C&I Bulk Material 14 29-Nov-16 12-Dec-16 78

XAC03-13507100 Drawing Review and Comments for Notice To Fabr icate (NTF) 1 29-Nov-16 29-Nov-16 91

XAC03-13507300 Factory Test 0 12-Dec-16 78

03PMS-BL00.1.3.5.08 Turbine
Tu Bypass Control 206 16-Jun-16 07-Jan-17 85

XAC03-135081B0 Drawing Review and Comments for Notice To Fabr icate (NTF) - Control 126 16-Jun-16 19-Oct-16 139

XAC03-135081A0 Drawing Review and Comments for Notice To Fabr icate (NTF) - Turbine Bypass 180 17-Jun-16 13-Dec-16 110

XAC03-135083B0 Factory Test - C ontrol 0 13-Nov-16 114

XAC03-135083A0 Factory Test - Turbine Bypass 0 07-Jan-17 85

03PMS-BL00.1.3.5.ZZ Others
O 21 02-Dec-16 22-Dec-16 89

XAC03-135ZZ100 Drawing Review and Comments for Notice To Fabr icate (NTF) - Cabling Bulk For C&I 10 02-Dec-16 11-Dec-16 100
Cable
XAC03-135ZZ300 Factory Test - C abling Bulk For C&I Cable 0 22-Dec-16 89

03PMS-BL00.1.3.6 Electrical
Electri system Detail Engineering 360 18-Feb-16 11-Feb-17 80

03PMS-BL00.1.3.6.01 Ge
Generator Step Up Transformer 291 23-Mar-16 07-Jan-17 9

XAC03-13601100 Drawing Review and Comments for Notice To Fabr icate (NTF) 125 23-Mar-16 25-Jul-16 175

XAC03-13601300 Factory Test 0 07-Jan-17 9

03PMS-BL00.1.3.6.02 Un
Unit Aux Transformer with remote OLTC panel 360 18-Feb-16 11-Feb-17 54

XAC03-13602100 Drawing Review and Comments for Notice To Fabr icate (NTF) 158 18-Feb-16 24-Jul-16 256

XAC03-13602300 Factory Test 0 11-Feb-17 54

03PMS-BL00.1.3.6.05 HV
HV/MV SWGR 250 30-Mar-16 04-Dec-16 116

XAC03-13605100 Drawing Review and Comments for Notice To Fabr icate (NTF) 161 30-Mar-16 06-Sep-16 205

XAC03-13605300 Factory Test 0 04-Dec-16 116

03PMS-BL00.1.3.6.06 Auxiliary
Au Transformer 242 08-May-16 04-Jan-17 93

XAC03-13606100 Drawing Review and Comments for Notice To Fabr icate (NTF) 102 08-May-16 17-Aug-16 233

XAC03-13606300 Factory Test 0 04-Jan-17 93

03PMS-BL00.1.3.6.07 LV SWGR / MCC / DP 194 08-Jun-16 18-Dec-16 118

XAC03-136071B0 Drawing Review and Comments for Notice To Fabr icate (NTF) - MCC /DB 156 08-Jun-16 10-Nov-16 156

XAC03-136071A0 Drawing Review and Comments for Notice To Fabr icate (NTF) - LV SWGR 100 03-Aug-16 10-Nov-16 147

XAC03-136073A0 Factory Test - LV SWGR 0 11-Dec-16 116

XAC03-136073B0 Factory Test - MCC/DB 0 18-Dec-16 118

03PMS-BL00.1.3.6.08 DC System / UPS 188 30-May-16 03-Dec-16 14

XAC03-13608100 Drawing Review and Comments for Notice To Fabr icate (NTF) 127 30-May-16 03-Oct-16 75

XAC03-13608300 Factory Test 0 03-Dec-16 14

03PMS-BL00.1.3.6.09 Em
Emergency Diesel Engine Generator 161 16-Jul-16 23-Dec-16 130

XAC03-13609100 Drawing Review and Comments for Notice To Fabr icate (NTF) 105 16-Jul-16 28-Oct-16 186

XAC03-13609300 Factory Test 0 23-Dec-16 130

03PMS-BL00.1.3.7 Electri
Electrical Bulk Material Detail Design 190 09-Apr-16 15-Oct-16 409

03PMS-BL00.1.3.7.05 BQ and Specification (RFQ) 190 09-Apr-16 15-Oct-16 409

03PMS-BL00.1.3.7.05.1 BQ List and Technical Specification for RFQ 67 09-Apr-16 14-Jun-16 183

XAC03-13705170 BQ and Specification (RFQ) - Cable Tray & Accessories 6 09-Apr-16 14-Apr-16 148

XAC03-13705180 BQ and Specification (RFQ) - Cable Tray Support 6 09-Apr-16 14-Apr-16 148

XAC03-13705190 BQ and Specification (RFQ) - Secondary Raceway 5 10-Apr-16 14-Apr-16 148

XAC03-137051C0 BQ and Specification (RFQ) - Grounding Material (Underground) 4 11-Apr-16 14-Apr-16 162

XAC03-137051D0 BQ and Specification (RFQ) - Grounding Material (Above Ground) 4 11-Apr-16 14-Apr-16 162

XAC03-137051E0 BQ and Specification (RFQ) - Lightning Protection Material 4 11-Apr-16 14-Apr-16 162

XAC03-13705110 BQ and Specification (RFQ) - Power Cable 4 11-Jun-16 14-Jun-16 162

XAC03-13705120 BQ and Specification (RFQ) - Control Cable 4 11-Jun-16 14-Jun-16 162

XAC03-13705130 BQ and Specification (RFQ) - Instrumentation Cable 4 11-Jun-16 14-Jun-16 162

XAC03-137051H0 BQ and Specification (RFQ) - Fire Sealing Material 4 11-Jun-16 14-Jun-16 183

03PMS-BL00.1.3.7.05.2 Manufacturer's Specification & Technical Data 154 15-May-16 15-Oct-16 409

XAC03-13705260 Manufacturer's Specification & Technical Data - Grounding System Material 20 15-May-16 03-Jun-16 352

XAC03-13705270 Manufacturer's Specification & Technical Data - Lightning System Material 60 15-May-16 13-Jul-16 198

XAC03-13705290 Manufacturer's Specification & Technical Data - Lighting & Small Power Supply System 30 15-May-16 13-Jun-16 533
Material
XAC03-13705220 Manufacturer's Specification & Technical Data - Cable Tray & Accessories 30 02-Jun-16 01-Jul-16 148

XAC03-13705240 Manufacturer's Specification & Technical Data - Secondary Rac eway Mater ial 30 02-Jun-16 01-Jul-16 148

XAC03-137052L0 Manufacturer's Specification & Technical Data - Fire Sealing Material 30 15-Jul-16 13-Aug-16 183

XAC03-13705210 Manufacturer's Specification & Technical Data - Power, Control & Instrument Cables 30 16-Sep-16 15-Oct-16 162

03PMS-BL00.1.3.7.06 Pr
Procurement Support 154 15-Apr-16 15-Sep-16 308

XAC03-13706700 Technical Clarification & Evaluation for Cable Tray & Accessorie s 78 15-Apr-16 01-Jul-16 148

XAC03-13706800 Technical Clarification & Evaluation for Cable Tray Support 78 15-Apr-16 01-Jul-16 148

XAC03-13706900 Technical Clarification & Evaluation for Secondary Raceway 78 15-Apr-16 01-Jul-16 148

XAC03-13706C00 Technical Clarification & Evaluation for Grounding Material (Underground) 30 15-Apr-16 14-May-16 262

XAC03-13706D00 Technical Clarification & Evaluation for Grounding Material (Above Ground) 30 15-Apr-16 14-May-16 262

XAC03-13706E00 Technical Clarification & Evaluation for Lightning Protection Material 30 15-Apr-16 14-May-16 196

XAC03-13706F00 Technical Clarification & Evaluation for Lighting & Small Power Supply System 30 15-Apr-16 14-May-16 432

XAC03-13706100 Technical Clarification & Evaluation for Power Cable 93 15-Jun-16 15-Sep-16 162

XAC03-13706200 Technical Clarification & Evaluation for Control Cable 93 15-Jun-16 15-Sep-16 162

XAC03-13706300 Technical Clarification & Evaluation for Instrumentation Cable 93 15-Jun-16 15-Sep-16 162

XAC03-13706H00 Technical Clarification & Evaluation for Fire Sealing Material 30 15-Jun-16 14-Jul-16 183

03PMS-BL00.1.3.8 Switchyard
Switch Detail Engineering 204 26-Mar-16 15-Oct-16 91

03PMS-BL00.1.3.8.06 Pr
Procurement Support 204 26-Mar-16 15-Oct-16 91

XAC03-13806000 Procurement Support 204 26-Mar-16 15-Oct-16 91

03PMS-BL00.2 PROCUREMENT
PROCUREM 649 01-Dec-15 10-Sep-17 144

03PMS-BL00.2.1 DIRECT M
MATERIALS (cost procured by ) 649 01-Dec-15 10-Sep-17 144

03PMS-BL00.2.1.1 Arrangement
Arrang 390 08-Jan-16 31-Jan-17 192

03PMS-BL00.2.1.1.01 Fir
Fire Fighting system 332 08-Jan-16 04-Dec-16 102

XAC03-211010-501 Issue RFQ 0 08-Jan-16* 164

XAC03-211010-502 Issue PO 0 28-Feb-16* 164

XAC03-211010-503 NTF : Notice to Fabricate 0 10-Aug-16 164

XAC03-211010-504 FAT : Factory Acceptance Test 0 10-Aug-16 164

XAC03-211010-508 FOB or ETD 0 04-Sep-16 164

XAC03-211010-510A MHO : Ring Main & Others 0 04-Sep-16 164

XAC03-211010-510B MHO : FF Pumps 0 04-Dec-16 102

03PMS-BL00.2.1.1.02 HVAC
HV 390 08-Jan-16 31-Jan-17 192

XAC03-211020-501 Issue RFQ 0 08-Jan-16* 201

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:8 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-211020-502 Issue PO 0 28-Feb-16* 201

XAC03-211020-503 NTF : Notice to Fabricate 0 30-Jul-16 201

XAC03-211020-504 FAT : Factory Acceptance Test 0 09-Nov-16 99

XAC03-211020-508 FOB or ETD 0 04-Dec-16 99

XAC03-211020-510A MHO : WTP Building 0 04-Dec-16 142

XAC03-211020-510B MHO : E&C Building 0 29-Dec-16 74

XAC03-211020-510C MHO : ST Bldg 0 31-Jan-17 192

03PMS-BL00.2.1.3 Mechanical
Mecha Equipment 530 01-Dec-15 14-May-17 117

03PMS-BL00.2.1.3.01 Gas
Ga turbine & Generator #31&32 442 01-Dec-15 15-Feb-17 37

XAC03-213010-501 Issue RFQ 0 01-Dec-15 0

XAC03-213010-502 Issue PO 0 02-Dec-15* 0

XAC03-213010-510 MHO : Lot-1 Embedded Materials - GTG 31&32 0 02-Jun-16 234

XAC03-213010-503 NTF : Notice to Fabricate Issue 0 05-Aug-16 0

XAC03-213010-504A FAT : Factory Acceptance Test - GTG 31 0 08-Dec-16 0

XAC03-213010-504B FAT : Factory Acceptance Test - GTG 32 0 15-Dec-16 40

XAC03-213010-508A FOB or ETD - GTG 31 0 23-Dec-16 0

XAC03-213010-508B FOB or ETD - GTG 32 0 30-Dec-16 40

XAC03-213010-510A MHO : Lot-2 Main Equipments - GTG 31 0 06-Feb-17 0

XAC03-213010-510B MHO : Lot-2 Main Equipments - GTG 32 0 13-Feb-17 40

XAC03-213010-510C MHO : Lot-3 Auxiliary Equipments & Accessories/Shortage Materials - GTG 31&32 0 15-Feb-17 36

XAC03-213010-510D MHO : Lot-4 Auxiliary Equipments (from China) - GTG 31&32 0 15-Feb-17 36

03PMS-BL00.2.1.3.02 HRSG
HR #31&32 446 01-Dec-15 19-Feb-17 113

XAC03-213020-501 Issue RFQ 0 01-Dec-15 0

XAC03-213020-502 Issue PO 0 01-Dec-15* 0

XAC03-213020-510 MHO : (Lot-1 Base Plate / Stack Template / Embedded Materials) 0 31-May-16 114

XAC03-213020-503 NTF : Notice to Fabricate 0 08-Sep-16 0

XAC03-213020-504 FAT : Factory Acceptance Test 0 16-Nov-16 0

XAC03-213020-508 FOB or ETD - HRSG #31&32 0 01-Dec-16 0

XAC03-213020-510A MHO : (Lot-2 Box Assembly / Module Header / Module Tubes) 0 15-Jan-17 12

XAC03-213020-510B MHO : (Lot-3 Blowdown Tank / Expansion Joint - Inlet duct / Bypass s tack Accessories 0 19-Jan-17 0
/ Diverter dumper)
XAC03-213020-510C MHO : (Lot-4 Inlet Duct / Field Connection / Bypass Stack) 0 22-Jan-17 10

XAC03-213020-510D MHO : (Lot-5 Steam Silencers) 0 31-Jan-17 132

XAC03-213020-510E MHO : (Lot-6 LP & HP Steam Drum / Platforms, Ladders, Stairs) 0 05-Feb-17 11

XAC03-213020-510F MHO : (Lot-7 Pipe & Supports) 0 05-Feb-17 14

XAC03-213020-510G MHO : (Lot-8 Main Stacks / Expansion Joint - Outlet duct) 0 09-Feb-17 20

XAC03-213020-510H MHO : (Lot-9 Valves & Instruments) 0 14-Feb-17 50

XAC03-213020-510I MHO : (Lot-10 Deaerator) 0 19-Feb-17 70

03PMS-BL00.2.1.3.03 St
Steam Turbine & Generator 530 01-Dec-15 14-May-17 21

XAC03-213030-501 Issue RFQ 0 01-Dec-15 266

XAC03-213030-502 Issue PO 0 01-Jan-16* 266

XAC03-213030-503 NTF : Notice to Fabricate 0 25-Aug-16 200

XAC03-213030-504 FAT : Factory Acceptance Test 0 13-Jan-17 59

XAC03-213030-508 FOB or ETD 0 28-Jan-17 59

XAC03-213030-510A MHO : Lot1 Embedded Materials 0 14-Mar-17 59

XAC03-213030-510B MHO : Lot2 Main Equipment 0 14-May-17 14

XAC03-213030-510C MHO : Lot-3 Auxiliary Equipments & Accessories/Shortage Materials 0 14-May-17 21

03PMS-BL00.2.1.3.07 Condenser
Co 444 14-Jan-16 02-Apr-17 54

XAC03-213070-501 Issue RFQ 0 14-Jan-16* 354

XAC03-213070-502 Issue PO 0 07-Jun-16* 209

XAC03-213070-503 NTF : Notice to Fabricate 0 31-Aug-16 208

XAC03-213070-510A MHO : Lot-1 Embedded Materials 0 18-Sep-16 250

XAC03-213070-504 FAT : Factory Acceptance Test 0 01-Feb-17 54

XAC03-213070-508 FOB or ETD 0 16-Feb-17 54

XAC03-213070-510B MHO : Lot-2 (Shell) 0 02-Apr-17 54

03PMS-BL00.2.1.3.09 Condensate
Co Extraction Pump 372 08-Jan-16 13-Jan-17 166

XAC03-213090-501 Issue RFQ 0 08-Jan-16* 209

XAC03-213090-502 Issue PO 0 19-Mar-16* 304

XAC03-213090-503 NTF : Notice to Fabricate 0 27-Jul-16 276

XAC03-213090-504 FAT : Factory Acceptance Test 0 14-Nov-16 166

XAC03-213090-508 FOB or ETD 0 29-Nov-16 166

XAC03-213090-510 MHO 0 13-Jan-17 166

03PMS-BL00.2.1.3.10 Bo
Boiler Feed Water Pump 416 08-Jan-16 27-Feb-17 86

03PMS-BL00.2.1.3.10.1 HP Boiler Feed Pump 390 08-Jan-16 31-Jan-17 113

XAC03-213101-501 Issue RFQ 0 08-Jan-16* 314

XAC03-213101-502 Issue PO 0 15-Feb-16* 327

XAC03-213101-503 NTF : Notice to Fabricate 0 29-Jul-16 239

XAC03-213101-504 FAT : Factory Acceptance Test 0 02-Dec-16 113

XAC03-213101-508 FOB or ETD 0 17-Dec-16 113

XAC03-213101-510 MHO for HP BFP 0 31-Jan-17 113

03PMS-BL00.2.1.3.10.2 LP Boiler Feed Pump 416 08-Jan-16 27-Feb-17 86

XAC03-213102-501 Issue RFQ 0 08-Jan-16* 314

XAC03-213102-502 Issue PO 0 15-Feb-16* 320

XAC03-213102-503 NTF : Notice to Fabricate 0 27-Jul-16 241

XAC03-213102-504 FAT : Factory Acceptance Test 0 29-Dec-16 86

XAC03-213102-508 FOB or ETD 0 13-Jan-17 86

XAC03-213102-510 MHO for LP BFP 0 27-Feb-17 86

03PMS-BL00.2.1.3.12 CW
CW/ACW System Equipment 404 08-Jan-16 14-Feb-17 57

03PMS-BL00.2.1.3.12.1 Main cooling water pump 337 08-Jan-16 09-Dec-16 110

XAC03-213121-501 Issue RFQ 0 08-Jan-16* 258

XAC03-213121-502 Issue PO 0 15-Feb-16* 235

XAC03-213121-503 NTF : Notice to Fabricate 0 11-Aug-16 170

XAC03-213121-504 FAT : Factory Acceptance Test 0 10-Oct-16 110

XAC03-213121-508 FOB or ETD 0 25-Oct-16 110

XAC03-213121-510 MHO lot 2 (MCW Pump) 0 09-Dec-16 110

03PMS-BL00.2.1.3.12.2 Auxiliary Cooling Water Pump 366 14-Feb-16 14-Feb-17 57

XAC03-213122-501 Issue RFQ 0 14-Feb-16 220

XAC03-213122-502 Issue PO 0 05-Jul-16* 125

XAC03-213122-503 NTF : Notice to Fabricate 0 09-Nov-16 94

XAC03-213122-504 FAT : Factory Acceptance Test 0 16-Dec-16 57

XAC03-213122-508 FOB or ETD 0 31-Dec-16 57

XAC03-213122-510 MHO for Auxiliary Water Pump 0 14-Feb-17 57

03PMS-BL00.2.1.3.13 CC
CCCW Pump 367 14-Feb-16 14-Feb-17 57

XAC03-213130-501 Issue RFQ 0 14-Feb-16* 186

XAC03-213130-502 Issue PO 0 05-Jul-16* 125

XAC03-213130-503 NTF : Notice to Fabricate 0 09-Nov-16 94

XAC03-213130-504 FAT : Factory Acceptance Test 0 16-Dec-16 57

XAC03-213130-508 FOB or ETD 0 31-Dec-16 57

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:9 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-213130-510 MHO for CCCW pump) 0 14-Feb-17 57

03PMS-BL00.2.1.3.15 Condenser
Co Vacuum Pump 447 14-Jan-16 05-Apr-17 156

XAC03-213150-501 Issue RFQ 0 14-Jan-16* 354

XAC03-213150-502 Issue PO 0 01-Mar-16* 328

XAC03-213150-503 NTF : Notice to Fabricate 0 26-Jul-16 349

XAC03-213150-504 FAT : Factory Acceptance Test 0 04-Feb-17 156

XAC03-213150-508 FOB or ETD 0 19-Feb-17 156

XAC03-213150-510 MHO for Condenser Vacuum Pump 0 05-Apr-17 156

03PMS-BL00.2.1.3.16 Ge
General Water Service Pump 364 15-Feb-16 12-Feb-17 122

03PMS-BL00.2.1.3.16.1 Raw Water Pump 325 15-Feb-16 04-Jan-17 98

XAC03-213161-501 Issue RFQ 0 15-Feb-16* 182

XAC03-213161-502 Issue PO 0 01-Apr-16* 182

XAC03-213161-503 NTF : Notice to Fabricate 0 14-Sep-16 150

XAC03-213161-504 FAT : Factory Acceptance Test 0 05-Nov-16 98

XAC03-213161-508 FOB or ETD 0 20-Nov-16 98

XAC03-213161-510 MHO for Raw Water Pump 0 04-Jan-17 98

03PMS-BL00.2.1.3.16.2 CT Make Up Pumps 333 15-Feb-16 12-Jan-17 116

XAC03-213162-501 Issue RFQ 0 15-Feb-16* 193

XAC03-213162-502 Issue PO 0 01-Apr-16* 193

XAC03-213162-503 NTF : Notice to Fabricate 0 30-Sep-16 160

XAC03-213162-504 FAT : Factory Acceptance Test 0 13-Nov-16 116

XAC03-213162-508 FOB or ETD 0 28-Nov-16 116

XAC03-213162-510 MHO for CT Make UP Pump 0 12-Jan-17 116

03PMS-BL00.2.1.3.16.3 Service Water Pump 364 15-Feb-16 12-Feb-17 122

XAC03-213163-501 Issue RFQ 0 15-Feb-16* 283

XAC03-213163-502 Issue PO 0 01-Apr-16* 283

XAC03-213163-503 NTF : Notice to Fabricate 0 09-Nov-16 157

XAC03-213163-504 FAT : Factory Acceptance Test 0 14-Dec-16 122

XAC03-213163-508 FOB or ETD 0 29-Dec-16 122

XAC03-213163-510 MHO for SWP 0 12-Feb-17 122

03PMS-BL00.2.1.3.16.4 DM Water Pump 364 15-Feb-16 12-Feb-17 36

XAC03-213164-501 Issue RFQ 0 15-Feb-16* 197

XAC03-213164-502 Issue PO 0 01-Apr-16* 197

XAC03-213164-503 NTF : Notice to Fabricate 0 09-Nov-16 71

XAC03-213164-504 FAT : Factory Acceptance Test 0 14-Dec-16 36

XAC03-213164-508 FOB or ETD 0 29-Dec-16 36

XAC03-213164-510 MHO for DM Pump 0 12-Feb-17 36

03PMS-BL00.2.1.3.17 Su
Sump Pump 276 01-May-16 31-Jan-17 59

XAC03-213170-501 Issue RFQ 0 01-May-16* 205

XAC03-213170-502 Issue PO 0 01-Jul-16* 205

XAC03-213170-503 NTF : Notice to Fabricate 0 27-Sep-16 126

XAC03-213170-504 FAT : Factory Acceptance Test 0 02-Dec-16 59

XAC03-213170-508 FOB or ETD 0 17-Dec-16 59

XAC03-213170-510 MHO for Sump Pump 0 31-Jan-17 59

03PMS-BL00.2.1.3.18 Ch
Chemical Dosing System 339 16-Apr-16 20-Mar-17 87

03PMS-BL00.2.1.3.18.1 Chemical Dosing System for HRSG 338 16-Apr-16 19-Mar-17 88

XAC03-213181-501 Issue RFQ 0 16-Apr-16* 227

XAC03-213181-502 Issue PO 0 31-May-16* 227

XAC03-213181-503 NTF : Notice to Fabricate 0 01-Jan-17 105

XAC03-213181-504 FAT : Factory Acceptance Test 0 18-Jan-17 88

XAC03-213181-508 FOB or ETD 0 02-Feb-17 88

XAC03-213181-510 MHO (Skid) 0 19-Mar-17 88

03PMS-BL00.2.1.3.18.2 Chemical Dosing System for CT 339 16-Apr-16 20-Mar-17 59

XAC03-213182-501 Issue RFQ 0 16-Apr-16* 186

XAC03-213182-502 Issue PO 0 31-May-16* 186

XAC03-213182-503 NTF : Notice to Fabricate 0 14-Jan-17 64

XAC03-213182-504 FAT : Factory Acceptance Test 0 19-Jan-17 59

XAC03-213182-508 FOB or ETD 0 03-Feb-17 59

XAC03-213182-510 MHO (Skid) 0 20-Mar-17 59

03PMS-BL00.2.1.3.19 Air
Ai Compressor System 377 01-Jan-16 12-Jan-17 93

XAC03-213190-501 Issue RFQ 0 01-Jan-16* 281

XAC03-213190-502 Issue PO 0 01-Mar-16* 281

XAC03-213190-503 NTF : Notice to Fabricate 0 23-Aug-16 175

XAC03-213190-504 FAT : Factory Acceptance Test 0 13-Nov-16 93

XAC03-213190-508 FOB or ETD 0 28-Nov-16 93

XAC03-213190-510 MHO Air Compressor System 0 12-Jan-17 93

03PMS-BL00.2.1.3.20 Fu
Fuel Gas Supply System 385 14-Jan-16 01-Feb-17 96

XAC03-213200-501 Issue RFQ 0 14-Jan-16* 294

XAC03-213200-502 Issue PO 5 26-Feb-16* 299

XAC03-213200-503 NTF : Notice to Fabricate 0 23-Jul-16 229

XAC03-213200-504 FAT : Factory Acceptance Test 0 03-Dec-16 96

XAC03-213200-508 FOB or ETD 0 18-Dec-16 96

XAC03-213200-510 MHO of Fuel Gas Filter 0 01-Feb-17 96

03PMS-BL00.2.1.3.23 Water
Wa Tank 371 30-Dec-15 04-Jan-17 109

03PMS-BL00.2.1.3.23.1 Raw water buffer tank 363 08-Jan-16 04-Jan-17 28

XAC03-213231-501 Issue RFQ 0 08-Jan-16* 255

XAC03-213231-502 Issue PO 0 08-Feb-16* 255

XAC03-213231-503 NTF : Notice to Fabricate 0 10-Sep-16 85

XAC03-213231-504 FAT : Factory Acceptance Test 0 05-Nov-16 28

XAC03-213231-508 FOB or ETD 0 20-Nov-16 28

XAC03-213231-510 MHO : Raw Buffer Tank 0 04-Jan-17 28

03PMS-BL00.2.1.3.23.2 CT Make-up Water Storage Tank 280 30-Dec-15 05-Oct-16 200

XAC03-213232-501 Issue RFQ 0 30-Dec-15 218

XAC03-213232-502 Issue PO 0 08-Feb-16* 218

XAC03-213232-503 NTF : Notice to Fabricate 0 14-Jul-16 106

XAC03-213232-504 FAT : Factory Acceptance Test 0 14-Jul-16 106

XAC03-213232-508 FOB or ETD 0 28-Jul-16 106

XAC03-213232-510A MHO : Lot-1 (Annular / Bottom Plate) 0 11-Sep-16 106

XAC03-213232-510B MHO : Lot-2 (Shell) 0 25-Sep-16 119

XAC03-213232-510C MHO : Lot-3 (Roof) 0 05-Oct-16 200

XAC03-213232-510D MHO : Lot-4 (Nozzle) 0 05-Oct-16 200

03PMS-BL00.2.1.3.23.3 Service Water & Fire Water Storage Tank 262 08-Jan-16 25-Sep-16 165

XAC03-213233-501 Issue RFQ 0 08-Jan-16* 172

XAC03-213233-502 Issue PO 0 08-Feb-16* 172

XAC03-213233-503 NTF : Notice to Fabricate 0 23-Jun-16 89

XAC03-213233-504 FAT : Factory Acceptance Test 0 26-Jun-16 86

XAC03-213233-508 FOB or ETD 0 11-Jul-16 86

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:10 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-213233-510A MHO : Lot-1 (Annular / Bottom Plate) 0 25-Aug-16 86

XAC03-213233-510B MHO : Lot-2 (Shell) 0 15-Sep-16 93

XAC03-213233-510C MHO : Lot-3 (Roof) 0 25-Sep-16 165

XAC03-213233-510D MHO : Lot-4 (Nozzle) 0 25-Sep-16 159

03PMS-BL00.2.1.3.23.4 DM Water Storage Tank 271 08-Jan-16 05-Oct-16 163

XAC03-213234-501 Issue RFQ 0 08-Jan-16* 182

XAC03-213234-502 Issue PO 0 09-Feb-16* 182

XAC03-213234-503 NTF : Notice to Fabricate 0 23-Jun-16 100

XAC03-213234-504 FAT : Factory Acceptance Test 0 06-Jul-16 87

XAC03-213234-508 FOB or ETD 0 21-Jul-16 87

XAC03-213234-510A MHO : Lot-1 (Annular / Bottom Plate) 0 04-Sep-16 87

XAC03-213234-510B MHO : Lot-2 (Shell) 0 25-Sep-16 84

XAC03-213234-510C MHO : Lot-3 (Roof) 0 05-Oct-16 163

XAC03-213234-510D MHO : Lot-4 (Nozzle) 0 05-Oct-16 106

03PMS-BL00.2.1.3.26 Heat
He exchanger 397 14-Jan-16 14-Feb-17 143

03PMS-BL00.2.1.3.26.1 CCCW Heat Echnager 305 16-Apr-16 14-Feb-17 83

XAC03-213261-501 Issue RFQ 0 16-Apr-16* 205

XAC03-213261-502 Issue PO 0 17-Jun-16* 209

XAC03-213261-503 NTF : Notice to Fabricate 0 30-Sep-16 160

XAC03-213261-504 FAT : Factory Acceptance Test 0 16-Dec-16 83

XAC03-213261-508 FOB or ETD 0 31-Dec-16 83

XAC03-213261-510 MHO for CCCW Heat Exchanger 0 14-Feb-17 83

03PMS-BL00.2.1.3.26.2 Feedwater Heat Exchnager 390 14-Jan-16 07-Feb-17 150

XAC03-213262-501 Issue RFQ 0 14-Jan-16* 374

XAC03-213262-502 Issue PO 0 15-Mar-16* 314

XAC03-213262-503 NTF : Notice to Fabricate 0 02-Aug-16 279

XAC03-213262-504 FAT : Factory Acceptance Test 0 09-Dec-16 150

XAC03-213262-508 FOB or ETD 0 24-Dec-16 150

XAC03-213262-510 MHO for FW Heat Exchanger 0 07-Feb-17 150

03PMS-BL00.2.1.3.27 Cooling
Co Tower 384 15-Jan-16 01-Feb-17 66

XAC03-213270-501 Issue RFQ 0 15-Jan-16* 182

XAC03-213270-502 Issue PO 0 01-Mar-16* 181

XAC03-213270-503 NTF : Notice to Fabricate 0 26-Aug-16 165

XAC03-213270-510A MHO : (Embedded Material) 0 20-Sep-16 200

XAC03-213270-504 FAT : Factory Acceptance Test 0 03-Dec-16 66

XAC03-213270-508 FOB or ETD 0 18-Dec-16 66

XAC03-213270-510B MHO : (Main Equipment) 0 01-Feb-17 66

03PMS-BL00.2.1.3.30 Waste
Wa Water Treatment System 366 01-Dec-15 01-Dec-16 64

XAC03-213300-501 Issue RFQ 0 01-Dec-15* 169

XAC03-213300-502 Issue PO 0 30-Jan-16* 169

XAC03-213300-503 NTF : Notice to Fabricate 0 02-Oct-16 64

XAC03-213300-504 FAT : Factory Acceptance Test 0 02-Oct-16 64

XAC03-213300-508 FOB or ETD 0 17-Oct-16 64

XAC03-213300-510A MHO : Lot 1 (Embedded Ports) 0 16-Nov-16 79

XAC03-213300-510B MHO : Lot 2 (Main Equipments) 0 01-Dec-16 64

03PMS-BL00.2.1.3.45 Overhead
Ov Crane 385 15-Jan-16 02-Feb-17 38

XAC03-213450-501 Issue RFQ 0 15-Jan-16* 294

XAC03-213450-502 Issue PO 0 01-Mar-16* 294

XAC03-213450-503 NTF : Notice to Fabricate 0 02-Oct-16 136

XAC03-213450-504 FAT : Factory Acceptance Test 0 08-Jan-17 38

XAC03-213450-508 FOB or ETD 0 02-Feb-17 38

XAC03-213450-510 MHO STG Building Overhead Crane 0 02-Feb-17 38

03PMS-BL00.2.1.3.ZZ Others
O 379 30-Jan-16 12-Feb-17 82

03PMS-BL00.2.1.3.ZZ.1 Condenser Ball Cleaning System 379 30-Jan-16 12-Feb-17 82

XAC03-213ZZ1-501 Issue RFQ 0 30-Jan-16* 183

XAC03-213ZZ1-502 Issue PO 0 30-May-16* 183

XAC03-213ZZ1-503 NTF : Notice to Fabricate 0 10-Nov-16 116

XAC03-213ZZ1-504 FAT : Factory Acceptance Test 0 14-Dec-16 82

XAC03-213ZZ1-508 FOB or ETD 0 29-Dec-16 82

XAC03-213ZZ1-510 MHO Condenser Ball Cleaning 0 12-Feb-17 82

03PMS-BL00.2.1.4 Piping 608 11-Jan-16 10-Sep-17 144

03PMS-BL00.2.1.4.01 CW Piping Material 236 23-May-16 13-Jan-17 81

XAC03-214010-501 Issue RFQ 0 23-May-16* 81

XAC03-214010-502 Issue PO 0 04-Jul-16* 81

XAC03-214010-510 MHO : lot 1 (MCW Pipe) - Arrive at Site 0 13-Jan-17* 81

03PMS-BL00.2.1.4.03 BOP
BO Piping Material (Bear) 70 25-Mar-16 02-Jun-16 234

03PMS-BL00.2.1.4.03.1 Under Ground pipe material (Stainless) 70 25-Mar-16 02-Jun-16 234

XAC03-214031-501 Issue RFQ 0 25-Mar-16* 234

XAC03-214031-502 Issue PO 0 22-Apr-16* 234

XAC03-214031-510 MHO : Under Ground pipe material (Stainless) - Arrive at Site 0 02-Jun-16* 234

03PMS-BL00.2.1.4.03.2 Under Ground pipe material (PVC / ABS) 70 25-Mar-16 02-Jun-16 234

XAC03-214032-501 Issue RFQ 0 25-Mar-16* 234

XAC03-214032-502 Issue PO 0 22-Apr-16* 234

XAC03-214032-510 MHO : Under Ground pipe material (PVC / ABS) - Arrive at Site 0 02-Jun-16* 234

03PMS-BL00.2.1.4.04 Sh
Shop Fabrication Piping 299 14-May-16 09-Mar-17 75

03PMS-BL00.2.1.4.04.1 Pipe Raw Material for BOP Yard Fabrication Large Bore (Carbon & Stainless Mater 160 14-May-16 21-Oct-16 91

XAC03-214041-501 Issue RFQ : Large Bore (Carbon & Stainless) 0 14-May-16* 103

XAC03-214041-502 Issue PO : Large Bore (Carbon & Stainless) 0 19-Jun-16* 103

XAC03-214041-508 FOB or ETD : Large Bore (Carbon & Stainless) 0 01-Sep-16 103

XAC03-214041-509 CFR Thailand Port To Inland Transportation 0 13-Oct-16 91

XAC03-214041-510 MHO : Large Bore (Carbon & Stainless) - Arrive at Prefabrication Vendor 0 21-Oct-16* 91

03PMS-BL00.2.1.4.04.2 Pipe Raw Material for BOP Yard Fabrication Large Bore (Alloy Materials) 270 14-May-16 08-Feb-17 62

XAC03-214042-501 Issue RFQ : Large Bore (Alloy) 0 14-May-16* 72

XAC03-214042-502 Issue PO : Large Bore (Alloy) 0 26-May-16* 72

XAC03-214042-508 FOB or ETD : Large Bore (Alloy) 0 22-Dec-16 72

XAC03-214042-509 CFR Thailand Port To Inland Transportation 0 31-Jan-17 62

XAC03-214042-510 MHO : Large Bore (Alloy) - Arrive at Prefabrication Vendor 0 08-Feb-17* 62

03PMS-BL00.2.1.4.04.3 BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 176 22-Jun-16 15-Dec-16 91

XAC03-214043-501 Issue RFQ : BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 0 22-Jun-16* 115

XAC03-214043-502 Issue PO : BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 0 03-Aug-16* 103

XAC03-214043-508 FOB or ETD : BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 0 26-Oct-16 103

XAC03-214043-509 CFR Thailand Port To Inland Transportation 0 07-Dec-16 91

XAC03-214043-510 MHO : BOP Yard Piping Procurement - Small Bore (Galvanized : RW/SW Materials) - 0 15-Dec-16* 91
Arrive at Site
03PMS-BL00.2.1.4.04.4 BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) 171 15-Aug-16 02-Feb-17 110

XAC03-214044-501 Issue RFQ : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) 0 15-Aug-16* 117

XAC03-214044-502 Issue PO : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) 0 26-Sep-16* 117

XAC03-214044-508 FOB or ETD : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless 0 19-Dec-16 117
Materials)

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:11 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-214044-509 CFR Thailand Port To Inland Transportation 0 25-Jan-17 110

XAC03-214044-510 MHO : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) - 0 02-Feb-17* 110
Arrive at Site
03PMS-BL00.2.1.4.04.5 BOP Yard Piping Procurement - Small Bore (Alloy Materials) 216 05-Aug-16 09-Mar-17 59

XAC03-214045-501 Issue RFQ : BOP Yard Piping Procurement - Small Bore (Alloy Materials) 0 05-Aug-16* 69

XAC03-214045-502 Issue PO : BOP Yard Piping Procurement - Small Bore (Alloy Materials) 0 16-Sep-16* 69

XAC03-214045-508 FOB or ETD : BOP Yard Piping Procurement - Small Bore (Alloy Materials) 0 20-Jan-17 69

XAC03-214045-509 CFR Thailand Port To Inland Transportation 0 01-Mar-17 59

XAC03-214045-510 MHO : BOP Yard Piping Procurement - Small Bore (Alloy Materials : Aux Steam, HP/Ext 0 09-Mar-17* 59
Steam Drain) - Arrive at Site
03PMS-BL00.2.1.4.05 Va
Valve 534 11-Jan-16 28-Jun-17 218

03PMS-BL00.2.1.4.05.1 General valve 263 17-Apr-16 05-Jan-17 68

XAC03-214051-501 Issue RFQ General Valve 0 17-Apr-16* 72

XAC03-214051-502 Issue PO General Valve 0 28-May-16* 72

XAC03-214051-508 FOB or ETD 0 24-Nov-16 72

XAC03-214051-509 CFR Thailand Port To Inland Transportation 0 28-Dec-16 68

XAC03-214051-510 MHO : General Valve 0 05-Jan-17* 68

03PMS-BL00.2.1.4.05.2 Ball Valve 266 15-May-16 05-Feb-17 39

XAC03-214052-501 Issue RFQ Ball Valve 0 15-May-16* 46

XAC03-214052-502 Issue PO Ball Valve 0 27-Jun-16* 45

XAC03-214052-508 FOB or ETD 0 23-Dec-16 45

XAC03-214052-509 CFR Thailand Port To Inland Transportation 0 28-Jan-17 39

XAC03-214052-510 MHO : Ball Valve 0 05-Feb-17* 39

03PMS-BL00.2.1.4.05.3 Motor Valve 327 08-Apr-16 01-Mar-17 15

XAC03-214053-501 Issue RFQ Motor Valve 0 08-Apr-16* 19

XAC03-214053-502 Issue PO Motor Valve 0 19-May-16* 19

XAC03-214053-508 FOB or ETD 0 18-Jan-17 19

XAC03-214053-509 CFR Thailand Port To Inland Transportation 0 21-Feb-17 15

XAC03-214053-510 MHO : Motor Valve 0 01-Mar-17* 15

03PMS-BL00.2.1.4.05.4 High Pressure Valve 399 11-Jan-16 14-Feb-17 82

XAC03-214054-501 Issue RFQ High Pressure Valve 0 11-Jan-16* 86

XAC03-214054-502 Issue PO High Pressure Valve 0 11-Feb-16 86

XAC03-214054-508 FOB or ETD 0 03-Jan-17 86

XAC03-214054-509 CFR Thailand Port To Inland Transportation 0 06-Feb-17 82

XAC03-214054-510 MHO : High Pressure Valve 0 14-Feb-17* 82

03PMS-BL00.2.1.4.05.5 High Temp Valve (Alloy Materials) 305 30-Apr-16 01-Mar-17 15

XAC03-214055-501 Issue RFQ Alloy Valve 0 30-Apr-16* 19

XAC03-214055-502 Issue PO Alloy Valve 0 11-Jun-16* 19

XAC03-214055-508 FOB or ETD 0 18-Jan-17 19

XAC03-214055-509 CFR Thailand Port To Inland Transportation 0 21-Feb-17 15

XAC03-214055-510 MHO : High Temp (Alloy Mtrls.) Valve 0 01-Mar-17* 15

03PMS-BL00.2.1.4.05.6 MCW Butterfly Valve & MCW Non Return Butterfly Valve 306 05-Mar-16 05-Jan-17 90

XAC03-214056-501 Issue RFQ MCW and Non Return Butterfly Valve 0 05-Mar-16* 94

XAC03-214056-502 Issue PO Large Butterfly Valve 0 17-Apr-16* 94

XAC03-214056-508 FOB or ETD 0 24-Nov-16 94

XAC03-214056-509 CFR Thailand Port To Inland Transportation 0 28-Dec-16 90

XAC03-214056-510 MHO : MCW and Non Return Butterfly Valve 0 05-Jan-17* 90

03PMS-BL00.2.1.4.05.7 General Butterfly Valve 265 17-Mar-16 07-Dec-16 97

XAC03-214057-501 Issue RFQ General Butterfly Valve 0 17-Mar-16* 202

XAC03-214057-502 Issue PO General Butterfly Valve 0 30-Apr-16* 202

XAC03-214057-508 FOB or ETD 0 30-Sep-16 127

XAC03-214057-509 CFR Thailand Port To Inland Transportation 0 29-Nov-16 97

XAC03-214057-510 MHO : General Butterfly Valve 0 07-Dec-16* 97

03PMS-BL00.2.1.4.05.8 Temporary valve for Steam Blow 70 20-Apr-17 28-Jun-17 218

XAC03-214058-501 Issue RFQ Temporar y Valve for Steam Blow 0 20-Apr-17* 218

XAC03-214058-502 Issue PO Temporary Valve for Steam Blow 0 08-May-17* 218

XAC03-214058-508 FOB or ETD 0 22-May-17 218

XAC03-214058-509 CFR Thailand Port To Inland Transportation 0 21-Jun-17 218

XAC03-214058-510 MHO : Temporary Valve for Steam Blow 0 28-Jun-17* 218

03PMS-BL00.2.1.4.05.9 Auto vent valve 283 15-May-16 22-Feb-17 102

XAC03-214059-501 Issue RFQ Auto Vent and Hoot Valve 0 15-May-16* 116

XAC03-214059-502 Issue PO Auto Vent and Hoot Valve 0 27-Jun-16* 116

XAC03-214059-508 FOB or ETD 0 01-Jan-17 116

XAC03-214059-509 CFR Thailand Port To Inland Transportation 0 14-Feb-17 102

XAC03-214059-510 MHO : Auto Vent and Hoot Valve 0 22-Feb-17* 102

03PMS-BL00.2.1.4.06 Sp
Specialty Product 437 17-Apr-16 28-Jun-17 219

03PMS-BL00.2.1.4.06.1 Expansion & Flexible Joint 188 09-Jul-16 13-Jan-17 62

XAC03-214061-501 Issue RFQ Expansion & Flexible Joint 0 09-Jul-16* 74

XAC03-214061-502 Issue PO Expansion & Flexible Joint 0 21-Aug-16* 74

XAC03-214061-508 FOB or ETD 0 24-Nov-16 74

XAC03-214061-509 CFR Thailand Port To Inland Transportation 0 05-Jan-17 62

XAC03-214061-510 MHO : Expansion & Flexible Joint 0 13-Jan-17* 62

03PMS-BL00.2.1.4.06.2 Strainer 271 17-Apr-16 13-Jan-17 62

XAC03-214062-501 Issue RFQ Strainer 0 17-Apr-16* 74

XAC03-214062-502 Issue PO Strainer 0 28-May-16* 74

XAC03-214062-508 FOB or ETD 0 24-Nov-16 74

XAC03-214062-509 CFR Thailand Port To Inland Transportation 0 05-Jan-17 62

XAC03-214062-510 MHO : Strainer 0 13-Jan-17* 62

03PMS-BL00.2.1.4.06.3 Drain Trap 228 24-Jul-16 09-Mar-17 7

XAC03-214063-501 Issue RFQ Drain Trap 0 24-Jul-16* 18

XAC03-214063-502 Issue PO Drain Trap 0 04-Sep-16* 18

XAC03-214063-508 FOB or ETD 0 19-Jan-17 18

XAC03-214063-509 CFR Thailand Port To Inland Transportation 0 01-Mar-17 7

XAC03-214063-510 MHO : Drain Trap 0 09-Mar-17* 7

03PMS-BL00.2.1.4.06.4 Silencer 228 24-Jul-16 09-Mar-17 7

XAC03-214064-501 Issue RFQ Silencer 0 24-Jul-16* 18

XAC03-214064-502 Issue PO Silencer 0 04-Sep-16* 18

XAC03-214064-508 FOB or ETD 0 19-Jan-17 18

XAC03-214064-509 CFR Thailand Port To Inland Transportation 0 01-Mar-17 7

XAC03-214064-510 MHO : Silencer 0 09-Mar-17* 7

03PMS-BL00.2.1.4.06.5 Target Plate for Steam Blow 105 15-Mar-17 28-Jun-17 219

XAC03-214065-501 Issue RFQ Target Pla te for Steam Blow 0 15-Mar-17* 221

XAC03-214065-502 Issue PO Target Plate for Steam Blow 0 30-Mar-17* 221

XAC03-214065-508 FOB or ETD 0 19-May-17 221

XAC03-214065-509 CFR Thailand Port To Inland Transportation 0 20-Jun-17 219

XAC03-214065-510 MHO : Target Plate for Steam Blow 0 28-Jun-17* 219

03PMS-BL00.2.1.4.07 Pip
Piping Support Materials 168 23-Sep-16 09-Mar-17 6

03PMS-BL00.2.1.4.07.1 Pipe Support - Hanger Parts 123 07-Nov-16 09-Mar-17 6

XAC03-214071-501 Issue RFQ 0 07-Nov-16* 6

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:12 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-214071-502 Issue PO 0 19-Dec-16* 6

XAC03-214071-510 MHO : Spring hanger - Arrive at Site 0 09-Mar-17* 6

03PMS-BL00.2.1.4.07.2 Structural Beam & Plate 1st Order (Pipe Chair, Clamp) 111 04-Nov-16 22-Feb-17 21

XAC03-214072-501 Issue RFQ 0 04-Nov-16* 21

XAC03-214072-502 Issue PO 0 02-Dec-16* 21

XAC03-214072-510 MHO : Pipe Chair - Arrive at Site 0 22-Feb-17* 21

03PMS-BL00.2.1.4.07.3 Structural Beam & Plate 2nd Order (80% Qty Beam, Anchor Bolt, U-Bolt, Plate etc.) 84 23-Sep-16 15-Dec-16 90

XAC03-214073-501 Issue RFQ 0 23-Sep-16* 90

XAC03-214073-502 Issue PO 0 04-Nov-16* 90

XAC03-214073-510 MHO : Structural Beam & Plate (2nd Order) - Arrive at Site 0 15-Dec-16* 90

03PMS-BL00.2.1.4.07.4 Structural Beam & Plate 3rd Order (20% Qty Beam, Anchor Bolt, U-Bolt, Plate etc.) 67 02-Jan-17 09-Mar-17 6

XAC03-214074-501 Issue RFQ 0 02-Jan-17* 6

XAC03-214074-502 Issue PO 0 30-Jan-17* 6

XAC03-214074-510 MHO : Structural Beam & Plate (3rd Order) - Arrive at Site 0 09-Mar-17* 6

03PMS-BL00.2.1.4.08 Pla
Platform for Valve 160 01-Nov-16 09-Apr-17 298

03PMS-BL00.2.1.4.08.1 Platform for Valve - HRSG Side Pipe Rack 104 01-Nov-16 12-Feb-17 52

XAC03-214081-501 Issue RFQ 0 01-Nov-16* 52

XAC03-214081-502 Issue PO 0 25-Nov-16* 52

XAC03-214081-510 MHO : Platform for Valve - HRSG Side Pipe Rack - Arrive at Site 0 12-Feb-17* 52

03PMS-BL00.2.1.4.08.2 Platform for Valve - Deaerator Tower Valve OperationStage 80 10-Jan-17 30-Mar-17 308

XAC03-214082-501 Issue RFQ 0 10-Jan-17* 308

XAC03-214082-502 Issue PO 0 26-Jan-17* 308

XAC03-214082-510 MHO : Platform for Valve - Deaerator Tower Valve OperationStage - Arrive at Site 0 30-Mar-17* 308

03PMS-BL00.2.1.4.08.3 Platform for Valve - STG Side Pipe Rack 160 01-Nov-16 09-Apr-17 56

XAC03-214083-501 Issue RFQ 0 01-Nov-16* 150

XAC03-214083-502 Issue PO 0 28-Feb-17* 56

XAC03-214083-510 MHO : Platform for Valve - STG Side Pipe Rack - Arrive at Site 0 09-Apr-17* 56

03PMS-BL00.2.1.4.08.4 Platform for Valve - GTG Side Pipe Rack 82 09-Dec-16 28-Feb-17 52

XAC03-214084-501 Issue RFQ 0 09-Dec-16* 52

XAC03-214084-502 Issue PO 0 23-Dec-16* 52

XAC03-214084-510 MHO : Platform for Valve - GTG Side Pipe Rack - Arrive at Site 0 28-Feb-17* 52

03PMS-BL00.2.1.4.09 Insulation
Ins 124 06-Feb-17 09-Jun-17 237

XAC03-214090-501 Issue RFQ 0 06-Feb-17* 237

XAC03-214090-502 Issue PO 0 17-Mar-17* 237

XAC03-214090-510 MHO : Thermal Insulation - Arrive at Site 0 09-Jun-17* 237

03PMS-BL00.2.1.4.10 Consumable
Co Material 151 21-Dec-16 20-May-17 101

03PMS-BL00.2.1.4.10.1 Consumable Material - Paint for Support Structure 54 21-Dec-16 12-Feb-17 31

XAC03-214101-501 Issue RFQ 0 21-Dec-16* 31

XAC03-214101-502 Issue PO 0 10-Jan-17* 31

XAC03-214101-510 MHO : Paint for Support structure - Arrive at Site 0 12-Feb-17* 31

03PMS-BL00.2.1.4.10.2 Consumable Material - Paint for Piping 53 29-Mar-17 20-May-17 101

XAC03-214102-501 Issue RFQ 0 29-Mar-17* 101

XAC03-214102-502 Issue PO 0 11-Apr-17* 101

XAC03-214102-510 MHO : Paint for Piping - Arrive at Site 0 20-May-17* 101

03PMS-BL00.2.1.4.11 Mi
Miscellaneous Material 374 02-Sep-16 10-Sep-17 144

03PMS-BL00.2.1.4.11.1 Orifice Procurement 70 07-Oct-16 15-Dec-16 90

XAC03-214111-501 Issue RFQ Orifice 0 07-Oct-16* 90

XAC03-214111-502 Issue PO Orifice 0 04-Nov-16* 90

XAC03-214111-510 MHO : Orifice - Arrive at Site 0 15-Dec-16* 90

03PMS-BL00.2.1.4.11.2 Funnel Procurement 110 15-Dec-16 03-Apr-17 304

XAC03-214112-501 Issue RFQ Funnel 0 15-Dec-16* 304

XAC03-214112-502 Issue PO Funnel 0 13-Jan-17* 304

XAC03-214112-510 MHO : Funnel - Arrive at Site 0 03-Apr-17* 304

03PMS-BL00.2.1.4.11.3 Fuel Gas Condensate Tank 111 04-Nov-16 22-Feb-17 47

XAC03-214113-501 Issue RFQ Fuel Gas Condensate Tank 0 04-Nov-16* 47

XAC03-214113-502 Issue PO Fuel Gas Condensate Tank 0 02-Dec-16* 47

XAC03-214113-510 MHO : Fuel Gas Condensate Tank - Arrive at Site 0 22-Feb-17* 47

03PMS-BL00.2.1.4.11.4 Drain Flash Pipe Procurement 115 25-Dec-16 18-Apr-17 159

XAC03-214114-501 Issue RFQ Drain Flash Pipe 0 25-Dec-16* 159

XAC03-214114-502 Issue PO Drain Flash Pipe 0 26-Jan-17* 159

XAC03-214114-510 MHO : Drain Flash Pipe - Arrive at Site 0 18-Apr-17* 159

03PMS-BL00.2.1.4.11.5 CCCW Head Pipe /Chemical Pot Procurement 110 15-Dec-16 03-Apr-17 304

XAC03-214115-501 Issue RFQ CCCW Head Pipe / CCCW Chemical Pot 0 15-Dec-16* 304

XAC03-214115-502 Issue PO CCCW Head Pipe / CCCW Chemical Pot 0 11-Jan-17* 304

XAC03-214115-510 MHO : CCCW Head Pipe / CCCW Chemical Pot - Arrive at Site 0 03-Apr-17* 304

03PMS-BL00.2.1.4.11.6 Bolt Nut and Gasket 105 02-Sep-16 15-Dec-16 90

XAC03-214116-501 Issue RFQ Bolt Nut and Gasket 0 02-Sep-16* 90

XAC03-214116-502 Issue PO Bolt Nut and Gasket 0 14-Oct-16* 90

XAC03-214116-510 MHO : Bolt Nut and Gasket - Arrive at Site 0 15-Dec-16* 90

03PMS-BL00.2.1.4.11.7 Water seal for Building penetration Rain Cover Procurement 49 24-Jul-17 10-Sep-17 35

XAC03-214117-501 Issue RFQ Water seal for Builing penetration Rain Cover Procurement 0 24-Jul-17* 63

XAC03-214117-502 Issue PO Water seal for Builing penetration Rain Cover 0 21-Aug-17* 35

XAC03-214117-510 MHO : Water seal for Builing penetration Rain Cover - Arrive at Site 0 10-Sep-17* 35

03PMS-BL00.2.1.4.11.8 Name Tag Plate for Replace 56 26-Jun-17 20-Aug-17 56

XAC03-214118-501 Issue RFQ Name Tag Plate for Replace 0 26-Jun-17* 56

XAC03-214118-502 Issue PO Name Tag Plate for Replace 0 15-Jul-17* 56

XAC03-214118-510 MHO : Name Tag Plate for Replace - Arrive at Site 0 20-Aug-17* 56

03PMS-BL00.2.1.4.12 St
Steam Blow Piping 70 20-Apr-17 28-Jun-17 218

XAC03-214120-501 Issue RFQ Support material / Steam Blow Piping 0 20-Apr-17* 202

XAC03-214120-502 Issue PO Support material / Steam Blow Piping 0 18-May-17* 202

XAC03-214120-510 MHO : Steam Blow Piping / Support Material 0 28-Jun-17* 218

03PMS-BL00.2.1.4.13 Shop
Sh Prefabricated Piping 313 25-May-16 03-Apr-17 175

03PMS-BL00.2.1.4.13.1 BOP Yard Piping Procurement 313 25-May-16 03-Apr-17 175

XAC03-214131-501 Issue RFQ : BOP Yard Pipe Prefabrication 0 25-May-16* 174

XAC03-214131-502 Issue PO 0 30-Jun-16* 174

XAC03-214131-510A MHO : Arrive at Site Raw & CT Make Up System (1st) 0 15-Dec-16* 90

XAC03-214131-510B MHO : Arrive at Site Condensate Water,MCW Blow & SW System (2nd) 0 13-Jan-17* 81

XAC03-214131-510C MHO : Arrive at Site DM Water, IA/SA Air (3rd) 0 05-Feb-17* 113

XAC03-214131-510D MHO : Arrive at Site Ext. Steam, HP/LP Feed & Fuel Gas (4th) 0 22-Feb-17* 47

XAC03-214131-510E MHO : Arrive at Site HP/LP Steam (5th) 0 09-Mar-17* 58

XAC03-214131-510F MHO : Arrive at Site CCCW, Condensate Drain & Vacuum System (6th) 0 03-Apr-17* 175

03PMS-BL00.2.1.5 C&I 528 01-Dec-15 12-May-17 265

03PMS-BL00.2.1.5.01 DCS
DC 406 14-Jan-16 22-Feb-17 52

XAC03-215010-501 Issue RFQ 0 14-Jan-16* 52

XAC03-215010-502 Issue PO 0 01-Mar-16* 52

XAC03-215010-503 NTF : Notice to Fabricate 0 09-Oct-16 52

XAC03-215010-504 FAT : Factory Acceptance Test 0 24-Dec-16 52

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:13 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-215010-508 FOB or ETD 0 08-Jan-17 52

XAC03-215010-510 MHO : DCS 0 22-Feb-17 52

03PMS-BL00.2.1.5.02 Co
Continuous Emission Monitoring System 351 27-May-16 12-May-17 4

XAC03-215020-501 Issue RFQ 0 27-May-16* 176

XAC03-215020-502 Issue PO 0 27-Jul-16* 176

XAC03-215020-503 NTF : Notice to Fabricate 0 16-Nov-16 156

XAC03-215020-504 FAT : Factory Acceptance Test 0 17-Apr-17 4

XAC03-215020-508 FOB or ETD 0 12-May-17 4

XAC03-215020-510 MHO : Continuous Emission Monitoring System 0 12-May-17 4

03PMS-BL00.2.1.5.03 Steam
St and Water Analysis System 297 17-May-16 09-Mar-17 153

XAC03-215030-501 Issue RFQ 0 17-May-16* 305

XAC03-215030-502 Issue PO 0 17-Jul-16* 305

XAC03-215030-503 NTF : Notice to Fabricate 0 03-Dec-16 224

XAC03-215030-504 FAT : Factory Acceptance Test 0 12-Feb-17 153

XAC03-215030-508 FOB or ETD 0 09-Mar-17 153

XAC03-215030-510 MHO : Steam and Water Sampling System Rack 0 09-Mar-17 153

03PMS-BL00.2.1.5.04 Pla
Plant Communication System, CCTV & Clock 242 08-Sep-16 08-May-17 25

XAC03-215040-501 Issue RFQ Communication & Clock System 0 08-Sep-16 131

XAC03-215040-502 Issue PO Communication & Clock System 0 09-Oct-16* 131

XAC03-215040-503 NTF : Notice to Fabricate 0 17-Feb-17 80

XAC03-215040-504 FAT : Factory Acceptance Test 0 13-Apr-17 25

XAC03-215040-508 FOB or ETD 0 08-May-17 25

XAC03-215040-510 MHO : Communication & Clock System 0 08-May-17 25

03PMS-BL00.2.1.5.05 Ch
Chemical Laboratory 520 01-Dec-15 05-May-17 273

XAC03-215050-501 Issue RFQ 0 01-Dec-15* 619

XAC03-215050-502 Issue PO 0 30-Jan-16* 619

XAC03-215050-503 NTF : Notice to Fabricate 0 14-Jan-17 358

XAC03-215050-504 FAT : Factory Acceptance Test 0 09-Apr-17 273

XAC03-215050-508 FOB or ETD 0 04-May-17 273

XAC03-215050-510 MHO Chemical laboratory equipment 0 05-May-17* 273

03PMS-BL00.2.1.5.06 Pr
Primary Energy Saving System 311 29-Apr-16 06-Mar-17 89

XAC03-215060-501 Issue RFQ 0 29-Apr-16* 278

XAC03-215060-502 Issue PO 0 29-May-16* 278

XAC03-215060-503 NTF : Notice to Fabricate 0 30-Dec-16 129

XAC03-215060-504 FAT : Factory Acceptance Test 0 08-Feb-17 89

XAC03-215060-508 FOB or ETD 0 05-Mar-17 89

XAC03-215060-510 MHO : PES 0 06-Mar-17* 89

03PMS-BL00.2.1.5.07 C&
C&I Bulk Material 137 13-Sep-16 28-Jan-17 78

XAC03-215070-501 Issue RFQ 0 13-Sep-16* 91

XAC03-215070-502 Issue PO 0 28-Nov-16* 91

XAC03-215070-503 NTF : Notice to Fabricate 0 29-Nov-16 91

XAC03-215070-504 FAT : Factory Acceptance Test 0 12-Dec-16 78

XAC03-215070-508 FOB or ETD 0 13-Dec-16 78

XAC03-215070-510 MHO : Instrument Bulk Materials 0 28-Jan-17* 78

03PMS-BL00.2.1.5.08 Turbine
Tu Bypass Valve 311 02-May-16 08-Mar-17 85

XAC03-215080-501 Issue RFQ 0 02-May-16* 110

XAC03-215080-502 Issue PO 0 16-Jun-16* 110

XAC03-215080-503 NTF : Notice to Fabricate 0 13-Dec-16 110

XAC03-215080-504 FAT : Factory Acceptance Test 0 07-Jan-17 85

XAC03-215080-508 FOB or ETD 0 22-Jan-17 85

XAC03-215080-510 MHO : HP / LP BYPASS VALVE 0 08-Mar-17 85

03PMS-BL00.2.1.5.09 Co
Control Valves 256 02-May-16 13-Jan-17 114

XAC03-215090-501 Issue RFQ 0 02-May-16* 139

XAC03-215090-502 Issue PO 0 15-Jun-16* 139

XAC03-215090-503 NTF : Notice to Fabricate 0 19-Oct-16 139

XAC03-215090-504 FAT : Factory Acceptance Test 0 13-Nov-16 114

XAC03-215090-508 FOB or ETD 0 28-Nov-16 114

XAC03-215090-510 MHO : Control Valve 0 13-Jan-17* 114

03PMS-BL00.2.1.5.ZZ Others
O 78 31-Oct-16 17-Jan-17 89

XAC03-215ZZ0-501 Issue RFQ - Cabling Bulk For C&I Cable 0 31-Oct-16* 100

XAC03-215ZZ0-502 Issue PO - Cabling Bulk For C&I Cable 0 01-Dec-16* 100

XAC03-215ZZ0-503 NTF : Notice to Fabricate 0 11-Dec-16 100

XAC03-215ZZ0-504 FAT : Factory Acceptance Test 0 22-Dec-16 89

XAC03-215ZZ0-508 FOB or ETD 0 16-Jan-17 89

XAC03-215ZZ0-510 MHO : Cabling Bulk for C&I Cable 0 17-Jan-17* 89

03PMS-BL00.2.1.6 Electrical
Electri 450 15-Dec-15 08-Mar-17 115

03PMS-BL00.2.1.6.01 Generator
Ge Transformer 450 15-Dec-15 08-Mar-17 9

XAC03-216010-501 Issue RFQ 0 15-Dec-15* 238

XAC03-216010-502 Issue PO GSUT/CUSTOMER TRANSFORMER 0 19-Jan-16* 238

XAC03-216010-503 NTF : Notice to Fabricate 0 25-Jul-16 175

XAC03-216010-504 FAT : Factory Acceptance Test 0 07-Jan-17 9

XAC03-216010-508 FOB or ETD 0 22-Jan-17 9

XAC03-216010-510 MHO : GSUT/ CUSTOMER TRANSFORMER 0 08-Mar-17 9

03PMS-BL00.2.1.6.02 Un
Unit Aux Transformer with remote OLTC panel 450 15-Dec-15 08-Mar-17 54

XAC03-216020-501 Issue RFQ 0 15-Dec-15* 285

XAC03-216020-502 Issue PO 0 19-Jan-16* 285

XAC03-216020-503 NTF : Notice to Fabricate 0 24-Jul-16 256

XAC03-216020-504 FAT : Factory Acceptance Test 0 11-Feb-17 54

XAC03-216020-508 FOB or ETD 0 08-Mar-17 54

XAC03-216020-510 MHO : Unit Auxilliary Transformer 0 08-Mar-17 54

03PMS-BL00.2.1.6.05 HV
HV/MV SWGR 312 22-Feb-16 29-Dec-16 116

XAC03-216050-501 Issue RFQ 0 22-Feb-16* 205

XAC03-216050-502 Issue PO 22kV / 6.6 kV Switvhgear 0 29-Mar-16* 205

XAC03-216050-503 NTF : Notice to Fabricate 0 06-Sep-16 205

XAC03-216050-504 FAT : Factory Acceptance Test 0 04-Dec-16 116

XAC03-216050-508 FOB or ETD 0 29-Dec-16 116

XAC03-216050-510 MHO : 22kV / 6.6kV Switchgear 0 29-Dec-16 116

03PMS-BL00.2.1.6.06 Auxiliary
Au Transformer 364 01-Feb-16 29-Jan-17 93

XAC03-216060-501 Issue RFQ 0 01-Feb-16* 290

XAC03-216060-502 Issue PO 0 11-Mar-16* 290

XAC03-216060-503 NTF : Notice to Fabricate 0 17-Aug-16 233

XAC03-216060-504 FAT : Factory Acceptance Test 0 04-Jan-17 93

XAC03-216060-508 FOB or ETD 0 29-Jan-17 93

XAC03-216060-510 MHO : Auxiliary Transformer 0 29-Jan-17 93

03PMS-BL00.2.1.6.07 LV SWGR 326 15-Feb-16 05-Jan-17 116

XAC03-216070-501 Issue RFQ 0 15-Feb-16* 226

XAC03-216070-502 Issue PO 0 29-Mar-16* 226

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:14 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-216070-503 NTF : Notice to Fabricate 0 10-Nov-16 147

XAC03-216070-504 FAT : Factory Acceptance Test 0 11-Dec-16 116

XAC03-216070-508 FOB or ETD 0 05-Jan-17 116

XAC03-216070-510 MHO : LV Switchgear 0 05-Jan-17 116

03PMS-BL00.2.1.6.08 MCC/AC
MC DB 288 31-Mar-16 12-Jan-17 118

XAC03-216080-501 Issue RFQ 0 31-Mar-16* 189

XAC03-216080-502 Issue PO 0 05-May-16* 189

XAC03-216080-503 NTF : Notice to Fabricate 0 10-Nov-16 156

XAC03-216080-504 FAT : Factory Acceptance Test 0 18-Dec-16 118

XAC03-216080-508 FOB or ETD 0 12-Jan-17 118

XAC03-216080-510 MHO : MCC / AC DB 0 12-Jan-17 118

03PMS-BL00.2.1.6.09 DC System / UPS 340 28-Feb-16 01-Feb-17 14

XAC03-216090-501 Issue RFQ 0 28-Feb-16* 106

XAC03-216090-502 Issue PO 0 28-Apr-16* 106

XAC03-216090-503 NTF : Notice to Fabricate 0 03-Oct-16 75

XAC03-216090-504 FAT : Factory Acceptance Test 0 03-Dec-16 14

XAC03-216090-508 FOB or ETD 0 18-Dec-16 14

XAC03-216090-510 MHO : DC System & UPS System 0 01-Feb-17 14

03PMS-BL00.2.1.6.10 Em
Emergency Diesel Engine Generator 360 28-Feb-16 21-Feb-17 130

XAC03-216100-501 Issue RFQ 0 28-Feb-16* 264

XAC03-216100-502 Issue PO 0 28-Apr-16* 264

XAC03-216100-503 NTF : Notice to Fabricate 0 28-Oct-16 186

XAC03-216100-504 FAT : Factory Acceptance Test 0 23-Dec-16 130

XAC03-216100-508 FOB or ETD 0 07-Jan-17 130

XAC03-216100-510 MHO : Emergency DG System 0 21-Feb-17 130

03PMS-BL00.2.1.7 Electrical
Electri bulk 377 15-Apr-16 26-Apr-17 245

03PMS-BL00.2.1.7.01 Cables
Ca 273 15-Jun-16 15-Mar-17 42

XAC03-217010-501 Issue RFQ 0 15-Jun-16* 162

XAC03-217010-502 Issue PO 0 15-Sep-16* 162

XAC03-217010-503 NTF : Notice to Fabricate 0 15-Oct-16 162

XAC03-217010-504 FAT : Factory Acceptance Test 0 17-Feb-17 37

XAC03-217010-508 FOB or ETD 0 14-Mar-17 37

XAC03-217010-510A MHO :Control Cable & Instrumentation Cable 0 15-Mar-17* 37

XAC03-217010-510B MHO : Cable 0 15-Mar-17* 42

03PMS-BL00.2.1.7.02 Raceway
Ra 179 15-Apr-16 11-Oct-16 72

XAC03-217020-501 Issue RFQ 0 15-Apr-16* 148

XAC03-217020-502 Issue PO 0 01-Jul-16* 148

XAC03-217020-503 NTF : Notice to Fabricate 0 01-Jul-16 148

XAC03-217020-504 FAT : Factory Acceptance Test 0 15-Sep-16 72

XAC03-217020-508 FOB or ETD 0 10-Oct-16 72

XAC03-217020-510 MHO : Raceway 0 11-Oct-16* 72

03PMS-BL00.2.1.7.03 Secondary
Se raceway 179 15-Apr-16 11-Oct-16 72

XAC03-217030-501 Issue RFQ 0 15-Apr-16* 148

XAC03-217030-502 Issue PO 0 01-Jul-16* 148

XAC03-217030-503 NTF : Notice to Fabricate 0 01-Jul-16 148

XAC03-217030-504 FAT : Factory Acceptance Test 0 15-Sep-16 72

XAC03-217030-508 FOB or ETD 0 10-Oct-16 72

XAC03-217030-510 MHO : Secondary Raceway 0 11-Oct-16* 72

03PMS-BL00.2.1.7.04 Grounding
Gr 90 15-Apr-16 14-Jul-16 337

XAC03-217040-501 Issue RFQ 0 15-Apr-16* 162

XAC03-217040-502 Issue PO 0 14-May-16* 262

XAC03-217040-503 NTF : Notice to Fabricate 0 03-Jun-16 352

XAC03-217040-504 FAT : Factory Acceptance Test 0 18-Jun-16 337

XAC03-217040-508 FOB or ETD 0 13-Jul-16 337

XAC03-217040-510 MHO : Grounding Cable 0 14-Jul-16* 337

03PMS-BL00.2.1.7.05 Lightning
Lig Protection system 291 15-Apr-16 30-Jan-17 22

XAC03-217050-501 Issue RFQ 0 15-Apr-16* 162

XAC03-217050-502 Issue PO 0 14-May-16* 196

XAC03-217050-503 NTF : Notice to Fabricate 0 13-Jul-16 198

XAC03-217050-504 FAT : Factory Acceptance Test 0 05-Jan-17 22

XAC03-217050-508 FOB or ETD 0 30-Jan-17 22

XAC03-217050-510 MHO : Lightning Protection 0 30-Jan-17 22

03PMS-BL00.2.1.7.06 Lighting
Lig System 377 15-Apr-16 26-Apr-17 245

XAC03-217060-501 Issue RFQ 0 15-Apr-16* 162

XAC03-217060-502 Issue PO 0 14-May-16 432

XAC03-217060-503 NTF : Notice to Fabricate 0 13-Jun-16 533

XAC03-217060-504 FAT : Factory Acceptance Test 0 28-Mar-17 245

XAC03-217060-508 FOB or ETD 0 11-Apr-17 245

XAC03-217060-510 MHO : Lighting and Small Power 0 26-Apr-17 245

03PMS-BL00.2.1.7.07 Sealing
Se Material 230 15-Jun-16 30-Jan-17 38

XAC03-217070-501 Issue RFQ 0 15-Jun-16* 183

XAC03-217070-502 Issue PO 0 14-Jul-16 183

XAC03-217070-503 NTF : Notice to Fabricate 0 13-Aug-16 183

XAC03-217070-504 FAT : Factory Acceptance Test 0 05-Jan-17 38

XAC03-217070-508 FOB or ETD 0 30-Jan-17 38

XAC03-217070-510 MHO : Sealing Materials 0 30-Jan-17 38

03PMS-BL00.2.1.8 Switchyard
Switch 374 06-Dec-15 14-Dec-16 308

03PMS-BL00.2.1.8.01 GI
GIS / AIS 374 06-Dec-15 14-Dec-16 308

XAC03-218010-501 Issue RFQ 0 06-Dec-15* 91

XAC03-218010-502 Issue PO 0 25-Mar-16* 91

XAC03-218010-510A MHO : Switch Yard (Embedded material) 0 30-Sep-16 383

XAC03-218010-503 NTF : Notice to Fabricate 0 15-Oct-16 91

XAC03-218010-504 FAT : Factory Acceptance Test 0 15-Oct-16 91

XAC03-218010-508 FOB or ETD 0 30-Oct-16 91

XAC03-218010-510B MHO : Switch Yard (Main Equipment) 0 14-Dec-16 91

XAC03-218010-510C MHO : Switch Yard (Protection Panels) 0 14-Dec-16 103

03PMS-BL00.3 CONSTRUC
CONSTRUCTION & COMMISSIONING 762 01-Dec-15 01-Jan-18 32

03PMS-BL00.3.1 GENERA
GENERAL WORK 125 01-Dec-15 22-Apr-16 93

03PMS-BL00.3.1.1 Civil P
Preparation (Soil Investigation) Work 125 01-Dec-15 22-Apr-16 93

03PMS-BL00.3.1.1.1 Civ
Civil Preparation (Soil Investigation) 125 01-Dec-15 22-Apr-16 93

XAC03-31111000 Civil Preparation (Soil Investigation) Work - Inform to Owner 0 01-Dec-15 45

XAC03-31112000 Civil Preparation (Soil Investigation) Work - Permit for Site Access from Owner 5 01-Dec-15 05-Dec-15 45

XAC03-31113000 Civil Preparation (Soil Investigation) Work - Preparation for Soil Investigation 6 05-Dec-15 12-Dec-15 45

XAC03-31114000 Civil Preparation (Soil Investigation) Work - Soil Investigation 14 12-Dec-15 29-Dec-15 45

XAC03-31115000 Civil Preparation (Soil Investigation) Work - Documentation for Report 18 29-Dec-15 19-Jan-16 45

XAC03-31116000 Civil Preparation (Soil Investigation) Work - Preliminary Report from Site 1 19-Jan-16 20-Jan-16 45

XAC03-31117000 Civil Preparation (Soil Investigation) Work - Report submit to Owner 5 20-Jan-16 26-Jan-16 45

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:15 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-31118000 Civil Preparation (Soil Investigation) Work - Pile Calculation 40 26-Jan-16 12-Mar-16 45

XAC03-31119000 Civil Preparation (Soil Investigation) Work - Pile Load Test 36 12-Mar-16 22-Apr-16 93

03PMS-BL00.3.2 CIVIL WORK


WO 497 27-Apr-16 06-Sep-17 148

03PMS-BL00.3.2.1 Civil (STG


(S #3 Area) 305 06-Jun-16 06-Apr-17 277

03PMS-BL00.3.2.1.01 St
Steam Turbine / Generator #3 305 06-Jun-16 06-Apr-17 155

03PMS-BL00.3.2.1.01.1 Pile Work (STG #3) 24 06-Jun-16 02-Jul-16 61

XAC03-32101110 Pile Work 24 06-Jun-16* 02-Jul-16 61

03PMS-BL00.3.2.1.01.2 Foundation Work 244 04-Jul-16 04-Mar-17 188

03PMS-BL00.3.2.1.01.2.1 STG #3 Foundation


03PMS-BL00.3.2.1.01.2 71 21-Sep-16 12-Dec-16 78

XAC03-32101211 STG Foundation - Excavation 14 21-Sep-16 06-Oct-16 70

XAC03-32101212 STG Foundation - Lean concrete 7 30-Sep-16 07-Oct-16 78

XAC03-32101213 STG Foundation - Pile cut off 7 01-Oct-16 08-Oct-16 78

XAC03-32101214 STG Foundation - Install Reinforcement 22 10-Oct-16 03-Nov-16 78

XAC03-32101215 STG Foundation - Install Embeded part material 9 10-Oct-16 19-Oct-16 92

XAC03-32101216 STG Foundation - Install side formwork 14 20-Oct-16 04-Nov-16 78

XAC03-32101217 STG Foundation - Casting concrete foundation 2 05-Nov-16 07-Nov-16 78

XAC03-32101219 STG Foundation - Concrete Curing 30 08-Nov-16 12-Dec-16 78

XAC03-32101218 STG Foundation - H/O to Mech 0 12-Dec-16 78

03PMS-BL00.3.2.1.01.2.2 CEP Pit Foundation


03PMS-BL00.3.2.1.01.2 79 04-Jul-16 20-Sep-16 81

XAC03-32101221 CEP PIT - Excavation 3 04-Jul-16* 06-Jul-16 61

XAC03-32101222 CEP PIT - Install the bracing 3 07-Jul-16 09-Jul-16 61

XAC03-32101223 CEP PIT - Excavation 5 11-Jul-16 15-Jul-16 61

XAC03-32101224 CEP PIT - Lean Concrete 1 16-Jul-16 16-Jul-16 61

XAC03-32101225 CEP PIT - Pump area - slab - Install Reinforcement 2 18-Jul-16 19-Jul-16 61

XAC03-32101226 CEP PIT - Pump area - slab - Install side formwork 1 20-Jul-16 20-Jul-16 61

XAC03-32101227 CEP PIT - Pump area - Slab - Casting concrete foundation 1 22-Jul-16 22-Jul-16 61

XAC03-32101228 CEP PIT - Pump area - Wall - Install Reinforcement 1 25-Jul-16 26-Jul-16 61

XAC03-32101229 CEP PIT - Pump area - Install side formwork 2 27-Jul-16 28-Jul-16 61

XAC03-3210122A CEP PIT - Pump area - Wall - Casting concrete foundation 2 29-Jul-16 30-Jul-16 61

XAC03-3210122B CEP PIT - CEP Base Foundation - Backfill 2 09-Aug-16 11-Aug-16 61

XAC03-3210122C CEP PIT - CEP Base Foundation - Lean concrete 2 13-Aug-16 15-Aug-16 61

XAC03-3210122D CEP PIT - CEP Base Foundation - Pile Cutting 2 16-Aug-16 17-Aug-16 61

XAC03-3210122E CEP PIT - CEP Base Foundation - Slab - Install Reinforcement 12 18-Aug-16 31-Aug-16 61

XAC03-3210122F CEP PIT - CEP Base Foundation - Slab - Install side formwork 3 30-Aug-16 02-Sep-16 70

XAC03-3210122G CEP PIT - CEP Base Foundation - Slab - Casting concrete foundation 1 03-Sep-16 05-Sep-16 61

XAC03-3210122H CEP PIT - CEP Base Foundation - Wall - Install Reinforcement 10 07-Sep-16 17-Sep-16 61

XAC03-3210122I CEP PIT - CEP Base Foundation - Wall - Install side formwork 5 13-Sep-16 17-Sep-16 70

XAC03-3210122J CEP PIT - CEP Base Foundation - Wall - Casting concrete foundation 2 19-Sep-16 20-Sep-16 70

XAC03-3210122K CEP Foundation - H/O to Mech 0 20-Sep-16 70

03PMS-BL00.3.2.1.01.2.3 CVP Foundation


03PMS-BL00.3.2.1.01.2 12 28-Nov-16 12-Dec-16 234

XAC03-32101231 CVP Pump Foundation - Install Reinforcement 6 28-Nov-16 05-Dec-16 100

XAC03-32101232 CVP Pump Foundation - Install side formwork 4 06-Dec-16 09-Dec-16 234

XAC03-32101233 CVP Pump Foundation - Casting concrete foundation 1 10-Dec-16 12-Dec-16 234

XAC03-32101234 CVP Pump Foundation - H/O to Mech 0 12-Dec-16 234

03PMS-BL00.3.2.1.01.2.4 Extraction Heater Foundation


03PMS-BL00.3.2.1.01.2 84 28-Nov-16 04-Mar-17 100

XAC03-32101241 Extraction Heater Foundation - Install Reinforcement 78 28-Nov-16 25-Feb-17 100

XAC03-32101242 Extraction Heater Foundation - Install side formwork 4 27-Feb-17 02-Mar-17 100

XAC03-32101243 Extraction Heater Foundation - Casting concrete foundation 1 03-Mar-17 04-Mar-17 100

XAC03-32101244 Extraction Heater Foundation - H/O to Mech 0 04-Mar-17 100

03PMS-BL00.3.2.1.01.3 Building Work (STG #3) 160 05-Oct-16 06-Apr-17 36

XAC03-32101340 STG Building - Footing - Install Reinforcement 39 05-Oct-16* 18-Nov-16 47

XAC03-32101350 STG Building - Footing - Install Embeded part material 39 06-Oct-16 19-Nov-16 47

XAC03-32101310 STG Building - Excavation 39 07-Oct-16 21-Nov-16 70

XAC03-32101360 STG Building - Footing - Install side formwork 38 08-Oct-16 21-Nov-16 47

XAC03-32101320 STG Building - Lean concrete 35 12-Oct-16 21-Nov-16 70

XAC03-32101330 STG Building - Pile cut off 34 22-Oct-16 30-Nov-16 70

XAC03-32101370 STG Building - Footing - Casting concrete foundation 1 22-Nov-16 23-Nov-16 47

XAC03-32101380 STG Building - Slab - Install Reinforcement 11 30-Nov-16 13-Dec-16 79

XAC03-321013B0 Structure Delivery 0 01-Dec-16* 48

XAC03-32101390 STG Building - Slab - Install side formwork 11 05-Dec-16 16-Dec-16 79

XAC03-321013A0 STG Building - Slab- Conrete Work - Install side formwork 11 05-Dec-16 16-Dec-16 79

XAC03-321013D0 STG Building - Slab - Casting concrete foundation 1 17-Dec-16 17-Dec-16 79

XAC03-321013C0 Steel Structure 46 19-Dec-16* 09-Feb-17 33

XAC03-321013F0 H/O to Crane Gutter 0 19-Jan-17 33

XAC03-321013J0 Roof Cadding 25 02-Feb-17 02-Mar-17 36

XAC03-321013G0 H/O to Mech Crane 0 02-Feb-17 33

XAC03-321013H0 H/O to Mech Condenser 0 09-Feb-17 84

XAC03-321013E0 Block Wall 18 10-Feb-17 02-Mar-17 36

XAC03-321013K0 Wall Cadding 30 03-Mar-17 06-Apr-17 36

XAC03-321013I0 H/O to Mech All 0 06-Apr-17 36

03PMS-BL00.3.2.1.02 Co
Condenser Ball Cleaning Foundation 12 11-Jan-17 23-Jan-17 102

03PMS-BL00.3.2.1.02.2 Foundation Work 12 11-Jan-17 23-Jan-17 102

XAC03-32102210 Foundation Condenser Ball Cleaning Water System 10 11-Jan-17 23-Jan-17 89

XAC03-32102220 Foundation Work - H/O to Mech 0 23-Jan-17 74

03PMS-BL00.3.2.1.03 Cl
Closed Cycle Cooling Water System 15 13-Jan-17 27-Jan-17 75

03PMS-BL00.3.2.1.03.2 Foundation Work 15 13-Jan-17 27-Jan-17 75

XAC03-32103210 Closed Cycle Cooling Water System - Civil Work 13 13-Jan-17* 27-Jan-17 64

XAC03-32103220 Closed Cycle Cooling Water System - H/O to Mech 0 27-Jan-17 53

03PMS-BL00.3.2.1.06 Pip
Pipe Rack RF (STG#30 / E&C Area) 47.5 m + 26.0 m. 191 07-Jun-16 14-Dec-16 91

03PMS-BL00.3.2.1.06.1 Pile Work 5 07-Jun-16 11-Jun-16 168

XAC03-32106110 Pile Work 5 07-Jun-16 11-Jun-16 168

03PMS-BL00.3.2.1.06.2 Foundation Work 40 08-Sep-16 24-Oct-16 92

XAC03-3210621A Excavation+Lean+Pile cutting 7 08-Sep-16* 15-Sep-16 92

XAC03-32106211 Slab - Install Reinforcement 10 16-Sep-16 27-Sep-16 92

XAC03-32106212 Slab - Install formwork 6 22-Sep-16 29-Sep-16 92

XAC03-32106213 Slab - Casting concrete 0 30-Sep-16 30-Sep-16 92

XAC03-32106214 Pedestal - Install Reinforcement 7 03-Oct-16 10-Oct-16 92

XAC03-32106215 Pedestal - Install anchor bolt 5 11-Oct-16 15-Oct-16 92

XAC03-32106216 Pedestal - Install formwork 2 17-Oct-16 18-Oct-16 92

XAC03-32106217 Pedestal - Casting concrete 1 19-Oct-16 19-Oct-16 92

XAC03-32106218 Backfill 4 20-Oct-16 24-Oct-16 92

XAC03-32106219 Pipe Rack RF Foundation - H/O to Mech 0 24-Oct-16 92

03PMS-BL00.3.2.1.06.4 Structure Work 36 09-Nov-16 14-Dec-16 91

XAC03-32106410 Structure Delvery 0 09-Nov-16* 79

XAC03-32106420 Steel Structure 30 09-Nov-16 13-Dec-16 79

XAC03-32106430 Steel Structure - H/O to Mech 0 14-Dec-16 65

03PMS-BL00.3.2.1.07 Ca
Cable Trench (STG#30 - Pipe Rack RB ) 60 07-Jun-16 15-Aug-16 444

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:16 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
03PMS-BL00.3.2.1.07.1 Pile Work 5 07-Jun-16 11-Jun-16 254

XAC03-32107110 Pile Work 5 07-Jun-16 11-Jun-16 254

03PMS-BL00.3.2.1.07.2 Cable Trench 54 13-Jun-16 15-Aug-16 444

XAC03-32107210 Cable Trench - Excavation 6 13-Jun-16 20-Jun-16 254

XAC03-32107220 Cable Trench - Lean concrete 2 18-Jun-16 21-Jun-16 254

XAC03-32107240 Cable Trench - Slab - Install Reinforcement 8 04-Jul-16 13-Jul-16 254

XAC03-32107250 Cable Trench - Slab - Install side formwork 9 14-Jul-16 23-Jul-16 254

XAC03-32107260 Cable Trench - Slab - Casting concrete 1 25-Jul-16 25-Jul-16 254

XAC03-32107270 Cable Trench - Wall - Install Reinforcement 12 27-Jul-16 09-Aug-16 254

XAC03-32107280 Cable Trench - Wall - Install side formwork 6 03-Aug-16 10-Aug-16 254

XAC03-32107290 Cable Trench - Wall - Casting concrete 1 11-Aug-16 11-Aug-16 254

XAC03-321072A0 Cable Trench - Backfill 1 13-Aug-16 15-Aug-16 254

XAC03-321072B0 Cable Trench - H/O to Mech 0 15-Aug-16 444

03PMS-BL00.3.2.1.08 Ca
Cable Trench (STG#30 - Pipe Rack RB Road Crossing ) 76 07-Jun-16 01-Sep-16 238

03PMS-BL00.3.2.1.08.1 Pile Work 5 07-Jun-16 11-Jun-16 238

XAC03-32108110 Pile Work 5 07-Jun-16 11-Jun-16 238

03PMS-BL00.3.2.1.08.2 Cable Trench 70 13-Jun-16 01-Sep-16 238

XAC03-32108210 Cable Trench - Excavation 4 13-Jun-16 17-Jun-16 238

XAC03-32108220 Cable Trench - Lean concrete 2 17-Jun-16 20-Jun-16 238

XAC03-32108240 Cable Trench - Slab - Install Reinforcement 10 21-Jun-16 01-Jul-16 238

XAC03-32108250 Cable Trench - Slab - Install side formwork 10 02-Jul-16 13-Jul-16 238

XAC03-32108260 Cable Trench - Slab - Casting concrete 1 14-Jul-16 14-Jul-16 238

XAC03-32108270 Cable Trench - Wall - Install Reinforcement 11 19-Jul-16 01-Aug-16 238

XAC03-32108280 Cable Trench - Wall - Install side formwork 6 27-Jul-16 03-Aug-16 238

XAC03-32108290 Cable Trench - Wall - Casting concrete 1 04-Aug-16 04-Aug-16 238

XAC03-321082A0 Cable Trench - Top Slab - Install Reinforcement 13 09-Aug-16 23-Aug-16 238

XAC03-321082B0 Cable Trench - Top Slab - Install side formwork 7 24-Aug-16 31-Aug-16 238

XAC03-321082C0 Cable Trench - Top Slab - Casting concrete 1 01-Sep-16 01-Sep-16 238

XAC03-321082E0 Cable Trench - H/O to Mech 0 01-Sep-16 238

03PMS-BL00.3.2.1.09 Ca
Cable Trench (STG Building) 56 18-Jul-16 19-Sep-16 224

03PMS-BL00.3.2.1.09.2 Cable Trench 56 18-Jul-16 19-Sep-16 224

XAC03-32109210 Cable Trench - Excavation and Lean concrete 6 18-Jul-16 23-Jul-16 224

XAC03-32109220 Cable Trench - Rebar 8 25-Jul-16 02-Aug-16 224

XAC03-32109230 Cable Trench - Formwork and Water Stop 4 30-Jul-16 04-Aug-16 224

XAC03-32109240 Cable Trench - Casting for Base Slab 1 05-Aug-16 05-Aug-16 224

XAC03-32109250 Cable Trench - Rebar Wall 10 10-Aug-16 20-Aug-16 224

XAC03-32109260 Cable Trench - Form Work Wall 5 24-Aug-16 29-Aug-16 224

XAC03-32109270 Cable Trench - Casting Concrete Wall 2 30-Aug-16 31-Aug-16 224

XAC03-32109290 Cable Trench - Scaffolding for TOP Slab 1 03-Sep-16 05-Sep-16 224

XAC03-321092A0 Cable Trench - Top Slab - Form Work 4 06-Sep-16 09-Sep-16 224

XAC03-321092B0 Cable Trench - Rebar for Top Slab 3 10-Sep-16 13-Sep-16 224

XAC03-321092C0 Cable Trench - Casting Concrete TOP Slab 1 14-Sep-16 14-Sep-16 224

XAC03-32109280 Cable Trench - Remove Form work and Reparing Concrete 4 15-Sep-16 19-Sep-16 224

XAC03-321092D0 Cable Trench - H/O to Mech 0 19-Sep-16 224

03PMS-BL00.3.2.1.10 Pipe
Pip Sleeper (STG #3 Area) 26 21-Dec-16 19-Jan-17 116

03PMS-BL00.3.2.1.10.6 Pipe Sleeper (STG #3 Area) 26 21-Dec-16 19-Jan-17 116

XAC03-32110610 Pipe Sleeper STG 3 Area 26 21-Dec-16* 19-Jan-17 85

XAC03-32110620 Pipe Sleeper - H/O to Mech 0 19-Jan-17 116

03PMS-BL00.3.2.1.ZZ O
Other Civil Work 50 13-Dec-16 08-Feb-17 100

XAC03-321ZZ100 STG 3 Area Drain Pit 36 13-Dec-16 23-Jan-17 89

XAC03-321ZZ200 STG 3 Area Drain Pit - H/O to Mech 0 08-Feb-17 100

03PMS-BL00.3.2.2 Civil (E
(E&C Bldg Area) 380 02-May-16 16-May-17 261

03PMS-BL00.3.2.2.01 Ele
Electrical & Control Building 330 02-May-16 27-Mar-17 311

03PMS-BL00.3.2.2.01.1 Pile Work 11 02-May-16 13-May-16 1

XAC03-32201110 Pile Work - E&C 11 02-May-16* 13-May-16 1

03PMS-BL00.3.2.2.01.2 Foundation Work 47 25-May-16 18-Jul-16 3

XAC03-32201210 Foundation Work at E&C Bldg. - Excavation 11 25-May-16 07-Jun-16 1

XAC03-32201220 Foundation Work at E&C Bldg. - Lean concrete 50THK 7 27-May-16 04-Jun-16 1

XAC03-32201230 Foundation Work at E&C Bldg. - Pile cut off 11 06-Jun-16 17-Jun-16 1

XAC03-32201240 Foundation Work at E&C Bldg. - Extend dowel by coupler 1 17-Jun-16 18-Jun-16 1

XAC03-32201250 Foundation Work at E&C Bldg. - Install Reinforcement 11 20-Jun-16 01-Jul-16 1

XAC03-32201260 Foundation Work at E&C Bldg. - Install side formwork 11 21-Jun-16 02-Jul-16 1

XAC03-32201270 Foundation Work at E&C Bldg. - Casting concrete foundation (pile cap) 1 04-Jul-16 04-Jul-16 1

XAC03-32201280 Foundation Work at E&C Bldg. - Remove formwork and repair concrete 12 05-Jul-16 18-Jul-16 3

03PMS-BL00.3.2.2.01.3 Building Work 263 07-Jul-16 27-Mar-17 311

03PMS-BL00.3.2.2.01.3.1 Tie Beam+Ground Slab


03PMS-BL00.3.2.2.01.3 44 07-Jul-16 27-Aug-16 1

XAC03-32201311 Tie Beam - Backfill 8 07-Jul-16 16-Jul-16 1

XAC03-32201312 Tie Beam - Lean concrete 50THK 3 18-Jul-16 20-Jul-16 1

XAC03-32201313 Tie Beam - Install side formwork (block wall) 10 21-Jul-16 01-Aug-16 1

XAC03-32201321 Ground Slab - Backfill 7 25-Jul-16 02-Aug-16 1

XAC03-32201322 Ground Slab - Lean concrete 50THK 2 30-Jul-16 02-Aug-16 1

XAC03-32201323 Tie Beam+Ground Slab - Install Reinforcement 10 03-Aug-16 13-Aug-16 1

XAC03-32201324 Tie Beam+Ground Slab - Install side formwork 3 15-Aug-16 17-Aug-16 1

XAC03-32201325 Tie Beam+Ground slab - Casting concrete 1 23-Aug-16 23-Aug-16 1

XAC03-32201326 Tie Beam+Ground slab - Curing 4 23-Aug-16 27-Aug-16 1

03PMS-BL00.3.2.2.01.3.3 Ground floor (Column) +0.20 m


03PMS-BL00.3.2.2.01.3 55 27-Aug-16 29-Oct-16 94

XAC03-32201336 Ground floor (Column) +0.20 m - Survey Marking 1 27-Aug-16 29-Aug-16 1

XAC03-32201337 Ground floor (Column) +0.20 m - Scaffolding installation 3 29-Aug-16 01-Sep-16 1

XAC03-32201331 Ground floor (Column) +0.20 m - Install Reinforcement 5 01-Sep-16 07-Sep-16 1

XAC03-32201332 Ground floor (Column) +0.20 m - Install side formwork 6 01-Sep-16 08-Sep-16 1

XAC03-32201333 Ground floor (Column) +0.20 m - Casting concrete 1 08-Sep-16 09-Sep-16 1

XAC03-32201334 Block Wall with plastering GF 11 17-Oct-16 29-Oct-16 57

XAC03-32201335 Ground floor (Column) +0.20 m - Cable Celler Room - H/O to Mech 0 29-Oct-16 94

03PMS-BL00.3.2.2.01.3.4 1st Floor (SWGR) (Beam+Slab) +2.70m


03PMS-BL00.3.2.2.01.3 79 09-Sep-16 09-Dec-16 67

XAC03-32201341 1st Floor (SWGR) (Beam+Slab) +2.70m - Scaffolding Installation 8 09-Sep-16 19-Sep-16 1

XAC03-32201342 1st Floor (SWGR) (Beam+Slab) +2.70m - Install Reinforcement 10 19-Sep-16 30-Sep-16 1

XAC03-32201343 1st Floor (SWGR) (Beam+Slab) +2.70m - Install side formwork 10 19-Sep-16 30-Sep-16 1

XAC03-32201344 1st Floor (SWGR) (Beam+Slab) +2.70m - Casting concrete 1 30-Sep-16 01-Oct-16 1

XAC03-3220134B 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Survey Marking 1 01-Oct-16 03-Oct-16 1

XAC03-3220134C 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Scaffolding Installation 2 03-Oct-16 05-Oct-16 1

XAC03-32201345 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Install Reinforcement 7 06-Oct-16 14-Oct-16 1

XAC03-32201346 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Install side formwork 7 06-Oct-16 14-Oct-16 1

XAC03-32201347 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Casting concrete 1 14-Oct-16 15-Oct-16 1

XAC03-32201348 Block Wall with plastering 1F +Floor coating 17 19-Nov-16 09-Dec-16 34

XAC03-3220134A 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - SWGR Room - H/O to 0 09-Dec-16 67
Mech
03PMS-BL00.3.2.2.01.3.5 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m
03PMS-BL00.3.2.2.01.3 77 15-Oct-16 12-Jan-17 29

XAC03-32201351 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Scaffolding Installation 5 15-Oct-16 21-Oct-16 1

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:17 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-32201352 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Install Reinforcement 11 21-Oct-16 03-Nov-16 1

XAC03-32201353 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Install side formwork 8 25-Oct-16 03-Nov-16 1

XAC03-32201354 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Casting concrete 1 03-Nov-16 04-Nov-16 1

XAC03-3220135A 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Survey 1 05-Nov-16 07-Nov-16 1
Marking
XAC03-3220135B 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - 3 07-Nov-16 10-Nov-16 1
Scaffolding Installation
XAC03-32201355 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Install 5 10-Nov-16 16-Nov-16 1
Reinforcement
XAC03-32201356 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Install side 5 10-Nov-16 16-Nov-16 1
formwork
XAC03-32201357 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Casting 3 16-Nov-16 19-Nov-16 1
concrete
XAC03-32201358 Block Wall with plastering 2F+Floor coating 12 29-Dec-16 12-Jan-17 1

XAC03-32201359 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - 0 12-Jan-17 29
Battery/HVAC Room - H/O to mech
03PMS-BL00.3.2.2.01.3.6 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m
03PMS-BL00.3.2.2.01.3 128 19-Nov-16 27-Mar-17 311

XAC03-32201361 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Scaffolding Installation 7 19-Nov-16 28-Nov-16 1

XAC03-32201362 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Install Reinforcement 10 01-Dec-16 13-Dec-16 1

XAC03-32201363 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Install side formwork 6 06-Dec-16 13-Dec-16 1

XAC03-3220136E Wall Paint 85 09-Dec-16 17-Mar-17 278

XAC03-32201364 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Casting concrete 1 13-Dec-16 14-Dec-16 1

XAC03-32201365 Column at 3rd Floor - Install Reinforcement 10 14-Dec-16 26-Dec-16 31

XAC03-32201366 Column at 3rd Floor - Install side formwork 5 21-Dec-16 26-Dec-16 36

XAC03-32201367 Column at 3rd Floor - Casting concrete 1 27-Dec-16 27-Dec-16 31

XAC03-32201368 Block Wall with plastering 3F (only DCS) 6 07-Jan-17 14-Jan-17 31

XAC03-32201369 Block Wall with plastering 3F 25 14-Jan-17 13-Feb-17 306

XAC03-3220136A Ceiling 26 14-Jan-17 14-Feb-17 305

XAC03-3220136B Free Access Floor (only DCS) 8 14-Jan-17 24-Jan-17 31

XAC03-3220136C Free Access Floor 54 25-Jan-17 27-Mar-17 270

XAC03-3220136D DCS/CCR Room - H/O to mech 0 13-Feb-17 37

03PMS-BL00.3.2.2.01.3.7 Roof Beam Work


03PMS-BL00.3.2.2.01.3 17 19-Dec-16 07-Jan-17 31

XAC03-332031290 Roof Beam - Scaffolding Installation 7 19-Dec-16 27-Dec-16 31

XAC03-32201371 Roof Beam - Install Reinforcement 9 27-Dec-16 06-Jan-17 31

XAC03-32201372 Roof Beam - Install side formwork 5 31-Dec-16 06-Jan-17 31

XAC03-332031390 Roof Beam - Install Embedded 5 02-Jan-17 06-Jan-17 31

XAC03-32201373 Roof Beam - Casting concrete 1 06-Jan-17 07-Jan-17 31

03PMS-BL00.3.2.2.01.3.8 Steel Structure


03PMS-BL00.3.2.2.01.3 45 07-Jan-17 01-Mar-17 90

XAC03-32201381 Steel structure Roof 10 07-Jan-17 19-Jan-17 37

XAC03-32201382 Roof Cadding 14 19-Jan-17 04-Feb-17 37

XAC03-32201383 Roof Finishing 21 04-Feb-17 01-Mar-17 90

03PMS-BL00.3.2.2.02 LV Transformer #3, #4 Area 324 01-Jun-16 20-Apr-17 54

03PMS-BL00.3.2.2.02.1 Pile Work 14 01-Jun-16 16-Jun-16 137

XAC03-32202110 Pile Work - LV Transformer 14 01-Jun-16* 16-Jun-16 137

03PMS-BL00.3.2.2.02.2 Foundation Work 176 27-Oct-16 20-Apr-17 54

03PMS-BL00.3.2.2.02.2.1 LV Transformer Found ation (South sid e)


03PMS-BL00.3.2.2.02.2 64 27-Oct-16 07-Jan-17 99

XAC03-32202211 LV Transformer Foundation (south side) - Excavation 4 27-Oct-16* 31-Oct-16 23

XAC03-32202212 LV Transformer Foundation (south side) - Lean concrete 50THK 6 01-Nov-16 07-Nov-16 91

XAC03-32202213 LV Transformer Foundation (south side) - Pile cut off 8 08-Nov-16 16-Nov-16 91

XAC03-32202214 LV Transformer Foundation (south side) - Install Reinforcement 19 17-Nov-16 08-Dec-16 91

XAC03-32202215 LV Transformer Foundation (south side) - Install sid e formwork 11 09-Dec-16 21-Dec-16 91

XAC03-32202216 LV Transformer Foundation (south side) - Casting c oncrete foundation 1 22-Dec-16 22-Dec-16 91

XAC03-32202217 Foundation - H/O to Mech 0 07-Jan-17 99

03PMS-BL00.3.2.2.02.2.2 LV Transformer Found ation (North side)


03PMS-BL00.3.2.2.02.2 48 04-Mar-17 20-Apr-17 54

XAC03-32202221 LV Transformer Foundation (North side) - Excavation 6 04-Mar-17* 10-Mar-17 37

XAC03-32202222 LV Transformer Foundation (North side) - Lean concrete 50THK 6 08-Mar-17 14-Mar-17 37

XAC03-32202223 LV Transformer Foundation (North side) - Pile cut off 6 15-Mar-17 21-Mar-17 37

XAC03-32202224 LV Transformer Foundation (North side) - Install Reinforcement 10 22-Mar-17 01-Apr-17 37

XAC03-32202225 LV Transformer Foundation (North side) - Install sid e formwork 10 23-Mar-17 04-Apr-17 37

XAC03-32202226 LV Transformer Foundation (North side) - Casting c oncrete foundation 1 05-Apr-17 05-Apr-17 37

XAC03-32202227 Foundation - H/O to Mech 0 20-Apr-17 38

03PMS-BL00.3.2.2.03 Ca
Cable Trench (E&C Building - Pipe Rack RE) 194 30-May-16 07-Jan-17 5

03PMS-BL00.3.2.2.03.1 Pile Work 11 30-May-16 10-Jun-16 146

XAC03-32203110 Pile Work 11 30-May-16* 10-Jun-16 146

03PMS-BL00.3.2.2.03.2 Cable Trench 42 21-Nov-16 07-Jan-17 5

XAC03-32203210 Cable Trench (E&C Bldg. - Pipe Rack RE) - Excavation 3 21-Nov-16* 23-Nov-16 5

XAC03-32203220 Cable Trench (E&C Bldg. - Pipe Rack RE) - Lean concrete 2 24-Nov-16 25-Nov-16 5

XAC03-32203230 Cable Trench (E&C Bldg. - Pipe Rack RE) - Pile cut off 3 26-Nov-16 29-Nov-16 5

XAC03-32203240 Cable Trench (E&C Bldg. - Pipe Rack RE) - Slab - Install Reinforcement 3 30-Nov-16 02-Dec-16 5

XAC03-32203250 Cable Trench (E&C Bldg. - Pipe Rack RE) - Slab - Install side formwork 3 03-Dec-16 06-Dec-16 5

XAC03-32203260 Cable Trench (E&C Bldg. - Pipe Rack RE) - Casting concrete 1 07-Dec-16 07-Dec-16 5

XAC03-32203270 Cable Trench (E&C Bldg. - Pipe Rack RE) - Wall - Install Reinforcement 7 12-Dec-16 20-Dec-16 5

XAC03-32203280 Cable Trench (E&C Bldg. - Pipe Rack RE) - Wall - Install side formwork 2 21-Dec-16 22-Dec-16 5

XAC03-32203290 Cable Trench (E&C Bldg. - Pipe Rack RE) - Wall - Casting concrete 1 23-Dec-16 23-Dec-16 5

XAC03-322032A0 Cable Trench (E&C Bldg. - Pipe Rack RE) - Backfill 3 04-Jan-17 07-Jan-17 5

XAC03-322032B0 Cable Trench (E&C Bldg. - Pipe Rack RE) - H/O to Mech 0 07-Jan-17 5

03PMS-BL00.3.2.2.04 Pip
Pipe Sleeper E&C Building Area 131 22-Dec-16 01-May-17 43

03PMS-BL00.3.2.2.04.1 Pipe Sleeper E&C Building Area 131 22-Dec-16 01-May-17 43

XAC03-32204110 Pipe Sleeper (E&C Bldg.) - East Side - LV Trans. Drain Pit 19 22-Dec-16 18-Jan-17 75

XAC03-32204130 Pipe Sleeper (E&C Bldg.) - East Side -H/O to Mech 0 18-Jan-17 91

XAC03-32204120 Pipe Sleeper (E&C Bldg.) - North Side - LV Trans. Drain Pit 19 05-Apr-17 01-May-17 31

XAC03-32204140 Pipe Sleeper (E&C Bldg.) - North Side -H/O to Mech 0 01-May-17 37

03PMS-BL00.3.2.2.ZZ O
Other Civil Work 225 03-Oct-16 16-May-17 261

XAC03-322ZZ100 Civil (E&C Bldg Area) - South Side - LV Trans. Drain Pit 37 03-Oct-16* 23-Nov-16 108

XAC03-322ZZ400 Civil (E&C Bldg Area) - South Side - LV Trans. Drain Pit - H/O to Mech 0 01-Dec-16 131

XAC03-322ZZ300 Civil (E&C Bldg Area) - North Side - LV Trans. Drain Pit 38 14-Feb-17* 06-Apr-17 204

XAC03-322ZZ200 Civil (E&C Bldg Area) - Septic Tank and Sanitary System 54 01-Mar-17* 16-May-17 187

XAC03-322ZZ600 Civil (E&C Bldg Area) - North Side - LV Trans. Drain Pit - H/O to Mech 0 21-Apr-17 248

XAC03-322ZZ500 Civil (E&C Bldg Area) - Septic Tank and Sanitary System - H/O to Mech 0 16-May-17 226

03PMS-BL00.3.2.3 Civil (HRSG/


(H GTG #3 Area) 435 27-Apr-16 06-Jul-17 210

03PMS-BL00.3.2.3.01 Ga
Gas Turbine / Generator #31 143 13-May-16 03-Oct-16 177

03PMS-BL00.3.2.3.01.1 Pile Work 12 13-May-16 26-May-16 39

XAC03-32301110 Pile - GTG 31 12 13-May-16* 26-May-16 39

03PMS-BL00.3.2.3.01.2 Foundation Work 114 10-Jun-16 03-Oct-16 177

03PMS-BL00.3.2.3.01.2.1 GTG Foundation


03PMS-BL00.3.2.3.01.2 109 10-Jun-16 27-Sep-16 117

XAC03-32301211 Foundation - Excavation 6 10-Jun-16* 17-Jun-16 39

XAC03-32301212 Foundation - Lean concrete 50THK 4 15-Jun-16 18-Jun-16 39

XAC03-32301213 Foundation - Pile cut off 9 20-Jun-16 29-Jun-16 39

XAC03-3230121E Foundatio&Pedestaln - Embedded (M&E) 7 30-Jun-16 07-Jul-16 45

XAC03-32301214 Foundatio&Pedestaln - Install Reinforcement 17 08-Jul-16 27-Jul-16 45

XAC03-32301215 Foundatio&Pedestaln - Embedded (M&E) 7 28-Jul-16 04-Aug-16 45

XAC03-32301216 Foundation&Pedestal - Install box out 13 05-Aug-16 19-Aug-16 45

XAC03-32301217 Foundation&Pedestal - Install side formwork 6 17-Aug-16 23-Aug-16 45

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:18 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3230121A Foundation&Pedestal - casting concrete foundation 1 24-Aug-16 24-Aug-16 45

XAC03-3230121B Foundation/Pedestal - curing time (Control Temparature) 20 25-Aug-16 16-Sep-16 45

XAC03-3230121C Foundation/Pedestal - Remove formwork 5 17-Sep-16 22-Sep-16 45

XAC03-3230121F Foundation/Pedestal - Epoxy Injection under steel plate 3 23-Sep-16 26-Sep-16 101

XAC03-3230121D GTG Foundation - H/O to Mech 0 27-Sep-16 83

03PMS-BL00.3.2.3.01.2.2 GTG Aux. Foundation


03PMS-BL00.3.2.3.01.2 19 02-Sep-16 24-Sep-16 160

XAC03-32301221 Foundation - GTG Auxilliary 31 19 02-Sep-16 24-Sep-16 160

XAC03-32301222 GTG Auxilliary 31 Foundation - H/O to Mech 0 24-Sep-16 160

03PMS-BL00.3.2.3.01.2.3 GT LV Transformer Foundation


03PMS-BL00.3.2.3.01.2 10 23-Sep-16 03-Oct-16 112

XAC03-32301231 Foundation - GT LV Transformer 31 8 23-Sep-16 03-Oct-16 97

XAC03-32301232 Foundation - GT LV Transformer 31 - H/O to Mech 0 03-Oct-16 80

03PMS-BL00.3.2.3.02 Ga
Gas Turbine / Generator #32 178 27-May-16 21-Nov-16 108

03PMS-BL00.3.2.3.02.1 Pile Work 12 27-May-16 09-Jun-16 50

XAC03-32302110 Pile - GTG 32 12 27-May-16 09-Jun-16 50

03PMS-BL00.3.2.3.02.2 Foundation Work 144 29-Jun-16 21-Nov-16 108

03PMS-BL00.3.2.3.02.2.1 GTG Foundation


03PMS-BL00.3.2.3.02.2 113 29-Jun-16 20-Oct-16 139

XAC03-32302211 Foundation - Excavation 6 29-Jun-16* 06-Jul-16 33

XAC03-32302212 Foundation - Lean concrete 50THK 3 04-Jul-16 07-Jul-16 33

XAC03-32302213 Foundation - Pile cut off 8 08-Jul-16 18-Jul-16 33

XAC03-32302217 Foundatio&Pedestaln - Embedded (M&E) 7 19-Jul-16 26-Jul-16 33

XAC03-32302214 Foundatio&Pedestaln - Install Reinforcement 18 27-Jul-16 16-Aug-16 33

XAC03-3230221F Foundatio&Pedestaln - Embedded (M&E) 7 17-Aug-16 24-Aug-16 33

XAC03-32302215 Foundation&Pedestal - Install box out 13 25-Aug-16 08-Sep-16 33

XAC03-32302218 Foundation&Pedestal - Install side formwork 6 06-Sep-16 12-Sep-16 33

XAC03-3230221B Foundation&Pedestal - casting concrete foundation 1 13-Sep-16 13-Sep-16 33

XAC03-3230221C Foundation/Pedestal - curing time (Control Temparature) 20 14-Sep-16 06-Oct-16 33

XAC03-32302219 Foundation/Pedestal - Remove formwork 6 07-Oct-16 13-Oct-16 120

XAC03-3230221E Foundation/Pedestal - Epoxy Injection under steel plate 5 14-Oct-16 19-Oct-16 120

XAC03-3230221D GTG Foundation - H/O to Mech 0 20-Oct-16 99

03PMS-BL00.3.2.3.02.2.2 GTG Aux. Foundation


03PMS-BL00.3.2.3.02.2 26 24-Sep-16 20-Oct-16 88

XAC03-32302221 Foundation - GTG Auxilliary 32 19 24-Sep-16 17-Oct-16 76

XAC03-32302222 GTG Auxilliary 32 Foundation - H/O to Mech 0 20-Oct-16 62

03PMS-BL00.3.2.3.02.2.3 GT LV Transformer Foundation


03PMS-BL00.3.2.3.02.2 10 11-Nov-16 21-Nov-16 56

XAC03-32302231 Foundation - GT LV Transformer 32 8 11-Nov-16 19-Nov-16 49

XAC03-32302232 Foundation - GT LV Transformer 32 - H/O to Mech 0 21-Nov-16 40

03PMS-BL00.3.2.3.03 HRSG
HR #31 / BDTP #31 167 27-Apr-16 12-Oct-16 478

03PMS-BL00.3.2.3.03.1 Pile Work 18 27-Apr-16 18-May-16 38

XAC03-32303110 Pile - HRSG#31 & Blowdown Pit 18 27-Apr-16* 18-May-16 38

03PMS-BL00.3.2.3.03.2 Foundation Work 135 30-May-16 12-Oct-16 478

03PMS-BL00.3.2.3.03.2.1 Blow Down Tank Pit #31


03PMS-BL00.3.2.3.03.2 71 30-May-16 08-Aug-16 542

XAC03-32303211 Driving the steel sheet pile 2 30-May-16* 31-May-16 29

XAC03-32303212 Excavation blowdown Tank 2 01-Jun-16* 02-Jun-16 29

XAC03-32303213 Install bracing 3 03-Jun-16 06-Jun-16 29

XAC03-32303214 Excavation blowdown Tank 8 07-Jun-16 15-Jun-16 29

XAC03-32303215 Lean concrete 50THK 3 16-Jun-16 18-Jun-16 29

XAC03-32303217 Slab - Install Reinforcement 7 20-Jun-16 27-Jun-16 29

XAC03-32303218 Slab - Install embedded material 5 23-Jun-16 28-Jun-16 29

XAC03-32303219 Slab - Install side formwork 2 29-Jun-16 30-Jun-16 29

XAC03-3230321A Slab - Casting concrete foundation (slab) 1 01-Jul-16 01-Jul-16 29

XAC03-3230321B Slab - Concrete Curing 1 02-Jul-16 02-Jul-16 29

XAC03-3230321E Wall - Install Reinforcement 5 04-Jul-16 08-Jul-16 29

XAC03-3230321F Wall - Install side formwork 4 07-Jul-16 12-Jul-16 29

XAC03-3230321G Wall - Casting concrete foundation 1 13-Jul-16 13-Jul-16 29

XAC03-3230321I Remove Formwork and Repairing concrete surface 5 14-Jul-16 19-Jul-16 29

XAC03-3230321J Water leak test, Monitoring and Repairing 7 20-Jul-16 27-Jul-16 29

XAC03-3230321C Backfill 5 28-Jul-16 02-Aug-16 29

XAC03-3230321D Remove Bracing 2 28-Jul-16 29-Jul-16 478

XAC03-3230321K Dewatering and Casting Pedestal 5 03-Aug-16 08-Aug-16 165

XAC03-3230321H Blowdown Tank Pit #31 Foundatio n - H/O to Mech 0 08-Aug-16 136

03PMS-BL00.3.2.3.03.2.2 HRSG #31


03PMS-BL00.3.2.3.03.2 92 11-Jul-16 12-Oct-16 478

XAC03-3230322K Stack - Excavation, Lean and pile cutting 19 11-Jul-16* 02-Aug-16 29

XAC03-32303226 Stack - Install embedded material (Erection company scope) 7 03-Aug-16 10-Aug-16 29

XAC03-32303223 Lean concrete 1 04-Aug-16 04-Aug-16 31

XAC03-32303228 Foundation HRSG 31 - Install Reinforcement 11 05-Aug-16 17-Aug-16 31

XAC03-32303225 Stack - Install Reinforcement 6 11-Aug-16 17-Aug-16 29

XAC03-32303224 Hand over to Erection company to mechanical work 4 18-Aug-16 22-Aug-16 31

XAC03-32303227 Stack - Install side formwork 2 18-Aug-16 19-Aug-16 29

XAC03-3230322A Stack - Casting concrete foundation 1 20-Aug-16 20-Aug-16 29

XAC03-3230322B Stack - Concrete Curing 20 22-Aug-16 13-Sep-16 29

XAC03-3230322L Foundation HRSG 31 - Install Reinforcement 10 23-Aug-16 02-Sep-16 31

XAC03-32303229 Foundation HRSG 31 - Install embedded material (Erection company scope) 7 03-Sep-16 10-Sep-16 31

XAC03-3230322C Foundation HRSG 31- Install side formwork 10 14-Sep-16 24-Sep-16 29

XAC03-3230322H Stack - Remove formwork and Cleaning 5 14-Sep-16 19-Sep-16 434

XAC03-3230322G Stack Foundation Work - H/O to Mech 0 19-Sep-16 358

XAC03-3230322D Foundation HRSG 31 - Casting concrete foundation 1 26-Sep-16 26-Sep-16 29

XAC03-3230322E Foundation HRSG 31 - Concrete Curing 13 27-Sep-16 11-Oct-16 29

XAC03-3230322F HRSG 31 Foundation Work - H/O to Mech 0 12-Oct-16 29

03PMS-BL00.3.2.3.04 HRSG
HR #32 / BDTP #32 164 10-May-16 20-Oct-16 469

03PMS-BL00.3.2.3.04.1 Pile Work 13 10-May-16 24-May-16 39

XAC03-32304110 Pile - HRSG#32 & Blowdown Pit 13 10-May-16* 24-May-16 39

03PMS-BL00.3.2.3.04.2 Foundation Work 141 02-Jun-16 20-Oct-16 469

03PMS-BL00.3.2.3.04.2.1 Blow Down Tank Pit #32


03PMS-BL00.3.2.3.04.2 78 02-Jun-16 18-Aug-16 532

XAC03-32304211 Driving the steel sheet pile 2 02-Jun-16* 03-Jun-16 99

XAC03-32304212 Excavation blowdown Tank 1 03-Jun-16 04-Jun-16 99

XAC03-32304213 Install bracing 3 06-Jun-16 08-Jun-16 99

XAC03-32304214 Excavation blowdown Tank 9 09-Jun-16 18-Jun-16 99

XAC03-32304215 Lean concrete 50THK 3 20-Jun-16 22-Jun-16 99

XAC03-32304217 Slab - Install Reinforcement 7 23-Jun-16 30-Jun-16 99

XAC03-32304218 Slab - Install embedded material 5 29-Jun-16 04-Jul-16 99

XAC03-32304219 Slab - Install side formwork 2 05-Jul-16 06-Jul-16 99

XAC03-3230421A Slab - Casting concrete foundation (slab) 1 07-Jul-16 07-Jul-16 99

XAC03-3230421B Slab - Concrete - Curing 2 08-Jul-16 09-Jul-16 99

XAC03-3230421E Wall - Install Reinforcement 7 11-Jul-16 18-Jul-16 99

XAC03-3230421F Wall - Install side formwork 8 13-Jul-16 21-Jul-16 99

XAC03-3230421H Wall - Casting concrete foundation (Wall) 1 22-Jul-16 22-Jul-16 99

XAC03-3230421G Remove Formwork and Repairing concrete surface 5 23-Jul-16 28-Jul-16 134

XAC03-3230421K Water leak test, Monitoring and Repairing 7 29-Jul-16 05-Aug-16 134

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:19 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3230421C Backfill 4 06-Aug-16 11-Aug-16 134

XAC03-3230421D Remove Bracing 2 06-Aug-16 08-Aug-16 470

XAC03-3230421J Dewatering and Casting Pedestal 5 13-Aug-16 18-Aug-16 134

XAC03-3230421I Blowdown Tank Pit #32 Foundatio n - H/O to Mech 0 18-Aug-16 111

03PMS-BL00.3.2.3.04.2.2 HRSG #32


03PMS-BL00.3.2.3.04.2 92 21-Jul-16 20-Oct-16 99

XAC03-332031490 Stack - Excavation, Lean and pile cutting 21 21-Jul-16* 13-Aug-16 104

XAC03-32304223 Lean concrete 1 15-Aug-16* 15-Aug-16 80

XAC03-32304226 Stack - Install embedded material (Erection company scope) 7 15-Aug-16 22-Aug-16 104

XAC03-32304228 Foundation HRSG 32 - Install Reinforcement 10 16-Aug-16 26-Aug-16 80

XAC03-32304225 Stack - Install Reinforcement 5 23-Aug-16 27-Aug-16 104

XAC03-32304224 Hand over to Erection company to mechanical work 4 27-Aug-16 31-Aug-16 80

XAC03-32304227 Stack - Install side formwork 2 29-Aug-16 30-Aug-16 104

XAC03-3230422A Stack - Casting concrete foundation 1 31-Aug-16 31-Aug-16 104

XAC03-32304221 Foundation HRSG 32 - Install Reinforcement 10 01-Sep-16 12-Sep-16 80

XAC03-3230422B Stack - Concrete Curing 20 01-Sep-16 23-Sep-16 104

XAC03-32304229 Foundation HRSG 32 - Install embedded material (Erection company scope) 15 13-Sep-16 29-Sep-16 80

XAC03-3230422B100 Stack - Remove formwork and cleaning 5 24-Sep-16 29-Sep-16 104

XAC03-3230422H Stack Foundation Work - H/O to Mech 0 29-Sep-16 86

XAC03-3230422C Foundation HRSG 32 - Install side formwork 10 30-Sep-16 11-Oct-16 80

XAC03-3230422D Foundation HRSG - Casting concrete foundation 1 12-Oct-16 12-Oct-16 80

XAC03-3230422G HRSG 32 Foundation Work - H/O to Mech 0 20-Oct-16 66

03PMS-BL00.3.2.3.05 Deaerator/
De BFP #3 283 06-Jun-16 15-Mar-17 46

03PMS-BL00.3.2.3.05.1 Pile Work 2 06-Jun-16 07-Jun-16 136

XAC03-32305110 Pile - Dearator & BFP 2 06-Jun-16* 07-Jun-16 136

03PMS-BL00.3.2.3.05.2 Foundation Work 19 27-Sep-16 18-Oct-16 130

XAC03-32305210 Excavation 2 27-Sep-16* 28-Sep-16 46

XAC03-32305220 Lean concrete 50THK 1 29-Sep-16 29-Sep-16 46

XAC03-32305230 Pile cut off 2 30-Sep-16 01-Oct-16 46

XAC03-32305240 Base Slab - Install Reinforcement 6 04-Oct-16 10-Oct-16 130

XAC03-32305250 Base Slab - Install embeded material and pocket 4 11-Oct-16 14-Oct-16 130

XAC03-32305260 Base Slab - Install side formwork 3 14-Oct-16 17-Oct-16 130

XAC03-32305270 Base Slab - Casting concrete foundation 1 18-Oct-16 18-Oct-16 130

03PMS-BL00.3.2.3.05.4 Steel Structure Work 44 31-Jan-17 15-Mar-17 46

XAC03-32305410 Steel Structure Installation 35 31-Jan-17* 11-Mar-17 40

XAC03-32305420 Steel Structure - H/O to Mech 0 15-Mar-17 32

03PMS-BL00.3.2.3.06 CEMS
CE #3 34 18-Jan-17 25-Feb-17 69

03PMS-BL00.3.2.3.06.2 Foundation Work 15 18-Jan-17 03-Feb-17 79

XAC03-32306210 CEMS 32 - Foundation 9 18-Jan-17* 27-Jan-17 69

XAC03-32306220 CEMS 31 - Foundation 9 25-Jan-17* 03-Feb-17 79

03PMS-BL00.3.2.3.06.4 Steel Structure Work 19 04-Feb-17 25-Feb-17 69

XAC03-32306410 CEMS #31 - Shed 9 04-Feb-17 14-Feb-17 79

XAC03-32306420 CEMS #32 - Shed 8 16-Feb-17 25-Feb-17 69

03PMS-BL00.3.2.3.07 HR
HRSG Chemical Dosing Skid #3 81 05-Apr-17 06-Jul-17 33

03PMS-BL00.3.2.3.07.2 Foundation Work 29 05-Apr-17 08-May-17 33

XAC03-32307210 Concrete HRSG Chemical Dosing Skid - Foundation 29 05-Apr-17* 08-May-17 33

03PMS-BL00.3.2.3.07.3 Steel Structure Work 17 17-Jun-17 06-Jul-17 33

XAC03-32307310 HRSG Chemical Dosing Skid #3 - Shed 17 17-Jun-17 06-Jul-17 33

03PMS-BL00.3.2.3.08 Sa
Sampling Rack #3 25 01-Oct-16 29-Oct-16 247

03PMS-BL00.3.2.3.08.2 Foundation Work 8 01-Oct-16 10-Oct-16 247

XAC03-32308210 Sampling Rack - Foundation Concrete 8 01-Oct-16* 10-Oct-16 247

03PMS-BL00.3.2.3.08.3 Steel Structure Work 17 11-Oct-16 29-Oct-16 247

XAC03-32308310 Sampling Rack #3 - Shed 17 11-Oct-16 29-Oct-16 247

XAC03-32308230 Sampling Rack - H/O to Mech 0 29-Oct-16 247

03PMS-BL00.3.2.3.09 HR
HRSG Local Control Building 44 30-Jan-17 14-Mar-17 52

03PMS-BL00.3.2.3.09.2 Foundation Work 12 30-Jan-17 11-Feb-17 46

XAC03-32309210 HRSG Local Control Compartment - Foundation 12 30-Jan-17* 11-Feb-17 46

03PMS-BL00.3.2.3.09.4 Building Work 29 14-Feb-17 14-Mar-17 52

XAC03-32309410 HRSG Local Control Compartment - 1 st Floor 11 14-Feb-17* 25-Feb-17 45

XAC03-32309420 HRSG Local Control Compartment - Roof 14 27-Feb-17 14-Mar-17 45

XAC03-32309430 HRSG Local Control Compartment - H/O to Mech 0 14-Mar-17 52

03PMS-BL00.3.2.3.10 Fu
Fuel Gas Filter Foundation #3 13 21-Oct-16 05-Nov-16 392

03PMS-BL00.3.2.3.10.2 Foundation Work 13 21-Oct-16 05-Nov-16 392

XAC03-32310210 Fuel Gas Fillter - Foundation Work #31 7 21-Oct-16 29-Oct-16 137

XAC03-32310220 Fuel Gas Fillter - Foundation Work #32 7 28-Oct-16 05-Nov-16 137

XAC03-32310240 Foundation Work - H/O to Mech - Fuel Gas Fillter #31 0 29-Oct-16 398

XAC03-32310230 Foundation Work - H/O to Mech - Fuel Gas Fillter #32 0 05-Nov-16 137

03PMS-BL00.3.2.3.11 Pipe
Pip Rack ( Main - HRSG #31,#32 Area) 262 27-Jun-16 24-Apr-17 246

03PMS-BL00.3.2.3.11.1 Pile Work 11 27-Jun-16 08-Jul-16 120

XAC03-32311110 Pile Work 11 27-Jun-16* 08-Jul-16 120

03PMS-BL00.3.2.3.11.2 Foundation Work 11 03-Oct-16 14-Oct-16 117

XAC03-32311210 Pipe Rack (HRSG #31,#32 Area) - Slab - Install Reinforcement 9 03-Oct-16 12-Oct-16 46

XAC03-32311220 Pipe Rack (HRSG #31,#32 Area) - Slab - Install formwork 4 10-Oct-16 13-Oct-16 64

XAC03-32311230 Pipe Rack (HRSG #31,#32 Area) - Slab - Casting concrete 1 14-Oct-16 14-Oct-16 64

XAC03-32311240 Pipe Rack (HRSG #31,#32 Area) - - H/O to Mech 0 14-Oct-16 117

03PMS-BL00.3.2.3.11.4 Structure Work 49 28-Feb-17 24-Apr-17 246

XAC03-32311450 Structure Work - Pipe Rack RE Part-After HRSG 14 28-Feb-17 15-Mar-17 0

XAC03-32311420 Structure Work - Pipe Rack RD (HRSG 31) 14 16-Mar-17* 31-Mar-17 61

XAC03-32311480 Structure Work - Pipe Rack RD (HRSG 32) 20 01-Apr-17* 24-Apr-17 246

03PMS-BL00.3.2.3.12 Pipe
Pip Rack (GTG #31 Area) 256 27-Jun-16 09-Mar-17 40

03PMS-BL00.3.2.3.12.1 Pile Work 4 27-Jun-16 30-Jun-16 177

XAC03-32312110 Pile - Pipe Rack GTG 31&32 4 27-Jun-16 30-Jun-16 177

03PMS-BL00.3.2.3.12.2 Foundation 19 12-Sep-16 03-Oct-16 114

XAC03-32312220 Pipe rack ( GTG#31 ) - excavation 1 12-Sep-16* 12-Sep-16 114

XAC03-32312210 Pipe rack ( GTG#31 ) - Lean concrete 2 13-Sep-16 14-Sep-16 114

XAC03-32312230 Pipe rack ( GTG#31 ) - Pile Cutting 2 15-Sep-16 16-Sep-16 114

XAC03-32312240 Pipe rack ( GTG#31 ) - Slab - Install Reinforcement 3 17-Sep-16 20-Sep-16 114

XAC03-32312250 Pipe rack ( GTG#31 ) - Install formwork 2 21-Sep-16 22-Sep-16 114

XAC03-32312260 Pipe rack ( GTG#31 ) - Slab - Casting concrete 1 23-Sep-16 23-Sep-16 114

XAC03-32312270 Pipe rack ( GTG#31 ) - Pedestal - Install Reinforcement 3 24-Sep-16 27-Sep-16 114

XAC03-32312280 Pipe rack ( GTG#31 ) - Pedestal - Install anchor bolt 1 28-Sep-16 28-Sep-16 114

XAC03-32312290 Pipe rack ( GTG#31 ) - Pedestal - Install formwork 3 29-Sep-16 01-Oct-16 114

XAC03-323122A0 Pipe rack ( GTG#31 ) - Pedestal - Casting concrete 1 03-Oct-16 03-Oct-16 114

03PMS-BL00.3.2.3.12.4 Structure Work 53 15-Jan-17 09-Mar-17 40

XAC03-32312400 Pipe rack ( GTG#31 ) - Delivery Steel Structure 25 15-Jan-17* 08-Feb-17 29

XAC03-32312410 Pipe rack ( GTG#31 ) - Steel Structure 25 09-Feb-17 09-Mar-17 26

XAC03-32312420 Steel Structure - H/O to Mech 0 09-Mar-17 28

03PMS-BL00.3.2.3.13 Pipe
Pip Rack (GTG #32 Area) 89 22-Nov-16 04-Mar-17 15

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:20 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
03PMS-BL00.3.2.3.13.2 Foundation 28 22-Nov-16 23-Dec-16 49

XAC03-32313210 Pipe rack ( GTG#32 ) - excavation 1 22-Nov-16 22-Nov-16 49

XAC03-32313220 Pipe rack ( GTG#32 ) - Lean concrete 2 23-Nov-16 24-Nov-16 49

XAC03-32313230 Pipe rack ( GTG#32 ) - Pile Cutting 2 25-Nov-16 26-Nov-16 49

XAC03-323132B0 Pipe rack ( GTG#32 ) - Backfill 1 06-Dec-16 07-Dec-16 49

XAC03-32313240 Pipe rack ( GTG#32 ) - Slab - Install Reinforcement 4 08-Dec-16 12-Dec-16 49

XAC03-32313250 Pipe rack ( GTG#32 ) - Slab - Install formwork 3 13-Dec-16 15-Dec-16 49

XAC03-32313260 Pipe rack ( GTG#32 ) - Slab - Casting concrete 1 16-Dec-16 16-Dec-16 49

XAC03-32313270 Pipe rack ( GTG#32 ) - Pedestal - Install Reinforcement 2 17-Dec-16 19-Dec-16 49

XAC03-32313280 Pipe rack ( GTG#32 ) - Pedestal - Install anchor bolt 2 20-Dec-16 21-Dec-16 49

XAC03-32313290 Pipe rack ( GTG#32 ) - Pedestal - Install formwork 1 22-Dec-16 22-Dec-16 49

XAC03-323132A0 Pipe rack ( GTG#32 ) - Pedestal - Casting concrete 1 23-Dec-16 23-Dec-16 49

03PMS-BL00.3.2.3.13.4 Structure Work 28 01-Feb-17 04-Mar-17 15

XAC03-32313400 Pipe rack ( GTG#32 ) - Delivery Steel Structure 7 01-Feb-17* 08-Feb-17 15

XAC03-32313410 Pipe rack ( GTG#32 ) - Steel Structure 25 02-Feb-17 02-Mar-17 15

XAC03-32313420 Steel Structure - H/O to Mech 0 04-Mar-17 15

03PMS-BL00.3.2.3.14 Cable
Ca Trench (GTG #31 Area) 33.00m 31 18-Aug-16 22-Sep-16 97

03PMS-BL00.3.2.3.14.5 Cable Trench 31 18-Aug-16 22-Sep-16 97

XAC03-32314510 Cable Trench (GTG 31 area ) - Excavation (Open cut) 2 18-Aug-16* 19-Aug-16 72

XAC03-32314520 Cable Trench (GTG 31 area ) - Lean concrete 2 20-Aug-16 22-Aug-16 72

XAC03-32314530 Cable Trench (GTG 31 area ) - Pile cut off 3 23-Aug-16 25-Aug-16 72

XAC03-32314550 Cable Trench (GTG 31 area ) - Slab - Install Reinforcement 3 26-Aug-16 29-Aug-16 72

XAC03-32314540 Cable Trench (GTG 31 area ) - Slab - Install side formwork 5 30-Aug-16 03-Sep-16 72

XAC03-32314580 Cable Trench (GTG 31 area ) - Wall - Install side formwork 9 02-Sep-16 13-Sep-16 72

XAC03-32314560 Cable Trench (GTG 31 area ) - Casting concrete 1 05-Sep-16 05-Sep-16 72

XAC03-32314570 Cable Trench (GTG 31 area ) - Wall - Install Reinforcement 8 06-Sep-16 14-Sep-16 72

XAC03-32314590 Cable Trench (GTG 31 area ) - Wall - Casting concrete 1 14-Sep-16 14-Sep-16 72

XAC03-323145A0 Cable Trench (GTG 31 area ) - Backfill 7 15-Sep-16 22-Sep-16 97

XAC03-323145B0 Cable Trench (GTG 31 area ) - H/O to Mech 0 22-Sep-16 97

03PMS-BL00.3.2.3.15 Cable
Ca Trench (GTG #32 Area) 33.00m 41 12-Oct-16 28-Nov-16 122

03PMS-BL00.3.2.3.15.5 Cable Trench 41 12-Oct-16 28-Nov-16 122

XAC03-32315510 Cable Trench (GTG 32 area ) - Excavation (Open cut) 3 12-Oct-16* 14-Oct-16 49

XAC03-32315520 Cable Trench (GTG 32 area ) - Lean concrete 1 15-Oct-16 15-Oct-16 49

XAC03-32315530 Cable Trench (GTG 32 area ) - Pile cut off 3 17-Oct-16 19-Oct-16 49

XAC03-32315540 Cable Trench (GTG 32 area ) - Slab - Install Reinforcement 3 20-Oct-16 22-Oct-16 49

XAC03-32315550 Cable Trench (GTG 32 area ) - Slab - Install side formwork 3 24-Oct-16 26-Oct-16 49

XAC03-32315560 Cable Trench (GTG 32 area ) - Slab - Casting concrete 1 27-Oct-16 27-Oct-16 49

XAC03-32315570 Cable Trench (GTG 32 area ) - Wall - Install Reinforcement 9 28-Oct-16 07-Nov-16 49

XAC03-32315580 Cable Trench (GTG 32 area ) - Wall - Install side formwork 9 08-Nov-16 17-Nov-16 49

XAC03-32315590 Cable Trench (GTG 32 area ) - Wall - Casting concrete 1 18-Nov-16 18-Nov-16 49

XAC03-323155A0 Cable Trench (GTG 32 area ) - Backfill 7 19-Nov-16 26-Nov-16 122

XAC03-323155B0 Cable Trench (GTG 32 area ) - H/O to Mech 0 28-Nov-16 122

03PMS-BL00.3.2.3.16 Ca
Cable Trench (Road Crossing GTG 31 - SWYD ) 33.00 m. 59 01-Dec-16 28-Jan-17 79

03PMS-BL00.3.2.3.16.5 Cable Trench 59 01-Dec-16 28-Jan-17 79

XAC03-32316510 Cable Trench (Road Crossing GTG 31 - SWYD ) - Excavation (Open cut) 3 01-Dec-16* 03-Dec-16 67

XAC03-32316520 Cable Trench (Road Crossing GTG 31 - SWYD ) -Lean concrete 1 05-Dec-16 05-Dec-16 67

XAC03-32316530 Cable Trench (Road Crossing GTG 31 - SWYD ) - Pile cut off 3 06-Dec-16 08-Dec-16 67

XAC03-32316540 Cable Trench (Road Crossing GTG 31 - SWYD ) - Slab - Install Reinforcement 3 09-Dec-16 12-Dec-16 67

XAC03-32316550 Cable Trench (Road Crossing GTG 31 - SWYD ) - Slab - Install side formwork 3 13-Dec-16 15-Dec-16 67

XAC03-32316560 Cable Trench (Road Crossing GTG 31 - SWYD ) - Slab - Casting concrete 1 16-Dec-16 16-Dec-16 67

XAC03-32316570 Cable Trench (Road Crossing GTG 31 - SWYD ) - Wall - Install Reinforcement 16 17-Dec-16 04-Jan-17 67

XAC03-32316580 Cable Trench (Road Crossing GTG 31 - SWYD ) - Wall - Install side formwork 1 05-Jan-17 05-Jan-17 67

XAC03-32316590 Cable Trench (Road Crossing GTG 31 - SWYD ) - Wall - Casting concrete 1 06-Jan-17 06-Jan-17 67

XAC03-323165C0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Top - Install Scaffolding and 7 07-Jan-17 14-Jan-17 67
formwork
XAC03-323165D0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Top - Install Reinforcement and side 5 15-Jan-17 19-Jan-17 78
formwork
XAC03-323165E0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Top - Casting concrete 1 20-Jan-17 20-Jan-17 68

XAC03-323165A0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Backfill 7 21-Jan-17 28-Jan-17 68

XAC03-323165B0 Cable Trench (Road Crossing GTG 31 - SWYD ) - H/O to Mech 0 28-Jan-17 68

03PMS-BL00.3.2.3.17 Ca
Cable Trench (Road Crossing GTG 32 - SWYD 2) 33.00 m. 111 02-Feb-17 09-Jun-17 205

03PMS-BL00.3.2.3.17.5 Cable Trench 111 02-Feb-17 09-Jun-17 205

XAC03-32317510 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Excavation (Open cut) 8 02-Feb-17* 10-Feb-17 205

XAC03-32317520 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Lean concrete 4 11-Feb-17 15-Feb-17 205

XAC03-32317530 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Pile cut off 6 16-Feb-17 22-Feb-17 205

XAC03-32317540 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Slab - Install Reinforcement 6 23-Feb-17 01-Mar-17 205

XAC03-32317550 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Slab - Install side formwork 6 02-Mar-17 08-Mar-17 205

XAC03-32317560 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Slab - Casting concrete 4 09-Mar-17 13-Mar-17 205

XAC03-32317570 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Wall - Install Reinforcement 14 14-Mar-17 29-Mar-17 205

XAC03-32317580 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Wall - Install side formwork 20 30-Mar-17 21-Apr-17 205

XAC03-32317590 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Wall - Casting concrete 4 22-Apr-17 26-Apr-17 205

XAC03-323175C0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Top - Install Scaffolding and 12 27-Apr-17 10-May-17 205
formwork
XAC03-323175D0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Top - Install Reinforcement and 10 11-May-17 22-May-17 205
side formwork
XAC03-323175E0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Top - Casting concrete 4 23-May-17 26-May-17 205

XAC03-323175A0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Backfill 12 27-May-17 09-Jun-17 205

XAC03-323175B0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - H/O to Mech 0 09-Jun-17 205

03PMS-BL00.3.2.3.18 Ca
Cable Trench (Road Crossing GTG 32 - E&C Building ) 33.00 m. 61 01-Dec-16 30-Jan-17 367

03PMS-BL00.3.2.3.18.5 Cable Trench 61 01-Dec-16 30-Jan-17 367

XAC03-32318510 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Excavation (Open cut) 3 01-Dec-16* 03-Dec-16 91

XAC03-32318520 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Lean concrete 1 05-Dec-16 05-Dec-16 318

XAC03-32318530 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Pile cut off 3 06-Dec-16 08-Dec-16 318

XAC03-32318540 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install Reinforcement 3 09-Dec-16 12-Dec-16 318

XAC03-32318550 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install side formwork 3 13-Dec-16 15-Dec-16 318

XAC03-32318560 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Casting concrete 1 16-Dec-16 16-Dec-16 318

XAC03-32318570 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install Reinforcement 16 17-Dec-16 04-Jan-17 318

XAC03-32318580 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install side formwork 2 05-Jan-17 06-Jan-17 318

XAC03-32318590 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Casting concrete 1 07-Jan-17 07-Jan-17 318

XAC03-323185C0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Top - Install Scaffolding and 7 09-Jan-17 15-Jan-17 367
formwork
XAC03-323185D0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Top - Install Reinforcement 5 16-Jan-17 20-Jan-17 318
and side formwork
XAC03-323185E0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Top - Casting concrete 1 21-Jan-17 21-Jan-17 318

XAC03-323185A0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Backfill 7 23-Jan-17 30-Jan-17 318

XAC03-323185B0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - H/O to Mech 0 30-Jan-17 318

03PMS-BL00.3.2.3.19 Ca
Cable Trench (Road Crossing STG #30 - SWYD) 33.00 m. 29 05-Dec-16 03-Jan-17 105

03PMS-BL00.3.2.3.19.5 Cable Trench 29 05-Dec-16 03-Jan-17 105

XAC03-32319510 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Excavation (Open cut) 3 05-Dec-16* 07-Dec-16 75

XAC03-32319520 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Lean concrete 1 08-Dec-16 08-Dec-16 91

XAC03-32319530 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Pile cut off 3 09-Dec-16 12-Dec-16 91

XAC03-32319540 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install Reinforcement 3 13-Dec-16 16-Dec-16 91

XAC03-32319550 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install side formwork 3 13-Dec-16 16-Dec-16 91

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:21 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-32319560 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Casting concrete 1 16-Dec-16 17-Dec-16 91

XAC03-32319570 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install Reinforcement 9 17-Dec-16 28-Dec-16 91

XAC03-32319580 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install side formwork 9 20-Dec-16 30-Dec-16 91

XAC03-32319590 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Casting concrete 1 30-Dec-16 31-Dec-16 91

XAC03-323195A0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Backfill 2 31-Dec-16 03-Jan-17 91

XAC03-323195B0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - H/O to Mech 0 03-Jan-17 91

03PMS-BL00.3.2.3.20 Pip
Pipe Sleeper (HRSG #31 & #32 Area) 18 02-Mar-17 22-Mar-17 71

03PMS-BL00.3.2.3.20.6 Pipe Sleeper (HRSG/ GTG #3 Area) 18 02-Mar-17 22-Mar-17 71

XAC03-32320610 FDN HRSG#31 Pipe Sleeper 10 02-Mar-17* 13-Mar-17 71

XAC03-32320620 FDN HRSG#32 Pipe Sleeper 9 11-Mar-17 22-Mar-17 71

03PMS-BL00.3.2.3.21 Emergency
Em Diesel Generator 22 09-Jan-17 30-Jan-17 123

03PMS-BL00.3.2.3.21.2 Foundation Work 22 09-Jan-17 30-Jan-17 123

XAC03-32321210 EDG Foundation 19 09-Jan-17* 30-Jan-17 105

XAC03-32321220 Civil Work - H/O to Mech 0 30-Jan-17 89

03PMS-BL00.3.2.3.22 E&C
E& - EDG Pipe Sleeper 14 01-Mar-17 16-Mar-17 80

03PMS-BL00.3.2.3.22.1 E&C - EDG Pipe Sleeper 14 01-Mar-17 16-Mar-17 80

XAC03-32322110 FDN EDG Pipe Sleeper 14 01-Mar-17* 16-Mar-17 80

XAC03-32322120 FDN EDG Pipe Sleeper - H/O to Mech 0 16-Mar-17 80

03PMS-BL00.3.2.3.23 Fu
Fuel Gas Heater Foundation 8 04-Nov-16 12-Nov-16 223

03PMS-BL00.3.2.3.23.2 Foundation Work 8 04-Nov-16 12-Nov-16 223

XAC03-32323210 Fuel Gas Heater - Foundation Work 8 04-Nov-16 12-Nov-16 223

XAC03-32323220 Foundation Work - H/O to Mech - Fuel Gas Heater 0 12-Nov-16 193

03PMS-BL00.3.2.3.24 Pip
Pipe Rack RE 168 27-Jun-16 05-Jan-17 60

03PMS-BL00.3.2.3.24.1 Pile Work 12 27-Jun-16 09-Jul-16 128

XAC03-32324110 Pile Work 12 27-Jun-16 09-Jul-16 128

03PMS-BL00.3.2.3.24.2 Foundation Work 21 13-Oct-16 05-Nov-16 46

XAC03-32324210 Pipe Rack RE - Slab - Install Reinforcement 10 13-Oct-16 24-Oct-16 46

XAC03-32324220 Pipe Rack RE - Slab - Install formwork 10 25-Oct-16 04-Nov-16 46

XAC03-32324230 Pipe Rack RE - Slab - Casting concrete 1 05-Nov-16 05-Nov-16 46

XAC03-32324240 Pipe Rack RE - H/O to Mech 0 05-Nov-16 46

03PMS-BL00.3.2.3.24.4 Structure Work 55 03-Nov-16 05-Jan-17 60

XAC03-32324400 Structure Work - Delivery Pipe Rack RE (ABPR3 Area) 0 03-Nov-16* 47

XAC03-32324410 Structure Work - Pipe Rack RE (ABPR3 Area) 53 07-Nov-16 05-Jan-17 46

XAC03-32324420 Structure Work - Pipe Rack RE - H/O to Mech 0 05-Jan-17 60

03PMS-BL00.3.2.3.ZZ O
Other Civil Work 175 28-Sep-16 22-Mar-17 72

03PMS-BL00.3.2.3.ZZ.1 GT Water Wash Pit 34 28-Sep-16 01-Nov-16 150

03PMS-BL00.3.2.3.ZZ.1.1 GT Water Wash Pit #31


03PMS-BL00.3.2.3.ZZ.1 22 28-Sep-16 20-Oct-16 163

XAC03-323ZZ111 Water Wash Pit #31 - GT Water Wash Pit Work 15 28-Sep-16 13-Oct-16 151

XAC03-323ZZ112 Water Wash Pit #31 - Chemical Coating 5 14-Oct-16 20-Oct-16 141

XAC03-323ZZ113 Water Wash Pit #31 - H/O to Mech 0 20-Oct-16 141

03PMS-BL00.3.2.3.ZZ.1.2 GT Water Wash Pit #32


03PMS-BL00.3.2.3.ZZ.1 20 10-Oct-16 01-Nov-16 131

XAC03-323ZZ121 Water Wash Pit #32 - GT Water Wash Pit Work 14 10-Oct-16 25-Oct-16 131

XAC03-323ZZ122 Water Wash Pit #32 - Chemical Coating 6 26-Oct-16 01-Nov-16 131

XAC03-323ZZ123 Water Wash Pit #32 - H/O to Mech 0 01-Nov-16 131

03PMS-BL00.3.2.3.ZZ.2 GT Area Sump Pit (4pcs) 23 27-Oct-16 23-Nov-16 125

03PMS-BL00.3.2.3.ZZ.2.1 GT#31 Oily Sump Pit


03PMS-BL00.3.2.3.ZZ.2 13 27-Oct-16 11-Nov-16 136

XAC03-323ZZ212 GT#31 Oily Sump Pit 13 27-Oct-16* 11-Nov-16 136

XAC03-323ZZ213 GT#31 Oily Sump Pit -H/O to Mech 0 11-Nov-16 136

03PMS-BL00.3.2.3.ZZ.2.2 GT#32 Oily Sump Pit


03PMS-BL00.3.2.3.ZZ.2 14 08-Nov-16 23-Nov-16 125

XAC03-323ZZ222 GT#32 Oily Sump Pit 14 08-Nov-16* 23-Nov-16 125

XAC03-323ZZ223 GT#32 Oily Sump Pit -H/O to Mech 0 23-Nov-16 125

03PMS-BL00.3.2.3.ZZ.3 HRSG 31&32 Drain Pit 32 14-Feb-17 22-Mar-17 63

XAC03-323ZZ310 HRSG 31 Drain Pit 14 14-Feb-17 01-Mar-17 63

XAC03-323ZZ330 HRSG 32 Drain Pit 14 01-Mar-17 16-Mar-17 63

XAC03-323ZZ320 HRSG 31 Drain Pit - H/O to Mech 0 01-Mar-17 81

XAC03-323ZZ340 HRSG 32 Drain Pit - H/O to Mech 0 22-Mar-17 63

03PMS-BL00.3.2.4 Civil (WTP


(W Area) 234 20-Jun-16 08-Feb-17 358

03PMS-BL00.3.2.4.01 Water
Wa Treatment System 234 20-Jun-16 08-Feb-17 358

03PMS-BL00.3.2.4.01.1 Pile Work 9 20-Jun-16 30-Jun-16 81

XAC03-32401110 Pile Work 9 20-Jun-16* 30-Jun-16 81

03PMS-BL00.3.2.4.01.2 Foundation / Civil Work 223 01-Jul-16 08-Feb-17 358

03PMS-BL00.3.2.4.01.2.1 Water Treatment Plant


03PMS-BL00.3.2.4.01.2 124 01-Aug-16 21-Dec-16 353

XAC03-32401211 WTP Shed Foundation - Excavation 5 01-Aug-16* 05-Aug-16 47

XAC03-32401212 WTP Shed Foundation - Lean Concrete 1 06-Aug-16* 06-Aug-16 47

XAC03-32401213 WTP Shed Foundation - Pile Cut off 7 08-Aug-16* 15-Aug-16 47

XAC03-32401214 WTP Shed Foundation - Install Reinforcement 21 16-Aug-16* 08-Sep-16 47

XAC03-32401215 WTP Shed Foundation - Install side formwork 12 09-Sep-16 22-Sep-16 47

XAC03-3240121A WTP Shed Foundation - Casting concrete foundation 1 23-Sep-16* 23-Sep-16 47

XAC03-32401216 WTP Shed plint - Install Reinforcement 25 24-Sep-16* 22-Oct-16 400

XAC03-32401217 WTP Shed plint - Install side formwork 25 28-Sep-16 26-Oct-16 400

XAC03-3240121B WTP Shed Column - Install scaffolding 4 28-Sep-16 01-Oct-16 47

XAC03-3240121C WTP Shed Column - Group 1 - Install Reinforcement 10 03-Oct-16* 13-Oct-16 47

XAC03-3240121G WTP Shed Column - Group 1 - Install side formwork 5 14-Oct-16 19-Oct-16 52

XAC03-3240121H WTP Shed Column - Group 2 - Install Reinforcement 10 14-Oct-16 25-Oct-16 47

XAC03-3240121I WTP Shed Column - Group 1 - Casting concrete foundation 1 20-Oct-16 20-Oct-16 52

XAC03-3240121F WTP Structure Delivery 5 21-Oct-16* 26-Oct-16 52

XAC03-3240121J WTP Shed Column - Group 2 - Install side formwork 5 26-Oct-16 31-Oct-16 47

XAC03-3240121D WTP Shed plint - Casting concrete foundation 1 27-Oct-16 27-Oct-16 400

XAC03-32401218 WTP Shed wall - Install Reinforcement 14 28-Oct-16* 12-Nov-16 110

XAC03-3240121K WTP Shed Column - Group 2 - Casting concrete foundation 1 01-Nov-16 01-Nov-16 47

XAC03-3240121L WTP Steel Structure 20 02-Nov-16 24-Nov-16 47

XAC03-32401219 WTP Shed wall - Install side formwork 7 08-Nov-16 15-Nov-16 110

XAC03-3240121E WTP Shed wall - Casting concrete foundation 1 16-Nov-16 16-Nov-16 110

XAC03-3240121O WTP FRP Lining 30 17-Nov-16 21-Dec-16 353

XAC03-3240121N WTP Metal Roof 14 25-Nov-16 10-Dec-16 47

XAC03-3240121M Water Treatment Plant - H/O to Mech 0 10-Dec-16 47

03PMS-BL00.3.2.4.01.2.2 Water Treatment Plant Buffer Tank


03PMS-BL00.3.2.4.01.2 88 02-Sep-16 12-Dec-16 361

XAC03-32401221 Excavation 4 02-Sep-16* 06-Sep-16 76

XAC03-32401222 Lean concrete 50THK 1 07-Sep-16 07-Sep-16 98

XAC03-32401223 Pile cut off 2 08-Sep-16 09-Sep-16 98

XAC03-32401226 Base Slab - Casting concrete foundation 1 10-Sep-16 10-Sep-16 98

XAC03-32401224 Base Slab - Install Reinforcement 5 12-Sep-16 16-Sep-16 98

XAC03-32401225 Base Slab - Install side formwork 4 17-Sep-16 21-Sep-16 98

XAC03-3240122L Wall - Install Scaffolding 1 22-Sep-16 22-Sep-16 98

XAC03-32401227 Wall - Install Reinforcement 5 23-Sep-16 28-Sep-16 98

XAC03-32401228 Wall - Install embedded material (Pipe N1-N6 Supply and Install by M&E) 2 29-Sep-16 30-Sep-16 98

XAC03-32401229 Wall - Install side formwork 4 29-Sep-16 03-Oct-16 98

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:22 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3240122A Wall - Casting concrete foundation 1 04-Oct-16 04-Oct-16 98

XAC03-3240122B Roof Slab - Install Scaffolding 2 05-Oct-16 06-Oct-16 98

XAC03-3240122C Roof Slab - Install Reinforcement 5 07-Oct-16 12-Oct-16 98

XAC03-3240122D Roof Slab - Install formwork 5 13-Oct-16 18-Oct-16 98

XAC03-3240122F Roof Slab - Casting concrete 1 19-Oct-16 19-Oct-16 98

XAC03-3240122G Stair - Install Scaffolding 3 20-Oct-16 22-Oct-16 98

XAC03-3240122H Stair - Wall - Ins tall Reinforcement 8 24-Oct-16 01-Nov-16 98

XAC03-3240122E Remove Scaffolding and Cleaning 6 01-Nov-16 08-Nov-16 390

XAC03-3240122I Stair - Wall - Ins tall formwork 5 02-Nov-16 07-Nov-16 98

XAC03-3240122J Stair - Wall - Casting concrete 1 08-Nov-16 08-Nov-16 98

XAC03-3240122K WTP Buffer Tank - H/O to Mech 0 12-Dec-16 99

03PMS-BL00.3.2.4.01.2.3 Neutralization
03PMS-BL00.3.2.4.01.2 107 04-Oct-16 03-Feb-17 52

XAC03-32401232 Excavation 2 04-Oct-16* 05-Oct-16 52

XAC03-32401233 Lean concrete 50THK 1 06-Oct-16 06-Oct-16 52

XAC03-32401234 Pile cut off 3 07-Oct-16 10-Oct-16 52

XAC03-32401235 Base Slab - Install Reinforcement 7 12-Oct-16* 19-Oct-16 52

XAC03-32401236 Base Slab - Install side formwork 3 20-Oct-16 22-Oct-16 52

XAC03-32401237 Base Slab - Casting concrete foundation 1 24-Oct-16 24-Oct-16 52

XAC03-32401238 Wall - Install Reinforcement 6 25-Oct-16 31-Oct-16 52

XAC03-3240123A Wall - Install embedded material 2 01-Nov-16 02-Nov-16 52

XAC03-32401239 Wall - Install side formwork 4 03-Nov-16 07-Nov-16 52

XAC03-3240123B Wall - Casting concrete 1 08-Nov-16 08-Nov-16 52

XAC03-3240123C Roof Beam+Slab - Install Scaffolding 3 09-Nov-16 11-Nov-16 52

XAC03-3240123D Roof Beam+Slab - Install Reinforcement 3 12-Nov-16 15-Nov-16 52

XAC03-3240123E Roof Beam+Slab - Install formwork 6 16-Nov-16 22-Nov-16 52

XAC03-3240123G Roof Beam+Slab - Casting concrete 1 23-Nov-16 23-Nov-16 52

XAC03-3240123J Roof Beam+Slab - Curing and remove scaffolding 14 24-Nov-16 09-Dec-16 52

XAC03-3240123H Backfill 6 26-Nov-16 03-Dec-16 106

XAC03-3240123K Nuetralization - Leak test and finishing 21 10-Dec-16 03-Jan-17 52

XAC03-3240123L FRP Coating Work 12 09-Jan-17 23-Jan-17 52

XAC03-3240123I Nuetralization - H/O to Mech 0 03-Feb-17 52

03PMS-BL00.3.2.4.01.2.4 Belt Press


03PMS-BL00.3.2.4.01.2 140 31-Aug-16 17-Jan-17 380

XAC03-32401241 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Excavation 2 31-Aug-16* 01-Sep-16 72

XAC03-32401242 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Lean Concrete 1 02-Sep-16 02-Sep-16 72

XAC03-32401243 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Pile Cut off 1 03-Sep-16 03-Sep-16 72

XAC03-32401244 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Install Reinforcement 5 05-Sep-16 09-Sep-16 72

XAC03-32401245 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Install formwork 4 10-Sep-16 14-Sep-16 72

XAC03-32401246 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Casting concrete 1 15-Sep-16 15-Sep-16 72

XAC03-32401247 WTP Belt Press Shed Column 1st floor - Scafolding installation 5 16-Sep-16 21-Sep-16 72

XAC03-32401248 WTP Belt Press Shed Column 1st floor - Install Reinforcement 6 22-Sep-16 28-Sep-16 72

XAC03-32401249 WTP Belt Press Shed Column 1st floor - Install formwork 3 27-Sep-16 30-Sep-16 83

XAC03-3240124A WTP Belt Press Shed Column 1st floor - Casting concrete 1 01-Oct-16 01-Oct-16 72

XAC03-3240124B 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Scafolding installation 7 03-Oct-16 10-Oct-16 72

XAC03-3240124D 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Install Reinforcement 6 11-Oct-16 17-Oct-16 72

XAC03-3240124C 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Install formwork 7 13-Oct-16 20-Oct-16 72

XAC03-3240124F 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Casting concrete 1 21-Oct-16 21-Oct-16 72

XAC03-3240124I WTP Belt Press Shed Column 2nd floor - Scafolding installation 2 24-Oct-16 25-Oct-16 72

XAC03-3240124G WTP Belt Press Shed Column 2nd floor - Install Reinforcement 5 26-Oct-16 31-Oct-16 72

XAC03-3240124H WTP Belt Press Shed Column 2nd floor - Install formwork 6 01-Nov-16 07-Nov-16 72

XAC03-3240124J WTP Belt Press Shed Column 2nd floor - Casting concrete 1 08-Nov-16 08-Nov-16 72

XAC03-3240124K WTP Belt Press Shed Roof Beam - Scafolding installation 7 09-Nov-16 16-Nov-16 72

XAC03-3240124L WTP Belt Press Shed Roof Beam - Install Reinforcement 5 17-Nov-16 22-Nov-16 72

XAC03-3240124M WTP Belt Press Shed Roof Beam - Install formwork 3 21-Nov-16 24-Nov-16 72

XAC03-3240124N WTP Belt Press Shed Roof Beam - Casting concrete 1 25-Nov-16 25-Nov-16 72

XAC03-3240124O WTP Belt Press Shed Stair - Scafolding installation 7 26-Nov-16 03-Dec-16 72

XAC03-3240124P WTP Belt Press Shed Roof Structure 22 26-Nov-16 22-Dec-16 353

XAC03-3240124Q WTP Belt Press Shed Stair - Install Reinforcement 7 05-Dec-16 12-Dec-16 72

XAC03-3240124R WTP Belt Press Shed Stair - Install formwork 7 13-Dec-16 20-Dec-16 72

XAC03-3240124S WTP Belt Press Shed Stair - Casting concrete 1 21-Dec-16 21-Dec-16 72

XAC03-3240124T WTP Belt Press - H/O to Mech 0 17-Jan-17 72

03PMS-BL00.3.2.4.01.2.5 Sludge Thickner


03PMS-BL00.3.2.4.01.2 77 27-Aug-16 23-Nov-16 102

XAC03-32401251 Excavation 2 27-Aug-16* 29-Aug-16 102

XAC03-32401252 Lean concrete 50THK 1 30-Aug-16 30-Aug-16 102

XAC03-32401253 Pile cut off 2 31-Aug-16 01-Sep-16 102

XAC03-32401254 Base Slab - Slab - Install Reinforcement 5 05-Sep-16 10-Sep-16 102

XAC03-32401255 Base Slab - Slab - Install side formwork 5 12-Sep-16 16-Sep-16 102

XAC03-32401257 Base Slab - Slab - Concrete work - Casting concrete foundation 1 17-Sep-16 17-Sep-16 102

XAC03-32401258 Base Slab - Wall - Scaffolding Installation 4 19-Sep-16 22-Sep-16 102

XAC03-32401259 Base Slab - Wall - Install Reinforcement 7 23-Sep-16 30-Sep-16 102

XAC03-3240125A Base Slab - Wall - Install side formwork 7 01-Oct-16 08-Oct-16 102

XAC03-3240125C Base Slab - Wall - Casting concrete foundation 4 10-Oct-16 13-Oct-16 102

XAC03-3240125D Gutter - Scaffolding Installation 7 14-Oct-16 21-Oct-16 102

XAC03-3240125E Gutter - Install Reinforcement 4 22-Oct-16 26-Oct-16 102

XAC03-3240125F Gutter - Install formwork 3 27-Oct-16 29-Oct-16 102

XAC03-3240125G Gutter - Casting concrete foundation 1 31-Oct-16 31-Oct-16 102

XAC03-32401256 Sludge Thickner - Leak test and finishing 20 01-Nov-16 23-Nov-16 102

XAC03-3240125H Sludge Thickner - H/O to Mech 0 23-Nov-16 102

03PMS-BL00.3.2.4.01.2.6 Water Treatment Plant Electrical Building


03PMS-BL00.3.2.4.01.2 139 01-Sep-16 08-Feb-17 310

XAC03-32401261 Excavation 2 01-Sep-16* 02-Sep-16 66

XAC03-32401262 Lean Concrete 1 03-Sep-16 03-Sep-16 66

XAC03-32401264 Ground Beam - Install Reinforcement 4 05-Sep-16 08-Sep-16 66

XAC03-32401265 Ground Beam - Install side formwork 4 09-Sep-16 13-Sep-16 66

XAC03-32401266 Ground Beam - Casting concrete 1 14-Sep-16 14-Sep-16 66

XAC03-3240126A Ground Slab +0.20 m - Backfill 2 15-Sep-16 16-Sep-16 66

XAC03-3240126B Ground Slab +0.20 m - Lean Concrete 1 17-Sep-16 17-Sep-16 66

XAC03-3240126C Ground Slab +0.20 m - Install Reinforcement 7 19-Sep-16 26-Sep-16 66

XAC03-3240126D Ground Slab +0.20 m - Install side formwork 4 27-Sep-16 30-Sep-16 66

XAC03-3240126E Ground Slab +0.20 m - Casting concrete 1 01-Oct-16 01-Oct-16 66

XAC03-32401267 Column Ground - Install Reinforcement 2 03-Oct-16 04-Oct-16 66

XAC03-32401268 Column Ground - Install formwork 1 05-Oct-16 05-Oct-16 66

XAC03-32401269 Column Ground - Casting concrete 1 06-Oct-16 06-Oct-16 66

XAC03-3240126F 1st floor slab+Beam +1.65 m - Install scaffolding 7 07-Oct-16 14-Oct-16 66

XAC03-3240126G 1st floor slab+Beam +1.65 m - Install Reinforcement 7 15-Oct-16 22-Oct-16 66

XAC03-3240126H 1st floor slab+Beam +1.65 m - Install formwork 5 24-Oct-16 28-Oct-16 66

XAC03-3240126I 1st floor slab+Beam +1.65 m - Casting concrete 1 29-Oct-16 29-Oct-16 66

XAC03-3240126J Column 1st floor - Install scaffolding 4 31-Oct-16 03-Nov-16 66

XAC03-3240126K Column 1st floor - Install Reinforcement 5 04-Nov-16 09-Nov-16 66

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:23 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3240126L Column 1st floor - Install formwork 4 10-Nov-16 14-Nov-16 66

XAC03-3240126M Column 1st floor - Casting concrete 1 15-Nov-16 15-Nov-16 66

XAC03-3240126N Roof Beam - Install Reinforcement 7 16-Nov-16 23-Nov-16 66

XAC03-3240126O Roof Beam - Install formwork 5 24-Nov-16 29-Nov-16 66

XAC03-3240126P Roof Beam - Casting concrete 1 30-Nov-16 30-Nov-16 66

XAC03-3240126R Stair - Install Reinforcement 10 01-Dec-16 12-Dec-16 97

XAC03-3240126S Stair - Install formwork 10 13-Dec-16 23-Dec-16 97

XAC03-3240126Q Steel Structure 20 13-Dec-16 05-Jan-17 66

XAC03-3240126V Stair - Casting concrete 1 24-Dec-16 24-Dec-16 97

XAC03-3240126U Septic Tank 28 03-Jan-17 04-Feb-17 97

XAC03-3240126T Roof Cladding 9 06-Jan-17 16-Jan-17 66

XAC03-32401263 Floor Coating 20 17-Jan-17 08-Feb-17 310

XAC03-3240126X Steel door 20 17-Jan-17 08-Feb-17 66

XAC03-3240126W Water Treatment Plant Electrical Building - H/O to Mech 0 08-Feb-17 66

03PMS-BL00.3.2.4.01.2.7 Clarifier
03PMS-BL00.3.2.4.01.2 162 01-Jul-16 09-Dec-16 102

XAC03-32401271 Excavation 5 01-Jul-16* 06-Jul-16 59

XAC03-32401272 Lean Concrete 1 07-Jul-16 07-Jul-16 59

XAC03-32401273 Pile Cut off 6 08-Jul-16 14-Jul-16 88

XAC03-32401274 Clarifier Foundation - Slab - Install Reinforcement 10 15-Jul-16 26-Jul-16 88

XAC03-32401275 Clarifier Foundation - Slab - Install side formwork 4 27-Jul-16 30-Jul-16 88

XAC03-32401276 Clarifier Foundation - Slab - Casting concrete foundation 1 01-Aug-16 01-Aug-16 88

XAC03-3240127F Clarifier Slope Slab - Install scaffolding 11 02-Aug-16 13-Aug-16 88

XAC03-3240127G Clarifier Slope Slab - Install formwork1/2 14 15-Aug-16 30-Aug-16 88

XAC03-32401277 Clarifier Slope Slab - Install Reinforcement 20 31-Aug-16 22-Sep-16 88

XAC03-32401278 Clarifier Slope Slab - Install formwork2/2 14 23-Sep-16 08-Oct-16 88

XAC03-32401279 Clarifier Slope Slab - Casting concrete 1 10-Oct-16 10-Oct-16 88

XAC03-3240127A Clarifier Wall -Slab - Install Reinforcement and scaffolding 7 12-Oct-16 19-Oct-16 88

XAC03-3240127B Clarifier Wall -Slab - Install formwork 10 20-Oct-16 31-Oct-16 88

XAC03-3240127C Clarifier Wall -Slab - Casting concrete 1 01-Nov-16 01-Nov-16 88

XAC03-3240127D Remove Formwork 10 02-Nov-16 12-Nov-16 88

XAC03-3240127H Repairing concrete surface 7 14-Nov-16 21-Nov-16 88

XAC03-3240127I Water Leak Test and Injection Repairing 16 22-Nov-16 09-Dec-16 88

XAC03-3240127E Clarifier - H/O to Mech 0 09-Dec-16 72

03PMS-BL00.3.2.4.01.2.Z Other Foundations


03PMS-BL00.3.2.4.01.2 29 13-Dec-16 10-Jan-17 101

XAC03-324012Z1 Foundation for Backwash / RO Feed / Regeneration Pump 7 13-Dec-16* 20-Dec-16 69

XAC03-324012Z2 Foundation for RO Water Tank 13 19-Dec-16 03-Jan-17 69

XAC03-324012Z5 Foundation for Backwash / RO Feed / Regeneration Pump - H/O to Mech 0 20-Dec-16 79

XAC03-324012Z3 Foundation for Air Blowers 13 24-Dec-16 09-Jan-17 69

XAC03-324012Z4 Foundation for Filtering / Clarifier water / Belt Press Washing Pump 6 03-Jan-17 10-Jan-17 78

XAC03-324012Z6 Foundation for RO Water Tank - H/O to Mech 0 03-Jan-17 78

XAC03-324012Z7 Foundation for Air Blowers - H/O to Mech 0 09-Jan-17 57

XAC03-324012Z8 Foundation for Filtering / Clarifier water / Belt Press Washing Pump - H/O to Mech 0 10-Jan-17 64

03PMS-BL00.3.2.4.02 Fir
Fire Fighting Pump Station 49 09-Nov-16 03-Jan-17 63

03PMS-BL00.3.2.4.02.2 Foundation Work 18 09-Nov-16 29-Nov-16 93

XAC03-32402210 Excavation 2 09-Nov-16* 10-Nov-16 56

XAC03-32402220 Lean Concrete 1 10-Nov-16 10-Nov-16 56

XAC03-32402230 Pile Cut off 1 11-Nov-16 11-Nov-16 56

XAC03-32402240 Fire Fighting Shed Foundation (Footing+Tie Beam+Slab) - Install Reinforcement 10 12-Nov-16 23-Nov-16 56

XAC03-32402250 Fire Fighting Shed Foundation (Footing+Tie Beam+Slab) - Install formwork 6 17-Nov-16 23-Nov-16 56

XAC03-32402260 Fire Fighting Shed Foundation (Footing+Tie Beam+Slab) - Casting concrete 1 24-Nov-16 24-Nov-16 56

XAC03-32402270 Fire Fighting Shed concrete plinth - Install Reinforcement 3 25-Nov-16 28-Nov-16 65

XAC03-32402280 Fire Fighting Shed concrete plinth - Install formwork 2 26-Nov-16 28-Nov-16 65

XAC03-32402290 Fire Fighting Shed concrete plinth - Casting concrete 1 29-Nov-16 29-Nov-16 65

XAC03-324022A0 Fire Fighting Pump Station - H/O to Mech 0 29-Nov-16 93

03PMS-BL00.3.2.4.02.4 Structure Work 27 02-Dec-16 03-Jan-17 56

XAC03-32402410 Fire Fighting Shed Steel structure 11 02-Dec-16 15-Dec-16 56

XAC03-32402420 Fire Fighting Shed Roof 16 16-Dec-16 03-Jan-17 56

XAC03-32402430 Fire Fighting Steel Structure - H/O to Mech 0 03-Jan-17 56

03PMS-BL00.3.2.5 Civil (CT


(C #3 Area) 301 08-Jun-16 04-Apr-17 303

03PMS-BL00.3.2.5.01 Cooling
Co Tower #3 301 08-Jun-16 04-Apr-17 303

03PMS-BL00.3.2.5.01.1 Pile Work 20 08-Jun-16 30-Jun-16 32

XAC03-32501100 Pile Work 20 08-Jun-16* 30-Jun-16 32

03PMS-BL00.3.2.5.01.2 Foundation/ Structute 275 04-Jul-16 04-Apr-17 303

03PMS-BL00.3.2.5.01.2.1 Foundation Work


03PMS-BL00.3.2.5.01.2 41 04-Jul-16 19-Aug-16 30

XAC03-32501211 Foundation Work - Excavation 10 04-Jul-16* 14-Jul-16 30

XAC03-32501212 Foundation Work - Lean Concrete 10 05-Jul-16 15-Jul-16 30

XAC03-32501213 Foundation Work - Pile Cut off 3 16-Jul-16 19-Jul-16 30

XAC03-32501214 Foundation Work - Install Reinforcement 20 20-Jul-16 11-Aug-16 30

XAC03-32501215 Foundation Work - Install side formwork & Water Stop 5 13-Aug-16 18-Aug-16 30

XAC03-32501216 Foundation Work - Casting concrete foundation 1 19-Aug-16 19-Aug-16 30

03PMS-BL00.3.2.5.01.2.2 Wall 1 Zone 1&2


03PMS-BL00.3.2.5.01.2 39 20-Aug-16 27-Sep-16 492

XAC03-32501221 Wall 1 Zone 1 - Install scaffolding 3 20-Aug-16 23-Aug-16 30

XAC03-32501222 Wall 1 Zone 2 - Install scaffolding 3 24-Aug-16 26-Aug-16 431

XAC03-32501223 Wall 1 Zone 1 - Install Reinforcement 10 24-Aug-16 03-Sep-16 30

XAC03-32501224 Wall 1 Zone 1 - Install Formwork 11 30-Aug-16 12-Sep-16 30

XAC03-32501225 Wall 1 Zone 2 - Install Reinforcement 12 05-Sep-16 17-Sep-16 434

XAC03-32501226 Wall 1 Zone 2 - Install Formwork 12 13-Sep-16 26-Sep-16 426

XAC03-32501227 Wall 1 Zone 1 - Casting concrete 1 13-Sep-16 13-Sep-16 35

XAC03-32501228 Wall 1 Zone 2 - Casting concrete 1 27-Sep-16 27-Sep-16 426

03PMS-BL00.3.2.5.01.2.3 Column 1 Zone 1&2


03PMS-BL00.3.2.5.01.2 23 27-Aug-16 22-Sep-16 431

XAC03-32501231 Column 1 Zone 1,2 - Install scaffolding 5 27-Aug-16 01-Sep-16 431

XAC03-32501232 Column 1 Zone 1,2 - Install Reinforcement 9 02-Sep-16 12-Sep-16 431

XAC03-32501233 Column 1 Zone 1,2 - Install Formwork 8 10-Sep-16 20-Sep-16 431

XAC03-32501234 Column 1 Zone 1,2 - Casting concrete 2 21-Sep-16 22-Sep-16 431

03PMS-BL00.3.2.5.01.2.4 Wall 2 Zone 1&2


03PMS-BL00.3.2.5.01.2 18 14-Sep-16 04-Oct-16 420

XAC03-32501241 Wall 2 Zone 1 - Install scaffolding 3 14-Sep-16 16-Sep-16 30

XAC03-32501242 Wall 2 Zone 2 - Install scaffolding 2 17-Sep-16 19-Sep-16 420

XAC03-32501243 Wall 2 Zone 1 - Install Reinforcement 2 17-Sep-16 19-Sep-16 30

XAC03-32501244 Wall 2 Zone 2 - Install Reinforcement 6 20-Sep-16 26-Sep-16 420

XAC03-32501245 Wall 2 Zone 1 - Install Formwork 6 20-Sep-16 26-Sep-16 30

XAC03-32501246 Wall 2 Zone 1 - Casting concrete 1 27-Sep-16 27-Sep-16 30

XAC03-32501247 Wall 2 Zone 2 - Install Formwork 6 27-Sep-16 03-Oct-16 420

XAC03-32501248 Wall 2 Zone 2 - Casting concrete 1 04-Oct-16 04-Oct-16 420

03PMS-BL00.3.2.5.01.2.5 Beam 2 Zone 1&2


03PMS-BL00.3.2.5.01.2 29 29-Sep-16 01-Nov-16 396

XAC03-32501251 Beam 2 Zone 1 - Install scaffolding 5 29-Sep-16 04-Oct-16 30

XAC03-32501252 Beam 2 Zone 1 - Install formwork 13 30-Sep-16 14-Oct-16 30

XAC03-32501253 Beam 2 Zone 1 - Install Reinforcement 9 05-Oct-16 14-Oct-16 30

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:24 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-32501254 Beam 2 Zone 2 - Install scaffolding 5 06-Oct-16 11-Oct-16 400

XAC03-32501255 Beam 2 Zone 2 - Install formwork 17 12-Oct-16 31-Oct-16 396

XAC03-32501256 Beam 2 Zone 1 - Casting concrete 1 15-Oct-16 15-Oct-16 30

XAC03-32501257 Beam 2 Zone 2 - Install Reinforcement 10 17-Oct-16 27-Oct-16 396

XAC03-32501258 Beam 2 Zone 2 - Casting concrete 1 31-Oct-16 01-Nov-16 396

03PMS-BL00.3.2.5.01.2.6 Wall 3 Zone 1&2


03PMS-BL00.3.2.5.01.2 22 17-Oct-16 10-Nov-16 388

XAC03-32501261 Wall 3 Zone 1 - Install scaffolding 3 17-Oct-16 19-Oct-16 30

XAC03-32501262 Wall 3 Zone 1 - Install Reinforcement 7 20-Oct-16 27-Oct-16 392

XAC03-32501263 Wall 3 Zone 2 - Install scaffolding 2 21-Oct-16 24-Oct-16 30

XAC03-32501264 Wall 3 Zone 2 - Install Reinforcement 7 25-Oct-16 01-Nov-16 388

XAC03-32501265 Wall 3 Zone 1 - Install Formwork 7 28-Oct-16 04-Nov-16 392

XAC03-32501266 Wall 3 Zone 2 - Install Formwork 7 02-Nov-16 09-Nov-16 388

XAC03-32501267 Wall 3 Zone 1 - Casting concrete 1 05-Nov-16 05-Nov-16 392

XAC03-32501268 Wall 3 Zone 2 - Casting concrete 1 10-Nov-16 10-Nov-16 388

03PMS-BL00.3.2.5.01.2.7 Column 3 Zone 1&2


03PMS-BL00.3.2.5.01.2 10 26-Oct-16 05-Nov-16 30

XAC03-32501271 Column 3 Zone 1,2 - Install scaffolding 2 26-Oct-16 27-Oct-16 30

XAC03-32501272 Column 3 Zone 1,2 - Install Reinforcement 3 28-Oct-16 31-Oct-16 30

XAC03-32501273 Column 3 Zone 1,2 - Install Formwork 4 01-Nov-16 04-Nov-16 30

XAC03-32501274 Column 3 Zone 1,2 - Casting concrete 1 05-Nov-16 05-Nov-16 30

03PMS-BL00.3.2.5.01.2.8 Beam 3 Zone 1&2


03PMS-BL00.3.2.5.01.2 14 07-Nov-16 22-Nov-16 30

XAC03-32501281 Beam 3 Zone 1 - Install scaffolding 3 07-Nov-16 09-Nov-16 30

XAC03-32501282 Beam 3 Zone 1 - Install formwork 7 08-Nov-16 15-Nov-16 32

XAC03-32501283 Beam 3 Zone 1 - Install Reinforcement 5 10-Nov-16 15-Nov-16 32

XAC03-32501284 Beam 3 Zone 2 - Install scaffolding 2 11-Nov-16 14-Nov-16 30

XAC03-32501285 Beam 3 Zone 2 - Install formwork 8 12-Nov-16 21-Nov-16 30

XAC03-32501286 Beam 3 Zone 2 - Install Reinforcement 5 15-Nov-16 19-Nov-16 30

XAC03-32501287 Beam 3 Zone 1 - Casting concrete 1 15-Nov-16 16-Nov-16 32

XAC03-32501288 Beam 3 Zone 2 - Casting concrete 1 21-Nov-16 22-Nov-16 30

03PMS-BL00.3.2.5.01.2.9 Wall 4 Zone 1&2


03PMS-BL00.3.2.5.01.2 21 17-Nov-16 10-Dec-16 362

XAC03-32501291 Wall 4 Zone 1 - Install scaffolding 3 17-Nov-16 19-Nov-16 32

XAC03-32501292 Wall 4 Zone 1 - Install Reinforcement 7 21-Nov-16 28-Nov-16 365

XAC03-32501293 Wall 4 Zone 2 - Install scaffolding 3 23-Nov-16 25-Nov-16 30

XAC03-32501294 Wall 4 Zone 2 - Install Reinforcement 6 26-Nov-16 02-Dec-16 362

XAC03-32501295 Wall 4 Zone 1 - Install Formwork 7 28-Nov-16 06-Dec-16 365

XAC03-32501296 Wall 4 Zone 2 - Install Formwork 6 03-Dec-16 09-Dec-16 362

XAC03-32501297 Wall 4 Zone 1 - Casting concrete 1 07-Dec-16 07-Dec-16 365

XAC03-32501298 Wall 4 Zone 2 - Casting concrete 1 10-Dec-16 10-Dec-16 362

03PMS-BL00.3.2.5.01.2.A Column 4 Zone 1&2


03PMS-BL00.3.2.5.01.2 17 26-Nov-16 15-Dec-16 30

XAC03-325012A1 Column 4 Zone 1,2 - Install scaffolding 2 26-Nov-16 28-Nov-16 30

XAC03-325012A2 Column 4 Zone 1,2 - Install Reinforcement 3 29-Nov-16 01-Dec-16 30

XAC03-325012A3 Column 4 Zone 1,2 - Install Formwork 4 02-Dec-16 06-Dec-16 30

XAC03-325012A4 Column 4 Zone 1,2 - Casting concrete 1 07-Dec-16 07-Dec-16 30

XAC03-325012A5 Remove Scaffolding 7 08-Dec-16 15-Dec-16 30

03PMS-BL00.3.2.5.01.2.B Precast Beam 1&2


03PMS-BL00.3.2.5.01.2 21 16-Dec-16 09-Jan-17 337

XAC03-325012B1 Install Precast Beam 1 7 16-Dec-16 23-Dec-16 30

XAC03-325012B2 Install Precast Beam 2 14 24-Dec-16 09-Jan-17 337

03PMS-BL00.3.2.5.01.2.C Roof Slab Zone 1&2


03PMS-BL00.3.2.5.01.2 85 24-Dec-16 18-Mar-17 320

XAC03-325012C1 Roof Slab Zone 1 - Install Scaffolding 14 24-Dec-16 09-Jan-17 30

XAC03-325012C2 Roof Slab Zone 1 - Install Reinforcement 13 07-Jan-17 21-Jan-17 285

XAC03-325012C3 Roof Slab Zone 1 - Install formwork 13 10-Jan-17 24-Jan-17 285

XAC03-325012C4 Roof Slab Zone 2 - Install Scaffolding 6 12-Jan-17 18-Jan-17 30

XAC03-325012C5 Roof Slab Zone 2 - Install formwork 14 19-Jan-17 03-Feb-17 30

XAC03-325012C6 Roof Slab Zone 2 - Install Reinforcement 9 21-Jan-17 01-Feb-17 30

XAC03-325012C7 Roof Slab Zone 1 - Casting concrete 1 24-Jan-17 25-Jan-17 285

XAC03-325012C8 Roof Slab Zone 1 - Curing Time 14 26-Jan-17 10-Feb-17 287

XAC03-325012C9 Roof Slab Zone 2 - Casting concrete 1 02-Feb-17 02-Feb-17 30

XAC03-325012CA Roof Slab Zone 2 - Curing Time 14 03-Feb-17 18-Feb-17 30

XAC03-325012CB Roof Slab Zone 1 - Remove Scaffolding and formwork 7 11-Feb-17 18-Feb-17 287

XAC03-325012CC Roof Slab Zone 1 - Repair concrete inside 14 20-Feb-17 07-Mar-17 287

XAC03-325012CD Roof Slab Zone 2 - Remove Scaffolding and formwork 7 20-Feb-17 27-Feb-17 30

XAC03-325012CE Roof Slab Zone 2 - Repair concrete inside 14 28-Feb-17 15-Mar-17 41

XAC03-325012D2 CT basin Water Leak Test & Repairing 10 28-Feb-17 10-Mar-17 64

XAC03-325012D3 CT basin Dewatering and cleaning 7 11-Mar-17 18-Mar-17 64

XAC03-325012C1F Cooling Tower #3 - H/O to Mech 0 15-Mar-17 34

XAC03-325012D4 CT Basin and Precast beam H/O 0 18-Mar-17 64

03PMS-BL00.3.2.5.01.2.E CT Over Flow Gutter


03PMS-BL00.3.2.5.01.2 37 26-Jan-17 09-Mar-17 285

XAC03-325012E1 Over flow guter - Install Scaffolding 14 26-Jan-17 10-Feb-17 285

XAC03-325012E2 Over flow guter - Install formwork 13 03-Feb-17 18-Feb-17 285

XAC03-325012E3 Over flow guter - Install Reinforcement 9 06-Feb-17 16-Feb-17 285

XAC03-325012E4 Over flow guter - Casting concrete 1 17-Feb-17 17-Feb-17 285

XAC03-325012E5 Over flow guter - Curing Time 14 18-Feb-17 06-Mar-17 288

XAC03-325012E6 Over flow guter - Remove inside formwork & Repair concrete 14 22-Feb-17 09-Mar-17 285

03PMS-BL00.3.2.5.01.2.F CT Stair Case


03PMS-BL00.3.2.5.01.2 52 03-Feb-17 04-Apr-17 263

XAC03-325012F1 CT Stair case 1 15 03-Feb-17 20-Feb-17 263

XAC03-325012F2 CT Stair case 2 15 21-Feb-17 09-Mar-17 263

XAC03-325012F3 CT Stair case 3 15 10-Mar-17 27-Mar-17 263

XAC03-325012F4 CT Stair case Finishing 7 28-Mar-17 04-Apr-17 263

XAC03-325012F5 CT Stair case H/O 0 04-Apr-17 263

03PMS-BL00.3.2.5.02 Re
Retention/Emergency (Pit & Pump Foundation) 211 20-Jun-16 16-Jan-17 381

03PMS-BL00.3.2.5.02.1 Pile Work 15 20-Jun-16 06-Jul-16 498

XAC03-32502100 Pile Work 15 20-Jun-16* 06-Jul-16 498

03PMS-BL00.3.2.5.02.2 Foundation Work 164 06-Aug-16 16-Jan-17 212

03PMS-BL00.3.2.5.02.2.1 Retention/Emergency Pit


03PMS-BL00.3.2.5.02.2 163 06-Aug-16 15-Jan-17 213

XAC03-32502211 Excavation 15 06-Aug-16* 23-Aug-16 131

XAC03-32502212 Lean concrete 50THK 4 23-Aug-16 26-Aug-16 131

XAC03-32502213 Pile cut off 14 27-Aug-16 13-Sep-16 131

XAC03-32502214 Base Slab - Slab - Install Reinforcement 20 15-Sep-16 07-Oct-16 131

XAC03-32502215 Base Slab - Slab - Install side formwork 13 30-Sep-16 15-Oct-16 131

XAC03-32502216 Base Slab - Slab - Casting concrete foundation 1 17-Oct-16 17-Oct-16 131

XAC03-32502217 Base Slab - Slab - Curing 2 18-Oct-16 19-Oct-16 131

XAC03-3250221E Wall - Install Scaffolding 7 20-Oct-16 27-Oct-16 131

XAC03-32502218 Wall - Install Reinforcement 14 22-Oct-16 08-Nov-16 131

XAC03-32502219 Wall - Install side formwork 13 01-Nov-16 16-Nov-16 131

XAC03-3250221A Wall - Install embedded material 2 07-Nov-16 08-Nov-16 243

XAC03-3250221D Foundation Work - H/O to Mech 0 15-Nov-16* 153

XAC03-3250221B Wall - Casting concrete foundation 1 17-Nov-16 17-Nov-16 131

XAC03-3250221F Remove formwork and Repair concrete 10 18-Nov-16 29-Nov-16 184

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:25 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3250221G Weter Leak Test and Repairing 14 30-Nov-16 15-Dec-16 184

XAC03-3250221C Backfill 31 16-Dec-16 15-Jan-17 213

03PMS-BL00.3.2.5.02.2.2 Retention/Emergency Pump Foundation


03PMS-BL00.3.2.5.02.2 53 16-Nov-16 16-Jan-17 120

XAC03-32502221 Retention Pit Pump Foundation 13 16-Nov-16* 01-Dec-16 120

XAC03-32502222 Emergency Pit Pump Foundation 14 01-Dec-16 16-Dec-16 120

XAC03-32502223 Retention Pit Pump Foundation - H/O to Mech 0 24-Dec-16 139

XAC03-32502224 Emergency Pit Pump Foundation - H/O to Mech 0 16-Jan-17 120

03PMS-BL00.3.2.5.03 CT Chemical Dosing Skid #3 139 14-Nov-16 01-Apr-17 74

03PMS-BL00.3.2.5.03.2 Foundation Work 63 14-Nov-16 16-Jan-17 123

XAC03-32503210 CT Chemical Dosing Skid 3 - Foundation 25 14-Nov-16* 12-Dec-16 106

XAC03-32503220 CT Chemical Dosing Skid 3 - Chemical Coating 24 22-Dec-16 15-Jan-17 123

XAC03-32503230 Civil Work - H/O to Mech 0 16-Jan-17 89

03PMS-BL00.3.2.5.03.4 Steel Structure 18 13-Mar-17 01-Apr-17 64

XAC03-32503410 CT Chemical Dosing Skid - Shed 18 13-Mar-17 01-Apr-17 64

03PMS-BL00.3.2.5.04 MC
MCWP #3 Foundation 162 20-Jun-16 28-Nov-16 141

03PMS-BL00.3.2.5.04.1 Pile Work 1 20-Jun-16 20-Jun-16 182

XAC03-32504110 Pile Work 1 20-Jun-16* 20-Jun-16 182

03PMS-BL00.3.2.5.04.2 Foundation Work 27 02-Nov-16 28-Nov-16 141

XAC03-32504210 Foundation Work 23 02-Nov-16* 28-Nov-16 116

XAC03-32504220 Foundation Work - H/O to Mech 0 28-Nov-16 101

03PMS-BL00.3.2.5.05 MCW
MC Pipe Sleeper FDN (CT #3 Area) 72 07-Nov-16 17-Jan-17 71

03PMS-BL00.3.2.5.05.2 MCW Pipe Sleeper 72 07-Nov-16 17-Jan-17 71

XAC03-32505210 CW Sleeper Foundation - Excavation 7 07-Nov-16* 14-Nov-16 62

XAC03-32505220 CW Sleeper Foundation - Lean Concrete 3 15-Nov-16 17-Nov-16 62

XAC03-32505230 CW Sleeper Foundation - Pile cut off 2 18-Nov-16 19-Nov-16 62

XAC03-32505240 CW Sleeper Foundation - Base Slab - Slab - Install Reinforcement 7 21-Nov-16 28-Nov-16 62

XAC03-32505250 CW Sleeper Foundation - Base Slab - Slab - Install formwork 6 29-Nov-16 05-Dec-16 62

XAC03-32505260 CW Sleeper Foundation - Base Slab - Slab - Casting concrete foundation 1 06-Dec-16 06-Dec-16 62

XAC03-32505270 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Install Reinforcement 7 07-Dec-16 14-Dec-16 62

XAC03-32505280 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Install side formwork 7 15-Dec-16 22-Dec-16 62

XAC03-32505290 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Casting concrete 1 23-Dec-16 23-Dec-16 62

XAC03-325052A0 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Remove formwork 12 24-Dec-16 06-Jan-17 62

XAC03-325052B0 CW Sleeper Foundation - Backfill 7 07-Jan-17 14-Jan-17 62

XAC03-325052C0 CW Sleeper Foundation - H/O to Mech 0 17-Jan-17 51

03PMS-BL00.3.2.5.06 Instrument
Ins Air System 63 30-Nov-16 31-Jan-17 307

03PMS-BL00.3.2.5.06.2 Compressor Shed/ Receiver Tank Foundation Work 37 30-Nov-16 05-Jan-17 102

XAC03-32506210 Compressor Shed/ Receiver Tank Foundation - Foundation 32 30-Nov-16* 05-Jan-17 73

XAC03-32506220 Compressor Shed/ Receiver Tank Foundation Work - H/O to Mech 0 05-Jan-17 72

03PMS-BL00.3.2.5.06.4 Structure Work 41 21-Dec-16 31-Jan-17 307

XAC03-32506410 Shed Structure 35 21-Dec-16 30-Jan-17 113

XAC03-32506420 Shed Roof 8 23-Jan-17 31-Jan-17 113

XAC03-32506430 Compressor Shed Steel Structue - H/O to Mech 0 31-Jan-17 219

03PMS-BL00.3.2.5.08 Oi
Oily Water Separator 184 27-Jun-16 24-Jan-17 112

03PMS-BL00.3.2.5.08.1 Pile Work 12 27-Jun-16 09-Jul-16 205

XAC03-32508110 PIle 12 27-Jun-16* 09-Jul-16 205

03PMS-BL00.3.2.5.08.2 Foundation Work 79 26-Oct-16 24-Jan-17 112

XAC03-32508210 Excavation 3 26-Oct-16* 28-Oct-16 112

XAC03-32508220 Lean concrete 50THK 3 27-Oct-16 29-Oct-16 112

XAC03-32508230 Pile cut off 5 31-Oct-16 04-Nov-16 112

XAC03-32508240 Base Slab - Install Reinforcement 4 05-Nov-16 09-Nov-16 112

XAC03-32508250 Base Slab - Install side formwork 4 10-Nov-16 14-Nov-16 112

XAC03-32508260 Base Slab - Casting concrete foundation (slab) 1 18-Nov-16 18-Nov-16 112

XAC03-32508270 Base Slab - Concrete Curing 2 19-Nov-16 21-Nov-16 112

XAC03-32508280 Wall - Install Reinforcement 10 22-Nov-16 02-Dec-16 112

XAC03-32508290 Wall - Install embedded material 3 30-Nov-16 02-Dec-16 119

XAC03-325082A0 Wall - Install side formwork 7 03-Dec-16 10-Dec-16 112

XAC03-325082B0 Wall - Casting concrete foundation (slab) 1 12-Dec-16 12-Dec-16 112

XAC03-325082E0 Top slab - Install scaffolding 3 13-Dec-16 15-Dec-16 112

XAC03-325082F0 Top slab - Install Reinforcement 5 16-Dec-16 21-Dec-16 112

XAC03-325082G0 Top slab - Install formwork 7 16-Dec-16 23-Dec-16 112

XAC03-325082H0 Top slab - Casting concrete 1 24-Dec-16 24-Dec-16 112

XAC03-325082I0 Water Leak Test 9 03-Jan-17 13-Jan-17 112

XAC03-325082J0 Remove formwork and Cleaning inside 9 14-Jan-17 24-Jan-17 112

XAC03-325082D0 Oily Water Separator - H/O to mech 0 24-Jan-17 112

03PMS-BL00.3.2.5.09 CT Area Pit 25 01-Sep-16 29-Sep-16 186

03PMS-BL00.3.2.5.09.1 Civil Work 25 01-Sep-16 29-Sep-16 186

XAC03-32509110 CT Area Drain Pit 25 01-Sep-16* 29-Sep-16 186

XAC03-32509120 CT Area Drain Pit - H/O to mech 0 29-Sep-16 186

03PMS-BL00.3.2.5.10 Au
Auxiliary Cooling Water System 23 01-Oct-16 24-Oct-16 157

03PMS-BL00.3.2.5.10.2 Foundation Work 23 01-Oct-16 24-Oct-16 157

XAC03-32510210 AUX Cooling Water System - Pump Foundation 10 01-Oct-16* 12-Oct-16 137

XAC03-32510220 AUX Cooling Water System - Pipe Supoort Foundation 9 13-Oct-16 22-Oct-16 137

XAC03-32510230 AUX Cooling Water System - H/O to Mech 0 24-Oct-16 113

03PMS-BL00.3.2.6 Civil (Tank


(T Area) 301 28-May-16 24-Mar-17 70

03PMS-BL00.3.2.6.01 Service
Se Water System 138 28-May-16 12-Oct-16 160

03PMS-BL00.3.2.6.01.1 Pile Work 14 28-May-16 13-Jun-16 77

XAC03-32601110 Pile Work - Service Water Tank 14 28-May-16* 13-Jun-16 77

03PMS-BL00.3.2.6.01.2 Foundation Work 113 22-Jun-16 12-Oct-16 160

XAC03-32601210 Service Water Tank - Foundation - Excavation 4 22-Jun-16* 25-Jun-16 70

XAC03-32601220 Service Water Tank - Foundation - Lean concrete 4 27-Jun-16 30-Jun-16 70

XAC03-32601230 Service Water Tank - Foundation - Pile Cut off 6 28-Jun-16 04-Jul-16 70

XAC03-32601240 Service Water Tank - Foundation - Rebar 14 05-Jul-16 20-Jul-16 70

XAC03-326012E0 Service Water Tank - Foundation - Formwork 3 21-Jul-16 23-Jul-16 70

XAC03-32601250 Service Water Tank - Foundation - Casting concrete 1 25-Jul-16 25-Jul-16 70

XAC03-32601260 Service Water Tank - Curb - Preparation surface 3 26-Jul-16 28-Jul-16 70

XAC03-32601270 Service Water Tank - Curb - Rebar 3 29-Jul-16 01-Aug-16 70

XAC03-32601280 Service Water Tank - Curb - Formwork 2 02-Aug-16 03-Aug-16 70

XAC03-32601290 Service Water Tank - Curb - Casting concrete 1 04-Aug-16 04-Aug-16 70

XAC03-326012A0 Service Water Tank - Curb - Remove formwork 3 05-Aug-16 08-Aug-16 70

XAC03-326012B0 Service Water Tank - Fill sand 8 09-Aug-16 17-Aug-16 70

XAC03-326012C0 Service Water Tank - Oil sand installation 4 18-Aug-16 22-Aug-16 70

XAC03-326012F0 Civil Work - H/O to Mech 0 30-Aug-16 58

XAC03-326012D0 SW Pump Foundation 13 27-Sep-16* 12-Oct-16 138

03PMS-BL00.3.2.6.02 DM Water System 140 28-May-16 14-Oct-16 158

03PMS-BL00.3.2.6.02.1 Pile Work 14 28-May-16 13-Jun-16 82

XAC03-32602110 Pile Work - DM Tank Pile work 14 28-May-16* 13-Jun-16 82

03PMS-BL00.3.2.6.02.2 Foundation Work 109 28-Jun-16 14-Oct-16 158

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:26 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-32602210 DM Water Tank - Foundation - Excavation 4 28-Jun-16* 01-Jul-16 77

XAC03-32602220 DM Water Tank - Foundation - Lean concrete 4 02-Jul-16 06-Jul-16 82

XAC03-32602230 DM Water Tank - Foundation - Pile Cut off 6 04-Jul-16 09-Jul-16 82

XAC03-32602240 DM Water Tank - Foundation - Rebar 10 11-Jul-16 22-Jul-16 82

XAC03-32602250 DM Water Tank - Foundation - Formwork 3 23-Jul-16 26-Jul-16 82

XAC03-32602260 DM Water Tank - Foundation - Casting concrete 1 27-Jul-16 27-Jul-16 82

XAC03-32602270 DM Water Tank - Curb - Preparation surface 3 28-Jul-16 30-Jul-16 82

XAC03-32602280 DM Water Tank - Curb - Rebar 3 01-Aug-16 03-Aug-16 82

XAC03-32602290 DM Water Tank - Curb - Formwork 2 04-Aug-16 05-Aug-16 82

XAC03-326022A0 DM Water Tank - Curb - Casting concrete 1 06-Aug-16 06-Aug-16 82

XAC03-326022B0 DM Water Tank - Curb - Remove formwork 3 08-Aug-16 10-Aug-16 94

XAC03-326022C0 DM Water Tank - Fill sand 8 11-Aug-16 19-Aug-16 94

XAC03-326022D0 DM Water Tank - Oil sand installation 4 20-Aug-16 24-Aug-16 94

XAC03-326022F0 Civil Work - H/O to Mech 0 01-Sep-16 77

XAC03-326022E0 DM Pump Foundation 14 29-Sep-16* 14-Oct-16 136

03PMS-BL00.3.2.6.03 CT Make Up Water System 130 14-Jun-16 21-Oct-16 199

03PMS-BL00.3.2.6.03.1 Pile Work 11 14-Jun-16 25-Jun-16 82

XAC03-32603110 Pile Work - CW Make Up Water Tank 11 14-Jun-16 25-Jun-16 82

03PMS-BL00.3.2.6.03.2 Foundation Work 109 05-Jul-16 21-Oct-16 199

XAC03-32603210 CT Make Up Tank - Foundation - Excavation 4 05-Jul-16* 08-Jul-16 75

XAC03-32603220 CT Make Up Tank - Foundation - Lean concrete 4 09-Jul-16 13-Jul-16 75

XAC03-32603230 CT Make Up Tank - Foundation - Pile Cut off 6 09-Jul-16 16-Jul-16 75

XAC03-32603240 CT Make Up Tank - Foundation - Rebar 10 18-Jul-16 29-Jul-16 75

XAC03-32603250 CT Make Up Tank - Foundation - Formwork 3 30-Jul-16 02-Aug-16 75

XAC03-32603260 CT Make Up Tank - Foundation - Casting concrete 1 03-Aug-16 03-Aug-16 75

XAC03-32603270 CT Make Up Tank - Curb - Preparation surface 3 04-Aug-16 06-Aug-16 75

XAC03-32603280 CT Make Up Tank - Curb - Rebar 3 08-Aug-16 10-Aug-16 75

XAC03-32603290 CT Make Up Tank - Curb - Formwork 3 11-Aug-16 13-Aug-16 75

XAC03-326032A0 CT Make Up Tank - Curb - Casting concrete 1 15-Aug-16 15-Aug-16 75

XAC03-326032B0 CT Make Up Tank - Curb - Remove formwork 3 16-Aug-16 18-Aug-16 117

XAC03-326032C0 CT Make Up Tank - Fill sand 7 19-Aug-16 26-Aug-16 117

XAC03-326032D0 CT Make Up Tank - Oil sand installation 4 27-Aug-16 31-Aug-16 117

XAC03-326032F0 Civil Work - H/O to Mech 0 08-Sep-16 96

XAC03-326032E0 CT make-up Pump Foundation 14 06-Oct-16* 21-Oct-16 172

03PMS-BL00.3.2.6.04 Pip
Pipe Trench (Tank - Fire Fighting Pump Station) 157 20-Jun-16 23-Nov-16 81

03PMS-BL00.3.2.6.04.1 Pile 5 20-Jun-16 24-Jun-16 120

XAC03-32604110 Pile Work 5 20-Jun-16* 24-Jun-16 120

03PMS-BL00.3.2.6.04.2 Pipe Trench 94 22-Aug-16 23-Nov-16 81

XAC03-32604210 Pipe Trench (Tank - FF Pump Sta.) - Excavation 3 22-Aug-16* 24-Aug-16 70

XAC03-32604220 Pipe Trench (Tank - FF Pump Sta.) - Lean concrete 1 25-Aug-16 26-Aug-16 70

XAC03-32604230 Pipe Trench (Tank - FF Pump Sta.) - Slab - Install Reinforcement 6 27-Aug-16 02-Sep-16 70

XAC03-32604240 Pipe Trench (Tank - FF Pump Sta.) - Slab - Install side formwork 6 03-Sep-16 09-Sep-16 70

XAC03-32604250 Pipe Trench (Tank - FF Pump Sta.) - Slab - Casting concrete 6 10-Sep-16 16-Sep-16 70

XAC03-32604260 Pipe Trench (Tank - FF Pump Sta.) - Wall - Install Reinforcement 12 17-Sep-16 30-Sep-16 70

XAC03-32604270 Pipe Trench (Tank - FF Pump Sta.) - Wall - Install side formwork 6 01-Oct-16 07-Oct-16 70

XAC03-32604280 Pipe Trench (Tank - FF Pump Sta.) - Wall - Casting concrete 1 08-Oct-16 08-Oct-16 70

XAC03-32604290 Pipe Trench (Tank - FF Pump Sta.) - Top Slab - Install Reinforcement 12 10-Oct-16 22-Oct-16 70

XAC03-326042A0 Pipe Trench (Tank - FF Pump Sta.) - Top Slab - Install side formwork 6 24-Oct-16 29-Oct-16 70

XAC03-326042B0 Pipe Trench (Tank - FF Pump Sta.) - Top Slab - Casting concrete 1 31-Oct-16 31-Oct-16 70

XAC03-326042C0 Pipe Trench (Tank - FF Pump Sta.) - Backfill 2 01-Nov-16 02-Nov-16 70

XAC03-326042D0 Pipe Trench (Tank - FF Pump Sta.) - H/O to Mech 0 23-Nov-16 57

03PMS-BL00.3.2.6.05 Pipe
Pip Trench (Tank - WTP) 164 30-Jul-16 04-Feb-17 82

03PMS-BL00.3.2.6.05.1 Pile 4 30-Jul-16 04-Aug-16 158

XAC03-32605110 Pile Work 4 30-Jul-16* 04-Aug-16 158

03PMS-BL00.3.2.6.05.2 Pipe Trench 84 01-Nov-16 04-Feb-17 82

XAC03-32605210 Pipe Trench (Tank - WTP) - Excavation 3 01-Nov-16* 03-Nov-16 82

XAC03-32605220 Pipe Trench (Tank - WTP) - Lean concrete 1 04-Nov-16 04-Nov-16 82

XAC03-32605230 Pipe Trench (Tank - WTP) - Slab - Install Reinforcement 6 05-Nov-16 11-Nov-16 82

XAC03-32605240 Pipe Trench (Tank - WTP) - Slab - Install side formwork 6 12-Nov-16 18-Nov-16 82

XAC03-32605250 Pipe Trench (Tank - WTP) - Slab - Casting concrete 1 19-Nov-16 19-Nov-16 82

XAC03-32605260 Pipe Trench (Tank - WTP) - Wall - Install Reinforcement 12 21-Nov-16 03-Dec-16 82

XAC03-32605270 Pipe Trench (Tank - WTP) - Wall - Install side formwork 6 05-Dec-16 10-Dec-16 82

XAC03-32605280 Pipe Trench (Tank - WTP) - Wall - Casting concrete 1 12-Dec-16 12-Dec-16 82

XAC03-32605290 Pipe Trench (Tank - WTP) - Top Slab - Install Reinforcement 19 13-Dec-16 03-Jan-17 82

XAC03-326052A0 Pipe Trench (Tank - WTP) - Top Slab - Install side formwork 6 04-Jan-17 10-Jan-17 82

XAC03-326052B0 Pipe Trench (Tank - WTP) - Top Slab - Casting concrete 1 11-Jan-17 11-Jan-17 82

XAC03-326052C0 Pipe Trench (Tank - WTP) - Backfill 2 12-Jan-17 13-Jan-17 82

XAC03-326052D0 Pipe Trench (Tank - WTP) - H/O to Mech 0 04-Feb-17 82

03PMS-BL00.3.2.6.06 Pipe
Pip Sleeper (Tank Area) 23 02-Mar-17 24-Mar-17 70

03PMS-BL00.3.2.6.06.6 Pipe Sleeper (Tank Area) 23 02-Mar-17 24-Mar-17 70

XAC03-32606610 Civil (Tank Area) - Pipe Sleeper (Tank Area) 20 02-Mar-17* 24-Mar-17 61

XAC03-32606620 Civil (Tank Area) - Pipe Sleeper (Tank Area) - H/O to Mech 0 24-Mar-17 50

03PMS-BL00.3.2.7 Civil (GSUT


(G #3 Area) 309 06-Jun-16 10-Apr-17 297

03PMS-BL00.3.2.7.01 GSUT
GS #31 & #32 & ST #30 & Unit Aux. #31 & #32 Transformer 254 06-Jun-16 14-Feb-17 352

03PMS-BL00.3.2.7.01.1 Pile Work 9 06-Jun-16 16-Jun-16 126

XAC03-32701110 Pile Work - GTG#31 / 32 / ST / UAT Tr. Pile Work 9 06-Jun-16* 16-Jun-16 126

03PMS-BL00.3.2.7.01.2 Foundation/Civil Work 214 13-Jun-16 14-Feb-17 305

03PMS-BL00.3.2.7.01.2.1 GSUT Foundation


03PMS-BL00.3.2.7.01.2 24 04-Aug-16 31-Aug-16 113

XAC03-32701211 Foundation Work - Excavation 4 04-Aug-16* 08-Aug-16 113

XAC03-32701212 Foundation Work - Base slab - Lean concrete 5 05-Aug-16 10-Aug-16 113

XAC03-32701213 Foundation Work - Base slab - Pile cut off 7 06-Aug-16 13-Aug-16 113

XAC03-32701214 Foundation Work - Base slab - Repair PC piles and Dowel 2 13-Aug-16 16-Aug-16 113

XAC03-32701215 Foundation Work - Base slab - Rebar work 10 17-Aug-16 27-Aug-16 113

XAC03-32701216 Foundation Work - Base slab - Formwork 7 23-Aug-16 30-Aug-16 113

XAC03-32701218 Foundation Work - Base slab - Concrete base slab 1 31-Aug-16 31-Aug-16 113

03PMS-BL00.3.2.7.01.2.2 GTG GSUT Unit 1


03PMS-BL00.3.2.7.01.2 21 01-Sep-16 26-Sep-16 147

XAC03-32701221 GTG GSUT Unit 1 - Wall - Scaffolding 1 01-Sep-16 02-Sep-16 113

XAC03-32701222 GTG GSUT Unit 1 - Wall - Rebar work 4 03-Sep-16 07-Sep-16 130

XAC03-32701223 GTG GSUT Unit 1 - Wall - Formwork 6 08-Sep-16 14-Sep-16 130

XAC03-32701224 GTG GSUT Unit 1 - Wall - Concrete wall 1 15-Sep-16 15-Sep-16 130

XAC03-32701225 GTG GSUT Unit 1 - Wall - Remove formwork and repair concrete 3 16-Sep-16 19-Sep-16 130

XAC03-32701226 GTG GSUT Unit 1 - Pedestal and kerb- Rebar work 3 17-Sep-16 20-Sep-16 147

XAC03-32701227 GTG GSUT Unit 1 - Pedestal and kerb - Formwork 4 21-Sep-16 24-Sep-16 147

XAC03-32701228 GTG GSUT Unit 1 - Pedestal and kerb - concrete 1 26-Sep-16 26-Sep-16 147

03PMS-BL00.3.2.7.01.2.3 GTG GSUT Unit 2


03PMS-BL00.3.2.7.01.2 23 06-Sep-16 01-Oct-16 142

XAC03-32701231 GTG GSUT Unit 2 - Wall - Scaffolding 1 06-Sep-16 07-Sep-16 113

XAC03-32701232 GTG GSUT Unit 2 - Wall - Rebar work 4 07-Sep-16 10-Sep-16 142

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:27 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-32701233 GTG GSUT Unit 2 - Wall - Formwork 6 12-Sep-16 17-Sep-16 142

XAC03-32701234 GTG GSUT Unit 2 - Wall - Concrete wall 1 19-Sep-16 19-Sep-16 142

XAC03-32701235 GTG GSUT Unit 2 - Wall - Remove formwork and repair concrete 5 20-Sep-16 24-Sep-16 142

XAC03-32701236 GTG GSUT Unit 2 - Pedestal and kerb- Rebar work 2 23-Sep-16 26-Sep-16 142

XAC03-32701237 GTG GSUT Unit 2 - Pedestal and kerb - Formwork 4 27-Sep-16 30-Sep-16 142

XAC03-32701238 GTG GSUT Unit 2 - Pedestal and kerb - concrete 1 01-Oct-16 01-Oct-16 142

03PMS-BL00.3.2.7.01.2.4 STG GSUT


03PMS-BL00.3.2.7.01.2 31 10-Sep-16 15-Oct-16 130

XAC03-32701241 STG GSUT - Wall - Scaffolding 2 10-Sep-16 12-Sep-16 113

XAC03-32701242 STG GSUT - Wall - Rebar work 4 21-Sep-16 24-Sep-16 130

XAC03-32701243 STG GSUT - Wall - Formwork 6 26-Sep-16 01-Oct-16 130

XAC03-32701244 STG GSUT - Wall - Concrete wall 1 03-Oct-16 03-Oct-16 130

XAC03-32701245 STG GSUT - Wall - Remove formwork and repair concrete 3 04-Oct-16 06-Oct-16 130

XAC03-32701246 STG GSUT - Pedestal and kerb- Rebar work 3 07-Oct-16 10-Oct-16 130

XAC03-32701247 STG GSUT - Pedestal and kerb - Formwork 4 11-Oct-16 14-Oct-16 130

XAC03-32701248 STG GSUT - Pedestal and kerb - concrete 1 15-Oct-16 15-Oct-16 130

03PMS-BL00.3.2.7.01.2.5 UAT Unit 1


03PMS-BL00.3.2.7.01.2 22 15-Sep-16 10-Oct-16 113

XAC03-32701251 UAT Unit 1 - Wall - Sc affolding 2 15-Sep-16 16-Sep-16 113

XAC03-32701252 UAT Unit 1 - Wall - Rebar work 4 17-Sep-16 21-Sep-16 113

XAC03-32701253 UAT Unit 1 - Wall - Formwork 6 20-Sep-16 26-Sep-16 113

XAC03-32701254 UAT Unit 1 - Wall - Concrete wall 1 26-Sep-16 27-Sep-16 113

XAC03-32701255 UAT Unit 1 - Wall - Remove formwork and repair concrete 3 28-Sep-16 30-Sep-16 113

XAC03-32701256 UAT Unit 1 - Pedestal and kerb- Rebar work 3 01-Oct-16 04-Oct-16 113

XAC03-32701257 UAT Unit 1 - Pedestal and kerb - Formwork 4 05-Oct-16 08-Oct-16 113

XAC03-32701258 UAT Unit 1 - Pedestal and kerb - concrete 1 10-Oct-16 10-Oct-16 113

03PMS-BL00.3.2.7.01.2.6 UAT Unit 2


03PMS-BL00.3.2.7.01.2 110 11-Oct-16 14-Feb-17 305

XAC03-32701261 UAT Unit 2 - Pedestal and kerb- Rebar work 3 11-Oct-16 13-Oct-16 113

XAC03-32701262 UAT Unit 2 - Pedestal and kerb - Formwork 3 14-Oct-16 17-Oct-16 113

XAC03-32701263 UAT Unit 2 - Pedestal and kerb - concrete 1 18-Oct-16 18-Oct-16 113

XAC03-32701264 GSUT Pedestal H/O 0 03-Nov-16 113

XAC03-32701265 GSUT GTG1&2/STG/UAT1&2 - H/O to Mech 0 04-Nov-16 113

XAC03-32701266 Transformer Installation (M&E) 52 04-Nov-16 03-Jan-17 305

XAC03-32701267 Install support and grating 18 07-Jan-17 28-Jan-17 305

XAC03-32701268 Gravel laying 14 30-Jan-17 14-Feb-17 305

03PMS-BL00.3.2.7.01.2.7 Oil Drain Pit


03PMS-BL00.3.2.7.01.2 42 13-Jun-16 30-Jul-16 196

XAC03-32701271 Oil Drain Pit - Excavation 4 13-Jun-16* 16-Jun-16 196

XAC03-32701272 Oil Drain Pit - Lean concrete 2 17-Jun-16 18-Jun-16 196

XAC03-32701273 Oil Drain Pit - Base slab - Rebar work 5 20-Jun-16 24-Jun-16 196

XAC03-32701274 Oil Drain Pit - Base slab - Formwork and water stop 3 25-Jun-16 28-Jun-16 196

XAC03-32701275 Oil Drain Pit - Base slab - Concrete base slab 1 29-Jun-16 29-Jun-16 196

XAC03-32701276 Oil Drain Pit - Wall - Scaffolding 2 30-Jun-16 01-Jul-16 196

XAC03-32701277 Oil Drain Pit - Wall - Rebar work 4 02-Jul-16 06-Jul-16 196

XAC03-32701278 Oil Drain Pit - Wall - Formwork and Embedded 7 07-Jul-16 14-Jul-16 196

XAC03-32701279 Oil Drain Pit - Wall - Concrete wall 1 15-Jul-16 15-Jul-16 196

XAC03-3270127A Oil Drain Pit - Wall - Remove formwork and repai concrete 2 16-Jul-16 18-Jul-16 196

XAC03-3270127B Oil Drain Pit - Wall - Water Leak test and repairing 10 19-Jul-16 29-Jul-16 196

XAC03-3270127C Oil Drain Pit - Wall - Backfill 1 30-Jul-16 30-Jul-16 196

03PMS-BL00.3.2.7.02 Cable
Ca Trench 6 (GSU Transformer area) 42 21-Jun-16 08-Aug-16 470

03PMS-BL00.3.2.7.02.5 Cable Trench 42 21-Jun-16 08-Aug-16 470

03PMS-BL00.3.2.7.02.5.1 Cable Trench - First section 20 meter


03PMS-BL00.3.2.7.02.5 35 21-Jun-16 30-Jul-16 477

XAC03-32702511 Cable Trench - Excavation (Open cut) 7 21-Jun-16* 28-Jun-16 470

XAC03-32702512 Cable Trench - First section 20 meter - Lean concrete 3 29-Jun-16 01-Jul-16 470

XAC03-32702513 Cable Trench - First section 20 meter - Base slab - Rebar work 7 02-Jul-16 09-Jul-16 470

XAC03-32702514 Cable Trench - First section 20 meter - Base slab - Formwork and water stop 6 06-Jul-16 12-Jul-16 477

XAC03-32702515 Cable Trench - First section 20 meter - Base slab - Concrete base slab 1 13-Jul-16 13-Jul-16 477

XAC03-32702516 Cable Trench - First section 20 meter - wall - Scaffolding 2 14-Jul-16 15-Jul-16 477

XAC03-32702517 Cable Trench - First section 20 meter - wall - Rebar work 5 14-Jul-16 19-Jul-16 477

XAC03-32702518 Cable Trench - First section 20 meter - wall - Formwork and Embedded 7 15-Jul-16 22-Jul-16 477

XAC03-32702519 Cable Trench - First section 20 meter - wall - Concrete wall 1 22-Jul-16 23-Jul-16 477

XAC03-3270251A Cable Trench - First section 20 meter - wall - Remove formwork and repair concrete 3 25-Jul-16 27-Jul-16 477

XAC03-3270251B Cable Trench - First section 20 meter - wall - Backfill for GSUT area 3 28-Jul-16 30-Jul-16 477

03PMS-BL00.3.2.7.02.5.2 Cable Trench - Second section 20 meter


03PMS-BL00.3.2.7.02.5 29 06-Jul-16 08-Aug-16 470

XAC03-32702521 Cable Trench - Second section 20 meter - Lean concrete 3 06-Jul-16 08-Jul-16 471

XAC03-32702522 Cable Trench - Second section 20 meter - Base slab - Rebar work 7 11-Jul-16 18-Jul-16 470

XAC03-32702523 Cable Trench - Second section 20 meter - Base slab - Formwork and water stop 6 14-Jul-16 20-Jul-16 470

XAC03-32702524 Cable Trench - Second section 20 meter - Base slab - Concrete base slab 1 21-Jul-16 21-Jul-16 470

XAC03-32702525 Cable Trench - Second section 20 meter - wall - Scaffolding 2 22-Jul-16 23-Jul-16 470

XAC03-32702526 Cable Trench - Second section 20 meter - wall - Rebar work 5 22-Jul-16 27-Jul-16 470

XAC03-32702527 Cable Trench - Second section 20 meter - wall - Formwork and Embedded 7 23-Jul-16 30-Jul-16 470

XAC03-32702528 Cable Trench - Second section 20 meter - wall - Concrete wall 1 30-Jul-16 01-Aug-16 470

XAC03-32702529 Cable Trench - Second section 20 meter - wall - Remove formwork and repair concrete 3 02-Aug-16 04-Aug-16 470

XAC03-3270252A Cable Trench - Second section 20 meter - wall - Backfill for GSUT area 3 05-Aug-16 08-Aug-16 470

XAC03-3270252B Civil Work - H/O to Mech 0 08-Aug-16 470

03PMS-BL00.3.2.7.ZZ O
Other Civil Work 7 01-Apr-17 10-Apr-17 34

XAC03-327ZZ200 GSUT Other - GSUT #3 Fence 7 01-Apr-17* 10-Apr-17 34

XAC03-327ZZ400 GSUT Other - GSUT #3 Fence - H/O to Mech 0 10-Apr-17 34

03PMS-BL00.3.2.8 Civil (BOP


(B Area) 297 06-Jun-16 30-Mar-17 78

03PMS-BL00.3.2.8.01 Raw
Ra Water System 60 06-Jun-16 04-Aug-16 176

03PMS-BL00.3.2.8.01.1 Pile Work 6 06-Jun-16 11-Jun-16 68

XAC03-32801110 Raw Water Tank - Pile 6 06-Jun-16* 11-Jun-16 68

03PMS-BL00.3.2.8.01.2 Foundation Work 35 01-Jul-16 04-Aug-16 176

XAC03-32801210 Foundation Raw Water Buffer Tank 23 01-Jul-16* 27-Jul-16 31

XAC03-32801220 Foundation Raw Water Pump 10 25-Jul-16 04-Aug-16 31

XAC03-32801230 Civil Work - H/O to Mech 0 04-Aug-16 126

03PMS-BL00.3.2.8.02 Inspection
Ins Pit 124 08-Jun-16 10-Oct-16 249

03PMS-BL00.3.2.8.02.1 Pile Work 6 08-Jun-16 14-Jun-16 261

XAC03-32802110 Inspection Pit - Pile work 6 08-Jun-16 14-Jun-16 261

03PMS-BL00.3.2.8.02.2 Foundation Work 66 04-Aug-16 10-Oct-16 249

XAC03-32802210 Excavation 2 04-Aug-16 06-Aug-16 216

XAC03-32802220 Lean concrete 50THK 2 08-Aug-16 09-Aug-16 216

XAC03-32802230 Pile cut off 1 10-Aug-16 10-Aug-16 216

XAC03-32802240 Base Slab - Install Reinforcement 3 15-Aug-16 18-Aug-16 216

XAC03-32802250 Base Slab - Install side formwork 4 17-Aug-16 20-Aug-16 216

XAC03-32802260 Base Slab - Casting concrete foundation 1 22-Aug-16 22-Aug-16 216

XAC03-32802270 Wall +Column C1 (6 number) - Install Reinforcement 9 23-Aug-16 01-Sep-16 216

XAC03-32802290 Wall +Column C1 (6 number) - Install embedded material 5 27-Aug-16 01-Sep-16 223

XAC03-32802280 Wall +Column C1 (6 number) - Install side formwork 7 27-Aug-16 03-Sep-16 216

XAC03-328022A0 Wall +Column C1 (6 number) - Casting concrete foundation 1 05-Sep-16 05-Sep-16 216

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:28 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-328022B0 Roof Beam (+2.275) - Scaffolding Installation 3 07-Sep-16 09-Sep-16 216

XAC03-328022C0 Roof Beam (+2.275) - Wall - Install Reinforcement 4 13-Sep-16 16-Sep-16 216

XAC03-328022D0 Roof Beam (+2.275) - Wall - Install side formwork 4 17-Sep-16 21-Sep-16 216

XAC03-328022E0 Roof Beam (+2.275) - Wall - Casting concrete 1 22-Sep-16 22-Sep-16 216

XAC03-328022J0 Civil Work - H/O to Mech 0 10-Oct-16 179

03PMS-BL00.3.2.8.06 Pip
Pipe Rack RA (BOP Area Road Crossing) 95 29-Jun-16 08-Nov-16 129

03PMS-BL00.3.2.8.06.1 Pile Work 2 29-Jun-16 30-Jun-16 96

XAC03-32806110 Pile Work - Pile Work 2 29-Jun-16* 30-Jun-16 96

03PMS-BL00.3.2.8.06.2 Foundation Work 19 15-Sep-16 11-Oct-16 149

XAC03-32806210 Foundation - Excavation 2 15-Sep-16 16-Sep-16 98

XAC03-32806220 Foundation - Reinforcement 3 20-Sep-16 22-Sep-16 98

XAC03-32806230 Foundation - Form 3 23-Sep-16 27-Sep-16 98

XAC03-32806240 Foundation - Concrete 1 28-Sep-16 28-Sep-16 98

XAC03-32806250 Foundation - Curing 7 29-Sep-16 07-Oct-16 98

XAC03-32806260 Foundation - Pedestal Concrete 5 04-Oct-16 10-Oct-16 98

XAC03-32806270 Foundation - Backfilling 2 10-Oct-16 11-Oct-16 98

XAC03-32806280 Civil Work - H/O to Mech 0 11-Oct-16 149

03PMS-BL00.3.2.8.06.4 Structure Work 17 17-Oct-16 08-Nov-16 95

XAC03-32806410 Steel Structure - Material Arrival 0 17-Oct-16 95

XAC03-32806420 Steel Structure - Erection 17 17-Oct-16 08-Nov-16 95

XAC03-32806430 Steel Structure - H/O to Mech 0 08-Nov-16 95

03PMS-BL00.3.2.8.07 Pip
Pipe Rack RB (BOP Area Road Crossing) 106 01-Jul-16 25-Nov-16 78

03PMS-BL00.3.2.8.07.1 Pile Work 2 01-Jul-16 04-Jul-16 96

XAC03-32807110 Pile Work - Pile Work 2 01-Jul-16* 04-Jul-16 96

03PMS-BL00.3.2.8.07.2 Foundation Work 26 16-Aug-16 20-Sep-16 96

XAC03-32807210 Foundation - Excavation 6 16-Aug-16 23-Aug-16 96

XAC03-32807220 Foundation - Reinforcement 5 24-Aug-16 30-Aug-16 96

XAC03-32807230 Foundation - Form 3 31-Aug-16 02-Sep-16 96

XAC03-32807240 Foundation - Concrete 1 05-Sep-16 05-Sep-16 96

XAC03-32807250 Foundation - Curing 7 06-Sep-16 14-Sep-16 96

XAC03-32807260 Foundation - Pedestal Concrete 5 07-Sep-16 13-Sep-16 101

XAC03-32807270 Foundation - Backfilling 4 15-Sep-16 20-Sep-16 96

XAC03-32807280 Civil Work - H/O to Mech 0 20-Sep-16 96

03PMS-BL00.3.2.8.07.4 Structure Work 30 17-Oct-16 25-Nov-16 78

XAC03-32807410 Steel Structure - Material Arrival 0 17-Oct-16* 78

XAC03-32807420 Steel Structure - Erection 30 17-Oct-16 25-Nov-16 78

XAC03-32807430 Steel Structure - H/O to Mech 0 25-Nov-16 78

03PMS-BL00.3.2.8.08 Pip
Pipe Sleeper (BOP Area) 272 01-Jul-16 30-Mar-17 40

03PMS-BL00.3.2.8.08.1 Sleeper FDN (BOP) 272 01-Jul-16 30-Mar-17 40

XAC03-32808110 Sleeper FDN for Gas Metering - WTP 31 01-Jul-16* 05-Aug-16 138

XAC03-32808120 Sleeper FDN for WTP area to Tank area 18 01-Aug-16 20-Aug-16 138

XAC03-32808180 Sleeper FDN for Gas Metering - WTP - H/O to Mech 0 05-Aug-16 162

XAC03-32808190 Sleeper FDN for WTP area to Tank area - H/O to Mech 0 22-Aug-16 152

XAC03-32808130 Sleeper FDN for WTP - Retention 24 22-Aug-16 17-Sep-16 140

XAC03-32808140 Sleeper FDN for SWYD - Pipe Rack RA 11 01-Sep-16 14-Sep-16 143

XAC03-328081E0 Sleeper FDN for SWYD - Pipe Rack RA - H/O to Mech 0 14-Sep-16 168

XAC03-328081A0 Sleeper FDN for WTP - Retention - H/O to Mech 0 19-Sep-16 166

XAC03-32808150 Sleeper FDN for Pipe Rack RF - Retention 18 01-Nov-16* 21-Nov-16 103

XAC03-328081B0 Sleeper FDN for Pipe Rack RF - Retention - H/O to Mech 0 21-Nov-16 102

XAC03-32808160 Sleeper FDN for CT - MCWP 33 20-Feb-17* 30-Mar-17 25

XAC03-32808170 Sleeper FDN for Retention Basin Around (Oily Separator) 9 02-Mar-17* 11-Mar-17 50

XAC03-328081C0 Sleeper FDN for Retention Basin Around (Oily Separator) - H/O to Mech 0 13-Mar-17 41

XAC03-328081D0 Sleeper FDN for CT - MCWP - H/O to Mech 0 30-Mar-17 21

03PMS-BL00.3.2.9 Civil (SWYD


(S Area] 132 01-Jul-16 30-Nov-16 371

03PMS-BL00.3.2.9.1 Pile Work 26 01-Jul-16 01-Aug-16 258

XAC03-32901110 Pile Work 26 01-Jul-16* 01-Aug-16 258

03PMS-BL00.3.2.9.2 ABPR3
ABP Zone-1 76 01-Aug-16 27-Oct-16 401

03PMS-BL00.3.2.9.2.1 ABPR3
A Equipment Foundation Zone-1 66 01-Aug-16 15-Oct-16 411

XAC03-32901211 Excavate 5 01-Aug-16 05-Aug-16 258

XAC03-32901212 Pile Cut 14 06-Aug-16 22-Aug-16 309

XAC03-32901213 Lean concrete 7 22-Aug-16 30-Aug-16 309

XAC03-32901214 Tying Rebar Foundation 7 30-Aug-16 07-Sep-16 309

XAC03-32901215 Assembly formwork Pedestal 10 07-Sep-16 19-Sep-16 309

XAC03-32901216 Concrete Pouring 1 19-Sep-16 20-Sep-16 309

XAC03-32901217 Tying Rebar Pedestal 7 20-Sep-16 28-Sep-16 309

XAC03-32901218 Assembly formwork Pedestal 7 28-Sep-16 06-Oct-16 309

XAC03-32901219 Set Anchorbplt 6 06-Oct-16 13-Oct-16 411

XAC03-3290121A Concrete Pouring 1 13-Oct-16 14-Oct-16 411

XAC03-3290121B Remove formwork 1 14-Oct-16 15-Oct-16 411

03PMS-BL00.3.2.9.2.2 ABPR3
A Cable Trench Zone-1 41 22-Aug-16 08-Oct-16 417

XAC03-32901221 Lean concrete 3 22-Aug-16 25-Aug-16 417

XAC03-32901222 Tying Rebar Slab Cable Trench 3 25-Aug-16 29-Aug-16 417

XAC03-32901223 Assembly formwork Slab Cable Trench 6 29-Aug-16 05-Sep-16 417

XAC03-32901224 Pour Concrete Slab Cable Trench 1 05-Sep-16 06-Sep-16 417

XAC03-32901225 Tying Rebar Wall Cable Trench 7 06-Sep-16 14-Sep-16 417

XAC03-32901226 Install Ladder 11 14-Sep-16 27-Sep-16 417

XAC03-32901227 Assembly formwork Wall Cable Trench 8 27-Sep-16 06-Oct-16 417

XAC03-32901228 Pour Concrete Wall Cable Trench 1 06-Oct-16 07-Oct-16 417

XAC03-32901229 Remove formwork 1 07-Oct-16 08-Oct-16 417

03PMS-BL00.3.2.9.2.3 A
ABPR3 Backfill Zone-1 18 06-Oct-16 27-Oct-16 309

XAC03-32901231 Layer-1 5 06-Oct-16 12-Oct-16 309

XAC03-32901232 Layer-2 5 12-Oct-16 18-Oct-16 309

XAC03-32901233 Grounding Grid Install 3 18-Oct-16 21-Oct-16 309

XAC03-32901234 Layer-3 5 21-Oct-16 27-Oct-16 309

03PMS-BL00.3.2.9.3 ABPR3
ABP Zone-2 76 09-Aug-16 04-Nov-16 394

03PMS-BL00.3.2.9.3.1 ABPR3
A Equipment Foundation Zone-2 66 09-Aug-16 24-Oct-16 404

XAC03-32901311 Excavate 5 09-Aug-16 13-Aug-16 258

XAC03-32901312 Pile Cut 14 13-Aug-16 30-Aug-16 302

XAC03-32901313 Lean concrete 7 30-Aug-16 07-Sep-16 302

XAC03-32901314 Tying Rebar Foundation 7 07-Sep-16 15-Sep-16 302

XAC03-32901315 Assembly formwork Pedestal 10 15-Sep-16 27-Sep-16 302

XAC03-32901316 Pour Concrete 1 27-Sep-16 28-Sep-16 302

XAC03-32901317 Tying Rebar Pedestal 7 28-Sep-16 06-Oct-16 302

XAC03-32901318 Assembly formwork Pedestal 7 06-Oct-16 14-Oct-16 302

XAC03-32901319 Set Anchorbplt 6 14-Oct-16 21-Oct-16 404

XAC03-3290131A Pour Concrete 1 21-Oct-16 22-Oct-16 404

XAC03-3290131B Remove formwork 1 22-Oct-16 24-Oct-16 404

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:29 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
03PMS-BL00.3.2.9.3.2 ABPR3
A Cable Trench Zone-2 42 30-Aug-16 18-Oct-16 409

XAC03-32901321 Lean concrete 4 30-Aug-16 03-Sep-16 409

XAC03-32901322 Tying Rebar Slab Cable Trench 3 03-Sep-16 07-Sep-16 409

XAC03-32901323 Assembly formwork Slab Cable Trench 6 07-Sep-16 14-Sep-16 409

XAC03-32901324 Pour Concrete Slab Cable Trench 1 14-Sep-16 15-Sep-16 409

XAC03-32901325 Tying Rebar Wall Cable Trench 7 15-Sep-16 23-Sep-16 409

XAC03-32901326 Install Ladder 11 23-Sep-16 06-Oct-16 409

XAC03-32901327 Assembly formwork Wall Cable Trench 8 06-Oct-16 15-Oct-16 409

XAC03-32901328 Pour Concrete Wall Cable Trench 1 15-Oct-16 17-Oct-16 409

XAC03-32901329 Remove formwork 1 17-Oct-16 18-Oct-16 409

03PMS-BL00.3.2.9.3.3 A
ABPR3 Backfill Zone-2 18 14-Oct-16 04-Nov-16 302

XAC03-32901331 Layer-1 5 14-Oct-16 20-Oct-16 302

XAC03-32901332 Layer-2 5 20-Oct-16 26-Oct-16 302

XAC03-32901333 Grounding Grid Install 3 26-Oct-16 29-Oct-16 302

XAC03-32901334 Layer-3 5 29-Oct-16 04-Nov-16 302

03PMS-BL00.3.2.9.4 ABPR3
ABP Zone-3 76 16-Aug-16 12-Nov-16 387

03PMS-BL00.3.2.9.4.1 ABPR3
A Equipment Foundation Zone-3 66 16-Aug-16 01-Nov-16 397

XAC03-32901411 Excavate 5 16-Aug-16 22-Aug-16 258

XAC03-32901412 Pile Cut 14 22-Aug-16 07-Sep-16 295

XAC03-32901413 Lean concrete 7 07-Sep-16 15-Sep-16 295

XAC03-32901414 Tying Rebar Foundation 7 15-Sep-16 23-Sep-16 295

XAC03-32901415 Assembly formwork Pedestal 10 23-Sep-16 05-Oct-16 295

XAC03-32901416 Pour Concrete 1 05-Oct-16 06-Oct-16 295

XAC03-32901417 Tying Rebar Pedestal 7 06-Oct-16 14-Oct-16 295

XAC03-32901418 Assembly formwork Pedestal 7 14-Oct-16 22-Oct-16 295

XAC03-32901419 Set Anchorbplt 6 22-Oct-16 29-Oct-16 397

XAC03-3290141A Pour Concrete 1 29-Oct-16 31-Oct-16 397

XAC03-3290141B Remove formwork 1 31-Oct-16 01-Nov-16 397

03PMS-BL00.3.2.9.4.2 ABPR3
A Cable Trench Zone-3 41 07-Sep-16 25-Oct-16 403

XAC03-32901421 Lean concrete 3 07-Sep-16 10-Sep-16 403

XAC03-32901422 Tying Rebar Slab Cable Trench 3 10-Sep-16 14-Sep-16 403

XAC03-32901423 Assembly formwork Slab Cable Trench 6 14-Sep-16 21-Sep-16 403

XAC03-32901424 Pour Concrete Slab Cable Trench 1 21-Sep-16 22-Sep-16 403

XAC03-32901425 Tying Rebar Wall Cable Trench 7 22-Sep-16 30-Sep-16 403

XAC03-32901426 Install Ladder 11 30-Sep-16 13-Oct-16 403

XAC03-32901427 Assembly formwork Wall Cable Trench 8 13-Oct-16 22-Oct-16 403

XAC03-32901428 Pour Concrete Wall Cable Trench 1 22-Oct-16 24-Oct-16 403

XAC03-32901429 Remove formwork 1 24-Oct-16 25-Oct-16 403

03PMS-BL00.3.2.9.4.3 A
ABPR3 Backfill Zone-3 18 22-Oct-16 12-Nov-16 295

XAC03-32901431 Layer-1 5 22-Oct-16 28-Oct-16 295

XAC03-32901432 Layer-2 5 28-Oct-16 03-Nov-16 295

XAC03-32901433 Grounding Grid Install 3 03-Nov-16 07-Nov-16 295

XAC03-32901434 Layer-3 5 07-Nov-16 12-Nov-16 295

03PMS-BL00.3.2.9.5 ABPR3
ABP Zone-4 76 03-Sep-16 30-Nov-16 371

03PMS-BL00.3.2.9.5.1 ABPR3
A Equipment Foundation Zone-4 66 03-Sep-16 19-Nov-16 381

XAC03-32901511 Excavate 5 03-Sep-16 09-Sep-16 258

XAC03-32901512 Pile Cut 14 09-Sep-16 26-Sep-16 258

XAC03-32901513 Lean concrete 7 26-Sep-16 04-Oct-16 258

XAC03-32901514 Tying Rebar Foundation 7 04-Oct-16 12-Oct-16 258

XAC03-32901515 Assembly formwork Pedestal 10 12-Oct-16 24-Oct-16 258

XAC03-32901516 Pour Concrete 1 24-Oct-16 25-Oct-16 258

XAC03-32901517 Tying Rebar Pedestal 7 25-Oct-16 02-Nov-16 258

XAC03-32901518 Assembly formwork Pedestal 7 02-Nov-16 10-Nov-16 258

XAC03-32901519 Set Anchorbplt 6 10-Nov-16 17-Nov-16 381

XAC03-3290151A Pour Concrete 1 17-Nov-16 18-Nov-16 381

XAC03-3290151B Remove formwork 1 18-Nov-16 19-Nov-16 381

03PMS-BL00.3.2.9.5.2 ABPR3
A Cable Trench Zone-4 41 26-Sep-16 12-Nov-16 387

XAC03-32901521 Lean concrete 3 26-Sep-16 29-Sep-16 387

XAC03-32901522 Tying Rebar Slab Cable Trench 3 29-Sep-16 03-Oct-16 387

XAC03-32901523 Assembly formwork Slab Cable Trench 6 03-Oct-16 10-Oct-16 387

XAC03-32901524 Pour Concrete Slab Cable Trench 1 10-Oct-16 11-Oct-16 387

XAC03-32901525 Tying Rebar Wall Cable Trench 7 11-Oct-16 19-Oct-16 387

XAC03-32901526 Install Ladder 11 19-Oct-16 01-Nov-16 387

XAC03-32901527 Assembly formwork Wall Cable Trench 8 01-Nov-16 10-Nov-16 387

XAC03-32901528 Pour Concrete Wall Cable Trench 1 10-Nov-16 11-Nov-16 387

XAC03-32901529 Remove formwork 1 11-Nov-16 12-Nov-16 387

03PMS-BL00.3.2.9.5.3 A
ABPR3 Backfill Zone-4 18 10-Nov-16 30-Nov-16 258

XAC03-32901531 Layer-1 5 10-Nov-16 16-Nov-16 258

XAC03-32901532 Layer-2 5 16-Nov-16 22-Nov-16 258

XAC03-32901533 Grounding Grid Install 3 22-Nov-16 24-Nov-16 258

XAC03-32901534 Layer-3 5 25-Nov-16 30-Nov-16 258

03PMS-BL00.3.2.A Civil (Landscape,


( Road, Stormwater) 361 18-Jul-16 06-Sep-17 128

03PMS-BL00.3.2.A.01 La
Landscape / Road / Stormwater / Soil Backfilling 361 18-Jul-16 06-Sep-17 128

03PMS-BL00.3.2.A.01.1 Road / Fence / Landscape 233 12-Dec-16 06-Sep-17 128

XAC03-32A01110 Storm Water 186 12-Dec-16* 13-Jul-17 176

XAC03-32A01120 Permanent Plant Road 133 11-Feb-17* 14-Jul-17 175

XAC03-32A01130 Landscape (Gravelling) 122 19-Apr-17* 06-Sep-17 128

03PMS-BL00.3.2.A.01.2 Soil Backfilling 358 18-Jul-16 02-Sep-17 131

XAC03-32A01210 Soil Backfilling (600mm THK) - E&C Bldg. Area 311 18-Jul-16* 11-Jul-17 178

XAC03-32A01220 Soil Backfilling (600mm THK) - Raw Water & WTP Area 207 09-Aug-16 05-Apr-17 31

XAC03-32A01230 Soil Backfilling (600mm THK) - ST & CT Area 314 06-Sep-16* 02-Sep-17 131

XAC03-32A01240 Soil Backfilling (600mm THK) - GTG & HRSG Area 225 31-Oct-16* 17-Jul-17 13

XAC03-32A01250 Soil Backfilling (600mm THK) - Switchyard Area 47 02-Dec-16* 25-Jan-17 322

XAC03-32A01260 Soil Backfilling (600mm THK) - Tank Area 57 24-Feb-17* 01-May-17 240

03PMS-BL00.3.3 M&E ERECTION


ERE WORK 422 01-Jun-16 30-Sep-17 107

03PMS-BL00.3.3.1 Major Equipment Package 422 01-Jun-16 30-Sep-17 107

03PMS-BL00.3.3.1.01 Ga
Gas turbine & Generator #31 (Siemens) 368 02-Jun-16 01-Aug-17 0

03PMS-BL00.3.3.1.01.0 Interface 368 02-Jun-16 01-Aug-17 0

XAC03-3310101A Interface - MHO-Lot1 Embedded Materials 0 02-Jun-16* 202

XAC03-33101020 Interface - CTO 0 31-Oct-16* 73

XAC03-3310101B Interface - MHO-Lot-2 Main Equipments 0 06-Feb-17* 0

XAC03-3310101C Interface - MHO-Lot-3 Auxiliary Equipments & Accessories/Shortage Materials 0 16-Feb-17* 31

XAC03-3310101D Interface - MHO-Lot-4 Auxiliary Equipments (from China) 0 16-Feb-17* 31

XAC03-33101030 Interface - MC 0 09-Jun-17* 0

XAC03-33101040 Interface - TOP 0 01-Aug-17* 0

03PMS-BL00.3.3.1.01.1 Mechanical Work 53 23-Jan-17 23-Mar-17 4

XAC03-33101110 Mechanical Work - Foundation Chipping and Packer Setting 9 23-Jan-17* 01-Feb-17 0

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:30 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33101120 Mechanical Work - On Base Preparation 6 02-Feb-17 08-Feb-17 0

XAC03-33101130 Mechanical Work - Gas Turbine On Base 1 09-Feb-17 09-Feb-17 0

XAC03-33101140 Mechanical Work - Generator On Base 1 10-Feb-17 10-Feb-17 0

XAC03-33101150 Mechanical Work - Remove the On Base Lifting Devise 1 11-Feb-17 11-Feb-17 0

XAC03-33101160 Mechanical Work - Gas Turbine Alignment to Center Line 2 11-Feb-17 13-Feb-17 0

XAC03-33101170 Mechanical Work - GT-Gen Pre-Alignment 6 14-Feb-17 20-Feb-17 0

XAC03-33101180 Mechanical Work - Exhaust Duct Installation 12 14-Feb-17 27-Feb-17 25

XAC03-33101190 Mechanical Work - Grouting of Gas Turbine Base 3 21-Feb-17 23-Feb-17 0

XAC03-331011A0 Mechanical Work - Platform Installation 6 24-Feb-17 02-Mar-17 0

XAC03-331011B0 Mechanical Work - Enclosure Installation 18 03-Mar-17 23-Mar-17 0

03PMS-BL00.3.3.1.01.2 Overhead Crane 48 17-Mar-17 11-May-17 25

XAC03-33101210 Overhead Crane - Rail Girder and Rail Installation 7 17-Mar-17 25-Mar-17 46

XAC03-33101220 Overhead Crane - Outdoor Rail and Sructure Installation 9 19-Apr-17 28-Apr-17 25

XAC03-33101230 Overhead Crane - Main Girder Installation 2 29-Apr-17 01-May-17 25

XAC03-33101240 Overhead Crane - Conduits Installaton and Cable Pulling 6 02-May-17 08-May-17 25

XAC03-33101250 Overhead Crane - Function Check and Overload Test 3 09-May-17 11-May-17 25

03PMS-BL00.3.3.1.01.3 Intake Air Filter System 100 07-Jan-17 02-May-17 27

XAC03-33101300 Intake Air Filter System - Delivery Filter House/Diffuser 0 07-Jan-17* 91

XAC03-33101310 Intake Air Filter System - Support Structure Installation 8 24-Mar-17 01-Apr-17 25

XAC03-33101320 Intake Air Filter System - Duct Installation 13 03-Apr-17 17-Apr-17 25

XAC03-33101330 Intake Air Filter System - Intake Air Filter House Assembly and Installation 13 18-Apr-17 02-May-17 27

03PMS-BL00.3.3.1.01.4 Water Wash and Drain System 25 22-Apr-17 20-May-17 17

XAC03-33101410 Water Wash and Drain System - Water Wash Equipment Installation 1 22-Apr-17 22-Apr-17 17

XAC03-33101420 Water Wash and Drain System - Water Wash Piping Installation 13 24-Apr-17 08-May-17 17

XAC03-33101430 Water Wash and Drain System - Line Check 2 09-May-17 10-May-17 17

XAC03-33101440 Water Wash and Drain System - Punch Clear 4 11-May-17 15-May-17 17

XAC03-33101450 Water Wash and Drain System - Hydro Test 3 16-May-17 18-May-17 17

XAC03-33101460 Water Wash and Drain System - Restoration 1 19-May-17 20-May-17 17

03PMS-BL00.3.3.1.01.5 Fuel Gas System 32 24-Mar-17 29-Apr-17 35

XAC03-33101510 Fuel Gas System - Fuel Gas Piping Work 25 24-Mar-17 21-Apr-17 17

XAC03-33101520 Fuel Gas System - Line Check 1 22-Apr-17 22-Apr-17 35

XAC03-33101530 Fuel Gas System - Punch Clear 4 24-Apr-17 27-Apr-17 35

XAC03-33101540 Fuel Gas System - Pneumatic Test 2 28-Apr-17 29-Apr-17 35

03PMS-BL00.3.3.1.01.6 Lube Oil / Control Oil System 82 18-Feb-17 23-May-17 15

XAC03-33101600 Lube Oil / Control Oil System - Delivery Lube Oil Skid 0 18-Feb-17* 40

XAC03-33101610 Lube Oil / Control Oil System - Lube Oil Tank Installation 2 28-Feb-17 01-Mar-17 31

XAC03-33101620 Lube Oil / Control Oil System - Lube Oil Cooler Installation 3 02-Mar-17 04-Mar-17 31

XAC03-33101630 Lube Oil / Control Oil System - Lube Oil Piping Work 25 24-Mar-17 21-Apr-17 15

XAC03-33101640 Lube Oil / Control Oil System - Control Oil Tubing Work 13 22-Apr-17 06-May-17 15

XAC03-33101650 Lube Oil / Control Oil System - RT of Lube Oil Piping (10%) 2 22-Apr-17 24-Apr-17 26

XAC03-33101660 Lube Oil / Control Oil System - Line Check 1 08-May-17 08-May-17 15

XAC03-33101670 Lube Oil / Control Oil System - Punch Clear 5 09-May-17 13-May-17 15

XAC03-33101680 Lube Oil / Control Oil System - Pressure Test 2 15-May-17 16-May-17 15

XAC03-33101690 Lube Oil / Control Oil System - Preparation of Oil Flushing 6 17-May-17 23-May-17 15

03PMS-BL00.3.3.1.01.7 Cooling and Sealing Air System 14 24-Mar-17 08-Apr-17 54

XAC03-33101710 Cooling and Sealing Air System - Bleed Air Piping Work 8 24-Mar-17 01-Apr-17 22

XAC03-33101720 Cooling and Sealing Air System - Line Check 1 03-Apr-17 03-Apr-17 54

XAC03-33101730 Cooling and Sealing Air System - Punch Clear 5 04-Apr-17 08-Apr-17 54

03PMS-BL00.3.3.1.01.8 Instrument Air System 26 03-Apr-17 03-May-17 33

XAC03-33101810 Instrument Air System - Instrument Air Tubing Work 16 03-Apr-17 20-Apr-17 22

XAC03-33101820 Instrument Air System - Line Check 1 21-Apr-17 21-Apr-17 33

XAC03-33101830 Instrument Air System - Punch Clear 4 22-Apr-17 26-Apr-17 33

XAC03-33101840 Instrument Air System - Pneumatic Test 2 27-Apr-17 28-Apr-17 33

XAC03-33101850 Instrument Air System - Air Blow 2 29-Apr-17 01-May-17 33

XAC03-33101860 Instrument Air System - Restoration 1 02-May-17 03-May-17 33

03PMS-BL00.3.3.1.01.9 CO2 System 23 19-Apr-17 15-May-17 22

XAC03-33101910 CO2 System - Fire Extinguisher/Bottle Cabinet On Base 3 19-Apr-17 21-Apr-17 22

XAC03-33101920 CO2 System - CO2 Piping Work 7 22-Apr-17 29-Apr-17 22

XAC03-33101930 CO2 System - Line Check 2 01-May-17 02-May-17 22

XAC03-33101940 CO2 System - Punch Clear 4 03-May-17 06-May-17 22

XAC03-33101950 CO2 System - Pneumatic Test 3 08-May-17 10-May-17 22

XAC03-33101960 CO2 System - Air Blow 3 11-May-17 13-May-17 22

XAC03-33101970 CO2 System - Restoration 1 15-May-17 15-May-17 22

03PMS-BL00.3.3.1.01.A Ventilation System 40 24-Mar-17 09-May-17 27

XAC03-33101A10 Ventilation System - Enclosure Ventilation SAG Installation 13 24-Mar-17 07-Apr-17 55

XAC03-33101A20 Ventilation System - Ventilation Pipe Installation 6 03-May-17 09-May-17 27

03PMS-BL00.3.3.1.01.B Fire Alarm System 21 24-Mar-17 17-Apr-17 39

XAC03-33101B10 Fire Alarm System - Conduit Work and Fire Alarm Installation 8 24-Mar-17 01-Apr-17 0

XAC03-33101B20 Fire Alarm System - Cable Pulling 13 03-Apr-17 17-Apr-17 39

03PMS-BL00.3.3.1.01.C Control Room 34 15-Feb-17 25-Mar-17 66

XAC03-33101C00 Control Room - Delivery Electrical Room 0 15-Feb-17* 69

XAC03-33101C10 Control Room - Preparation of On Base 2 24-Mar-17 25-Mar-17 66

XAC03-33101C20 Control Room - Control Room On Base 1 24-Mar-17 24-Mar-17 66

XAC03-33101C30 Control Room - Support Structure Welding 1 25-Mar-17 25-Mar-17 66

03PMS-BL00.3.3.1.01.D Battery Module 42 16-Feb-17 05-Apr-17 26

XAC03-33101D00 Battery Module - Delivery Battery Module 0 16-Feb-17* 68

XAC03-33101D10 Battery Module - Foundation Work of Battery Module 8 24-Mar-17 01-Apr-17 0

XAC03-33101D20 Battery Module - On Base 1 05-Apr-17 05-Apr-17 26

03PMS-BL00.3.3.1.01.E Start Transformer 9 24-Mar-17 03-Apr-17 51

XAC03-33101E10 Start Transformer - Foundation Work of Start Transformer 8 24-Mar-17 01-Apr-17 51

XAC03-33101E20 Start Transformer - On Base 1 03-Apr-17 03-Apr-17 51

03PMS-BL00.3.3.1.01.F Conduits and Cable Tray Installation 28 24-Mar-17 25-Apr-17 26

XAC03-33101F10 Conduit & Cable Tray Installation - Outside Enclosure 21 24-Mar-17 18-Apr-17 0

XAC03-33101F20 Conduit & Cable Tray Installation - Inside Enclosure 17 06-Apr-17 25-Apr-17 26

03PMS-BL00.3.3.1.01.G Cabling Work 31 22-Apr-17 27-May-17 3

XAC03-33101G10 Cabling Work - Cable Pulling and Termination Work 26 22-Apr-17 22-May-17 3

XAC03-33101G20 Cabling Work - Continuity Check 13 13-May-17 27-May-17 3

03PMS-BL00.3.3.1.01.H Instrument 30 06-May-17 09-Jun-17 0

XAC03-33101H10 Instrument Work - Instrument install 18 06-May-17* 27-May-17 0

XAC03-33101H20 Instrument Work - Tubing Install 12 27-May-17 09-Jun-17 0

03PMS-BL00.3.3.1.01.I Electrical Work 8 27-May-17 06-Jun-17 3

XAC03-33101I10 Electrical Work - Commissioning Handover Walk Down 4 27-May-17 01-Jun-17 3

XAC03-33101I20 Electrical Work - Punch Clear 4 01-Jun-17 06-Jun-17 3

XAC03-33101I30 Electrical Work - Handover to Commissioning 0 06-Jun-17 3

03PMS-BL00.3.3.1.02 Ga
Gas turbine & Generator #32 (Siemens) 381 02-Jun-16 17-Aug-17 5

03PMS-BL00.3.3.1.02.0 Interface 381 02-Jun-16 17-Aug-17 5

XAC03-3310201A Interface - MHO-Lot-1 Embedded Material 0 02-Jun-16* 241

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:31 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33102020 Interface - CTO 0 31-Oct-16* 112

XAC03-3310201B Interface - MHO-Lot-2 Main Equipments 0 13-Feb-17* 35

XAC03-3310201C Interface - MHO-Lot-3 Auxiliary Equipments & Accessories/Shortage Materials 0 16-Feb-17* 78

XAC03-3310201D Interface - MHO-Lot-4 Auxiliary Equipments (from China) 0 16-Feb-17* 78

XAC03-33102030 Interface - MC 0 19-Jun-17* 57

XAC03-33102040 Interface - TOP 0 17-Aug-17* 5

03PMS-BL00.3.3.1.02.1 Mechanical Work 68 30-Jan-17 17-Apr-17 60

XAC03-33102110 Mechanical Work - Foundation Chipping and Packer Setting 9 30-Jan-17* 08-Feb-17 33

XAC03-33102120 Mechanical Work - On Base Preparation 5 09-Feb-17 14-Feb-17 33

XAC03-33102130 Mechanical Work - Gas Turbine On Base 1 15-Feb-17 15-Feb-17 33

XAC03-33102140 Mechanical Work - Generator On Base 2 16-Feb-17 17-Feb-17 33

XAC03-33102150 Mechanical Work - Remove the On Base Lifting Devise 1 18-Feb-17 18-Feb-17 49

XAC03-33102160 Mechanical Work - Gas Turbine Alignment to Center Line 3 28-Feb-17 02-Mar-17 25

XAC03-33102170 Mechanical Work - GT-Gen Pre-Alignment 6 03-Mar-17 09-Mar-17 25

XAC03-33102180 Mechanical Work - Exhaust Duct Installation 12 03-Mar-17 16-Mar-17 87

XAC03-33102190 Mechanical Work - Grouting of Gas Turbine Base 2 10-Mar-17 11-Mar-17 25

XAC03-331021A0 Mechanical Work - Platform Installation 6 13-Mar-17 18-Mar-17 25

XAC03-331021B0 Mechanical Work - Enclosure Installation 25 20-Mar-17 17-Apr-17 25

03PMS-BL00.3.3.1.02.2 Overhead Crane 48 03-Apr-17 27-May-17 75

XAC03-33102210 Overhead Crane - Rail Girder and Rail Installation 15 03-Apr-17 20-Apr-17 87

XAC03-33102220 Overhead Crane - Outdoor Rail and Sructure Installation 8 05-May-17 13-May-17 75

XAC03-33102230 Overhead Crane - Main Girder Installation 3 15-May-17 17-May-17 75

XAC03-33102240 Overhead Crane - Conduits Installaton and Cable Pulling 6 18-May-17 24-May-17 75

XAC03-33102250 Overhead Crane - Function Check and Overload Test 3 25-May-17 27-May-17 75

03PMS-BL00.3.3.1.02.3 Intake Air Filter System 108 14-Jan-17 19-May-17 76

XAC03-33102300 Intake Air Filter System - Delivery Filter House/Diffuser 0 14-Jan-17* 156

XAC03-33102310 Intake Air Filter System - Support Structure Installation 9 18-Apr-17 27-Apr-17 75

XAC03-33102320 Intake Air Filter System - Duct Installation 6 28-Apr-17 04-May-17 75

XAC03-33102330 Intake Air Filter System - Intake Air Filter House Assembly and Installation 12 05-May-17 19-May-17 76

03PMS-BL00.3.3.1.02.4 Water Wash and Drain System 24 09-May-17 06-Jun-17 68

XAC03-33102410 Water Wash and Drain System - Water Wash Equipment Installation 2 09-May-17 10-May-17 68

XAC03-33102420 Water Wash and Drain System - Water Wash Piping Installation 13 11-May-17 25-May-17 68

XAC03-33102430 Water Wash and Drain System - Line Check 2 26-May-17 27-May-17 68

XAC03-33102440 Water Wash and Drain System - Punch Clear 4 29-May-17 01-Jun-17 68

XAC03-33102450 Water Wash and Drain System - Hydro Test 2 02-Jun-17 03-Jun-17 68

XAC03-33102460 Water Wash and Drain System - Restoration 1 05-Jun-17 06-Jun-17 68

03PMS-BL00.3.3.1.02.5 Fuel Gas System 25 18-Apr-17 16-May-17 85

XAC03-33102510 Fuel Gas System - Fuel Gas Piping Work 18 18-Apr-17 08-May-17 68

XAC03-33102520 Fuel Gas System - Line Check 1 09-May-17 09-May-17 85

XAC03-33102530 Fuel Gas System - Punch Clear 4 10-May-17 13-May-17 85

XAC03-33102540 Fuel Gas System - Pneumatic Test 2 15-May-17 16-May-17 85

03PMS-BL00.3.3.1.02.6 Lube Oil / Control Oil System 91 25-Feb-17 09-Jun-17 64

XAC03-33102600 Lube Oil / Control Oil System - Delivery Lube Oil Skid 0 25-Feb-17* 104

XAC03-33102610 Lube Oil / Control Oil System - Lube Oil Tank Installation 2 17-Mar-17 18-Mar-17 87

XAC03-33102620 Lube Oil / Control Oil System - Lube Oil Cooler Installation 2 20-Mar-17 21-Mar-17 87

XAC03-33102630 Lube Oil / Control Oil System - Lube Oil Piping Work 18 18-Apr-17 08-May-17 64

XAC03-33102640 Lube Oil / Control Oil System - Control Oil Tubing Work 13 09-May-17 23-May-17 64

XAC03-33102650 Lube Oil / Control Oil System - RT of Lube Oil Piping (10%) 3 09-May-17 11-May-17 74

XAC03-33102660 Lube Oil / Control Oil System - Line Check 2 24-May-17 25-May-17 64

XAC03-33102670 Lube Oil / Control Oil System - Punch Clear 4 26-May-17 30-May-17 64

XAC03-33102680 Lube Oil / Control Oil System - Pressure Test 3 31-May-17 02-Jun-17 64

XAC03-33102690 Lube Oil / Control Oil System - Preparation of Oil Flushing 6 03-Jun-17 09-Jun-17 64

03PMS-BL00.3.3.1.02.7 Cooling and Sealing Air System 14 18-Apr-17 03-May-17 96

XAC03-33102710 Cooling and Sealing Air System - Bleed Air Piping Work 9 18-Apr-17 27-Apr-17 71

XAC03-33102720 Cooling and Sealing Air System - Line Check 1 28-Apr-17 28-Apr-17 96

XAC03-33102730 Cooling and Sealing Air System - Punch Clear 4 29-Apr-17 03-May-17 96

03PMS-BL00.3.3.1.02.8 Instrument Air System 20 28-Apr-17 20-May-17 81

XAC03-33102810 Instrument Air System - Instrument Air Tubing Work 8 28-Apr-17 06-May-17 71

XAC03-33102820 Instrument Air System - Line Check 1 08-May-17 08-May-17 81

XAC03-33102830 Instrument Air System - Punch Clear 5 09-May-17 13-May-17 81

XAC03-33102840 Instrument Air System - Pneumatic Test 1 15-May-17 15-May-17 81

XAC03-33102850 Instrument Air System - Air Blow 3 16-May-17 18-May-17 81

XAC03-33102860 Instrument Air System - Restoration 2 19-May-17 20-May-17 81

03PMS-BL00.3.3.1.02.9 CO2 System 23 06-May-17 01-Jun-17 71

XAC03-33102910 CO2 System - Fire Extinguisher/Bottle Cabinet On Base 2 06-May-17 08-May-17 71

XAC03-33102920 CO2 System - CO2 Piping Work 8 09-May-17 17-May-17 71

XAC03-33102930 CO2 System - Line Check 2 18-May-17 19-May-17 71

XAC03-33102940 CO2 System - Punch Clear 4 20-May-17 24-May-17 71

XAC03-33102950 CO2 System - Pneumatic Test 3 25-May-17 27-May-17 71

XAC03-33102960 CO2 System - Air Blow 2 29-May-17 30-May-17 71

XAC03-33102970 CO2 System - Restoration 2 31-May-17 01-Jun-17 71

03PMS-BL00.3.3.1.02.A Ventilation System 34 18-Apr-17 26-May-17 76

XAC03-33102A10 Ventilation System - Enclosure Ventilation SAG Installation 13 18-Apr-17 02-May-17 91

XAC03-33102A20 Ventilation System - Ventilation Pipe Installation 6 20-May-17 26-May-17 76

03PMS-BL00.3.3.1.02.B Fire Alarm System 15 18-Apr-17 04-May-17 60

XAC03-33102B10 Fire Alarm System - Conduit Work and Fire Alarm Installation 9 18-Apr-17 27-Apr-17 25

XAC03-33102B20 Fire Alarm System - Cable Pulling 6 28-Apr-17 04-May-17 60

03PMS-BL00.3.3.1.02.C Control Room 54 22-Feb-17 24-Apr-17 104

XAC03-33102C00 Control Room - Delivery Electrical Room 0 22-Feb-17* 73

XAC03-33102C10 Control Room - Preparation of On Base 3 18-Apr-17 20-Apr-17 25

XAC03-33102C20 Control Room - Control Room On Base 1 21-Apr-17 21-Apr-17 104

XAC03-33102C30 Control Room - Support Structure Welding 2 22-Apr-17 24-Apr-17 104

03PMS-BL00.3.3.1.02.D Battery Module 58 23-Feb-17 29-Apr-17 48

XAC03-33102D00 Battery Module - Delivery Battery Module 0 23-Feb-17* 72

XAC03-33102D10 Battery Module - Foundation Work of Battery Module 9 18-Apr-17 27-Apr-17 25

XAC03-33102D20 Battery Module - On Base 1 29-Apr-17 29-Apr-17 48

03PMS-BL00.3.3.1.02.E Start Transformer 10 18-Apr-17 28-Apr-17 100

XAC03-33102E10 Start Transformer - Foundation Work of Start Transformer 9 18-Apr-17 27-Apr-17 100

XAC03-33102E20 Start Transformer - On Base 1 28-Apr-17 28-Apr-17 100

03PMS-BL00.3.3.1.02.F Conduits and Cable Tray Installation 22 18-Apr-17 12-May-17 48

XAC03-33102F10 Conduit & Cable Tray Installation - Outside Enclosure 16 18-Apr-17 05-May-17 25

XAC03-33102F20 Conduit & Cable Tray Installation - Inside Enclosure 11 01-May-17 12-May-17 48

03PMS-BL00.3.3.1.02.G Cabling Work 31 09-May-17 13-Jun-17 25

XAC03-33102G10 Cabling Work - Cable Pulling and Termination Work 27 09-May-17 08-Jun-17 25

XAC03-33102G20 Cabling Work - Continuity Check 13 30-May-17 13-Jun-17 25

03PMS-BL00.3.3.1.02.H Instrument 30 06-May-17 09-Jun-17 28

XAC03-33102H10 Instrument Work - Instrument install 18 06-May-17 26-May-17 28

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:32 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33102H20 Instrument Work - Tubing Install 12 27-May-17 09-Jun-17 28

03PMS-BL00.3.3.1.02.I Electrical Work 13 14-Jun-17 28-Jun-17 25

XAC03-33102I10 Electrical Work - Commissioning Handover Walk Down 4 14-Jun-17 17-Jun-17 25

XAC03-33102I20 Electrical Work - Punch Clear 4 23-Jun-17 28-Jun-17 25

XAC03-33102I30 Electrical Work - Handover to Commissioning 0 28-Jun-17 25

03PMS-BL00.3.3.1.03 HRSG
HR #31 (Vogt Power) 394 01-Jun-16 29-Aug-17 0

03PMS-BL00.3.3.1.03.0 Interface 394 01-Jun-16 29-Aug-17 0

XAC03-3310301A Interface - MHO - Lot-1 (Base Plate / Stack Template) 0 01-Jun-16* 99

XAC03-33103020 Interface - CTO 0 12-Oct-16 109

XAC03-3310301B Interface - MHO- Lot-2 (Box Assembly / Module Header / Module Tubes) 0 16-Jan-17* 104

XAC03-3310301C Interface - MHO- Lot-3 (Blowdown Tank / Expansion Joint - Inlet duct / Bypass stack 0 20-Jan-17* 18
Accessories / Diverter dumper)
XAC03-3310301D Interface - MHO- Lot-4 (Inlet Duct / Spool Duct / Field Connection / Bypass Stack / 0 23-Jan-17* 20
Bypass Damper)
XAC03-3310301E Interface - MHO- Lot-5 (Steam Silencers) 0 01-Feb-17* 132

XAC03-3310301F Interface - MHO- Lot-6 (LP & HP Steam Drum / Platforms, Ladders, Stairs) 0 06-Feb-17* 13

XAC03-3310301G Interface - MHO - Lot-7 (Pipe & Supports) 0 06-Feb-17* 13

XAC03-3310301H Interface - MHO- Lot-8 (Main Stacks / Expansion Joint - Outlet duct) 0 10-Feb-17* 18

XAC03-3310301I Interface - MHO- Lot-9 (Valves & Instruments) 0 15-Feb-17* 46

XAC03-3310301J Interface - MHO- Lot-10 (Deaerator) 0 20-Feb-17* 61

XAC03-33103030 Interface - MC 0 31-Jul-17* 0

XAC03-33103040 Interface - TOP 0 29-Aug-17 0

03PMS-BL00.3.3.1.03.1 Tube Blocks & Duct Assemble 132 01-Dec-16 02-May-17 77

03PMS-BL00.3.3.1.03.1.1 Heavy Lifting


03PMS-BL00.3.3.1.03.1 41 01-Dec-16 17-Jan-17 103

XAC03-33103111 Tube Blocks & Duct Assemble - Heavy Lifting - Heavy Lifting 0 01-Dec-16* 20

XAC03-33103112 Tube Blocks & Duct Assemble - Heavy Lifting - Crane Parts Delivery and assembly 9 01-Dec-16 10-Dec-16 20
250ton
XAC03-33103113 Tube Blocks & Duct Assemble - Heavy Lifting - Load Test 250ton 1 12-Dec-16 12-Dec-16 20

XAC03-33103114 Tube Blocks & Duct Assemble - Heavy Lifting - Crane Parts Delivery and assembly 6 12-Dec-16 17-Dec-16 20
750ton
XAC03-33103115 Tube Blocks & Duct Assemble - Heavy Lifting - Load Test 750ton 1 19-Dec-16 19-Dec-16 20

XAC03-33103116 Tube Blocks & Duct Assemble - Heavy Lifting - Preparation 6 09-Jan-17 16-Jan-17 20

XAC03-33103117 Tube Blocks & Duct Assemble - Heavy Lifting - Heavy Lifting 0 16-Jan-17 104

XAC03-33103118 Tube Blocks & Duct Assemble - Heavy Lifting - Paker Plate boxout grouting and curing 1 17-Jan-17 17-Jan-17 103

XAC03-33103119 Tube Blocks & Duct Assemble - Heavy Lifting - Setting center line and elevation of base 1 17-Jan-17 17-Jan-17 103
plates
XAC03-3310311A Tube Blocks & Duct Assemble - Heavy Lifting - Packer Plate Setting 1 17-Jan-17* 17-Jan-17 103

XAC03-3310311B Tube Blocks & Duct Assemble - Heavy Lifting - Formwork setting for grouting 1 17-Jan-17 17-Jan-17 103

03PMS-BL00.3.3.1.03.1.2 Lift and Install Tube Boxes


03PMS-BL00.3.3.1.03.1 1 16-Jan-17 16-Jan-17 104

XAC03-33103121 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Module Box Alignment 1 16-Jan-17* 16-Jan-17 104

XAC03-33103122 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Module Box#1,2,3 1 16-Jan-17 16-Jan-17 104
Installation and alignment
XAC03-33103123 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Welding base plates of 1 16-Jan-17 16-Jan-17 104
Column HRSG Module
XAC03-33103124 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - PT Check welding joint of 1 16-Jan-17 16-Jan-17 104
Column HRSG Module
XAC03-33103125 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Grouting Base plates of 1 16-Jan-17 16-Jan-17 104
Column HRSG Module
03PMS-BL00.3.3.1.03.1.3 Spool Duct Installation
03PMS-BL00.3.3.1.03.1 7 23-Jan-17 30-Jan-17 99

XAC03-33103131 Tube Blocks & Duct Assemble - Spool Duct Installation - Spool Duct Box 1-2 installation 1 23-Jan-17* 23-Jan-17 99

XAC03-33103132 Tube Blocks & Duct Assemble - Spool Duct Installation - Spool Duct Box 2-3 installation 1 24-Jan-17 24-Jan-17 99

XAC03-33103133 Tube Blocks & Duct Assemble - Spool Duct Installation - Scaffolding setting Left & Right 1 25-Jan-17 25-Jan-17 99
side
XAC03-33103134 Tube Blocks & Duct Assemble - Spool Duct Installation - Spool Duct Alignment 1 26-Jan-17 26-Jan-17 99

XAC03-33103135 Tube Blocks & Duct Assemble - Module Box Grout 3 27-Jan-17 30-Jan-17 99

03PMS-BL00.3.3.1.03.1.4 Complete Module Box/Panel Seal Welding


03PMS-BL00.3.3.1.03.1 56 31-Jan-17 04-Apr-17 77

XAC03-33103141 Tube Blocks & Duct Assemble - Complete Module Box/Panel Seal Welding - Welding 1 31-Jan-17 31-Jan-17 99
joint connect spool duct for HRSG Module
XAC03-33103142 Tube Blocks & Duct Assemble - Complete Module Box/Panel Seal Welding - Insulation 24 08-Mar-17 04-Apr-17 77
and liners
03PMS-BL00.3.3.1.03.1.5 Install HP/LP Drums
03PMS-BL00.3.3.1.03.1 20 05-Apr-17 27-Apr-17 77

XAC03-33103151 Tube Blocks & Duct Assemble - Install HP/LP Drums - Support Installation of HP/LP 13 05-Apr-17 19-Apr-17 77
Drum
XAC03-33103152 Tube Blocks & Duct Assemble - Install HP/LP Drums - Install HP/LP Drums 6 20-Apr-17 26-Apr-17 77

XAC03-33103153 Tube Blocks & Duct Assemble - Install HP/LP Drums - HP/LP Drum alignment 1 27-Apr-17 27-Apr-17 77

03PMS-BL00.3.3.1.03.1.6 Support Structure & Silencers Installation


03PMS-BL00.3.3.1.03.1 4 27-Apr-17 02-May-17 77

XAC03-33103161 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation 1 27-Apr-17 28-Apr-17 77

XAC03-33103162 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation - Welding of 2 28-Apr-17 01-May-17 77
column structure silencers
XAC03-33103163 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation - Install and 1 01-May-17 02-May-17 77
alignment Silencers
03PMS-BL00.3.3.1.03.1.7 Platform & Stairway
03PMS-BL00.3.3.1.03.1 16 06-Feb-17 23-Feb-17 112

XAC03-33103171 Tube Blocks & Duct Assemble - Platform & Stairway - Packer Plates setting for Base 1 06-Feb-17 06-Feb-17 13
Plate Stair Tower
XAC03-33103172 Tube Blocks & Duct Assemble - Platform & Stairway - Setting center line and elevation 2 07-Feb-17 08-Feb-17 112
of base plates
XAC03-33103173 Tube Blocks & Duct Assemble - Platform & Stairway - Assembly Stair Tower Structure 4 09-Feb-17 13-Feb-17 112

XAC03-33103174 Tube Blocks & Duct Assemble - Platform & Stairway - Install Stair Tow er Structure 3 13-Feb-17 16-Feb-17 112

XAC03-33103175 Tube Blocks & Duct Assemble - Platform & Stairway - Stair Tower Str ucture Alignment 1 16-Feb-17 17-Feb-17 112

XAC03-33103176 Tube Blocks & Duct Assemble - Platform & Stairway - Grouting Base plates of Column 2 17-Feb-17 20-Feb-17 112
Stair Tower
XAC03-33103177 Tube Blocks & Duct Assemble - Platform & Stairway - Install Main Deck Platform, 3 20-Feb-17 23-Feb-17 112
Handrail and ladder
03PMS-BL00.3.3.1.03.2 Blowdown Tank 5 26-Jan-17 31-Jan-17 18

XAC03-33103210 Blowdown Tank - Blowdown Tank Installation 5 26-Jan-17 31-Jan-17 18

03PMS-BL00.3.3.1.03.3 Bypass Damper and Bypass Stack 44 17-Jan-17 08-Mar-17 125

XAC03-33103310 Bypass Damper and Bypass Stack - Foundation Preparation 4 17-Jan-17 20-Jan-17 20

XAC03-33103320 Bypass Damper and Bypass Stack - Diverter Damper On-Base 4 23-Jan-17 26-Jan-17 20

XAC03-33103330 Bypass Damper and Bypass Stack - Bypass Stack Painting & Platform installation 8 26-Jan-17 04-Feb-17 21

XAC03-33103340 Bypass Damper and Bypass Stack - Erect Bypass Stack steel structure 8 27-Jan-17 04-Feb-17 20

XAC03-33103350 Bypass Damper and Bypass Stack - Install Stack Exp.Joint 1 06-Feb-17 06-Feb-17 20

XAC03-33103360 Bypass Damper and Bypass Stack - Bypass Stack On-base 1 07-Feb-17 07-Feb-17 20

XAC03-33103370 Bypass Damper and Bypass Stack - Seal Air Fan/Diverter ancillaries Installation 14 08-Feb-17 23-Feb-17 125

XAC03-33103380 Bypass Damper and Bypass Stack - Bypass Damper Tes t 11 24-Feb-17 08-Mar-17 125

03PMS-BL00.3.3.1.03.4 Inlet Duct and Expansion Joint 58 27-Jan-17 04-Apr-17 77

XAC03-33103410 Inlet Duct and Expansion Joint - Bottom Panels 2 27-Jan-17 30-Jan-17 77

XAC03-33103420 Inlet Duct and Expansion Joint - Siding Panels 10 31-Jan-17 10-Feb-17 77

XAC03-33103430 Inlet Duct and Expansion Joint - Top Panels 7 11-Feb-17 18-Feb-17 77

XAC03-33103440 Inlet Duct and Expansion Joint - Seal Welding 14 20-Feb-17 07-Mar-17 77

XAC03-33103450 Inlet Duct and Expansion Joint - Insulation and liners 24 08-Mar-17 04-Apr-17 77

03PMS-BL00.3.3.1.03.5 Outlet Duct and Stack 39 10-Feb-17 27-Mar-17 18

XAC03-33103510 Outlet Duct and Stack - Main Stack (Lower Parts) On Base 1 10-Feb-17 10-Feb-17 18

XAC03-33103520 Outlet Duct and Stack - Main Stack (Upper Parts) Assembly & Painting 10 11-Feb-17 22-Feb-17 18

XAC03-33103530 Outlet Duct and Stack - Main Stack (Upper Parts) On Base & Welding 3 23-Feb-17 25-Feb-17 18

XAC03-33103540 Outlet Duct and Stack - Outlet Duct Install 12 27-Feb-17 11-Mar-17 18

XAC03-33103550 Outlet Duct and Stack - Expansion Install 13 13-Mar-17 27-Mar-17 18

03PMS-BL00.3.3.1.03.6 Internal Piping 149 07-Feb-17 28-Jul-17 28

XAC03-33103610 Internal Piping - Large Bore Piping & Support 48 07-Feb-17 01-Apr-17 13

XAC03-33103630 Internal Piping - NDE at field welding of piping 37 13-Mar-17 25-Apr-17 39

XAC03-33103620 Internal Piping - Small Bore Piping & Support 37 14-Mar-17 25-Apr-17 50

XAC03-33103640 Internal Piping - Line Check 11 25-Apr-17 09-May-17 39

XAC03-33103650 Internal Piping - HRSG Hydro Tes t 6 22-Jun-17 28-Jun-17 1

XAC03-33103660 Internal Piping - Prepare Chemical Clean 6 29-Jun-17 05-Jul-17 9

XAC03-33103670 Internal Piping - Final Insulation Work 20 29-Jun-17 21-Jul-17 1

XAC03-33103680 Internal Piping - Chemical Cleaning 6 06-Jul-17 12-Jul-17 9

XAC03-33103690 Internal Piping - Restoration for Chemical Clean 6 13-Jul-17 19-Jul-17 36

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:33 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-331036A0 Internal Piping - Final Inspection Application to MOI 6 21-Jul-17 28-Jul-17 1

03PMS-BL00.3.3.1.03.7 Electrical work 98 24-Mar-17 15-Jul-17 13

XAC03-33103710 Electrical work - Instrument Calibration 16 24-Mar-17 12-Apr-17 13

XAC03-33103720 Electrical work - Instrument Installation 35 12-Apr-17 23-May-17 13

XAC03-33103730 Electrical work - Tray Installation 11 24-Apr-17 06-May-17 40

XAC03-33103740 Electrical work - Conduit Installation 26 08-May-17 06-Jun-17 40

XAC03-33103750 Electrical work - Cabling / Termination 40 23-May-17 08-Jul-17 13

XAC03-33103760 Electrical work - Handover to Commissioning Walkdown 1 08-Jul-17 10-Jul-17 13

XAC03-33103770 Electrical work - Punch Clear 4 10-Jul-17 14-Jul-17 13

XAC03-33103780 Electrical work - Handover to Commissioning 2 14-Jul-17 15-Jul-17 13

03PMS-BL00.3.3.1.03.Z Others 27 01-Mar-17 31-Mar-17 104

XAC03-33103Z10 Access Platform - BD Tank Access - Delivery 0 01-Mar-17* 104

XAC03-33103Z20 Access Platform - Isolation Valve Access - Delivery 0 01-Mar-17 114

XAC03-33103Z30 Access Platform - HRSG#31 Flow Nozzle - Delivery 0 01-Mar-17 122

XAC03-33103Z40 Access Platform - BD Tank Access - Installation 9 02-Mar-17 11-Mar-17 104

XAC03-33103Z50 Access Platform - Isolation Valve Access - Installation 8 13-Mar-17 21-Mar-17 104

XAC03-33103Z60 Access Platform - HRSG#31 Flow Nozzle - Installation 9 22-Mar-17 31-Mar-17 104

03PMS-BL00.3.3.1.04 HRSG
HR #32 (Vogt Power) 391 05-Jul-16 29-Sep-17 109

03PMS-BL00.3.3.1.04.0 Interface 391 05-Jul-16 29-Sep-17 109

XAC03-3310401A Interface - MHO - Lot-1 (Base Plate / Stack Template / Embedded Material) 0 05-Jul-16* 126

XAC03-33104020 Interface - CTO 0 20-Oct-16 80

XAC03-3310401B Interface - MHO - Lot-2 (Box Assembly / Module Header / Module Tubes) 0 23-Jan-17* 5

XAC03-3310401D Interface - MHO - Lot-4 (Inlet Duct / Spool Duct / Field Connection / Bypass Stack / 0 26-Jan-17* 6
Bypass Damper)
XAC03-3310401C Interface -MHO - Lot-3 (Blowdown Tank / Expansion Joint - Inlet duct / Bypass stack 0 04-Feb-17* 0
Accessories / Diverter dumper)
XAC03-3310401F Interface - MHO - Lot-6 (LP & HP Steam Drum / Platforms, Ladders, Stairs) 0 08-Feb-17* 8

XAC03-3310401E Interface - MHO- Lot-5 (Steam Silencers) 0 16-Feb-17* 101

XAC03-3310401H Interface - MHO - Lot-8 (Main Stacks / Expansion Joint - Outlet duct) 0 17-Feb-17* 264

XAC03-3310401G Interface - MHO - Lot-7 (Pipe & Supports & Vent) 0 20-Feb-17* 14

XAC03-3310401J Interface - MHO- Lot-10 (Deaerator) 0 20-Feb-17* 61

XAC03-3310401I Interface -MHO- Lot-9 (Valves & Instruments) 0 02-Mar-17* 31

XAC03-33104030 Interface - MC 0 15-Aug-17* 149

XAC03-33104040 Interface - TOP 0 29-Sep-17* 109

03PMS-BL00.3.3.1.04.1 Tube Blocks & Duct Assemble 84 16-Jan-17 21-Apr-17 85

XAC03-33104110 Tube Blocks & Duct Assemble - Preparation 6 16-Jan-17 21-Jan-17 5

XAC03-33104120 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes 2 23-Jan-17 24-Jan-17 5

XAC03-33104130 Tube Blocks & Duct Assemble - Module Box Alignment 3 25-Jan-17 27-Jan-17 5

XAC03-33104140 Tube Blocks & Duct Assemble - Spool Duct Installation 2 28-Jan-17 30-Jan-17 5

XAC03-33104150 Tube Blocks & Duct Assemble - Module Box Grout 5 31-Jan-17 04-Feb-17 91

XAC03-33104160 Tube Blocks & Duct Assemble - Complete Module Box/Panel Seal Welding 13 06-Feb-17 20-Feb-17 91

XAC03-33104170 Tube Blocks & Duct Assemble - Platform & Stairway 16 08-Feb-17 25-Feb-17 8

XAC03-33104180 Tube Blocks & Duct Assemble - Support Installation of HP/LP Drum 6 21-Feb-17 27-Feb-17 91

XAC03-33104190 Tube Blocks & Duct Assemble - Install HP/LP Drums 6 28-Feb-17 06-Mar-17 91

XAC03-331041A0 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation 4 07-Mar-17 10-Mar-17 91

XAC03-331041B0 Tube Blocks & Duct Assemble - Insulation and liners 31 17-Mar-17 21-Apr-17 85

03PMS-BL00.3.3.1.04.2 Blowdown Tank 5 04-Feb-17 10-Feb-17 21

XAC03-33104210 Blowdown Tank - Blowdown Tank Installation 5 04-Feb-17 10-Feb-17 21

03PMS-BL00.3.3.1.04.3 Bypass Damper and Bypass Stack 42 23-Jan-17 11-Mar-17 121

XAC03-33104310 Bypass Damper and Bypass Stack - Foundation Preparation 4 23-Jan-17 26-Jan-17 5

XAC03-33104320 Bypass Damper and Bypass Stack - Diverter Damper On-Base 3 27-Jan-17 30-Jan-17 5

XAC03-33104330 Bypass Damper and Bypass Stack - Erect Bypass Stack steel structure 9 31-Jan-17 09-Feb-17 121

XAC03-33104340 Bypass Damper and Bypass Stack - Bypass Stack Painting & Platform installation 9 31-Jan-17 10-Feb-17 121

XAC03-33104350 Bypass Damper and Bypass Stack - Install Stack Exp.Joint 1 10-Feb-17 10-Feb-17 121

XAC03-33104360 Bypass Damper and Bypass Stack - Bypass Stack On-base 1 11-Feb-17 11-Feb-17 121

XAC03-33104370 Bypass Damper and Bypass Stack - Seal Air Fan/Diverter ancillaries Installation 13 13-Feb-17 27-Feb-17 121

XAC03-33104380 Bypass Damper and Bypass Stack - Bypass Damper Tes t 11 28-Feb-17 11-Mar-17 121

03PMS-BL00.3.3.1.04.4 Inlet Duct and Expansion Joint 66 06-Feb-17 21-Apr-17 85

XAC03-33104410 Inlet Duct and Expension Joint - Bottom Panels 3 06-Feb-17 08-Feb-17 0

XAC03-33104420 Inlet Duct and Expension Joint - Siding Panels 9 09-Feb-17 18-Feb-17 0

XAC03-33104430 Inlet Duct and Expension Joint - Top Panels 7 20-Feb-17 27-Feb-17 0

XAC03-33104440 Inlet Duct and Expension Joint - Seal Welding 15 28-Feb-17 16-Mar-17 85

XAC03-33104450 Inlet Duct and Expension Joint - Insulation and liners 31 17-Mar-17 21-Apr-17 85

03PMS-BL00.3.3.1.04.5 Outlet Duct and Stack 39 17-Feb-17 03-Apr-17 264

XAC03-33104510 Outlet Duct and Stack - Main Stack (Lower Parts) On Base 1 17-Feb-17 17-Feb-17 264

XAC03-33104520 Outlet Duct and Stack - Main Stack (Upper Parts) Assembly & Painting 10 18-Feb-17 01-Mar-17 264

XAC03-33104530 Outlet Duct and Stack - Main Stack (Upper Parts) On Base & Welding 3 02-Mar-17 04-Mar-17 264

XAC03-33104540 Outlet Duct and Stack - Outlet Duct Install 12 06-Mar-17 18-Mar-17 264

XAC03-33104550 Outlet Duct and Stack - Expansion Install 13 20-Mar-17 03-Apr-17 264

03PMS-BL00.3.3.1.04.6 Internal Piping 142 27-Feb-17 09-Aug-17 153

XAC03-33104610 Internal Piping - Large Bore Piping & Support 55 27-Feb-17 29-Apr-17 8

XAC03-33104620 Internal Piping - Small Bore Piping & Support 37 03-Apr-17 15-May-17 65

XAC03-33104630 Internal Piping - NDE at field welding of piping 37 03-Apr-17 15-May-17 53

XAC03-33104640 Internal Piping - Line Check 12 16-May-17 29-May-17 53

XAC03-33104650 Internal Piping - HRSG Hydro Tes t 6 29-Jun-17 05-Jul-17 27

XAC03-33104660 Internal Piping - Prepare Chemical Clean 4 06-Jul-17 10-Jul-17 27

XAC03-33104670 Internal Piping - Final Insulation Work 24 06-Jul-17 02-Aug-17 153

XAC03-33104680 Internal Piping - Chemical Cleaning 6 13-Jul-17 19-Jul-17 25

XAC03-33104690 Internal Piping - Restoration for Chemical Clean 6 20-Jul-17 26-Jul-17 36

XAC03-331046A0 Internal Piping - Final Inspection Application to MOI 6 03-Aug-17 09-Aug-17 153

03PMS-BL00.3.3.1.04.7 Electrical work 118 17-Mar-17 01-Aug-17 31

XAC03-33104710 Electrical Work - Instrument Calibration 16 17-Mar-17 05-Apr-17 31

XAC03-33104720 Electrical Work - Tray Installation 12 01-May-17 13-May-17 8

XAC03-33104730 Electrical Work - Instrument Installation 30 01-May-17 03-Jun-17 9

XAC03-33104740 Electrical Work - Conduit Installation 25 15-May-17 12-Jun-17 8

XAC03-33104750 Electrical Work - Cabling / Termination 39 06-Jun-17 20-Jul-17 8

XAC03-33104760 Electrical work - Handover to Commissioning Walkdown 1 26-Jul-17 26-Jul-17 31

XAC03-33104770 Electrical work - Punch Clear 4 27-Jul-17 31-Jul-17 31

XAC03-33104780 Electrical work - Handover to Commissioning 1 01-Aug-17 01-Aug-17 31

03PMS-BL00.3.3.1.04.Z Others 27 15-Mar-17 14-Apr-17 119

XAC03-33104Z10 Access Platform - BD Tank Access - Delivery 0 15-Mar-17* 119

XAC03-33104Z20 Access Platform - Isolation Valve Access - Delivery 0 15-Mar-17 129

XAC03-33104Z30 Access Platform - HRSG#31 Flow Nozzle - Delivery 0 15-Mar-17 137

XAC03-33104Z40 Access Platform - BD Tank Access - Installation 9 16-Mar-17 25-Mar-17 119

XAC03-33104Z50 Access Platform - Isolation Valve Access - Installation 8 27-Mar-17 04-Apr-17 119

XAC03-33104Z60 Access Platform - HRSG#31 Flow Nozzle - Installation 9 05-Apr-17 14-Apr-17 119

03PMS-BL00.3.3.1.05 St
Steam Turbine & Generator (Siemens) 174 15-Mar-17 30-Sep-17 107

03PMS-BL00.3.3.1.05.0 Interface 159 15-Mar-17 14-Sep-17 28

XAC03-3310501A Interface - MHO-Lot1 Embedded Materials 0 15-Mar-17* 52

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:34 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33105020 Interface - CTO 0 06-Apr-17* 36

XAC03-3310501B Interface - MHO-Lot2 Main Equipment 0 15-May-17* 12

XAC03-3310501C Interface - MHO-Lot-3 Auxiliary Equipments & Accessories/Shortage Materials 0 15-May-17* 19

XAC03-33105030 Interface - MC-O/F 0 29-Aug-17* 42

XAC03-33105040 Interface - TOP 0 14-Sep-17* 28

03PMS-BL00.3.3.1.05.1 Mechanical Work 94 04-May-17 19-Aug-17 49

XAC03-33105110 Mechanical Work - Preparation 9 04-May-17 13-May-17 12

XAC03-33105120 Mechanical Work - ST #3 On Base 1 15-May-17 15-May-17 12

XAC03-33105130 Mechanical Work - ST Gear Box #3 On Base 1 16-May-17 16-May-17 12

XAC03-33105140 Mechanical Work - STG #3 On Base 4 17-May-17 20-May-17 12

XAC03-33105150 Mechanical Work - STG #3 Assembly 51 22-May-17 19-Jul-17 12

XAC03-33105160 Mechanical Work - Turbine Exhaust Pipe Installation 18 22-May-17 10-Jun-17 71

XAC03-33105170 Mechanical Work - Internal Piping 48 29-May-17 22-Jul-17 12

XAC03-33105180 Mechanical Work - Alignment 12 24-Jul-17 05-Aug-17 49

XAC03-33105190 Mechanical Work - ST Insulation 12 07-Aug-17 19-Aug-17 49

03PMS-BL00.3.3.1.05.2 Electrical Work 24 31-Jul-17 28-Aug-17 17

XAC03-33105210 Electrical Work - Conduit & Tray Install 11 31-Jul-17 12-Aug-17 17

XAC03-33105220 Electrical Work - Cable Pull & Termination 18 05-Aug-17 26-Aug-17 17

XAC03-33105230 Electrical Work - Megger Check & Continuity Cable 1 28-Aug-17 28-Aug-17 17

03PMS-BL00.3.3.1.05.3 Instrument Work 36 24-Jul-17 02-Sep-17 12

XAC03-33105310 Instrument Work - Instrument Install 18 24-Jul-17 12-Aug-17 12

XAC03-33105320 Instrument Work - Tubing Install 12 14-Aug-17 26-Aug-17 12

XAC03-33105330 Instrument Work - Leak Test 1 28-Aug-17 28-Aug-17 12

XAC03-33105340 Instrument Work - System Handover Walk Down 1 29-Aug-17 29-Aug-17 12

XAC03-33105360 Instrument Work - Punch Clear 3 30-Aug-17 01-Sep-17 12

XAC03-33105370 Instrument Work - Handover to Commissioning 1 01-Sep-17 02-Sep-17 12

03PMS-BL00.3.3.1.05.Z Others 30 26-Aug-17 30-Sep-17 107

XAC03-33105Z10 Access Platform - Access & Maintenance Platform for O/H Crane - Delivery 0 26-Aug-17 107

XAC03-33105Z30 Access Platform - Access & Maintenance Platform for ST - Delivery 0 26-Aug-17 117

XAC03-33105Z50 Access Platform - Platform for CEP Pit - Delivery 0 26-Aug-17 127

XAC03-33105Z20 Access Platform - Access & Maintenance Platform for O/H Crane - Installation 10 28-Aug-17 07-Sep-17 107

XAC03-33105Z40 Access Platform - Access & Maintenance Platform for ST - Installation 10 07-Sep-17 19-Sep-17 107

XAC03-33105Z60 Access Platform - Platform for CEP Pit - Installation 10 19-Sep-17 30-Sep-17 107

03PMS-BL00.3.3.2 Unit Package


P 370 14-Jul-16 13-Sep-17 122

03PMS-BL00.3.3.2.01 DM Tank (Common) 148 05-Sep-16 22-Feb-17 92

03PMS-BL00.3.3.2.01.0 Interface 144 05-Sep-16 17-Feb-17 96

XAC03-3320101A Interface - MHO Lot-1 (Annular / Bottom Plate) 0 05-Sep-16* 76

XAC03-33201020 Interface - CTO 0 12-Sep-16* 86

XAC03-3320101B Interface - MHO Lot-2 (Shell) 0 26-Sep-16* 73

XAC03-3320101C Interface - MHO Lot-3 (Roof) 0 06-Oct-16* 142

XAC03-3320101D Interface - MHO Lot-4 (Nozzle) 0 06-Oct-16* 92

XAC03-33201030 Interface - MC 0 17-Feb-17* 96

XAC03-33201040 Interface - TOP-Flushing 0 17-Feb-17* 96

03PMS-BL00.3.3.2.01.1 DM Water Storage Tank 146 07-Sep-16 22-Feb-17 74

XAC03-33201110 DM Water Tank - Foundation Inspection 2 07-Sep-16 08-Sep-16 76

XAC03-33201120 DM Water Tank - Erection & Fit-up Annular Plate 3 09-Sep-16 13-Sep-16 76

XAC03-33201130 DM Water Tank - Annular Plate Welding 4 13-Sep-16 16-Sep-16 76

XAC03-33201140 DM Water Tank - NDE (RT) Annular Plate Before Shell Erection 2 16-Sep-16 19-Sep-16 76

XAC03-33201150 DM Water Tank - Bottom Plate Installation 3 22-Sep-16 27-Sep-16 76

XAC03-33201160 DM Water Tank - Bottom Plate Welding 16 27-Sep-16 14-Oct-16 76

XAC03-33201170 DM Water Tank - Shell Plate Erection and Fit-up Course-1 2 30-Sep-16 01-Oct-16 73

XAC03-33201180 DM Water Tank - Shell Course-1 Inspection (Fit-up, Roundness, Levelness, 2 03-Oct-16 04-Oct-16 73
Plumbness)
XAC03-33201190 DM Water Tank - Shell Course-1 Vertical Join t Welding 2 06-Oct-16 07-Oct-16 73

XAC03-332011A0 DM Water Tank - Shell Course-2 Erection & Fit-up 1 10-Oct-16 11-Oct-16 73

XAC03-332011B0 DM Water Tank - Shell Course-2 Fit-up Inspection 2 12-Oct-16 13-Oct-16 73

XAC03-332011C0 DM Water Tank - Shell Course-2 Vertical Join t Welding 2 14-Oct-16 15-Oct-16 73

XAC03-332011D0 DM Water Tank - Shell Course 1&2 Horizontal Joint Fit-up 3 17-Oct-16 19-Oct-16 73

XAC03-332011E0 DM Water Tank - Shell Course 1&2 Horizontal Joint Fit-up Inspection 1 20-Oct-16 20-Oct-16 73

XAC03-332011F0 DM Water Tank - Shell Course 1&2 Horizontal Joint Welding 7 21-Oct-16 28-Oct-16 73

XAC03-332011G0 DM Water Tank - Shell Course-2 Peaking, Banding & Plumbness Inspection 6 24-Oct-16 29-Oct-16 73

XAC03-332011H0 DM Water Tank - Shell Course-3 Erection & Fit-up 2 26-Oct-16 27-Oct-16 73

XAC03-332011I0 DM Water Tank - Shell Course-3 Fit-up Inspection 1 27-Oct-16 28-Oct-16 73

XAC03-332011J0 DM Water Tank - Shell Course-3 Vertical Join t Welding 1 29-Oct-16 29-Oct-16 73

XAC03-332011K0 DM Water Tank - Shell Course 2&3 Horizontal Joint Fit-up 3 31-Oct-16 02-Nov-16 73

XAC03-332011L0 DM Water Tank - Shell Course 2&3 Horizontal Joint Fit-up Inspection 2 02-Nov-16 03-Nov-16 73

XAC03-332011M0 DM Water Tank - Shell Course 2&3 Horizontal Joint Welding 2 03-Nov-16 05-Nov-16 73

XAC03-332011N0 DM Water Tank - Shell Course 1&2 Welding Seam NDE (RT) 3 03-Nov-16 07-Nov-16 73

XAC03-332011O0 DM Water Tank - Shell Course-3 Peaking, Banding, Plumbness Inspection 1 07-Nov-16 07-Nov-16 73

XAC03-332011P0 DM Water Tank - Annular Plate & Bottom Plate Welding 2 07-Nov-16 08-Nov-16 73

XAC03-332011Q0 DM Water Tank - Shell Course-1 & Annular Plate Fit-up & Inspection 2 07-Nov-16 08-Nov-16 73

XAC03-332011R0 DM Water Tank - Draw-off Sump Installation & Welding 2 08-Nov-16 10-Nov-16 73

XAC03-332011S0 DM Water Tank - Internal Structure Erection (Column, Grider, Internal Rafter) 2 08-Nov-16 10-Nov-16 73

XAC03-332011T0 DM Water Tank - Shell Course-1 & Annular Plate Welding 2 09-Nov-16 11-Nov-16 73

XAC03-332011U0 DM Water Tank - Bottom Plate Welding Seam Vacuum Test 2 09-Nov-16 11-Nov-16 73

XAC03-332011V0 DM Water Tank - Shell Course-4 Erection & Fit-up 1 10-Nov-16 11-Nov-16 73

XAC03-332011X0 DM Water Tank - Shell Course-4 Fit-up Inspection 2 11-Nov-16 12-Nov-16 73

XAC03-332011W0 DM Water Tank - Shell Course-1 & Annular Plate Welding Seam NDE (PT) 1 11-Nov-16 12-Nov-16 73

XAC03-332011Y0 DM Water Tank - Shell Course-4 Vertical Join t Welding 2 12-Nov-16 14-Nov-16 73

XAC03-332011Z0 DM Water Tank - Shell Course 3&4 Horizontal Joint Fit-up 2 14-Nov-16 15-Nov-16 73

XAC03-33201111 DM Water Tank - Shell Course 3&4 Horizontal Joint Fit-up Inspection 2 16-Nov-16 17-Nov-16 73

XAC03-33201112 DM Water Tank - Shell Course 3&4 Horizontal Joint Welding 2 17-Nov-16 19-Nov-16 73

XAC03-33201113 DM Water Tank - Shell Course 3&4 Welding Seam NDE (RT) 2 19-Nov-16 22-Nov-16 73

XAC03-33201114 DM Water Tank - Shell Course-5 Erection & Fit-up 3 21-Nov-16 23-Nov-16 73

XAC03-33201115 DM Water Tank - Shell Course-4 Peaking, Banding, Plumbness Inspection 1 21-Nov-16 21-Nov-16 73

XAC03-33201116 DM Water Tank - Shell Course-5 Fit-up Inspection 2 23-Nov-16 24-Nov-16 73

XAC03-33201117 DM Water Tank - Shell Course-5 Vertical Join t Welding 3 24-Nov-16 26-Nov-16 73

XAC03-33201118 DM Water Tank - Shell Course 4&5 Horizontal Joint Fit-up 1 26-Nov-16 26-Nov-16 73

XAC03-33201119 DM Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Inspection 1 26-Nov-16 28-Nov-16 73

XAC03-3320111A DM Water Tank - Scaffolding Installation 13 26-Nov-16 10-Dec-16 73

XAC03-3320111B DM Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Welding 4 28-Nov-16 01-Dec-16 73

XAC03-3320111C DM Water Tank - Shell Course-5 Peaking, Banding, Plumbness Inspection 2 01-Dec-16 02-Dec-16 73

XAC03-3320111D DM Water Tank - Shell Course-6 Erection & Fit-up 1 02-Dec-16 03-Dec-16 73

XAC03-3320111E DM Water Tank - Shell Course-6 Fit-up Inspection 1 05-Dec-16 05-Dec-16 73

XAC03-3320111F DM Water Tank - Shell Course-6 Vertical Join t Welding 1 05-Dec-16 06-Dec-16 73

XAC03-3320111G DM Water Tank - Shell Course 5&6 Horizontal Joint Fit-up 2 07-Dec-16 08-Dec-16 73

XAC03-3320111H DM Water Tank - Shell Course 5&6 Horizontal Joint Fit-up Inspection 2 08-Dec-16 09-Dec-16 73

XAC03-3320111I DM Water Tank - Shell Course 5&6 Horizontal Joint Welding 3 09-Dec-16 12-Dec-16 73

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:35 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3320111J DM Water Tank - Shell Course-6 Peaking, Banding, Plumbness Inspection 2 12-Dec-16 13-Dec-16 73

XAC03-3320111K DM Water Tank - Nozzles & Manhole Installation & Welding 5 12-Dec-16 16-Dec-16 73

XAC03-3320111L DM Water Tank - Shell Course-7 Erection & Fit-up 2 13-Dec-16 14-Dec-16 73

XAC03-3320111N DM Water Tank - Shell Course-7 Fit-up Inspection 2 14-Dec-16 15-Dec-16 73

XAC03-3320111O DM Water Tank - Shell Course-7 Vertical Join t Welding 2 15-Dec-16 16-Dec-16 73

XAC03-3320111P DM Water Tank - Nozzle & Manhole Welding Seam NDE 3 15-Dec-16 17-Dec-16 73

XAC03-3320111Q DM Water Tank - Shell Course 6&7 Horizontal Joint Fit-up 1 16-Dec-16 17-Dec-16 73

XAC03-3320111R DM Water Tank - Shell Course 6&7 Horizontal Joint Fit-up Inspection 1 16-Dec-16 17-Dec-16 73

XAC03-3320111S DM Water Tank - Shell Course 5&6 Welding Seam NDE (RT) 4 19-Dec-16 22-Dec-16 73

XAC03-3320111T DM Water Tank - Top Angle Erection & Welding 4 19-Dec-16 22-Dec-16 73

XAC03-3320111U DM Water Tank - Platform & Handrail Erection & Welding 6 19-Dec-16 24-Dec-16 73

XAC03-3320111V DM Water Tank - Shell Course 6&7 Horizontal Joint Welding 3 19-Dec-16 21-Dec-16 73

XAC03-3320111W DM Water Tank - Rafter Clip Support Fit-up & Welding 3 20-Dec-16 22-Dec-16 73

XAC03-3320111X DM Water Tank - Shell Course-7 Peaking, Banding, Plumbness Inspection 2 21-Dec-16 22-Dec-16 73

XAC03-3320111Y DM Water Tank - Outside Rafter Installation 2 21-Dec-16 22-Dec-16 73

XAC03-3320111Z DM Water Tank - Internal Structure Alignment & Bolt Tightening 3 21-Dec-16 23-Dec-16 73

XAC03-332011110 DM Water Tank - Anc hor Chair Installation & Welding 3 21-Dec-16 23-Dec-16 73

XAC03-332011120 DM Water Tank - Anc hor Bolts Installation & G routing 12 23-Dec-16 05-Jan-17 73

XAC03-332011130 DM Water Tank - Roof Plate Erection & Fit-up 11 23-Dec-16 05-Jan-17 73

XAC03-332011140 DM Water Tank - Roof Plate Fit-up Inspection & Welding 4 05-Jan-17 09-Jan-17 73

XAC03-332011150 DM Water Tank - Roof Plate Welding Seam NDE (PT) 2 05-Jan-17 06-Jan-17 73

XAC03-332011160 DM Water Tank - Downcomer Pipes Installation 4 05-Jan-17 09-Jan-17 73

XAC03-332011170 DM Water Tank - Final Inspection Before Water Filling Test 2 05-Jan-17 06-Jan-17 73

XAC03-332011180 DM Water Tank - Water Filling Test Preparation 2 05-Jan-17 06-Jan-17 73

XAC03-332011190 DM Water Tank - Full Water Test & Holding Time 7 05-Jan-17 12-Jan-17 73

XAC03-3320111A0 DM Water Tank - Settlement Inspection 4 05-Jan-17 09-Jan-17 73

XAC03-3320111B0 DM Water Tank - Drain Water & Internal Cleaning 3 07-Jan-17 10-Jan-17 73

XAC03-3320111C0 DM Water Tank - External Painting 25 07-Jan-17 04-Feb-17 73

XAC03-3320111D0 DM Water Tank - Internal Painting Shell & Roof 25 09-Jan-17 06-Feb-17 88

XAC03-3320111E0 DM Water Tank - Tank Labelling Work 2 17-Jan-17 19-Jan-17 88

XAC03-3320111F0 DM Water Tank - External Painting Inspection 2 04-Feb-17 07-Feb-17 73

XAC03-3320111G0 DM Water Tank - External Scaffolding Removal Work 4 04-Feb-17 09-Feb-17 73

XAC03-3320111H0 DM Water Tank - Internal Painting Inspection for Shell & Roof 2 08-Feb-17 10-Feb-17 73

XAC03-3320111I0 DM Water Tank - Internal Scaffolding Removal Work 4 10-Feb-17 15-Feb-17 73

XAC03-3320111J0 DM Water Tank - Internal Bottom Plate Welding 4 15-Feb-17 20-Feb-17 73

XAC03-3320111K0 DM Water Tank - Final Inspection (Including Painting) 2 20-Feb-17 22-Feb-17 73

XAC03-3320111L0 DM Water Tank - Hand-Over to TPSC 1 21-Feb-17 22-Feb-17 73

03PMS-BL00.3.3.2.02 Se
Service Water & Fire Water Storage Tank (Common) 158 26-Aug-16 24-Feb-17 118

03PMS-BL00.3.3.2.02.0 Interface 158 26-Aug-16 24-Feb-17 118

XAC03-3320201A Interface - MHO Lot-1 (Annular / Bottom Plate) 0 26-Aug-16* 75

XAC03-33202020 Interface - CTO 0 01-Sep-16* 70

XAC03-3320201B Interface - MHO Lot-2 (Shell) 0 16-Sep-16* 81

XAC03-3320201C Interface - MHO Lot-3 (Roof) 0 26-Sep-16* 143

XAC03-3320201D Interface - MHO Lot-4 (Nozzle) 0 26-Sep-16* 138

XAC03-33202030 Interface - MC 0 08-Feb-17* 118

XAC03-33202040 Interface - TOP 0 24-Feb-17* 118

03PMS-BL00.3.3.2.02.1 Service Water Tank 150 01-Sep-16 21-Feb-17 82

XAC03-33202110 Service Water Tank - Shell Course-3 Erection & Fit-up 2 01-Sep-16 02-Sep-16 70

XAC03-33202120 Service Water Tank - Foundation Inspection 1 07-Sep-16 08-Sep-16 70

XAC03-33202130 Service Water Tank - Erection & Fit-up Annular Plate 3 09-Sep-16 13-Sep-16 70

XAC03-33202140 Service Water Tank - Annular Plate Welding 5 13-Sep-16 19-Sep-16 70

XAC03-33202150 Service Water Tank - NDE (RT) Annular Plate Before Shell Erection 1 19-Sep-16 20-Sep-16 70

XAC03-33202160 Service Water Tank - Bottom Plate Installation 3 20-Sep-16 23-Sep-16 70

XAC03-33202170 Service Water Tank - Shell Plate Erection and Fit-up Course-1 2 29-Sep-16 01-Oct-16 70

XAC03-33202180 Service Water Tank - Shell Course-1 Inspection (Fit-up, Roundness, Levelness, 1 05-Oct-16 06-Oct-16 70
Plumbness)
XAC03-33202190 Service Water Tank - Shell Course-1 Vertical Joint Welding 5 07-Oct-16 13-Oct-16 70

XAC03-332021A0 Service Water Tank - Shell Course-2 Fit-up Inspection 2 12-Oct-16 14-Oct-16 70

XAC03-332021B0 Service Water Tank - Shell Course-2 Erection & Fit-up 2 14-Oct-16 17-Oct-16 71

XAC03-332021C0 Service Water Tank - Shell Course-2 Vertical Joint Welding 3 14-Oct-16 18-Oct-16 70

XAC03-332021D0 Service Water Tank - Shell Course 1&2 Horizontal Joint Fit-up 1 18-Oct-16 19-Oct-16 70

XAC03-332021E0 Service Water Tank - Shell Course 1&2 Horizontal Joint Fit-up Inspection 1 19-Oct-16 20-Oct-16 70

XAC03-332021F0 Service Water Tank - Shell Course 1&2 Horizontal Joint Welding 5 20-Oct-16 26-Oct-16 70

XAC03-332021G0 Service Water Tank - Shell Course-2 Peaking, Banding & Plumbness Inspection 1 24-Oct-16 25-Oct-16 70

XAC03-332021H0 Service Water Tank - Bottom Plate Welding 17 25-Oct-16 14-Nov-16 70

XAC03-332021I0 Service Water Tank - Shell Course-3 Fit-up Inspection 1 26-Oct-16 27-Oct-16 70

XAC03-332021J0 Service Water Tank - Shell Course-3 Vertical Joint Welding 4 28-Oct-16 02-Nov-16 70

XAC03-332021K0 Service Water Tank - Shell Course 2&3 Horizontal Joint Fit-up 3 29-Oct-16 02-Nov-16 70

XAC03-332021L0 Service Water Tank - Shell Course 2&3 Horizontal Joint Fit-up Inspection 1 01-Nov-16 02-Nov-16 70

XAC03-332021M0 Service Water Tank - Shell Course 2&3 Horizontal Joint Welding 5 02-Nov-16 08-Nov-16 70

XAC03-332021N0 Service Water Tank - Shell Course-3 Peaking, Banding, Plumbness Inspection 2 04-Nov-16 07-Nov-16 70

XAC03-332021O0 Service Water Tank - Shell Course 1&2 Welding Seam NDE (RT) 3 04-Nov-16 08-Nov-16 70

XAC03-332021P0 Service Water Tank - Annular Plate & Bottom Plate Welding 2 05-Nov-16 08-Nov-16 70

XAC03-332021Q0 Service Water Tank - Shell Course-1 & Annular Plate Fit-up & Inspection 2 05-Nov-16 08-Nov-16 70

XAC03-332021R0 Service Water Tank - Internal Structure Erection (Column, Grider, Internal R after) 3 05-Nov-16 09-Nov-16 70

XAC03-332021S0 Service Water Tank - Shell Course-4 Erection & Fit-up 3 05-Nov-16 09-Nov-16 70

XAC03-332021U0 Service Water Tank - Bottom Plate Welding Seam Vacuum Test 2 07-Nov-16 09-Nov-16 70

XAC03-332021V0 Service Water Tank - Draw-off Sump Installation & Welding 2 07-Nov-16 09-Nov-16 70

XAC03-332021T0 Service Water Tank - Shell Course-1 & Annular Plate Welding 1 08-Nov-16 09-Nov-16 70

XAC03-332021W0 Service Water Tank - Shell Course-1 & Annular Plate Welding Seam NDE (PT) 1 08-Nov-16 09-Nov-16 70

XAC03-332021X0 Service Water Tank - Shell Course-4 Fit-up Inspection 1 08-Nov-16 09-Nov-16 70

XAC03-332021Y0 Service Water Tank - Shell Course-4 Vertical Joint Welding 2 09-Nov-16 11-Nov-16 70

XAC03-332021Z0 Service Water Tank - Shell Course 3&4 Horizontal Joint Fit-up 3 09-Nov-16 12-Nov-16 70

XAC03-33202111 Service Water Tank - Shell Course 3&4 Horizontal Joint Fit-up Inspection 2 10-Nov-16 12-Nov-16 70

XAC03-33202112 Service Water Tank - Shell Course 3&4 Horizontal Joint Welding 4 11-Nov-16 16-Nov-16 70

XAC03-33202113 Service Water Tank - Shell Course 3&4 Welding Seam NDE (RT) 3 12-Nov-16 16-Nov-16 70

XAC03-33202114 Service Water Tank - Shell Course-4 Peaking, Banding, Plumbness Inspection 1 15-Nov-16 16-Nov-16 70

XAC03-33202115 Service Water Tank - Shell Course-5 Erection & Fit-up 2 16-Nov-16 18-Nov-16 70

XAC03-33202116 Service Water Tank - Shell Course-5 Fit-up Inspection 2 18-Nov-16 21-Nov-16 70

XAC03-33202117 Service Water Tank - Shell Course-5 Vertical Joint Welding 3 18-Nov-16 22-Nov-16 70

XAC03-33202118 Service Water Tank - Shell Course 4&5 Horizontal Joint Fit-up 1 22-Nov-16 23-Nov-16 70

XAC03-33202119 Service Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Inspection 1 23-Nov-16 24-Nov-16 70

XAC03-3320211A Service Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Welding 4 23-Nov-16 28-Nov-16 70

XAC03-3320211B Service Water Tank - Scaffolding Installation 12 23-Nov-16 07-Dec-16 70

XAC03-3320211C Service Water Tank - Shell Course-5 Peaking, Banding, Plumbness Inspection 2 28-Nov-16 30-Nov-16 70

XAC03-3320211D Service Water Tank - Shell Course-6 Erection & Fit-up 2 29-Nov-16 01-Dec-16 70

XAC03-3320211E Service Water Tank - Shell Course-6 Fit-up Inspection 2 30-Nov-16 02-Dec-16 70

XAC03-3320211F Service Water Tank - Shell Course-6 Vertical Joint Welding 2 01-Dec-16 03-Dec-16 70

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:36 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3320211G Service Water Tank - Shell Course 5&6 Horizontal Joint Fit-up 3 02-Dec-16 06-Dec-16 70

XAC03-3320211H Service Water Tank - Shell Course 5&6 Horizontal Joint Fit-up Inspection 2 05-Dec-16 07-Dec-16 70

XAC03-3320211I Service Water Tank - Shell Course 5&6 Horizontal Joint Welding 3 06-Dec-16 09-Dec-16 70

XAC03-3320211J Service Water Tank - Shell Course-6 Peaking, Banding, Plumbness Inspection 2 09-Dec-16 12-Dec-16 70

XAC03-3320211K Service Water Tank - Nozzles & Manhole Installation & Welding 4 09-Dec-16 14-Dec-16 70

XAC03-3320211L Service Water Tank - Platform & Handrail Erection & Welding 6 09-Dec-16 16-Dec-16 70

XAC03-3320211M Service Water Tank - Shell Course-7 Erection & Fit-up 3 10-Dec-16 14-Dec-16 70

XAC03-3320211N Service Water Tank - Shell Course-7 Fit-up Inspection 1 13-Dec-16 14-Dec-16 70

XAC03-3320211O Service Water Tank - Shell Course-7 Vertical Joint Welding 1 14-Dec-16 15-Dec-16 70

XAC03-3320211P Service Water Tank - Shell Course 6&7 Horizontal Joint Fit-up 3 14-Dec-16 17-Dec-16 70

XAC03-3320211Q Service Water Tank - Top Angle Erection & Welding 4 14-Dec-16 19-Dec-16 70

XAC03-3320211R Service Water Tank - Nozzle & Manhole Welding Seam NDE 3 14-Dec-16 17-Dec-16 70

XAC03-3320211S Service Water Tank - Shell Course 6&7 Horizontal Joint Fit-up Inspection 1 16-Dec-16 17-Dec-16 70

XAC03-3320211T Service Water Tank - Shell Course 6&7 Horizontal Joint Welding 4 16-Dec-16 21-Dec-16 70

XAC03-3320211U Service Water Tank - Shell Course-7 Peaking, Banding, Plumbness Inspection 2 16-Dec-16 19-Dec-16 70

XAC03-3320211V Service Water Tank - Shell Course 5&6 Welding Seam NDE (RT) 4 16-Dec-16 21-Dec-16 70

XAC03-3320211W Service Water Tank - Rafter Clip Support Fit-up & Welding 3 16-Dec-16 20-Dec-16 70

XAC03-3320211X Service Water Tank - Anchor Chair Installation & Welding 3 16-Dec-16 20-Dec-16 70

XAC03-3320211Y Service Water Tank - Outside Rafter Installation 2 17-Dec-16 20-Dec-16 70

XAC03-3320211Z Service Water Tank - Internal Structure Alignment & Bolt Tightening 1 20-Dec-16 21-Dec-16 70

XAC03-332021110 Service Water Tank - Roof Plate Erection & Fit-up 1 20-Dec-16 21-Dec-16 70

XAC03-332021120 Service Water Tank - Anchor Bolts Installation & Gr outing 1 20-Dec-16 21-Dec-16 70

XAC03-332021130 Service Water Tank - Roof Plate Fit-up Inspection & Welding 4 21-Dec-16 26-Dec-16 70

XAC03-332021140 Service Water Tank - Downcomer Pipes Installation 4 21-Dec-16 26-Dec-16 70

XAC03-332021150 Service Water Tank - Roof Plate Welding Seam NDE (PT) 2 23-Dec-16 26-Dec-16 70

XAC03-332021160 Service Water Tank - Final Inspection Before Water Filling Test 1 24-Dec-16 26-Dec-16 70

XAC03-332021170 Service Water Tank - Water Filling Test Preparation 2 24-Dec-16 27-Dec-16 70

XAC03-332021180 Service Water Tank - Full Water Test & Holding Time 16 27-Dec-16 14-Jan-17 70

XAC03-332021190 Service Water Tank - Settlement Inspection 3 09-Jan-17 12-Jan-17 70

XAC03-3320211A0 Service Water Tank - Drain Water & Internal Cleaning 2 09-Jan-17 11-Jan-17 70

XAC03-3320211B0 Service Water Tank - External Painting 25 09-Jan-17 06-Feb-17 70

XAC03-3320211C0 Service Water Tank - Internal Painting Shell & Roof 25 09-Jan-17 06-Feb-17 95

XAC03-3320211D0 Service Water Tank - External Painting Inspection 1 06-Feb-17 08-Feb-17 70

XAC03-3320211E0 Service Water Tank - Tank Labelling Work 3 07-Feb-17 09-Feb-17 70

XAC03-3320211F0 Service Water Tank - Internal Painting Inspection for Shell & Roof 2 08-Feb-17 09-Feb-17 70

XAC03-3320211G0 Service Water Tank - Internal Scaffolding Removal Work 3 08-Feb-17 10-Feb-17 70

XAC03-3320211H0 Service Water Tank - Internal Bottom Plate Painting 4 09-Feb-17 13-Feb-17 70

XAC03-3320211I0 Service Water Tank - External Scaffolding Removal Work 4 09-Feb-17 14-Feb-17 70

XAC03-3320211J0 Service Water Tank - Final Inspection (Including Painting) 2 15-Feb-17 17-Feb-17 70

XAC03-3320211K0 Service Water Tank - Hand-Over to TPSC 2 18-Feb-17 21-Feb-17 70

03PMS-BL00.3.3.2.03 CT Make-up Water Storage Tank (Common) 149 12-Sep-16 02-Mar-17 92

03PMS-BL00.3.3.2.03.0 Interface 138 12-Sep-16 17-Feb-17 93

XAC03-33203020 Interface - CTO 0 12-Sep-16* 115

XAC03-3320301A Interface - MHO Lot-1 (Annular / Bottom Plate) 0 12-Sep-16* 92

XAC03-3320301B Interface - MHO Lot-2 (Shell) 0 26-Sep-16* 103

XAC03-3320301C Interface - MHO Lot-3 (Roof) 0 06-Oct-16* 173

XAC03-3320301D Interface - MHO Lot-4 (Nozzle) 0 06-Oct-16* 173

XAC03-33203030 Interface - MC 0 17-Feb-17* 93

XAC03-33203040 Interface - TOP 0 17-Feb-17* 93

03PMS-BL00.3.3.2.03.1 CT Make Up Water Tank 138 23-Sep-16 02-Mar-17 92

XAC03-33203110 CT Make Up Water Tank - Foundation Inspection 1 23-Sep-16* 24-Sep-16 92

XAC03-33203120 CT Make Up Water Tank - Erection & Fit-up Annular Plate 3 26-Sep-16 28-Sep-16 92

XAC03-33203130 CT Make Up Water Tank - Annular Plate Welding 3 29-Sep-16 01-Oct-16 92

XAC03-33203140 CT Make Up Water Tank - NDE (RT) Annular Plate Before Shell Erection 2 03-Oct-16 04-Oct-16 92

XAC03-33203150 CT Make Up Water Tank - Bottom Plate Installation 3 05-Oct-16 07-Oct-16 92

XAC03-33203160 CT Make Up Water Tank - Bottom Plate Welding 19 06-Oct-16 28-Oct-16 92

XAC03-33203170 CT Make Up Water Tank - Shell Plate Erection and Fit-up Course-1 3 07-Oct-16 11-Oct-16 92

XAC03-33203180 CT Make Up Water Tank - Shell Course-1 Inspection (Fit-up, Roundness, Levelness, 2 12-Oct-16 13-Oct-16 92
Plumbness)
XAC03-33203190 CT Make Up Water Tank - Shell Course-1 Vertical Joint Welding 3 13-Oct-16 17-Oct-16 92

XAC03-332031A0 CT Make Up Water Tank - Shell Course-2 Erection & Fit-up 1 20-Oct-16 21-Oct-16 92

XAC03-332031B0 CT Make Up Water Tank - Shell Course-2 Fit-up Inspection 1 21-Oct-16 22-Oct-16 92

XAC03-332031C0 CT Make Up Water Tank - Shell Course-2 Vertical Joint Welding 2 24-Oct-16 25-Oct-16 92

XAC03-332031D0 CT Make Up Water Tank - Shell Course 1&2 Horizontal Joint Fit-up 2 26-Oct-16 27-Oct-16 92

XAC03-332031E0 CT Make Up Water Tank - Shell Course 1&2 Horizontal Joint Fit-up Inspection 1 27-Oct-16 28-Oct-16 92

XAC03-332031F0 CT Make Up Water Tank - Shell Course 1&2 Horizontal Joint Welding 7 28-Oct-16 05-Nov-16 92

XAC03-332031G0 CT Make Up Water Tank - Shell Course-2 Peaking, Banding & Plumbness Inspection 1 02-Nov-16 02-Nov-16 92

XAC03-332031H0 CT Make Up Water Tank - Shell Course-3 Erection & Fit-up 1 02-Nov-16 02-Nov-16 92

XAC03-332031I0 CT Make Up Water Tank - Shell Course-3 Fit-up Inspection 1 03-Nov-16 03-Nov-16 92

XAC03-332031J0 CT Make Up Water Tank - Shell Course-3 Vertical Joint Welding 1 03-Nov-16 04-Nov-16 92

XAC03-332031K0 CT Make Up Water Tank - Shell Course 2&3 Horizontal Joint Fit-up 3 05-Nov-16 08-Nov-16 92

XAC03-332031L0 CT Make Up Water Tank - Shell Course 2&3 Horizontal Joint Fit-up Inspection 1 09-Nov-16 09-Nov-16 92

XAC03-332031M0 CT Make Up Water Tank - Shell Course 2&3 Horizontal Joint Welding 2 10-Nov-16 11-Nov-16 92

XAC03-332031N0 CT Make Up Water Tank - Shell Course 1&2 Welding Seam NDE (RT) 2 10-Nov-16 11-Nov-16 92

XAC03-332031O0 CT Make Up Water Tank - Annular Plate & Bottom Plate Welding 1 10-Nov-16 10-Nov-16 92

XAC03-332031P0 CT Make Up Water Tank - Shell Course-1 & Annular Plate Fit-up & Inspection 2 10-Nov-16 11-Nov-16 92

XAC03-332031Q0 CT Make Up Water Tank - Shell Course-3 Peaking, Banding, Plumbness Inspection 2 10-Nov-16 12-Nov-16 92

XAC03-332031R0 CT Make Up Water Tank - Shell Course-1 & Annular Plate Welding 3 10-Nov-16 14-Nov-16 92

XAC03-332031S0 CT Make Up Water Tank - Bottom Plate Welding Seam Vacuum Test 3 10-Nov-16 14-Nov-16 92

XAC03-332031T0 CT Make Up Water Tank - Draw-off Sump Installation & Welding 3 10-Nov-16 14-Nov-16 92

XAC03-332031U0 CT Make Up Water Tank - Internal Structure Erection (Column, Grider, Internal Rafter) 3 10-Nov-16 14-Nov-16 92

XAC03-332031V0 CT Make Up Water Tank - Shell Course-1 & Annular Plate Welding Seam NDE (PT) 2 14-Nov-16 15-Nov-16 92

XAC03-332031W0 CT Make Up Water Tank - Shell Course-4 Erection & Fit-up 2 14-Nov-16 15-Nov-16 92

XAC03-332031X0 CT Make Up Water Tank - Shell Course-4 Fit-up Inspection 1 14-Nov-16 15-Nov-16 92

XAC03-332031Y0 CT Make Up Water Tank - Shell Course-4 Vertical Joint Welding 2 15-Nov-16 17-Nov-16 92

XAC03-332031Z0 CT Make Up Water Tank - Shell Course 3&4 Horizontal Joint Fit-up 2 17-Nov-16 19-Nov-16 92

XAC03-33203111 CT Make Up Water Tank - Shell Course 3&4 Horizontal Joint Fit-up Inspection 1 19-Nov-16 21-Nov-16 92

XAC03-33203112 CT Make Up Water Tank - Shell Course 3&4 Horizontal Joint Welding 2 21-Nov-16 23-Nov-16 92

XAC03-33203113 CT Make Up Water Tank - Shell Course-4 Peaking, Banding, Plumbness Inspection 2 23-Nov-16 24-Nov-16 92

XAC03-33203114 CT Make Up Water Tank - Shell Course 3&4 Welding Seam NDE (RT) 3 23-Nov-16 25-Nov-16 92

XAC03-33203115 CT Make Up Water Tank - Shell Course-5 Erection & Fit-up 2 24-Nov-16 26-Nov-16 92

XAC03-33203116 CT Make Up Water Tank - Shell Course-5 Fit-up Inspection 1 26-Nov-16 28-Nov-16 92

XAC03-33203117 CT Make Up Water Tank - Shell Course-5 Vertical Joint Welding 2 28-Nov-16 29-Nov-16 92

XAC03-33203118 CT Make Up Water Tank - Shell Course 4&5 Horizontal Joint Fit-up 1 30-Nov-16 30-Nov-16 92

XAC03-33203119 CT Make Up Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Inspection 2 30-Nov-16 01-Dec-16 92

XAC03-3320311A CT Make Up Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Welding 4 01-Dec-16 05-Dec-16 92

XAC03-3320311B CT Make Up Water Tank - Scaffolding Installation 13 01-Dec-16 16-Dec-16 92

XAC03-3320311C CT Make Up Water Tank - Shell Course-5 Peaking, Banding, Plumbness Inspection 1 05-Dec-16 06-Dec-16 92

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:37 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3320311D CT Make Up Water Tank - Shell Course-6 Erection & Fit-up 2 05-Dec-16 07-Dec-16 92

XAC03-3320311E CT Make Up Water Tank - Shell Course-6 Fit-up Inspection 2 06-Dec-16 08-Dec-16 92

XAC03-3320311F CT Make Up Water Tank - Shell Course-6 Vertical Joint Welding 2 08-Dec-16 10-Dec-16 92

XAC03-3320311G CT Make Up Water Tank - Shell Course 5&6 Horizontal Joint Fit-up 2 09-Dec-16 12-Dec-16 92

XAC03-3320311H CT Make Up Water Tank - Shell Course 5&6 Horizontal Joint Fit-up Inspection 2 12-Dec-16 13-Dec-16 92

XAC03-3320311I CT Make Up Water Tank - Shell Course 5&6 Horizontal Joint Welding 3 13-Dec-16 15-Dec-16 92

XAC03-3320311J CT Make Up Water Tank - Shell Course-6 Peaking, Banding, Plumbness Inspection 2 15-Dec-16 16-Dec-16 92

XAC03-3320311K CT Make Up Water Tank - Shell Course-7 Erection & Fit-up 2 15-Dec-16 17-Dec-16 92

XAC03-3320311L CT Make Up Water Tank - Shell Course-7 Fit-up Inspection 2 16-Dec-16 19-Dec-16 92

XAC03-3320311N CT Make Up Water Tank - Nozzles & Manhole Installation & Welding 4 19-Dec-16 22-Dec-16 92

XAC03-3320311M CT Make Up Water Tank - Shell Course-7 Vertical Joint Welding 2 19-Dec-16 20-Dec-16 92

XAC03-3320311O CT Make Up Water Tank - Shell Course 6&7 Horizontal Joint Fit-up 1 20-Dec-16 20-Dec-16 92

XAC03-3320311P CT Make Up Water Tank - Shell Course 6&7 Horizontal Joint Fit-up Inspection 1 21-Dec-16 21-Dec-16 92

XAC03-3320311Q CT Make Up Water Tank - Shell Course 6&7 Horizontal Joint Welding 4 21-Dec-16 24-Dec-16 92

XAC03-3320311R CT Make Up Water Tank - Nozzle & Manhole Welding Seam NDE 2 21-Dec-16 22-Dec-16 92

XAC03-3320311S CT Make Up Water Tank - Shell Course 5&6 Welding Seam NDE (RT) 4 22-Dec-16 26-Dec-16 92

XAC03-3320311T CT Make Up Water Tank - Platform & Handrail Erection & Welding 16 22-Dec-16 10-Jan-17 92

XAC03-3320311U CT Make Up Water Tank - Shell Course-7 Peaking, Banding, Plumbness Inspection 2 23-Dec-16 26-Dec-16 92

XAC03-3320311V CT Make Up Water Tank - Top Angle Erection & Welding 13 23-Dec-16 07-Jan-17 92

XAC03-3320311W CT Make Up Water Tank - Rafter Clip Support Fit-up & Welding 3 06-Jan-17 10-Jan-17 92

XAC03-3320311X CT Make Up Water Tank - Outside Rafter Installation 2 06-Jan-17 09-Jan-17 92

XAC03-3320311Y CT Make Up Water Tank - Internal Structure Alignment & Bolt Tightening 3 06-Jan-17 10-Jan-17 92

XAC03-3320311Z CT Make Up Water Tank - Roof Plate Erection & Fit-up 3 06-Jan-17 10-Jan-17 92

XAC03-332031110 CT Make Up Water Tank - Roof Plate Fit-up Inspection & Welding 4 06-Jan-17 11-Jan-17 92

XAC03-332031120 CT Make Up Water Tank - Roof Plate Welding Seam NDE (PT) 2 06-Jan-17 09-Jan-17 92

XAC03-332031130 CT Make Up Water Tank - Anchor Chair Installation & Welding 3 06-Jan-17 10-Jan-17 92

XAC03-332031140 CT Make Up Water Tank - Anchor Bolts Installation & Grouting 3 06-Jan-17 10-Jan-17 92

XAC03-332031150 CT Make Up Water Tank - Downcomer Pipes Installation 4 06-Jan-17 11-Jan-17 92

XAC03-332031160 CT Make Up Water Tank - Final Inspection Before Water Filling Test 1 10-Jan-17 10-Jan-17 92

XAC03-332031170 CT Make Up Water Tank - Water Filling Test Preparation 1 10-Jan-17 10-Jan-17 92

XAC03-332031180 CT Make Up Water Tank - Full Water Test & Holding Time 6 11-Jan-17 17-Jan-17 92

XAC03-332031190 CT Make Up Water Tank - Settlement Inspection 4 12-Jan-17 17-Jan-17 92

XAC03-3320311A0 CT Make Up Water Tank - Drain Water & Internal C leanin g 3 18-Jan-17 20-Jan-17 92

XAC03-3320311B0 CT Make Up Water Tank - External Painting 25 18-Jan-17 15-Feb-17 92

XAC03-3320311C0 CT Make Up Water Tank - Internal Painting Shell & Roof 25 19-Jan-17 17-Feb-17 92

XAC03-3320311D0 CT Make Up Water Tank - External Painting Inspection 2 15-Feb-17 17-Feb-17 92

XAC03-3320311E0 CT Make Up Water Tank - Internal Painting Inspection for Shell & Roof 1 16-Feb-17 17-Feb-17 92

XAC03-3320311F0 CT Make Up Water Tank - Internal Scaffolding Removal Work 3 17-Feb-17 21-Feb-17 92

XAC03-3320311G0 CT Make Up Water Tank - Tank Labelling Work 2 17-Feb-17 20-Feb-17 92

XAC03-3320311H0 CT Make Up Water Tank - Internal Bottom Plate Welding 5 20-Feb-17 25-Feb-17 92

XAC03-3320311I0 CT Make Up Water Tank - External Scaffolding Removal Work 4 20-Feb-17 24-Feb-17 92

XAC03-3320311J0 CT Make Up Water Tank - Final Inspection (Including Painting) 2 27-Feb-17 01-Mar-17 92

XAC03-3320311K0 CT Make Up Water Tank - Hand-Over to TPSC 1 01-Mar-17 02-Mar-17 92

03PMS-BL00.3.3.2.04 Water
Wa Treatment Plant (Common) 158 01-Nov-16 03-May-17 13

03PMS-BL00.3.3.2.04.0 Interface 158 01-Nov-16 03-May-17 8

XAC03-3320402G Interface - CTO (WTP shed Column finish) 0 01-Nov-16 149

XAC03-3320401A Interface - MHO Lot 1 (Embedded Ports) 0 16-Nov-16* 68

XAC03-3320401B Interface - MHO Lot 2 (Main Equipments) 0 01-Dec-16* 55

XAC03-3320402A Interface - CTO (Clarifier / Sludge Thickener) 0 12-Dec-16* 87

XAC03-3320402B Interface - CTO (Sludge Container) 0 27-Dec-16* 87

XAC03-3320402C Interface - CTO (WTP Control Building) 0 05-Jan-17* 26

XAC03-3320402E Interface - CTO (Belt Press) 0 17-Jan-17* 72

XAC03-3320402F Interface - CTO (Buffer Tank) 0 03-Feb-17* 53

XAC03-3320402D Interface - CTO (Neutralization Pit) 0 03-Feb-17* 52

XAC03-33204030 Interface - MC 0 03-May-17* 8

XAC03-33204040 Interface - TOP 0 03-May-17 8

03PMS-BL00.3.3.2.04.1 Clarifier Installation 67 21-Nov-16 04-Feb-17 83

XAC03-33204110 Mobilization / Equipment, Material at site 10 21-Nov-16 01-Dec-16 55

XAC03-33204120 Clarifier Installation - Body and Sehll Assembly 12 02-Dec-16 16-Dec-16 83

XAC03-33204130 Clarifier Installation - Welding 27 17-Dec-16 17-Jan-17 83

XAC03-33204140 Clarifier Installation - Drive Unit and Agitator Installation 8 19-Jan-17 27-Jan-17 83

XAC03-33204150 Clarifier Installation - Platform Installation 3 28-Jan-17 31-Jan-17 83

XAC03-33204160 Clarifier Installation - Painting Work 4 01-Feb-17 04-Feb-17 83

03PMS-BL00.3.3.2.04.2 Filtering Pump, Clarified Water Pump, Belt Press Washing Pump, Air Blowers 20 13-Jan-17 04-Feb-17 83

XAC03-33204210 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 6 13-Jan-17 19-Jan-17 66
Chipping and Packer Setting
XAC03-33204220 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 2 20-Jan-17 21-Jan-17 66
Equipment on the Foundation
XAC03-33204230 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 6 23-Jan-17 28-Jan-17 66
Equipment Alignment
XAC03-33204240 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 6 30-Jan-17 04-Feb-17 83
Grouting
03PMS-BL00.3.3.2.04.3 Multi Media Filter (2 pcs) 12 06-Jan-17 20-Jan-17 96

XAC03-33204310 Multi Media Filter (2 pcs) - Chipping and Packer Setting 5 06-Jan-17 12-Jan-17 66

XAC03-33204320 Multi Media Filter (2 pcs) - Equipment on the Foundation 2 13-Jan-17 14-Jan-17 66

XAC03-33204330 Multi Media Filter (2 pcs) - Equipment Alignment 4 16-Jan-17 19-Jan-17 96

XAC03-33204340 Multi Media Filter (2 pcs) - Grouting 1 20-Jan-17 20-Jan-17 96

03PMS-BL00.3.3.2.04.4 Sludge Shute / Sludge Thickner / Sludge Container 11 03-Feb-17 16-Feb-17 73

XAC03-33204410 Sludge Shute / Sludge Thickner / Sludge Container - Chipping and Packer Setting 4 03-Feb-17 08-Feb-17 52

XAC03-33204420 Sludge Shute / Sludge Thickner / Sludge Container - Installation and Alignment 5 08-Feb-17 14-Feb-17 73

XAC03-33204430 Sludge Shute / Sludge Thickner / Sludge Container - Grouting 2 14-Feb-17 16-Feb-17 73

03PMS-BL00.3.3.2.04.5 Belt Press Unit 11 08-Feb-17 21-Feb-17 52

XAC03-33204510 Belt Press Unit - Chipping and Packer Setting 4 08-Feb-17* 13-Feb-17 52

XAC03-33204520 Belt Press Unit - Installation and Alignment 6 13-Feb-17 20-Feb-17 52

XAC03-33204530 Belt Press Unit - Grouting 1 20-Feb-17 21-Feb-17 52

03PMS-BL00.3.3.2.04.6 Chemical Tanks / Chemical Pumps 16 21-Feb-17 11-Mar-17 52

XAC03-33204610 Chemical Tanks / Chemical Pumps - Chipping and Packer Setting 6 21-Feb-17 28-Feb-17 52

XAC03-33204620 Chemical Tanks / Chemical Pumps - Installation and Alignment 6 28-Feb-17 07-Mar-17 52

XAC03-33204630 Chemical Tanks / Chemical Pumps - Grouting 4 07-Mar-17 11-Mar-17 52

03PMS-BL00.3.3.2.04.7 Piping Work 102 02-Dec-16 29-Mar-17 42

XAC03-33204710 Piping Work - Pipe Rack Installation 12 02-Dec-16 15-Dec-16 55

XAC03-33204720 Piping Work - Inside WTP 42 09-Dec-16 26-Jan-17 61

XAC03-33204730 Piping Work - Outside WTP 10 30-Jan-17 09-Feb-17 66

XAC03-33204740 Piping Work - Line Check 6 13-Mar-17 18-Mar-17 35

XAC03-33204750 Piping Work - Punch Clear 2 20-Mar-17 21-Mar-17 35

XAC03-33204760 Piping Work - Hydro Test 4 22-Mar-17 25-Mar-17 35

XAC03-33204770 Piping Work - Restoration 3 27-Mar-17 29-Mar-17 42

03PMS-BL00.3.3.2.04.8 WTP Area Electrical Work 65 11-Jan-17 25-Mar-17 23

XAC03-33204810 WTP Area Electrical Work - Cable Tray installation 26 11-Jan-17* 09-Feb-17 21

XAC03-33204820 WTP Area Electrical Work - Cabling and Termination Work 38 10-Feb-17 25-Mar-17 21

XAC03-33204830 WTP Area Electrical Work - Instrument and Tubing Installation 12 25-Feb-17 11-Mar-17 35

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:38 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
03PMS-BL00.3.3.2.04.9 WTP Electrical Room 131 02-Dec-16 03-May-17 8

XAC03-33204910 WTP Electrical Room - MCC Installation 6 02-Dec-16* 08-Dec-16 106

XAC03-33204920 WTP Electrical Room - Control Panel Installation 6 02-Dec-16 08-Dec-16 106

XAC03-33204930 WTP Electrical Room - Internal Cabling 8 10-Feb-17 18-Feb-17 51

XAC03-33204940 System Handover Walk Down 2 26-Apr-17 28-Apr-17 8

XAC03-33204950 Punch Clear 3 28-Apr-17 02-May-17 8

XAC03-33204960 Handover to Commissioning 1 02-May-17 03-May-17 8

03PMS-BL00.3.3.2.05 Condenser
Co 287 19-Sep-16 16-Aug-17 53

03PMS-BL00.3.3.2.05.0 Interface 287 19-Sep-16 16-Aug-17 53

XAC03-3320501A Interface - MHO Lot-1 Embedded Materials 0 19-Sep-16* 217

XAC03-33205020 Interface - CTO 0 15-Feb-17* 88

XAC03-3320501B Interface - MHO Lot-2 Main Equipments 0 03-Apr-17* 48

XAC03-33205030 Interface - MC 0 01-Aug-17* 66

XAC03-33205040 Interface - TOP 0 16-Aug-17* 53

03PMS-BL00.3.3.2.05.1 Mechanical Work 26 09-Mar-17 07-Apr-17 44

XAC03-33205110 Mechanical Work - Base Plate / Sliding Plate Setting 13 09-Mar-17 23-Mar-17 44

XAC03-33205120 Mechanical Work - Preparation of On Base 12 24-Mar-17 06-Apr-17 44

XAC03-33205130 Mechanical Work - On Base Work 1 07-Apr-17 07-Apr-17 44

03PMS-BL00.3.3.2.06 Cooling
Co Tower 244 21-Sep-16 28-Jun-17 2

03PMS-BL00.3.3.2.06.0 Interface 244 21-Sep-16 28-Jun-17 2

XAC03-3320601A Interface - MHO (Embedded Material) 0 21-Sep-16* 174

XAC03-3320601B Interface - MHO (Main Equipment) 0 02-Feb-17* 57

XAC03-33206020 Interface - CTO (Top slab) 0 15-Mar-17* 41

XAC03-33206030 Interface - MC 0 09-May-17 30

XAC03-33206040 Interface - TOP 0 28-Jun-17 2

03PMS-BL00.3.3.2.06.1 Mechanical Work 73 02-Feb-17 26-Apr-17 41

XAC03-33206110 Mechanical Work - Fin Assembly 20 02-Feb-17 24-Feb-17 57

XAC03-33206120 Mechanical Work - Scaffolding Installation 9 28-Feb-17 09-Mar-17 30

XAC03-33206130 Mechanical Work - Platform / Walk Way Installation 6 10-Mar-17 16-Mar-17 30

XAC03-33206150 Mechanical Work - Filling Installation 25 15-Mar-17 13-Apr-17 41

XAC03-33206140 Mechanical Work - Fan / Motor / Gear Box / Reducer Installation 9 16-Mar-17 27-Mar-17 30

XAC03-33206160 Mechanical Work - FRP Fan Stack Installation 1 28-Mar-17 28-Mar-17 55

XAC03-33206170 Mechanical Work - Distribution Pipe Installation 6 13-Apr-17 20-Apr-17 41

XAC03-33206180 Mechanical Work - Drift Eliminator Installation 2 18-Apr-17 20-Apr-17 41

XAC03-33206190 Mechanical Work - Distribution Pipe Installation 5 20-Apr-17 26-Apr-17 41

03PMS-BL00.3.3.2.06.2 Electrical Work 37 28-Mar-17 09-May-17 30

XAC03-33206210 Electrical Work - Conduits/Cabling/Termination 26 28-Mar-17 27-Apr-17 30

XAC03-33206220 Electrical Work - Megger Check & Continuity Cable 4 27-Apr-17 01-May-17 30

XAC03-33206230 Electrical Work - Handover to Commissioning Walkdown 1 02-May-17 02-May-17 30

XAC03-33206240 Electrical Work - Punch Clear 5 03-May-17 08-May-17 30

XAC03-33206250 Electrical Work - Handover to Commissioning 1 08-May-17 09-May-17 30

03PMS-BL00.3.3.2.07 Air
Ai Compressor System 134 13-Jan-17 16-Jun-17 199

03PMS-BL00.3.3.2.07.0 Interface 134 13-Jan-17 16-Jun-17 0

XAC03-33207010 Interface - MHO Air Compressor 0 13-Jan-17* 81

XAC03-33207020 Interface - CTO Air Compressor 0 19-Jan-17* 77

XAC03-33207030 Interface - MC Air Compressor 0 09-Mar-17* 81

XAC03-33207040 Interface - TOP Air Compressor 0 16-Jun-17* 0

03PMS-BL00.3.3.2.07.1 Air Compressor 6 17-Jan-17 25-Jan-17 73

XAC03-33207110 Air Compressor - Chipping and Packer Setting 4 17-Jan-17 23-Jan-17 73

XAC03-33207120 Air Compressor - Equipment Installation 2 23-Jan-17 25-Jan-17 73

03PMS-BL00.3.3.2.07.2 Dryer 5 18-Jan-17 24-Jan-17 73

XAC03-33207210 Dryer - Chipping and Packer Setting 4 18-Jan-17 23-Jan-17 73

XAC03-33207220 Dryer - Dryer Installation 1 23-Jan-17 24-Jan-17 73

03PMS-BL00.3.3.2.07.3 Air Receiver Tank 5 18-Jan-17 24-Jan-17 73

XAC03-33207310 Air Reciever Tank - Chipping and Packer Setting 4 18-Jan-17 23-Jan-17 73

XAC03-33207320 Air Reciever Tank - Air Receiver Tank Installation 1 23-Jan-17 24-Jan-17 73

03PMS-BL00.3.3.2.07.4 Piping Work 28 25-Jan-17 25-Feb-17 295

XAC03-33207410 Piping Work - Compressor to Air recieving Tank 25 25-Jan-17 22-Feb-17 91

XAC03-33207420 Piping Work - Pneumatic Test 5 20-Feb-17 25-Feb-17 295

XAC03-33207430 Piping Work - Punch Clear 3 22-Feb-17 25-Feb-17 91

03PMS-BL00.3.3.2.07.5 Electrical / C&I Work 64 02-Mar-17 15-May-17 227

XAC03-33207520 Handover to Commissioning Walkdown 1 02-Mar-17 03-Mar-17 81

XAC03-33207530 Punch Clear 3 03-Mar-17 07-Mar-17 81

XAC03-33207540 Handover to Commissioning 1 08-Mar-17 09-Mar-17 81

XAC03-33207510 Conduits/Cabling/Termination 13 01-May-17 15-May-17 227

03PMS-BL00.3.3.2.09 Co
Condenser Ball Cleaning System 169 23-Jan-17 07-Aug-17 61

03PMS-BL00.3.3.2.09.0 Interface 169 23-Jan-17 07-Aug-17 61

XAC03-33209020 Interface - CTO 0 23-Jan-17 89

XAC03-33209010 Interface - MHO - Ball Cleaning Equipment 0 13-Feb-17* 71

XAC03-33209030 Interface - MC 0 15-Jul-17* 71

XAC03-33209040 Interface - TOP 0 07-Aug-17* 61

03PMS-BL00.3.3.2.09.1 Mechanical Work 3 13-Feb-17 15-Feb-17 71

XAC03-33209110 Mechanical Work - Ball Cleaning Equipment Installation 3 13-Feb-17 15-Feb-17 71

03PMS-BL00.3.3.2.09.2 Piping Work 21 21-Jun-17 14-Jul-17 72

XAC03-33209210 Piping Work - Site Installation 12 21-Jun-17 04-Jul-17 71

XAC03-33209220 Piping Work - Hydro Test 6 05-Jul-17 11-Jul-17 72

XAC03-33209230 Piping Work - Flushing/Air Blow 3 12-Jul-17 14-Jul-17 72

03PMS-BL00.3.3.2.09.3 Electrical/C&I Work 17 26-Jun-17 14-Jul-17 72

XAC03-33209310 Electrical / C&I Work - Conduits 12 26-Jun-17 08-Jul-17 72

XAC03-33209320 Electrical / C&I Work - Cabling & Termination Works 3 10-Jul-17 12-Jul-17 72

XAC03-33209330 Electrical / C&I Work - Megger Check & Continuity Cable 2 13-Jul-17 14-Jul-17 72

03PMS-BL00.3.3.2.09.4 Instrument Work 11 04-Jul-17 15-Jul-17 71

XAC03-33209410 Instrument - Instrument Install 2 04-Jul-17 05-Jul-17 71

XAC03-33209420 Instrument - Instrument Tubing 4 06-Jul-17 10-Jul-17 71

XAC03-33209430 Instrument - Tubing Leak Test 1 11-Jul-17 11-Jul-17 71

XAC03-33209440 Instrument - System Handover Walk Down 1 12-Jul-17 12-Jul-17 71

XAC03-33209450 Instrument - Punch Clear 2 13-Jul-17 14-Jul-17 71

XAC03-33209460 Instrument - Handover to Commissioning 1 15-Jul-17 15-Jul-17 71

03PMS-BL00.3.3.2.10 Ch
Chemical dosing system for HRSG Unit #30 109 20-Mar-17 24-Jul-17 33

03PMS-BL00.3.3.2.10.0 Interface 109 20-Mar-17 24-Jul-17 33

XAC03-33210010 Interface - MHO (Skid) 0 20-Mar-17* 77

XAC03-33210020 Interface - CTO 0 09-May-17* 33

XAC03-33210030 Interface - MC (H/O to Civil for Shed) 0 16-Jun-17* 33

XAC03-33210040 Interface - TOP 0 24-Jul-17* 33

03PMS-BL00.3.3.2.10.1 Mechanical Work 3 10-May-17 12-May-17 33

XAC03-33210110 Mechianical Workv - HRSG Chemical Dosing Skid Installation 3 10-May-17 12-May-17 33

03PMS-BL00.3.3.2.10.2 Pipe #31 15 12-May-17 30-May-17 33

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:39 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33210210 Piping work #31 15 12-May-17 30-May-17 33

03PMS-BL00.3.3.2.10.3 Pipe #32 15 30-May-17 16-Jun-17 33

XAC03-33210310 Piping work #32 15 30-May-17 16-Jun-17 33

03PMS-BL00.3.3.2.10.4 Electrical/C&I Work 54 12-May-17 13-Jul-17 33

XAC03-33210410 Electrical/C&I Work - Panel Installation 1 12-May-17 13-May-17 58

XAC03-33210420 Electrical/C&I Work - Conduit/ Cabling 4 15-May-17 18-May-17 58

XAC03-33210430 Electrical/C&I Work - Handover to Commissioning Walkdown 1 07-Jul-17 07-Jul-17 33

XAC03-33210440 Electrical/C&I Work - Punch Clear 4 08-Jul-17 12-Jul-17 33

XAC03-33210450 Electrical/C&I Work - Handover to Commissioning 1 13-Jul-17 13-Jul-17 33

03PMS-BL00.3.3.2.11 Ch
Chemical dosing system for CT Unit #30 142 16-Jan-17 28-Jun-17 2

03PMS-BL00.3.3.2.11.0 Interface 142 16-Jan-17 28-Jun-17 2

XAC03-33211020 Interface - CTO (Skid foundation) 0 16-Jan-17* 107

XAC03-33211010 Interface - MHO (Skid) 0 21-Mar-17* 52

XAC03-33211030 Interface - MC (H/O to Civil for Shed) 0 23-Mar-17 72

XAC03-33211040 Interface - TOP 0 28-Jun-17 2

03PMS-BL00.3.3.2.11.1 Mechanical Work 25 21-Mar-17 18-Apr-17 52

XAC03-33211110 Mechanical Work - CT Chemical Dosing Skid Installation 3 21-Mar-17 23-Mar-17 52

XAC03-33211120 Mechanical Work - Pipe Installation 19 23-Mar-17 14-Apr-17 52

XAC03-33211130 Mechanical Work - Hydro Test 2 14-Apr-17 17-Apr-17 52

XAC03-33211140 Mechanical Work - Restoration 1 17-Apr-17 18-Apr-17 52

03PMS-BL00.3.3.2.11.2 Electrical/C&I Work 13 23-Mar-17 07-Apr-17 60

XAC03-33211210 Electrical/C&I Work - Panel Installation 2 23-Mar-17 25-Mar-17 60

XAC03-33211220 Electrical/C&I Work - Conduit/ Cabling 11 25-Mar-17 07-Apr-17 60

03PMS-BL00.3.3.2.13 HVAC
HV 163 05-Dec-16 10-Jun-17 205

03PMS-BL00.3.3.2.13.0 Interface 163 05-Dec-16 10-Jun-17 205

XAC03-3321301A Interface - MHO-WTP 0 05-Dec-16* 123

XAC03-3321302F Interface - CTO-HRSG Local Control Compartment 0 10-Dec-16 170

XAC03-3321303D Interface - MC - HRSG Local Control Compartment 0 17-Dec-16 356

XAC03-3321301B Interface - MHO-EC Bldg 0 30-Dec-16* 63

XAC03-3321302C Interface - CTO-EC Bldg (1F SWGR Room) 0 30-Dec-16* 63

XAC03-3321302D Interface - CTO-EC Bldg (2F HVAC Room) 0 12-Jan-17 64

XAC03-3321301C Interface - MHO-ST Bldg 0 01-Feb-17* 167

XAC03-3321302A Interface - CTO-WTP 0 08-Feb-17* 66

XAC03-3321302E Interface - CTO-EC Bldg (3F CCR) 0 14-Feb-17* 38

XAC03-3321303A Interface - MC-WTP 0 24-Feb-17* 66

XAC03-3321303C Interface - MC-EC Bldg 0 03-Mar-17* 38

XAC03-3321302B Interface - CTO-ST Bldg 0 06-Apr-17* 110

XAC03-3321303B Interface - MC-ST Bldg 0 10-Jun-17 110

03PMS-BL00.3.3.2.13.1 WTP 14 09-Feb-17 24-Feb-17 66

XAC03-33213110 WTP - AC Unit Installation 14 09-Feb-17 24-Feb-17 66

03PMS-BL00.3.3.2.13.2 ECB Ground Floor 17 03-Mar-17 23-Mar-17 47

XAC03-33213210 HVAC Installation - GF Fan Installation 17 03-Mar-17 23-Mar-17 47

03PMS-BL00.3.3.2.13.3 ECB 1st Floor (Switchgear Room) 12 16-Jan-17 30-Jan-17 49

XAC03-33213310 HVAC Installation - 1F Duct Installation 12 16-Jan-17 30-Jan-17 49

03PMS-BL00.3.3.2.13.4 EC BLDG 2nd Floor 64 30-Jan-17 13-Apr-17 49

XAC03-33213410 HVAC Installation - 2F Duct Installation 17 30-Jan-17 18-Feb-17 49

XAC03-33213420 HVAC Installation - Unit Installation 47 20-Feb-17 13-Apr-17 49

03PMS-BL00.3.3.2.13.5 EC Bldg 3rd Floor 19 14-Feb-17 09-Mar-17 39

XAC03-33213510 HVAC Installation - 3F Duct Installation 14 14-Feb-17 02-Mar-17 38

XAC03-33213520 HVAC Installation - Partial Energize (for DCS) 5 03-Mar-17 09-Mar-17 39

03PMS-BL00.3.3.2.13.6 ST Bldg 56 07-Apr-17 10-Jun-17 110

XAC03-33213610 ST Bldg - Ventillation Fan Installation 21 07-Apr-17 01-May-17 110

XAC03-33213620 ST Bldg - Conduit & Cabling Work 30 01-May-17 05-Jun-17 110

XAC03-33213630 ST Bldg - Ventillation Commissioning 5 05-Jun-17 10-Jun-17 110

XAC03-33213640 ST Bldg - Ready for In-Service 0 10-Jun-17 110

03PMS-BL00.3.3.2.13.7 HRSG Local Control Compartment 6 10-Dec-16 17-Dec-16 170

XAC03-33213710 HRSG Local Control Compartment - HVAC System - Install AC Unit 6 10-Dec-16 17-Dec-16 170

03PMS-BL00.3.3.2.14 Fir
Fire Fighting System 272 05-Sep-16 15-Jul-17 175

03PMS-BL00.3.3.2.14.0 Interface 272 05-Sep-16 15-Jul-17 175

XAC03-3321401A Interface - MHO for Fire Fighting Ring Main & Others 0 05-Sep-16* 143

XAC03-3321402F Interface - CTO for HRSG 0 01-Nov-16 360

XAC03-3321402A Interface - CTO for Transformer Area(GSUT) 0 21-Nov-16 99

XAC03-3321402B Interface - CTO for Fire Fighting Pump Station 0 30-Nov-16* 93

XAC03-3321401B Interface - MHO for Pump Station 0 05-Dec-16* 89

XAC03-3321402C Interface - CTO for E&C Biulding For Ground Floor 0 17-Dec-16* 72

XAC03-3321403B Interface - MC for Pump Station 0 03-Jan-17* 105

XAC03-3321404E Interface - Erection Hand over Transformer Area (ABPR3) 0 18-Apr-17* 92

XAC03-3321402D Interface - CTO for WTP 0 20-Apr-17* 235

XAC03-3321403C Interface - MC for E&C Biulding 0 20-Apr-17* 22

XAC03-3321404B Interface - TOP For E&C Building 0 24-Apr-17 19

XAC03-3321402E Interface - CTO for STG 0 12-May-17* 99

XAC03-3321403A Interface - MC for Transformer Area (ABPR3) 0 18-May-17* 66

XAC03-3321404A Interface - TOP for Transformer Area (ABPR3) 0 29-May-17* 56

XAC03-3321403E Interface - MC for STG 0 15-Jun-17* 106

XAC03-3321403D Interface - MC for WTP 0 19-Jun-17* 183

XAC03-3321403F Interface - MC for HRSG 0 19-Jun-17* 183

XAC03-3321404C Interface - TOP for WTP 0 05-Jul-17 183

XAC03-3321404F Interface - TOP for HRSG 0 05-Jul-17 183

XAC03-3321404D Interface - TOP for STG 0 15-Jul-17* 80

03PMS-BL00.3.3.2.14.1 WTP Area 22 02-Nov-16 26-Nov-16 359

XAC03-33214110 Fire Alarm System - Devices, Conduit, Cabling Installation 22 02-Nov-16* 26-Nov-16 359

03PMS-BL00.3.3.2.14.2 Transformer Area 131 21-Dec-16 20-May-17 63

03PMS-BL00.3.3.2.14.2.1 GT 31 GSUT
03PMS-BL00.3.3.2.14.2 38 31-Mar-17 15-May-17 8

XAC03-33214211 GT 31 GSUT - Scaffolding Work Including Inspection 4 31-Mar-17* 05-Apr-17 8

XAC03-33214212 GT 31 GSUT - Support Installation & Piping Work 18 05-Apr-17 26-Apr-17 8

XAC03-33214213 GT 31 GSUT - Line Check & Punch Clearing 5 26-Apr-17 02-May-17 8

XAC03-33214214 GT 31 GSUT - Hydro-Test 3 02-May-17 05-May-17 8

XAC03-33214215 GT 31 GSUT - Painting Work 6 05-May-17 12-May-17 8

XAC03-33214216 GT 31 GSUT - Painting Inspection & Remove Scaffolding 2 12-May-17 15-May-17 8

03PMS-BL00.3.3.2.14.2.2 GT 32 GSUT
03PMS-BL00.3.3.2.14.2 38 31-Mar-17 15-May-17 68

XAC03-33214221 GT 32 GSUT - Scaffolding Work Including Inspection 4 31-Mar-17 05-Apr-17 16

XAC03-33214222 GT 32 GSUT - Support Installation & Piping Work 18 05-Apr-17 26-Apr-17 16

XAC03-33214223 GT 32 GSUT - Line Check & Punch Clearing 5 26-Apr-17 02-May-17 16

XAC03-33214224 GT 32 GSUT - Hydro-Test 3 02-May-17 05-May-17 16

XAC03-33214225 GT 32 GSUT - Painting Work 6 05-May-17 12-May-17 16

XAC03-33214226 GT 32 GSUT - Painting Inspection & Remove Scaffolding 2 12-May-17 15-May-17 68

03PMS-BL00.3.3.2.14.2.3 ST 3 GSUT
03PMS-BL00.3.3.2.14.2 39 01-Apr-17 17-May-17 66

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:40 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33214231 ST 3 GSUT - Scaffolding Work Including Inspection 5 01-Apr-17 07-Apr-17 66

XAC03-33214232 ST 3 GSUT - Support Installation & Piping Work 18 07-Apr-17 28-Apr-17 66

XAC03-33214233 ST 3 GSUT - Line Check & Punch Clearing 5 28-Apr-17 04-May-17 66

XAC03-33214234 ST 3 GSUT - Hydro-Test 2 04-May-17 06-May-17 66

XAC03-33214235 ST 3 GSUT - Painting Work 6 06-May-17 13-May-17 66

XAC03-33214236 ST 3 GSUT - Painting Inspection & Remove Scaffolding 3 13-May-17 17-May-17 66

03PMS-BL00.3.3.2.14.2.4 Unit Auxiliary Trans 31 & 32


03PMS-BL00.3.3.2.14.2 113 11-Jan-17 20-May-17 63

XAC03-33214241 Unit Auxilliary Trans. 31 & 32 - Scaffolding Work Including Inspction 3 11-Jan-17* 13-Jan-17 77

XAC03-33214242 Unit Auxilliary Trans. 31 & 32 - Support Installation & Piping Work 21 14-Jan-17 07-Feb-17 77

XAC03-33214244 Unit Auxilliary Trans. 31 & 32 - Line Check & Punch Clearing 4 08-Feb-17 11-Feb-17 77

XAC03-33214245 Unit Auxilliary Trans. 31 & 32 - Hydro-Test 2 13-Feb-17 14-Feb-17 77

XAC03-33214246 Unit Auxilliary Trans. 31 & 32 - Painting Work 6 15-Feb-17 21-Feb-17 77

XAC03-33214247 Unit Auxilliary Trans. 31 & 32 - Painting Inspection & Remove Scaffolding 3 22-Feb-17 24-Feb-17 77

XAC03-33214243 Unit Auxilliary Trans. 31 & 32 - Conduit and Cabling Work 39 05-Apr-17 20-May-17 63

03PMS-BL00.3.3.2.14.2.5 LV Transformer
03PMS-BL00.3.3.2.14.2 62 21-Dec-16 01-Mar-17 73

XAC03-33214251 LV Transformer - Fire Fighting System - Scaffolding Work Including Inspction 14 21-Dec-16* 05-Jan-17 73

XAC03-33214252 LV Transformer - Fire Fighting System - Support Installation & Piping Work 26 06-Jan-17 04-Feb-17 73

XAC03-33214253 LV Transformer - Fire Fighting System - Line Check & Punch Clearing 6 06-Feb-17 11-Feb-17 73

XAC03-33214254 LV Transformer - Fire Fighting System - Hydro-Test 6 13-Feb-17 18-Feb-17 73

XAC03-33214255 LV Transformer - Fire Fighting System - Painting Work 6 20-Feb-17 25-Feb-17 73

XAC03-33214256 LV Transformer - Fire Fighting System - Painting Inspection & Remove Scaffolding 3 27-Feb-17 01-Mar-17 73

03PMS-BL00.3.3.2.14.3 E & C Building 86 30-Jan-17 09-May-17 32

03PMS-BL00.3.3.2.14.3.1 Ground Floor Sprinkle


03PMS-BL00.3.3.2.14.3 43 30-Jan-17 21-Mar-17 34

XAC03-33214311 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Support Installation & Piping Work 27 30-Jan-17 02-Mar-17 34

XAC03-33214312 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Line Check & Punch Clearing 6 02-Mar-17 09-Mar-17 34

XAC03-33214313 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Hydro-Test 3 09-Mar-17 13-Mar-17 34

XAC03-33214314 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Painting Work 6 13-Mar-17 20-Mar-17 34

XAC03-33214315 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Painting Inspection 1 20-Mar-17 21-Mar-17 34

03PMS-BL00.3.3.2.14.3.2 Hydrant installation (1st FL - 3rd FL)


03PMS-BL00.3.3.2.14.3 70 30-Jan-17 20-Apr-17 19

XAC03-33214321 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Support Installation & 61 30-Jan-17* 10-Apr-17 19
Piping Work
XAC03-33214322 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Line Check & Punch 2 10-Apr-17 12-Apr-17 19
Clearing
XAC03-33214323 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Hydro-Test 3 12-Apr-17 15-Apr-17 19

XAC03-33214324 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Painting Work 2 15-Apr-17 18-Apr-17 19

XAC03-33214325 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Painting Inspection 2 18-Apr-17 20-Apr-17 19

03PMS-BL00.3.3.2.14.3.3 Fire Alarm System


03PMS-BL00.3.3.2.14.3 86 30-Jan-17 09-May-17 32

XAC03-33214331 Fire Alarm System - 1F Fire Alarm Installation 26 30-Jan-17* 01-Mar-17 32

XAC03-33214332 Fire Alarm System - 2F Fire Alarm Installation 33 01-Mar-17 08-Apr-17 32

XAC03-33214333 Fire Alarm System - 3F Fire Alarm Installation 26 08-Apr-17 09-May-17 32

03PMS-BL00.3.3.2.14.4 STG Area 36 12-May-17 22-Jun-17 99

03PMS-BL00.3.3.2.14.4.1 Indoor Hydrant


03PMS-BL00.3.3.2.14.4 36 12-May-17 22-Jun-17 99

XAC03-33214411 Indoor Hydrant - Scaffolding Work Including Inspection 4 12-May-17* 16-May-17 99

XAC03-33214412 Indoor Hydrant - Support Installation & Piping Work 18 17-May-17 06-Jun-17 99

XAC03-33214413 Indoor Hydrant - Line Check & Punch Clearing 3 07-Jun-17 09-Jun-17 99

XAC03-33214414 Indoor Hydrant - Hydro-Test 2 10-Jun-17 12-Jun-17 99

XAC03-33214415 Indoor Hydrant - Painting Work 6 13-Jun-17 19-Jun-17 99

XAC03-33214416 Indoor Hydrant - Painting Inspection & Remove Scaffolding 3 20-Jun-17 22-Jun-17 99

03PMS-BL00.3.3.2.14.4.2 Fire Alarm System


03PMS-BL00.3.3.2.14.4 34 12-May-17 20-Jun-17 101

XAC03-33214421 Fire Alarm Install - STG 4 Hall 8 12-May-17* 20-May-17 101

XAC03-33214422 Fire Alarm Install - STG Building (Lube Oil & Transfer) 26 22-May-17 20-Jun-17 101

03PMS-BL00.3.3.2.14.6 Pump Station 72 30-Nov-16 20-Feb-17 70

03PMS-BL00.3.3.2.14.6.1 Mechanical Work


03PMS-BL00.3.3.2.14.6 13 30-Nov-16 14-Dec-16 121

XAC03-33214611 Mechanical Work - Padding Work 3 30-Nov-16 02-Dec-16 122

XAC03-33214612 Mechanical Work - On Base Diesel/Electric/Jucky Pump/Fuel Oil Tank 3 05-Dec-16 07-Dec-16 121

XAC03-33214613 Mechanical Work - Anchor Bolt Grouting 3 08-Dec-16 10-Dec-16 121

XAC03-33214614 Mechanical Work - Base Grouting 3 10-Dec-16 14-Dec-16 121

03PMS-BL00.3.3.2.14.6.2 Piping Work - FF Pumps, Sunction, Discharge & Recirculating Line


03PMS-BL00.3.3.2.14.6 48 30-Nov-16 24-Jan-17 93

XAC03-33214621 FF Pumps Suction, Discharge & Recirculation Line - Scaffolding Work Including 3 30-Nov-16 02-Dec-16 65
Inspection
XAC03-33214622 FF Pumps Suction, Discharge & Recirculation Line - Support Installation & Piping Work 25 06-Dec-16 03-Jan-17 63

XAC03-33214623 FF Pumps Suction, Discharge & Recirculation Line - Line Check & Punch Clearing 6 04-Jan-17 10-Jan-17 63

XAC03-33214624 FF Pumps Suction, Discharge & Recirculation Line - Hydro-Test 3 11-Jan-17 13-Jan-17 63

XAC03-33214625 FF Pumps Suction, Discharge & Recirculation Line - Painting Work 6 13-Jan-17 20-Jan-17 93

XAC03-33214626 FF Pumps Suction, Discharge & Recirculation Line - Painting Inspection & Remove 3 20-Jan-17 24-Jan-17 93
Scaffolding
03PMS-BL00.3.3.2.14.6 Electrical / C&I Work
03PMS-BL00.3.3.2.14.6.3 32 13-Jan-17 20-Feb-17 63

XAC03-33214631 Electrical / C&I Work - Cable Tray & Support 3 13-Jan-17 17-Jan-17 63

XAC03-33214632 Electrical / C&I Work - Cable Pulling/Termination 15 18-Jan-17 03-Feb-17 63

XAC03-33214633 Electrical / C&I Work - Instrument installation 6 03-Feb-17 10-Feb-17 63

XAC03-33214634 Electrical / C&I Work - Handover to Commissioning Walkdown 1 10-Feb-17 11-Feb-17 63

XAC03-33214635 Electrical / C&I Work - Punch Clear 6 11-Feb-17 18-Feb-17 63

XAC03-33214636 Electrical / C&I Work - Handover to Commissioinng 1 18-Feb-17 20-Feb-17 63

03PMS-BL00.3.3.2.14.7 Ring Main Pipe Installation 64 05-Sep-16 16-Nov-16 153

03PMS-BL00.3.3.2.14.7.1 Underground HDPE Pipe


03PMS-BL00.3.3.2.14.7 57 05-Sep-16 09-Nov-16 160

XAC03-33214711 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - Excavation & Sand Bedding Including 6 05-Sep-16* 10-Sep-16 160
Density Test (by TPSC)
XAC03-33214712 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - HDPE Pipe Line-up & Welding Work 4 12-Sep-16 15-Sep-16 160

XAC03-33214713 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - Hydro-Test 2 16-Sep-16 17-Sep-16 160

XAC03-33214714 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - Backfilling Including Density Test (by 6 19-Sep-16 24-Sep-16 160
TPSC)
XAC03-33214715 U/G HDPE Pipe - HRGS 31 to STG Bldg Area - Excavation & Sand Bedding Including 6 26-Sep-16 01-Oct-16 160
Density Test (by TPSC)
XAC03-33214716 U/G HDPE Pipe - HRGS 31 to STG Bldg Area - HDPE Pipe Line-up & Welding Work 4 03-Oct-16 06-Oct-16 160

XAC03-33214717 U/G HDPE Pipe - HRGS 31 to STG Bldg Area - Hydro-Test 3 07-Oct-16 10-Oct-16 160

XAC03-33214718 U/G HDPE Pipe Installation - HRGS 31 to STG Bldg Area - Backfilling Including Density 6 11-Oct-16 17-Oct-16 160
Test (by TPSC)
XAC03-33214719 U/G HDPE Pipe - GSUT & UAT Area - Excavation & Sand Bedding Including Density 6 18-Oct-16 24-Oct-16 160
Test (by TPSC)
XAC03-3321471A U/G HDPE Pipe - GSUT & UAT Area - HDPE Pipe Line-up & Welding Work 4 25-Oct-16 28-Oct-16 160

XAC03-3321471B U/G HDPE Pipe - GSUT & UAT Area - Hydro-Test 3 29-Oct-16 01-Nov-16 160

XAC03-3321471C U/G HDPE Pipe - GSUT & UAT Area - Backfilling Including Density Test (by TPSC) 6 02-Nov-16 09-Nov-16 160

03PMS-BL00.3.3.2.14.7.2 Aboveground Steel Pipe


03PMS-BL00.3.3.2.14.7 31 12-Oct-16 16-Nov-16 153

XAC03-33214721 A/G Steel Pipe - A/G Pipe on Pipe Sleeper (WTP Area) 12 12-Oct-16* 25-Oct-16 160

XAC03-33214722 A/G Steel Pipe - A/G Pipe on Pipe Sleeper (Tank Ar ea) 12 12-Oct-16* 25-Oct-16 160

XAC03-33214723 A/G Steel Pipe - A/G Pipe on Pipe Rack (South-2 Area 13.5m) 6 02-Nov-16* 08-Nov-16 154

XAC03-33214724 A/G Steel Pipe - A/G Pipe on Pipe Rack (South-1 Area 18m) 6 10-Nov-16* 16-Nov-16 153

03PMS-BL00.3.3.2.14.8 EDG Area 12 25-Feb-17 10-Mar-17 284

XAC03-33214810 EDG - Sprinkler System - Marking and Check Location 1 25-Feb-17* 25-Feb-17 284

XAC03-33214820 EDG - Sprinkler System - Piping and Support Fabrication 2 27-Feb-17 28-Feb-17 284

XAC03-33214880 EDG - Fire Alarm - Conduit/Cableing Termination 5 27-Feb-17 03-Mar-17 290

XAC03-33214830 EDG - Sprinkler System - Support Installation & Piping Work 4 01-Mar-17 04-Mar-17 284

XAC03-33214840 EDG - Sprinkler System - Line Check before Hydro Test 1 06-Mar-17 06-Mar-17 284

XAC03-33214850 EDG - Sprinkler System - Hydro Test 1 07-Mar-17 07-Mar-17 284

XAC03-33214860 EDG - Sprinkler System - Painting Work 2 08-Mar-17 09-Mar-17 284

XAC03-33214870 EDG - Sprinkler System - Painting Inspection and Punch Clearing 1 10-Mar-17 10-Mar-17 284

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:41 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
03PMS-BL00.3.3.2.14.9 HRSG Area 22 02-Nov-16 26-Nov-16 360

XAC03-33214910 Fire Alarm System - Devices, Conduit, Cabling Installation 22 02-Nov-16* 26-Nov-16 360

03PMS-BL00.3.3.2.15 11
115kV Switch Yard 216 30-Sep-16 08-Jun-17 207

03PMS-BL00.3.3.2.15.1 Interface 216 30-Sep-16 08-Jun-17 207

XAC03-3321501A Interface - ABPR3 SWYD MHO-1 (Embedded material) 0 30-Sep-16* 423

XAC03-3321501C Interface - ABPR3 SWYD MHO-3 (Main Equipment & AC/DC Panel) 0 15-Dec-16* 79

XAC03-3321501B Interface - ABPR3 SWYD MHO-2 (Structures) 0 15-Dec-16* 267

XAC03-3321502A Interface - ABPR3 SWYD CTO 0 24-Dec-16* 258

XAC03-3321501D Interface - ABPR3 SWYD MHO-4 (Protection Panels ABPR3) 0 15-Feb-17* 36

XAC03-3321503A Interface - ABPR3 SWYD MC (H/O to TPSC commissionig) 0 29-Apr-17 1

XAC03-3321504A Interface - ABPR3 SWYD TOP 0 08-Jun-17 0

XAC03-3321504B Interface - Ready for 115kV Backfeeding (ABPR3) 0 08-Jun-17 0

03PMS-BL00.3.3.2.15.2 Take off Structure (ABPR 3) 25 24-Dec-16 23-Jan-17 325

XAC03-33215210 Structure Work - Take off Structure 25 24-Dec-16 23-Jan-17 325

03PMS-BL00.3.3.2.15.3 Equipment Installation 101 15-Dec-16 10-Apr-17 258

03PMS-BL00.3.3.2.15.3.1 115 kV ABPR-3 Main Bus No.1


03PMS-BL00.3.3.2.15.3 48 24-Dec-16 17-Feb-17 302

XAC03-33215311 Lifting Steel Support For Main Bus No.1 1 24-Dec-16 26-Dec-16 258

XAC03-33215312 Install Steel Support For Main Bus No.1 5 26-Dec-16 31-Dec-16 308

XAC03-33215313 Lifting Steel Support For CVT -Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258

XAC03-33215314 Lifting Steel Support For Main Bus No.1-Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258

XAC03-33215315 Install Steel Support For Main Bus No.1-Pile Deviated FDN. 5 02-Jan-17 07-Jan-17 302

XAC03-33215316 Install Steel Support For CVT Main Bus No.1-Pile Deviated 5 02-Jan-17 07-Jan-17 258

XAC03-33215317 Install Station Post Insulator 115 kV 15 07-Jan-17 25-Jan-17 302

XAC03-33215318 Install CVT 115 kV included Junction Box 15 07-Jan-17 25-Jan-17 302

XAC03-33215319 AL Tube - Assembly AL Tube on ground 14 31-Jan-17 16-Feb-17 302

XAC03-3321531A AL Tube - Lifting AL tube and Fixing-(After lifting PASS M00) 1 16-Feb-17 17-Feb-17 302

03PMS-BL00.3.3.2.15.3.2 115 kV APBR-3 Main Bus No.2


03PMS-BL00.3.3.2.15.3 48 24-Dec-16 17-Feb-17 302

XAC03-33215321 Lifting Steel Support For Main Bus No.2 1 24-Dec-16 26-Dec-16 258

XAC03-33215322 Install Steel Support For Main Bus No.2 5 26-Dec-16 31-Dec-16 258

XAC03-33215323 Lifting Steel Support For Main Bus No.2-Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258

XAC03-33215324 Lifting Steel Support For CVT -Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258

XAC03-33215325 Install Steel Support For Main Bus No.2-Pile Deviated FDN. 5 02-Jan-17 07-Jan-17 307

XAC03-33215326 Install Steel Support For CVT Main Bus No.2-Pile Deviated 5 02-Jan-17 07-Jan-17 258

XAC03-33215327 Install Station Post Insulator 115 kV 15 07-Jan-17 25-Jan-17 307

XAC03-33215328 Install CVT 115 kV included Junction Box 15 07-Jan-17 25-Jan-17 302

XAC03-33215329 AL Tube - Assembly AL Tube on ground 14 31-Jan-17 16-Feb-17 302

XAC03-3321532A AL Tube - Lifting AL tube and Fixing-(After lifting PASS M00) 1 16-Feb-17 17-Feb-17 302

03PMS-BL00.3.3.2.15.3.3 Bay Industrial Substation-I (T7)


03PMS-BL00.3.3.2.15.3 35 07-Jan-17 17-Feb-17 277

XAC03-33215331 Lifting Steel Support For CVT+ES,CVT,LA 1 07-Jan-17 09-Jan-17 258

XAC03-33215332 Install Steel Support CVT +ES 5 09-Jan-17 14-Jan-17 258

XAC03-33215333 Install Steel Support For CVT 6 14-Jan-17 21-Jan-17 258

XAC03-33215334 Install Steel Support For LA 6 14-Jan-17 21-Jan-17 258

XAC03-33215335 Install TOS 15 16-Jan-17 02-Feb-17 277

XAC03-33215336 Lifting TOS 1 02-Feb-17 03-Feb-17 278

XAC03-33215337 PASS M00 - Unload/Unpack PASS M00 1 02-Feb-17 03-Feb-17 277

XAC03-33215338 PASS M00 - Lifting onto Foundation 1 04-Feb-17 06-Feb-17 277

XAC03-33215339 PASS M00 - Install PASS M00 3 06-Feb-17 09-Feb-17 277

XAC03-3321533A Lifting CVT ES and LA 1 09-Feb-17 10-Feb-17 277

XAC03-3321533B Install CVT and Junction Box 5 10-Feb-17 16-Feb-17 278

XAC03-3321533C Install ES 5 10-Feb-17 16-Feb-17 278

XAC03-3321533D Install LA 6 10-Feb-17 17-Feb-17 277

03PMS-BL00.3.3.2.15.3.4 Bay Industrial Substation-II (T8)


03PMS-BL00.3.3.2.15.3 36 21-Jan-17 03-Mar-17 277

XAC03-33215341 Lifting Steel Support For CVT+ES,CVT,LA 1 21-Jan-17 23-Jan-17 258

XAC03-33215342 Install Steel Support CVT +ES 5 23-Jan-17 28-Jan-17 258

XAC03-33215343 Install Steel Support For CVT 6 28-Jan-17 04-Feb-17 258

XAC03-33215344 Install Steel Support For LA 6 28-Jan-17 04-Feb-17 258

XAC03-33215345 Install TOS 15 30-Jan-17 16-Feb-17 279

XAC03-33215349 Lifting TOS 1 16-Feb-17 17-Feb-17 279

XAC03-33215346 PASS M00 - Unload/Unpack PASS M00 1 17-Feb-17 17-Feb-17 277

XAC03-33215347 PASS M00 - Lifting onto Foundation 1 20-Feb-17 20-Feb-17 277

XAC03-33215348 PASS M00 - Install PASS M00 3 20-Feb-17 23-Feb-17 277

XAC03-3321534A Lifting CVT ES and LA 1 23-Feb-17 24-Feb-17 277

XAC03-3321534B Install CVT and Junction Box 5 24-Feb-17 02-Mar-17 278

XAC03-3321534C Install ES 5 24-Feb-17 02-Mar-17 278

XAC03-3321534D Install LA 6 24-Feb-17 03-Mar-17 277

03PMS-BL00.3.3.2.15.3.5 Bay Terminal Substation (T6)


03PMS-BL00.3.3.2.15.3 36 04-Feb-17 18-Mar-17 277

XAC03-33215351 Lifting Steel Support For CVT+ES,CVT,LA 1 04-Feb-17 06-Feb-17 258

XAC03-33215352 Install Steel Support CVT +ES 5 06-Feb-17 11-Feb-17 258

XAC03-33215357 Install Steel Support For CVT 6 11-Feb-17 18-Feb-17 258

XAC03-33215358 Install Steel Support For LA 6 11-Feb-17 18-Feb-17 258

XAC03-33215353 Install TOS 15 11-Feb-17 01-Mar-17 285

XAC03-33215359 Lifting TOS 1 01-Mar-17 02-Mar-17 285

XAC03-33215354 PASS M00 - Unload/Unpack PASS M00 1 04-Mar-17 04-Mar-17 277

XAC03-33215355 PASS M00 - Lifting onto Foundation 1 06-Mar-17 07-Mar-17 277

XAC03-33215356 PASS M00 - Install PASS M00 3 07-Mar-17 10-Mar-17 277

XAC03-3321535A Lifting CVT ES and LA 1 10-Mar-17 11-Mar-17 277

XAC03-3321535B Install CVT and Junction Box 5 11-Mar-17 17-Mar-17 278

XAC03-3321535C Install ES 5 11-Mar-17 17-Mar-17 278

XAC03-3321535D Install LA 6 11-Mar-17 18-Mar-17 277

03PMS-BL00.3.3.2.15.3.6 Bay STG-30


03PMS-BL00.3.3.2.15.3 18 18-Feb-17 11-Mar-17 258

XAC03-33215361 Lifting Steel Support CVT and ES 1 18-Feb-17 20-Feb-17 258

XAC03-33215362 Install Steel Support CVT and ES 5 20-Feb-17 25-Feb-17 264

XAC03-33215363 Install Steel Support Junction Box CVT 5 20-Feb-17 25-Feb-17 270

XAC03-33215364 Install Operation Platform 5 20-Feb-17 25-Feb-17 258

XAC03-33215365 PASS M00 - Unload/Unpack PASS M00 1 25-Feb-17 27-Feb-17 258

XAC03-33215366 PASS M00 - Lifting onto Foundation 1 27-Feb-17 28-Feb-17 258

XAC03-33215368 PASS M00 - Install PASS M00 2 02-Mar-17 04-Mar-17 258

XAC03-33215367 Lifting CVT and ES 1 04-Mar-17 06-Mar-17 258

XAC03-33215369 Install CVT and Junction Box 5 06-Mar-17 11-Mar-17 258

XAC03-3321536A Install ES 5 06-Mar-17 11-Mar-17 258

03PMS-BL00.3.3.2.15.3.7 Bay GTG-32


03PMS-BL00.3.3.2.15.3 22 25-Feb-17 23-Mar-17 258

XAC03-33215371 Lifting Steel Support CVT and ES 1 25-Feb-17 27-Feb-17 268

XAC03-33215372 Install Steel Support CVT and ES 5 27-Feb-17 04-Mar-17 268

XAC03-33215373 Install Steel Support Junction Box CVT 5 27-Feb-17 04-Mar-17 268

XAC03-33215374 Install Operation Platform 5 27-Feb-17 04-Mar-17 268

XAC03-33215375 PASS M00 - Unload/Unpack PASS M00 1 11-Mar-17 13-Mar-17 258

XAC03-33215376 PASS M00 - Lifting onto Foundation 1 13-Mar-17 14-Mar-17 258

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:42 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3321537A PASS M00 - Install PASS M00 2 14-Mar-17 16-Mar-17 258

XAC03-33215377 Lifting CVT and ES 1 16-Mar-17 17-Mar-17 258

XAC03-33215378 Install CVT and Junction Box 5 17-Mar-17 23-Mar-17 258

XAC03-33215379 Install ES 5 17-Mar-17 23-Mar-17 258

03PMS-BL00.3.3.2.15.3.8 Bay GTG-31


03PMS-BL00.3.3.2.15.3 27 04-Mar-17 05-Apr-17 258

XAC03-33215381 Lifting Steel Support CVT and ES 1 04-Mar-17 06-Mar-17 272

XAC03-33215382 Install Steel Support CVT and ES 5 06-Mar-17 11-Mar-17 273

XAC03-33215383 Install Steel Support Junction Box CVT 5 06-Mar-17 11-Mar-17 272

XAC03-33215384 Install Operation Platform 5 06-Mar-17 11-Mar-17 272

XAC03-33215385 PASS M00 - Unload/Unpack PASS M00 1 23-Mar-17 24-Mar-17 258

XAC03-33215386 PASS M00 - Lifting onto Foundation 1 24-Mar-17 25-Mar-17 258

XAC03-3321538A PASS M00 - Install PASS M00 3 25-Mar-17 29-Mar-17 258

XAC03-33215387 Lifting CVT and ES 1 29-Mar-17 30-Mar-17 258

XAC03-33215388 Install CVT and Junction Box 5 30-Mar-17 05-Apr-17 258

XAC03-33215389 Install ES 5 30-Mar-17 05-Apr-17 258

03PMS-BL00.3.3.2.15.3.9 Bay Bus Coupler


03PMS-BL00.3.3.2.15.3 4 05-Apr-17 10-Apr-17 258

XAC03-33215391 PASS M00 - Unload/Unpack PASS M00 1 05-Apr-17 06-Apr-17 258

XAC03-33215392 PASS M00 - Lifting onto Foundation 1 06-Apr-17 07-Apr-17 258

XAC03-33215393 PASS M00 - Install PASS M00 3 07-Apr-17 10-Apr-17 258

03PMS-BL00.3.3.2.15.3.A Indoo r Equipments


03PMS-BL00.3.3.2.15.3 64 15-Dec-16 25-Feb-17 36

XAC03-332153A1 AC/DC Board Panel 10 15-Dec-16 26-Dec-16 79

XAC03-332153A2 115 kV Control and Protection Panel 10 15-Feb-17 25-Feb-17 36

03PMS-BL00.3.3.2.15.3.B Control and LV Cable


03PMS-BL00.3.3.2.15.3 62 24-Jan-17 04-Apr-17 1

XAC03-332153B1 TPSC Handover Cable Route to ABB 0 24-Jan-17 1

XAC03-332153B2 Cable Connection between Switchyard and CCP 59 24-Jan-17* 31-Mar-17 1

XAC03-332153B3 Cable Connection inside Switchyard 56 24-Jan-17 28-Mar-17 4

XAC03-332153B4 Handover to Commissioning Walkdown 1 01-Apr-17 01-Apr-17 1

XAC03-332153B5 Punch Clear 1 03-Apr-17 03-Apr-17 1

XAC03-332153B6 Handover to Commissioning 1 04-Apr-17 04-Apr-17 1

03PMS-BL00.3.3.2.16 Lig
Lightning Protection 124 12-Jan-17 05-Jun-17 210

03PMS-BL00.3.3.2.16.0 Interface 124 12-Jan-17 05-Jun-17 210

XAC03-33216020 Interface - Lighning Protection - CTO 0 12-Jan-17 123

XAC03-33216010 Interface - Lighning Protection - MHO 0 30-Jan-17* 19

XAC03-33216030 Interface - Lighning Protection - MC 0 05-Jun-17 210

03PMS-BL00.3.3.2.16.1 Erection 89 22-Feb-17 05-Jun-17 210

XAC03-33216110 Erection - Lighning Protection Installation 89 22-Feb-17 05-Jun-17 210

03PMS-BL00.3.3.2.17 Earthing
Ea 223 14-Jul-16 28-Mar-17 269

03PMS-BL00.3.3.2.17.0 Interface 135 14-Jul-16 16-Dec-16 357

XAC03-33217010 Interface - Earthing - MHO 0 14-Jul-16* 292

XAC03-3321702B Interface - Earthing - CTO for Power Plant Area 0 10-Aug-16 269

XAC03-3321702A Interface - Earthing - CTO for Switchyard 0 30-Aug-16 380

XAC03-33217030 Interface - Earthing - MC for Switchyard 0 16-Dec-16* 357

03PMS-BL00.3.3.2.17.1 Erection 200 10-Aug-16 28-Mar-17 269

XAC03-33217110 Erection - Earthing - Power Plant Area 200 10-Aug-16 28-Mar-17 269

XAC03-33217120 Erection - Earthing - Switchyard 27 20-Oct-16 19-Nov-16 380

03PMS-BL00.3.3.2.18 Lig
Lighting 211 12-Jan-17 13-Sep-17 122

03PMS-BL00.3.3.2.18.0 Interface 211 12-Jan-17 13-Sep-17 122

XAC03-33218010 Interface - Lighting - CTO 0 12-Jan-17 34

XAC03-33218020 Interface - Lighting - MHO 0 30-Jan-17 19

XAC03-33218030 Interface - Lighting - MC 0 13-Sep-17 122

03PMS-BL00.3.3.2.18.1 Lighting for WTP 31 27-Apr-17 01-Jun-17 213

XAC03-33218110 Lighting for WTP - Lighting Work 31 27-Apr-17 01-Jun-17 213

03PMS-BL00.3.3.2.18.2 Lighting for E&C Building 72 30-Jan-17 22-Apr-17 247

XAC03-33218210 Lighting - GF Installation 26 30-Jan-17 01-Mar-17 34

XAC03-33218220 Lighting - 1F Installation 26 30-Jan-17 01-Mar-17 19

XAC03-33218230 Lighting - 2F Installation 17 30-Jan-17 18-Feb-17 49

XAC03-33218240 Lighting - 3F Installation 33 30-Jan-17 09-Mar-17 52

XAC03-33218250 Lighting - Common Installation 38 09-Mar-17 22-Apr-17 247

03PMS-BL00.3.3.2.18.3 Lighting for Other 120 28-Apr-17 13-Sep-17 122

XAC03-33218310 Lighting for Other - Lighting System 120 28-Apr-17 13-Sep-17 122

03PMS-BL00.3.3.2.19 ST Building Overhead Crane 73 02-Feb-17 28-Apr-17 33

03PMS-BL00.3.3.2.19.0 Interface 73 02-Feb-17 28-Apr-17 33

XAC03-33219020 Interface - CTO 0 02-Feb-17 33

XAC03-3321901A Interface - MHO Lot -1 Rail 0 02-Feb-17 33

XAC03-3321901B Interface - MHO Lot -2 O/H Crane 0 20-Feb-17 39

XAC03-33219030 Interface - MC 0 21-Apr-17 33

XAC03-33219040 Interface - TOP 0 28-Apr-17 33

03PMS-BL00.3.3.2.19.1 ST Over Head Crane 5 ton 67 02-Feb-17 21-Apr-17 33

XAC03-33219110 ST Over Head Crane 5 ton - Rail Installation 21 02-Feb-17 27-Feb-17 33

XAC03-33219120 ST Over Head Crane 5 ton - Assembly 10 27-Feb-17 10-Mar-17 33

XAC03-33219130 ST Over Head Crane 5 ton - Conductor Installation 21 10-Mar-17 04-Apr-17 33

XAC03-33219140 ST Over Head Crane 5 ton - Panel Install 1 04-Apr-17 05-Apr-17 33

XAC03-33219150 ST Over Head Crane 5 ton - Conduit and Internal Cabling 14 05-Apr-17 21-Apr-17 33

03PMS-BL00.3.3.2.20 GT Evaporator 18 02-Jan-17 23-Jan-17 166

03PMS-BL00.3.3.2.20.0 Interface 18 02-Jan-17 23-Jan-17 166

XAC03-33220010 Interface - MHO GT Evaporator 0 02-Jan-17* 167

XAC03-33220020 Interface - CTO 0 02-Jan-17* 166

XAC03-33220030 Interface - MC 0 07-Jan-17 179

XAC03-33220040 Interface - TOP 0 23-Jan-17 166

03PMS-BL00.3.3.2.20.1 Mechanical Work 4 03-Jan-17 07-Jan-17 166

XAC03-33220110 Mechanical Work - GT Evaporator Intallation 4 03-Jan-17 07-Jan-17 166

03PMS-BL00.3.3.2.20.2 Piping Work 11 07-Jan-17 20-Jan-17 166

XAC03-33220210 Piping Work - Installation 7 07-Jan-17 16-Jan-17 166

XAC03-33220220 Piping Work - Punch Clear 4 16-Jan-17 20-Jan-17 166

03PMS-BL00.3.3.3 Process
Proces Package 298 01-Oct-16 11-Sep-17 125

03PMS-BL00.3.3.3.01 HP Steam System 185 08-Feb-17 11-Sep-17 125

03PMS-BL00.3.3.3.01.0 Interface 185 08-Feb-17 11-Sep-17 125

XAC03-33301020 Interface - HP Steam System - CTO 0 08-Feb-17 310

XAC03-3330101A Interface - HP Steam System - MHO (Pipe) 0 09-Mar-17* 50

XAC03-3330101B Interface - HP Steam System - MHO (Bypass Valve) 0 24-Mar-17* 271

XAC03-33301030 Interface - HP Steam System - MC 0 11-Aug-17* 152

XAC03-33301040 Interface - HP Steam System - TO P 0 11-Sep-17* 125

03PMS-BL00.3.3.3.01.1 HP Main Steam System 1 25-Mar-17 25-Mar-17 271

XAC03-33301110 HP Main Steam System - HP Turbine Bypass Valve Installation 1 25-Mar-17 25-Mar-17 271

03PMS-BL00.3.3.3.01.2 Piping Work 95 15-Mar-17 01-Jul-17 51

XAC03-33301210 Piping Work - Pipe Support Installation 12 15-Mar-17 28-Mar-17 50

XAC03-33301220 Piping Work - Large Bore Pipe Installation 46 22-Mar-17 13-May-17 50

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:43 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33301230 Piping Work - Small Bore Pipe Installation 26 21-Apr-17 20-May-17 50

XAC03-33301240 Piping Work - RT / UT / PT 26 28-Apr-17 27-May-17 50

XAC03-33301250 Piping Work - Line Check 4 29-May-17 01-Jun-17 50

XAC03-33301260 Piping Work - Punch Clear 8 02-Jun-17 10-Jun-17 56

XAC03-33301270 Piping Work - Insulation Work 26 02-Jun-17 01-Jul-17 51

XAC03-33301280 Piping Work - Hydro Test 2 12-Jun-17 13-Jun-17 56

03PMS-BL00.3.3.3.02 LP Steam System 185 08-Feb-17 11-Sep-17 125

03PMS-BL00.3.3.3.02.0 Interface 185 08-Feb-17 11-Sep-17 125

XAC03-33302020 Interface - LP Steam System - CTO 0 08-Feb-17 310

XAC03-3330201A Interface - LP Steam System - MHO (Bypass Valve) 0 09-Mar-17* 73

XAC03-3330201B Interface - LP Steam System - MHO (Pipe) 0 09-Mar-17* 68

XAC03-33302030 Interface - LP Steam System - MC 0 11-Aug-17* 152

XAC03-33302040 Interface - LP Steam System - TOP 0 11-Sep-17* 125

03PMS-BL00.3.3.3.02.1 Bypass Valve 1 09-Mar-17 09-Mar-17 285

XAC03-33302110 Bypass Valve - LP Turbine Bypass Valve Installation 1 09-Mar-17 09-Mar-17 285

03PMS-BL00.3.3.3.02.2 Piping Work 121 15-Mar-17 01-Aug-17 25

XAC03-33302210 Piping Work - Pipe Support Installation 12 15-Mar-17 28-Mar-17 68

XAC03-33302220 Piping Work - Large Bore Pipe Installation 32 22-Mar-17 28-Apr-17 68

XAC03-33302230 Piping Work - Small Bore Pipe Installation 13 21-Apr-17 05-May-17 68

XAC03-33302240 Piping Work - Line Check 5 06-May-17 11-May-17 68

XAC03-33302250 Piping Work - Punch Clear 12 12-May-17 25-May-17 73

XAC03-33302260 Piping Work - Insulation Work 26 12-May-17 10-Jun-17 69

XAC03-33302270 Piping Work - Hydro Test 2 26-May-17 27-May-17 73

XAC03-33302290 Additonal Chemical Clean for Steam Line - Preparation for Steam Pipe Chemical Clean 4 20-Jul-17 24-Jul-17 25

XAC03-333022A0 Additonal Chemical Clean for Steam Line - Steam Pipe Chemical Clean 5 25-Jul-17 29-Jul-17 25

XAC03-333022B0 Additonal Chemical Clean for Steam Line - Restoration 2 31-Jul-17 01-Aug-17 25

03PMS-BL00.3.3.3.03 Extraction
Ex Steam System 185 08-Feb-17 11-Sep-17 125

03PMS-BL00.3.3.3.03.0 Interface 185 08-Feb-17 11-Sep-17 125

XAC03-33303020 Interface - Extraction Steam System - CTO 0 08-Feb-17 290

XAC03-33303010 Interface - Extraction Steam System - MHO 0 09-Mar-17* 4

XAC03-33303030 Interface - Extraction Steam System - MC 0 11-Aug-17* 152

XAC03-33303040 Interface - Extraction Steam System - TOP 0 11-Sep-17* 125

03PMS-BL00.3.3.3.03.1 Equipment 21 09-Mar-17 01-Apr-17 265

XAC03-33303110 Equipment - Silencer Structure Fabrication and Installation 7 09-Mar-17 16-Mar-17 265

XAC03-33303120 Equipment - Silencer Installation 7 16-Mar-17 24-Mar-17 265

XAC03-33303130 Equipment - Extraction Steam Bypass Valve Installation 7 24-Mar-17 01-Apr-17 265

03PMS-BL00.3.3.3.03.2 Piping Work 139 09-Mar-17 16-Aug-17 12

XAC03-33303210 Piping Work - Pipe Support Installation 16 09-Mar-17 28-Mar-17 4

XAC03-33303220 Piping Work - Large Bore Pipe Installation 75 18-Mar-17 14-Jun-17 4

XAC03-33303230 Piping Work - Small Bore Pipe Installation 26 22-May-17 21-Jun-17 4

XAC03-33303240 Piping Work - RT / UT / PT 26 29-May-17 27-Jun-17 4

XAC03-33303250 Piping Work - Line Check 3 28-Jun-17 01-Jul-17 4

XAC03-33303260 Piping Work - Punch Clear 18 01-Jul-17 22-Jul-17 4

XAC03-33303270 Piping Work - Insulation Work 39 01-Jul-17 16-Aug-17 12

XAC03-33303280 Piping Work - Hydro Test 2 22-Jul-17 25-Jul-17 4

03PMS-BL00.3.3.3.04 Aux
Au Steam System 150 09-Mar-17 30-Aug-17 0

03PMS-BL00.3.3.3.04.0 Interface 150 09-Mar-17 30-Aug-17 0

XAC03-33304010 Interface - Aux Steam System - MHO 0 09-Mar-17* 5

XAC03-33304020 Interface - Aux Steam System - CTO 0 15-Mar-17* 0

XAC03-33304030 Interface - Aux Steam System - MC 0 22-Aug-17 0

XAC03-33304040 Interface - Aux Steam System - TOP 0 30-Aug-17 0

03PMS-BL00.3.3.3.04.1 Piping Work 138 16-Mar-17 22-Aug-17 0

XAC03-33304110 Piping Work - Pipe Support Installation 16 16-Mar-17 04-Apr-17 0

XAC03-33304120 Piping Work - Large Bore Pipe Installation 75 24-Mar-17 20-Jun-17 0

XAC03-33304130 Piping Work - Small Bore Pipe Installation 26 27-May-17 27-Jun-17 0

XAC03-33304140 Piping Work - RT / UT / PT 26 03-Jun-17 03-Jul-17 0

XAC03-33304150 Piping Work - Line Check 3 04-Jul-17 07-Jul-17 0

XAC03-33304160 Piping Work - Punch Clear 14 07-Jul-17 22-Jul-17 4

XAC03-33304170 Piping Work - Insulation Work 39 07-Jul-17 22-Aug-17 0

XAC03-33304180 Piping Work - Hydro Test 2 24-Jul-17 25-Jul-17 4

XAC03-33304190 Piping Work - Prepartion of Steam Blow 20 26-Jul-17 17-Aug-17 4

03PMS-BL00.3.3.3.05 Condensate
Co Water System 146 13-Jan-17 01-Jul-17 91

03PMS-BL00.3.3.3.05.0 Interface 146 13-Jan-17 01-Jul-17 91

XAC03-33305010 Interface - MHO- Condensate Water System 0 13-Jan-17* 144

XAC03-33305020 Interface - CTO - Condensate Water System 0 15-Mar-17* 91

XAC03-33305030 Interface - MC - Condensate Water System 0 12-Jun-17* 91

XAC03-33305040 Interface - TOP - Condensate Water System 0 01-Jul-17* 91

03PMS-BL00.3.3.3.05.1 Mechanical Work 10 15-Mar-17 27-Mar-17 91

XAC03-33305110 Mechanical Work - Condensate Pump Installation 10 15-Mar-17 27-Mar-17 91

03PMS-BL00.3.3.3.05.2 Piping Work - Condensate Line 66 27-Mar-17 12-Jun-17 91

03PMS-BL00.3.3.3.05.2.1 From CEP to Pipe Rack


03PMS-BL00.3.3.3.05.2 21 27-Mar-17 20-Apr-17 136

XAC03-33305211 From CEP to Pipe Rack - On Pipe Rack to Deaerator 21 27-Mar-17 20-Apr-17 136

XAC03-33305212 From CEP to Pipe Rack - Condenser to CEP 6 27-Mar-17 03-Apr-17 91

03PMS-BL00.3.3.3.05.2.2 Piping Work


03PMS-BL00.3.3.3.05.2 60 03-Apr-17 12-Jun-17 91

XAC03-33305221 Piping Work - CEP Suction Line 5 03-Apr-17 08-Apr-17 133

XAC03-33305222 Piping Work - STG Building Area 21 03-Apr-17 27-Apr-17 91

XAC03-33305223 Piping Work - CEP Suction Line Check with Owner 1 08-Apr-17 10-Apr-17 133

XAC03-33305224 Piping Work - CEP Suction Line Punch A, B Clear 2 10-Apr-17 12-Apr-17 133

XAC03-33305225 Piping Work - Main Pipe Rack Area 30 10-Apr-17 15-May-17 91

XAC03-33305226 Piping Work - Deaerator Area 10 11-Apr-17 22-Apr-17 95

XAC03-33305227 Piping Work - Bearing Sealing/Vacuum Seal Line 10 19-Apr-17 01-May-17 103

XAC03-33305228 Piping Work - Condenser Recirculation Line 3 20-Apr-17 24-Apr-17 109

XAC03-33305229 Piping Work - Retention Pit Line 10 22-Apr-17 04-May-17 100

XAC03-3330522A Piping Work - HP Turbine Bypass Spray Line 10 22-Apr-17 04-May-17 95

XAC03-3330522B Piping Work - Gland Seal Steam Spray Line 5 22-Apr-17 28-Apr-17 105

XAC03-3330522C Piping Work - ST Exhaust Hood Spray Line 15 22-Apr-17 10-May-17 95

XAC03-3330522D Piping Work - CEP Discharge Line Check with Owner 7 15-May-17 23-May-17 91

XAC03-3330522E Piping Work - Punch Clear A, B 7 23-May-17 31-May-17 91

XAC03-3330522F Piping Work - Hydro Test 7 31-May-17 08-Jun-17 91

XAC03-3330522G Piping Work - Restoration 3 08-Jun-17 12-Jun-17 91

03PMS-BL00.3.3.3.05.3 Electrical/C&I Work 23 27-Mar-17 22-Apr-17 110

XAC03-33305310 Electrical/C&I Work - Conduits/Cabling/Termination (to Local) 21 27-Mar-17 20-Apr-17 110

XAC03-33305320 Electrical/C&I Work - Continuity Check 2 20-Apr-17 22-Apr-17 110

03PMS-BL00.3.3.3.06 HP Feedwater System 122 01-Feb-17 21-Jun-17 195

03PMS-BL00.3.3.3.06.0 Interface 122 01-Feb-17 21-Jun-17 60

XAC03-3330601B Interfacem - MHO for BFP - HP Feedwater System 0 01-Feb-17* 98

XAC03-3330601A Interface - MHO for FW Heat Exchanger - HP Feedwater System 0 08-Feb-17* 131

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:44 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-3330601D Interface - MHO- Deaerator 0 20-Feb-17* 61

XAC03-3330601C Interface - MHO for Pipe - HP Feedwater System 0 01-Mar-17* 83

XAC03-33306020 Interface - CTO - HP Feedwater System 0 15-Mar-17* 40

XAC03-33306030 Interface - MC - HP Feedwater System 0 10-May-17* 83

XAC03-33306040 Interface - TOP - HP Feedwater System 0 21-Jun-17* 60

03PMS-BL00.3.3.3.06.1 HP Feed Water Pump 9 15-Mar-17 25-Mar-17 60

XAC03-33306110 HP Feed Water Pump - HP Feed Water Pump Installation 9 15-Mar-17 25-Mar-17 60

03PMS-BL00.3.3.3.06.2 Deaerator System 34 15-Mar-17 22-Apr-17 217

XAC03-33306210 Dearator System - Dearator Installation 10 15-Mar-17 27-Mar-17 40

XAC03-33306220 Dearator System - Dearator Insulation 18 03-Apr-17* 22-Apr-17 217

03PMS-BL00.3.3.3.06.3 Piping Work 81 15-Mar-17 16-Jun-17 199

XAC03-33306310 Piping Work - HP Feedwater Piping Work 52 15-Mar-17 13-May-17 100

XAC03-33306320 Hydro Test 3 13-May-17 17-May-17 199

XAC03-33306330 Insulation Work 26 17-May-17 16-Jun-17 199

03PMS-BL00.3.3.3.06.Z Others 18 15-Mar-17 04-Apr-17 263

XAC03-33306Z10 Access Platform - Dearator Tower Access - Delivery 0 15-Mar-17* 123

XAC03-33306Z20 Access Platform - Dearator Tower Access - Installation 9 16-Mar-17 25-Mar-17 271

XAC03-33306Z30 Access Platform - FWHE Outlet Isolation Valve Acc ess - Delivery 0 25-Mar-17* 114

XAC03-33306Z40 Access Platform - FWHE Outlet Isolation Valve Acc ess - Installation 8 27-Mar-17 04-Apr-17 114

03PMS-BL00.3.3.3.07 LP Feedwater System 106 22-Feb-17 24-Jun-17 192

03PMS-BL00.3.3.3.07.0 Interface 106 22-Feb-17 24-Jun-17 192

XAC03-3330701B Interface - MHO for Pipe - LP Feedwater System 0 22-Feb-17* 298

XAC03-3330701A Interface - MHO for BFP - LP Feedwater System 0 27-Feb-17* 75

XAC03-33307020 Interface - CTO - LP Feedwater System 0 15-Mar-17* 60

XAC03-33307030 Interface - MC - LP Feedwater System 0 10-May-17* 84

XAC03-33307040 Interface - TOP - LP Feedwater System 0 24-Jun-17* 57

03PMS-BL00.3.3.3.07.1 LP Feed Water Pump 9 15-Mar-17 25-Mar-17 60

XAC03-33307110 Mechanical Work - LP Feed Water Pump Installation 9 15-Mar-17 25-Mar-17 60

03PMS-BL00.3.3.3.07.2 Piping Work 72 25-Mar-17 16-Jun-17 199

XAC03-33307210 Piping Work - LP Feedwater Piping Work 30 25-Mar-17 29-Apr-17 60

XAC03-33307220 Hydro Test 3 29-Apr-17 03-May-17 90

XAC03-33307230 Insulation Work 26 17-May-17 16-Jun-17 199

03PMS-BL00.3.3.3.07.3 Electrical Work 62 25-Mar-17 06-Jun-17 60

XAC03-33307310 Electrical Work - Conduit Installation 12 25-Mar-17 08-Apr-17 85

XAC03-33307320 Electrical Work - Cabling 6 08-May-17 15-May-17 60

XAC03-33307330 Electrical Work - Handover Walk Down to Commissioning 1 31-May-17 01-Jun-17 60

XAC03-33307340 Electrical Work - Punch Clear 3 01-Jun-17 05-Jun-17 60

XAC03-33307350 Electrical Work - Handover to Commissioning 1 05-Jun-17 06-Jun-17 60

03PMS-BL00.3.3.3.07.4 Instrument Work 16 29-Apr-17 18-May-17 71

XAC03-33307410 Instrument Work - Instrument Install 7 29-Apr-17* 08-May-17 60

XAC03-33307420 Instrument Work - Instrument Tubing Install 10 03-May-17 15-May-17 71

XAC03-33307430 Instrument Work - Instrument Tubing Leak test 3 15-May-17 18-May-17 71

03PMS-BL00.3.3.3.08 Main
Ma Cooling Water System 197 10-Dec-16 25-Jul-17 71

03PMS-BL00.3.3.3.08.0 Interface 197 10-Dec-16 25-Jul-17 71

XAC03-33308010 Interface - Main Cooling Water System - MHO lot 2 (MCW Pump) 0 10-Dec-16* 95

XAC03-33308030 Interface - Main Cooling Water System - MHO lot 1 (Pipe) 0 13-Jan-17* 69

XAC03-33308020 Interface - Main Cooling Water System - CTO for Pump 0 17-Jan-17* 79

XAC03-33308040 Interface - Main Cooling Water System - CTO for Piping 0 30-Mar-17* 71

XAC03-33308050 Interface - Main Cooling Water System - MC 0 03-Jul-17 71

XAC03-33308060 Interface - Main Cooling Water System - TOP 0 25-Jul-17 71

03PMS-BL00.3.3.3.08.1 Mechanical Work (Main CW. Pump) 24 10-Jan-17 07-Feb-17 79

XAC03-33308110 Mechanical Work - Foundation chipping 2 10-Jan-17 12-Jan-17 79

XAC03-33308120 Mechanical Work - Packer plate 4 12-Jan-17 17-Jan-17 79

XAC03-33308130 Mechanical Work - On base Pump & Motor 5 18-Jan-17 23-Jan-17 79

XAC03-33308140 Mechanical Work - Alignment Pump Skid 4 23-Jan-17 27-Jan-17 79

XAC03-33308150 Mechanical Work - Coupling Pre-Alignment 3 27-Jan-17 31-Jan-17 79

XAC03-33308160 Mechanical Work - Grouting base 6 31-Jan-17 07-Feb-17 79

03PMS-BL00.3.3.3.08.2 Piping Work 102 07-Mar-17 03-Jul-17 71

XAC03-33308210 Piping Work - CWP Discharge Line 12 07-Mar-17 21-Mar-17 79

XAC03-33308220 Piping Work - CWP Suction Line 6 21-Mar-17 28-Mar-17 149

XAC03-33308230 Piping Work - CW Pipe in Trench 32 21-Mar-17 27-Apr-17 110

XAC03-33308240 Piping Work - Return Line to CT. 64 30-Mar-17 12-Jun-17 71

XAC03-33308260 Piping Work - Touch Up Painting and Inspection 26 26-May-17 26-Jun-17 71

XAC03-33308250 Piping Work - Condensor Area 8 12-Jun-17 20-Jun-17 71

XAC03-33308270 Piping Work - Punch Clear 6 26-Jun-17 03-Jul-17 71

03PMS-BL00.3.3.3.08.3 Electrical / C&I Work 30 03-May-17 06-Jun-17 94

XAC03-33308310 Electrical Work - Conduits/Cabling/Termination 18 03-May-17* 23-May-17 94

XAC03-33308320 Electrical Work - Megger Check & Continuity Cable 4 24-May-17 27-May-17 94

XAC03-33308330 Electrical Work - Handover to Commissioing Walkdown 1 29-May-17 29-May-17 94

XAC03-33308340 Electrical Work - Punch Clear 6 30-May-17 05-Jun-17 94

XAC03-33308350 Electrical Work - Handover to Commissioing 1 05-Jun-17 06-Jun-17 94

03PMS-BL00.3.3.3.09 Au
Auxiliary Cooling Water System 176 10-Dec-16 30-Jun-17 0

03PMS-BL00.3.3.3.09.0 Interface 176 10-Dec-16 30-Jun-17 0

XAC03-3330901A Interface - MHO - Aux. Cooling Water Pump 0 10-Dec-16 95

XAC03-3330901B Interface - MHO - Aux. Cooling Water Pipe 0 14-Jan-17 69

XAC03-33309020 Interface - CTO - Aux. Cooling Water 0 17-Jan-17 62

XAC03-33309030 Interface - MC - Aux. Cooling Water 0 30-Mar-17 62

XAC03-33309040 Interface - TOP - Aux. Cooling Water 0 30-Jun-17 0

03PMS-BL00.3.3.3.09.1 Auxiliary Cooling Water Pump 4 18-Jan-17 23-Jan-17 62

XAC03-33309110 Auxiliary Cooling Water Pump - Auxiliary Cooling Water Pump Intallatio n 4 18-Jan-17 23-Jan-17 62

03PMS-BL00.3.3.3.09.3 Piping Work 30 23-Jan-17 27-Feb-17 62

XAC03-33309310 Piping Work - Site Installation 26 23-Jan-17 22-Feb-17 62

XAC03-33309320 Piping Work - Hydro Test 4 22-Feb-17 27-Feb-17 62

03PMS-BL00.3.3.3.09.4 Electrical / C&I Work 27 27-Feb-17 30-Mar-17 62

XAC03-33309410 Electrical / C&I Work - Conduits 10 27-Feb-17 10-Mar-17 62

XAC03-33309420 Electrical / C&I Work - Cabling & Termination Works 3 10-Mar-17 14-Mar-17 62

XAC03-33309440 Electrical / C&I Work - Instrument Install 1 14-Mar-17 15-Mar-17 62

XAC03-33309450 Electrical / C&I Work - Instrument Tubing 4 15-Mar-17 20-Mar-17 62

XAC03-33309460 Electrical / C&I Work - Tubing Leak Test 1 20-Mar-17 21-Mar-17 62

XAC03-33309430 Electrical / C&I Work - Megger Check & Continuity Cable 2 21-Mar-17 23-Mar-17 62

XAC03-33309470 Electrical / C&I Work - System Handover Walk Down 1 23-Mar-17 24-Mar-17 62

XAC03-33309480 Electrical / C&I Work - Punch Clear 4 24-Mar-17 29-Mar-17 62

XAC03-33309490 Electrical / C&I Work - Handover to Commissioning 1 29-Mar-17 30-Mar-17 62

03PMS-BL00.3.3.3.10 CT Make up Water (Common) 140 13-Jan-17 23-Jun-17 6

03PMS-BL00.3.3.3.10.0 Interface 140 13-Jan-17 23-Jun-17 6

XAC03-3331001A Interface - MHO - CT Make up Pumps 0 13-Jan-17* 100

XAC03-3331021B Interface - MHO - CT Make up (Pipe) 0 13-Jan-17 106

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:45 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33310020 Interface - CTO - CT Make up Pumps 0 13-Mar-17* 50

XAC03-33310030 Interface - MC - CT Make up Water 0 26-May-17 18

XAC03-33310040 Interface - TOP - CT Make up Water 0 23-Jun-17 6

03PMS-BL00.3.3.3.10.1 CT Make Up Pump 6 13-Mar-17 18-Mar-17 50

XAC03-33310110 CT Make-up Pumps Installation 6 13-Mar-17 18-Mar-17 50

03PMS-BL00.3.3.3.10.2 Piping Work 28 20-Mar-17 20-Apr-17 50

XAC03-33310220 Piping Work - BOP Pipe Sleeper line, Tank - Pump 6 20-Mar-17 25-Mar-17 50

XAC03-33310230 Piping Work - BOP Pipe Sleeper line, Pump - Cooling Tower 9 27-Mar-17 06-Apr-17 50

XAC03-33310210 Piping Work - BOP Pipe Sleeper line, WTP - Tank 6 29-Mar-17 04-Apr-17 51

XAC03-33310240 Piping Work - Punch Clear 2 06-Apr-17 07-Apr-17 50

XAC03-33310250 Piping Work - Hydrotest 2 08-Apr-17 11-Apr-17 50

XAC03-33310260 Piping Work - CT MU Water System Handover to commissioning walkdown 1 12-Apr-17 12-Apr-17 50

XAC03-33310270 Piping Work - Punch Clear 6 13-Apr-17 19-Apr-17 50

XAC03-33310280 Piping Work - CT MU Water System Handover to comissioing 1 19-Apr-17 20-Apr-17 50

03PMS-BL00.3.3.3.11 Clo
Closed Cycle Cooling Water System 199 14-Nov-16 30-Jun-17 0

03PMS-BL00.3.3.3.11.0 Interface 199 14-Nov-16 30-Jun-17 0

XAC03-3331101A Interface - MHO (CCCW Head Tank) - Closed Cycle Cooling Water System 0 14-Nov-16* 134

XAC03-3331101B Interface - MHO (CCCW pump) - Closed Cycle Cooling Water System 0 15-Feb-17* 49

XAC03-3331101C Interface - MHO (Heat Exchanger) - Closed Cycle Cooling Water System 0 15-Feb-17* 72

XAC03-3331101D Interface - MHO (Pipe) - Closed Cycle Cooling Water System 0 15-Feb-17* 26

XAC03-33311020 Interface - CTO - Closed Cycle Cooling Water System 0 04-Mar-17* 34

XAC03-33311030 Interface - MC - Closed Cycle Cooling Water System 0 17-May-17 23

XAC03-33311040 Interface - TOP - Closed Cycle Cooling Water System 0 30-Jun-17 0

03PMS-BL00.3.3.3.11.1 CCCW Pump 10 04-Mar-17 16-Mar-17 34

XAC03-33311110 CCCW Pump - Chipping and Packer Setting 4 04-Mar-17 09-Mar-17 34

XAC03-33311120 CCCW Pump - CCCW Pump Installation 2 09-Mar-17 11-Mar-17 34

XAC03-33311130 CCCW Pump - Equipment Alignment 2 11-Mar-17 14-Mar-17 34

XAC03-33311140 CCCW Pump - Grouting 2 14-Mar-17 16-Mar-17 34

03PMS-BL00.3.3.3.11.2 CCCW Heat Exchanger 10 15-Feb-17 25-Feb-17 72

XAC03-33311210 CCCW Heat Exchanger - Chipping and Packer Setting 4 15-Feb-17 18-Feb-17 72

XAC03-33311220 CCCW Heat Exchanger - CCCW Heat Exchanger Installation 1 20-Feb-17 21-Feb-17 72

XAC03-33311230 CCCW Heat Exchanger - Equipment Alignment 1 22-Feb-17 23-Feb-17 72

XAC03-33311240 CCCW Heat Exchanger - Grouting 2 24-Feb-17 25-Feb-17 72

03PMS-BL00.3.3.3.11.3 Chemical Pot 5 27-Feb-17 03-Mar-17 72

XAC03-33311310 Chemical Pot - Support Structure Installation 3 27-Feb-17 01-Mar-17 72

XAC03-33311320 Chemical Pot - Chemical Pot Installation 2 02-Mar-17 03-Mar-17 72

03PMS-BL00.3.3.3.11.4 Support and Piping Work 62 16-Mar-17 25-May-17 32

XAC03-33311420 Piping Work - On HRSG Pipe Rack 12 16-Mar-17 30-Mar-17 8

XAC03-33311410 Piping Work - At CCCW Pump area to Pipe Rack 17 16-Mar-17 05-Apr-17 44

XAC03-33311430 Piping Work -Connect to GTG#31 9 30-Mar-17 10-Apr-17 8

XAC03-33311440 Piping Work - On GTG#31 Pipe Rack 8 10-Apr-17 19-Apr-17 37

XAC03-33311450 Piping Work - Connect to GTG#32 7 10-Apr-17 18-Apr-17 23

XAC03-33311460 Piping Work - On GTG#32 Pipe Rack 9 19-Apr-17 28-Apr-17 23

XAC03-33311470 Piping Work - Connect to STG & ST 9 29-Apr-17 10-May-17 38

XAC03-33311480 Piping Work - Temporary Bypass Piping for Flushing 4 29-Apr-17 04-May-17 23

XAC03-33311490 Piping Work - Line Check 3 04-May-17 06-May-17 23

XAC03-333114A0 Piping Work -Punch Clear 5 08-May-17 12-May-17 23

XAC03-333114B0 Piping Work - Hydrotest 2 13-May-17 17-May-17 23

XAC03-333114C0 Piping Work - Hydotest for ST line 8 17-May-17 25-May-17 32

03PMS-BL00.3.3.3.11.5 Electrical / C&I Work 20 12-Apr-17 04-May-17 34

XAC03-33311510 Electrical Work - Stantion / Instrument / Tubing Work 9 12-Apr-17 21-Apr-17 8

XAC03-33311520 Electrical Work - Cabling and Termination Work 9 15-Apr-17 25-Apr-17 8

XAC03-33311530 Electrical Work - System Handover Walk Down 2 27-Apr-17 01-May-17 34

XAC03-33311540 Electrical Work - Punch Clear 3 01-May-17 04-May-17 34

XAC03-33311550 Electrical Work - Handover to Commissioning 1 04-May-17 04-May-17 34

03PMS-BL00.3.3.3.11.Z Others 1 25-Apr-17 26-Apr-17 41

XAC03-33311Z10 Access Platform - Platform for Process Steam Header - Delivery 0 25-Apr-17 41

XAC03-33311Z20 Access Platform - Platform for Process Steam Header - Installation 1 26-Apr-17 26-Apr-17 41

03PMS-BL00.3.3.3.12 Condenser
Co Vacuum System 115 10-Feb-17 23-Jun-17 99

03PMS-BL00.3.3.3.12.0 Interface 115 10-Feb-17 23-Jun-17 99

XAC03-33312020 Interface - CTO - Condenser Vacuum System 0 10-Feb-17* 182

XAC03-3331201A Interface - MHO (CVP) - Condenser Vacuum System 0 06-Apr-17* 135

XAC03-3331201B Interface - MHO for Pipe - Condenser Vacuum System 0 18-Apr-17* 138

XAC03-33312030 Interface - MC - Condenser Vacuum System 0 31-May-17* 107

XAC03-33312040 Interface - TOP - Condenser Vacuum System 0 23-Jun-17* 99

03PMS-BL00.3.3.3.12.1 Mechanical Work 6 06-Apr-17 12-Apr-17 135

XAC03-33312110 Mechanical Work - Vacuum Pump Installation 6 06-Apr-17 12-Apr-17 135

03PMS-BL00.3.3.3.12.2 Piping Work 6 19-Apr-17 25-Apr-17 138

XAC03-33312210 Piping Work - Pipe Installation 6 19-Apr-17 25-Apr-17 138

03PMS-BL00.3.3.3.12.3 Electrical/C&I Work 14 12-Apr-17 28-Apr-17 135

XAC03-33312310 Electrical/C&I Work - Conduits/Cabling/Termination (Local) 14 12-Apr-17 28-Apr-17 135

03PMS-BL00.3.3.3.13 Ra
Raw Water Distribution System (Common) 169 01-Oct-16 13-Apr-17 24

03PMS-BL00.3.3.3.13.0 Interface 169 01-Oct-16 13-Apr-17 24

XAC03-33313020 Interface - CTO Raw Water Pump, Buffa Tank 0 01-Oct-16* 103

XAC03-3331301C Interface - MHO - Lot 1 Pipe (Around Pond) 0 15-Dec-16* 78

XAC03-3331301A Interface - MHO - Raw water pumps 0 05-Jan-17* 85

XAC03-3331301B Interface - MHO - Raw Buffer Tank 0 05-Jan-17* 24

XAC03-3331301D Interface - MHO - Lot 2 Pipe 0 13-Jan-17* 53

XAC03-33313030 Interface - MC - Raw Water Distribution System 0 04-Apr-17* 24

XAC03-33313040 Interface - TOP - Raw Water Distribution System 0 13-Apr-17* 24

03PMS-BL00.3.3.3.13.1 Raw Water Buffer Tank 13 30-Dec-16 14-Jan-17 93

XAC03-33313110 Raw Water Buffer tank - Chipping and Packer Setting 4 30-Dec-16 04-Jan-17 24

XAC03-33313120 Raw Water Buffer tank - Raw Water Buffer Tank On Base 3 05-Jan-17 07-Jan-17 24

XAC03-33313130 Raw Water Buffer tank - Equipment Alignment 3 07-Jan-17 11-Jan-17 24

XAC03-33313140 Raw Water Buffer tank - Grouting 3 12-Jan-17 14-Jan-17 93

03PMS-BL00.3.3.3.13.2 Raw Water Pump 11 31-Dec-16 12-Jan-17 95

XAC03-33313210 Raw Water Pump - Chipping and Packer Setting 4 31-Dec-16 04-Jan-17 85

XAC03-33313220 Raw Water Pump - Raw Water Pump On Base 2 05-Jan-17 06-Jan-17 85

XAC03-33313230 Raw Water Pump - Equipment Alignment 2 06-Jan-17 09-Jan-17 95

XAC03-33313240 Raw Water Pump - Grouting 3 09-Jan-17 12-Jan-17 95

03PMS-BL00.3.3.3.13.4 Piping Work 72 12-Jan-17 04-Apr-17 24

XAC03-33313410 Piping Work - Buffer Tank and Pump Area 35 12-Jan-17 21-Feb-17 24

XAC03-33313420 Piping Work - on the Pipe Rack Area 18 16-Feb-17 08-Mar-17 24

XAC03-33313430 Piping Work - on the Pipe sleeper to clarifier 19 09-Mar-17 30-Mar-17 24

XAC03-33313440 Piping Work - Punch Clear 2 30-Mar-17 01-Apr-17 24

XAC03-33313450 Piping Work - Hydro Test 2 03-Apr-17 04-Apr-17 24

03PMS-BL00.3.3.3.13.5 Electrical Work 61 12-Jan-17 22-Mar-17 35

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:46 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33313510 Electrical Work - Raceway Installation on Pipe Rack 45 12-Jan-17 04-Mar-17 35

XAC03-33313520 Electrical Work - Conduits/Cabling/Termination 12 04-Mar-17 18-Mar-17 35

XAC03-33313530 Electrical Work - Handover to Commissioning Walkdown 1 18-Mar-17 20-Mar-17 35

XAC03-33313540 Electrical Work - Punch Clear 1 21-Mar-17 21-Mar-17 35

XAC03-33313550 Electrical Work - Handover to Commissioning 1 22-Mar-17 22-Mar-17 35

03PMS-BL00.3.3.3.14 Service
Se water Distribution System 112 13-Feb-17 21-Jun-17 36

03PMS-BL00.3.3.3.14.0 Interface 112 13-Feb-17 21-Jun-17 36

XAC03-3331401B Interface - Service Water Distribution System - MHO for SWP 0 13-Feb-17* 106

XAC03-3331401C Interface - Service Water Distribution System - MHO for Pipe Lot-1 (Around Tank) 0 20-Feb-17* 113

XAC03-3331401A Interface - Service Water Distribution System - MHO for Pipe Lot-2 0 20-Feb-17* 92

XAC03-33314020 Interface - Service Water Distribution System - CTO 0 04-Mar-17* 90

XAC03-33314030 Interface - Service Water Distribution System - MC 0 26-May-17* 50

XAC03-33314040 Interface - Service Water Distribution System - TOP 0 21-Jun-17* 36

03PMS-BL00.3.3.3.14.1 Service Water Pump 8 04-Mar-17 14-Mar-17 90

XAC03-33314110 Service Water Pump - SW Pump Installation 8 04-Mar-17 14-Mar-17 90

03PMS-BL00.3.3.3.14.2 Piping Work 48 20-Feb-17 15-Apr-17 85

XAC03-33314210 Piping Work - Pipe Delivery 0 20-Feb-17* 92

XAC03-33314230 Piping Work - BOP Pipe Sleeper line, Tank - Pump 5 14-Mar-17 20-Mar-17 90

XAC03-33314220 Piping Work - BOP Pipe Sleeper line, WTP - Tank 7 15-Mar-17 23-Mar-17 92

XAC03-33314240 Piping Work - BOP Pipe Sleeper line, Pump - Fire Pump 6 20-Mar-17 27-Mar-17 90

XAC03-33314250 Piping Work - BOP Pipe Sleeper line, Pump - other 6 25-Mar-17 31-Mar-17 85

XAC03-33314280 Piping Work - Main Pipe rack line 6 25-Mar-17 31-Mar-17 85

XAC03-33314260 Piping Work - Punch Clear 2 31-Mar-17 03-Apr-17 85

XAC03-33314270 Piping Work - Hydrotest 3 03-Apr-17 06-Apr-17 85

XAC03-33314290 Piping Work - Sirvice Water System Handover to commissioning walkdown 1 06-Apr-17 07-Apr-17 85

XAC03-333142A0 Piping Work - Punch Clear 6 07-Apr-17 14-Apr-17 85

XAC03-333142B0 Piping Work - Sirvice Water System Handover to comissioing 1 14-Apr-17 15-Apr-17 85

03PMS-BL00.3.3.3.15 De
Demineralized water Distribution System 118 06-Feb-17 21-Jun-17 0

03PMS-BL00.3.3.3.15.0 Interface 118 06-Feb-17 21-Jun-17 0

XAC03-3331501A Interface - Demineralized Water Distribution System - MHO for Pipe Lot-1 (Around 0 06-Feb-17* 98
Tank)
XAC03-3331501B Interface - Demineralized Water Distribution System - MHO Pump 0 13-Feb-17* 31

XAC03-3331501C Interface - Demineralized Water Distribution System - MHO for Pipe Lot-2 0 20-Feb-17* 92

XAC03-33315020 Interface - Demineralized Water Distribution System - CTO 0 04-Mar-17* 15

XAC03-33315030 Interface - Demineralized Water Distribution System - MC 0 26-May-17* 14

XAC03-33315040 Interface - Demineralized Water Distribution System - TOP 0 21-Jun-17* 0

03PMS-BL00.3.3.3.15.1 Mechanical Work 8 04-Mar-17 14-Mar-17 15

XAC03-33315110 Mechanical Work - DM Pump Installation 8 04-Mar-17 14-Mar-17 15

03PMS-BL00.3.3.3.15.2 Piping Work 84 06-Feb-17 12-May-17 26

XAC03-33315230 Piping Work - BOP Pipe Sleeper line, WTP - Tank 6 06-Feb-17 11-Feb-17 98

XAC03-33315240 Piping Work - BOP Pipe Sleeper line, Tank - Pump 5 14-Mar-17 20-Mar-17 55

XAC03-33315250 Piping Work - BOP Pipe Sleeper line, Pump - Sleeper 11 20-Mar-17 01-Apr-17 55

XAC03-33315210 Piping Work - Main Pipe rack line 25 07-Apr-17* 05-May-17 26

XAC03-33315220 Piping Work - Pipe Delivery 0 26-Apr-17* 35

XAC03-33315260 Piping Work - Punch Clear 3 06-May-17 09-May-17 26

XAC03-33315270 Piping Work - Hydrotest 3 10-May-17 12-May-17 26

03PMS-BL00.3.3.3.15.3 Electrical Work 64 14-Mar-17 26-May-17 14

XAC03-33315320 Electrical Work - CT Make up / SW / DM Water - Instrument installation 18 14-Mar-17 04-Apr-17 15

XAC03-33315310 Electrical Work - CT Make up / SW / DM Water - Tray Installation 19 05-Apr-17* 26-Apr-17 14

XAC03-33315330 Electrical Work - CT Make up / SW / DM Water - Conduit / Cabling 18 27-Apr-17 17-May-17 14

XAC03-33315340 Electrical Work - CT Make up / SW / DM Water System Handover to commissioning 1 18-May-17 18-May-17 14
walkdown
XAC03-33315350 Electrical Work - Punch Clear 6 18-May-17 25-May-17 14

XAC03-33315360 Electrical Work - CT Make up / SW / DM Water System Handover to comissioing 1 25-May-17 26-May-17 14

03PMS-BL00.3.3.3.16 Waste
Wa water collection System 138 09-Jan-17 17-Jun-17 199

03PMS-BL00.3.3.3.16.0 Interface 138 09-Jan-17 17-Jun-17 199

XAC03-3331601A Interface - Waste Water Collection System - MHO Pipe 0 09-Jan-17* 71

XAC03-3331601B Interface - Waste Water Collection System - MHO for Retention Pump 0 01-Feb-17* 117

XAC03-3331601C Interface - Waste Water Collection System - MHO for Sump Pump 0 01-Feb-17* 52

XAC03-33316020 Interface - Waste Water Collection System - CTO 0 22-Mar-17* 63

XAC03-33316030 Interface - Waste Water Collection System - MC 0 05-May-17* 236

XAC03-33316040 Interface - Waste Water Collection System - TOP 0 17-Jun-17* 39

03PMS-BL00.3.3.3.16.1 Mechanical Work 27 14-Mar-17 14-Apr-17 63

XAC03-33316110 Mechanical Work - Sump pump Installation 7 14-Mar-17 22-Mar-17 63

XAC03-33316120 Mechanical Work - Piping 20 22-Mar-17 14-Apr-17 63

03PMS-BL00.3.3.3.16.2 Electrical Work 56 01-Mar-17 05-May-17 63

03PMS-BL00.3.3.3.16.2.1 Retention Pit / Emergency Pit


03PMS-BL00.3.3.3.16.2 33 28-Mar-17 05-May-17 63

XAC03-33316211 Electrical Work - Retention Pit / Emergency Pit - Consuit / Support 4 28-Mar-17 01-Apr-17 74

XAC03-33316212 Electrical Work - Retention Pit / Emergency Pit - Cabling / Termination 10 14-Apr-17 26-Apr-17 63

XAC03-33316213 Electrical Work - Retention Pit / Emergency Pit - Instrument Installation 2 26-Apr-17 28-Apr-17 63

XAC03-33316214 Electrical Work - Retention Pit / Emergency Pit - Handover to Commissioning Walkdown 1 28-Apr-17 29-Apr-17 63

XAC03-33316215 Electrical Work - Retention Pit / Emergency Pit - Punch Clear 4 29-Apr-17 04-May-17 63

XAC03-33316216 Electrical Work - Retention Pit / Emergency Pit - Handover to Commissioning 1 04-May-17 05-May-17 63

03PMS-BL00.3.3.3.16.2.2 Oily Water Separator


03PMS-BL00.3.3.3.16.2 21 01-Mar-17 25-Mar-17 98

XAC03-33316221 Electrical Work - Oily Water Separator - Consuit / Support 3 01-Mar-17 04-Mar-17 98

XAC03-33316222 Electrical Work - Oily Water Separator - Cabling / Termination 4 04-Mar-17 09-Mar-17 98

XAC03-33316223 Electrical Work - Oily Water Separator - Instrument Installation 1 09-Mar-17 10-Mar-17 98

XAC03-33316224 Electrical Work - Oily Water Separator - Handover to Commissioning Walkdown 1 10-Mar-17 11-Mar-17 98

XAC03-33316225 Electrical Work - Oily Water Separator - Punch Clear 5 11-Mar-17 17-Mar-17 98

XAC03-33316226 Electrical Work - Oily Water Separator - Handover to Commissioning 1 25-Mar-17 25-Mar-17 98

03PMS-BL00.3.3.3.16.2.3 CT/CWP Area Pit


03PMS-BL00.3.3.3.16.2 14 04-Mar-17 20-Mar-17 103

XAC03-33316231 Electrical Work - Oily Water Separator - Consuit / Support 3 04-Mar-17 07-Mar-17 103

XAC03-33316232 Electrical Work - Oily Water Separator - Cabling / Termination 4 08-Mar-17 11-Mar-17 103

XAC03-33316233 Electrical Work - Oily Water Separator - Instrument Installation 1 13-Mar-17 13-Mar-17 103

XAC03-33316234 Electrical Work - Oily Water Separator - Handover to Commissioning Walkdown 1 14-Mar-17 14-Mar-17 103

XAC03-33316235 Electrical Work - Oily Water Separator - Punch Clear 4 15-Mar-17 18-Mar-17 103

XAC03-33316236 Electrical Work - Oily Water Separator - Handover to Commissioning 1 20-Mar-17 20-Mar-17 103

03PMS-BL00.3.3.3.16.3 Retention/Emergency Pit 31 20-Feb-17 28-Mar-17 74

XAC03-33316310 Retention Pit - Piping Retention Basin Pit Piping Installation 26 20-Feb-17* 22-Mar-17 79

XAC03-33316320 Retention Pit - Mechanical Retention Pit / Emergency Pump Installation 5 22-Mar-17 28-Mar-17 74

03PMS-BL00.3.3.3.16.4 Auxiliary Transformer Area Drain Pit 19 09-Mar-17 30-Mar-17 60

XAC03-33316410 Auxiliary Transformer Area Drain Pit - Sump Pump for pit 1 & 2 Installation 5 09-Mar-17 14-Mar-17 60

XAC03-33316420 Auxiliary Transformer Area Drain Pit - Piping to Oil Water Separator Sump Pit 14 14-Mar-17 30-Mar-17 60

XAC03-33316430 Auxiliary Transformer Area Drain Pit - Handover to Comm. prior to Tr pre-commissioning 0 30-Mar-17 60

03PMS-BL00.3.3.3.16.5 Step Up / UAT Transform er Area Drain Pit 41 01-Feb-17 20-Mar-17 52

XAC03-33316510 Step Up / UAT Transformer Area Drain Pit - Sump Pump Installation 5 01-Feb-17 06-Feb-17 52

XAC03-33316520 Step Up / UAT Transformer Area Drain Pit - Piping to Oil Water Seperator Sump Pit 36 06-Feb-17 20-Mar-17 52

XAC03-33316530 Step Up / UAT Transformer Area Drain Pit - Handover to Comm. prior to Tr 0 20-Mar-17 52
pre-commissioning
03PMS-BL00.3.3.3.16.6 GTG Oily Drain Pit 67 01-Feb-17 19-Apr-17 77

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:47 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33316610 GTG Oily Drain Pit - Sump Pump for pit 1 & 2 Installation 5 01-Feb-17 06-Feb-17 109

XAC03-33316620 GTG Oily Drain Pit - Piping to Oil Water Separator Sump Pit 30 16-Mar-17 19-Apr-17 77

XAC03-33316630 GTG Oily Drain Pit - Handover to Comm. prior to Tr pre-commissioning 0 19-Apr-17 77

03PMS-BL00.3.3.3.16.7 Oil Water Separator Sump Pit 24 02-Feb-17 01-Mar-17 98

XAC03-33316720 Oil Water Separator Sump Pit - Retention Basin Pit Piping Installation 24 02-Feb-17* 01-Mar-17 50

XAC03-33316710 Oil Water Separator Sump Pit - Mechanical Retention Pit Pump Installation 2 27-Feb-17 01-Mar-17 98

03PMS-BL00.3.3.3.16.8 HRSG Blowdown Tank Pit Sump 41 22-Mar-17 09-May-17 71

XAC03-33316810 HRSG Blowdown Tank Pit Sump - Sump Pump for pit 1 & 2 Installation 10 22-Mar-17 03-Apr-17 71

XAC03-33316820 HRSG Blowdown Tank Pit Sump - Piping to CT Area basin 31 03-Apr-17 09-May-17 71

XAC03-33316830 HRSG Blowdown Tank Pit Sump - Handover to Comm. prior to Simple Cycle opreration 0 09-May-17 71

03PMS-BL00.3.3.3.16.A CEP Pit Sump 29 27-Mar-17 29-Apr-17 136

XAC03-33316A10 CEP Pit Sump - Sump Pump Installation 5 27-Mar-17 01-Apr-17 136

XAC03-33316A20 CEP Pit Sump - Piping to Oil Water Separator Sump Pit 24 01-Apr-17 29-Apr-17 136

XAC03-33316A30 CEP Pit Sump - Handover to Comm. prior to CEP commissioning 0 29-Apr-17 136

03PMS-BL00.3.3.3.16.B CT/CWP Area Pit 26 02-Feb-17 03-Mar-17 103

XAC03-33316B20 CT/CWP Area Pit - Piping to Retention Pit 26 02-Feb-17* 03-Mar-17 93

XAC03-33316B10 CT/CWP Area Pit - Sump Pump Installation 2 02-Mar-17* 03-Mar-17 103

03PMS-BL00.3.3.3.16.C STG Area Pit 35 07-Apr-17 17-May-17 106

XAC03-33316C10 STG Area Pit - Sump Pump Installation 5 07-Apr-17 12-Apr-17 106

XAC03-33316C20 STG Area Pit - Piping to Retention Pit 30 13-Apr-17 17-May-17 106

XAC03-33316C30 STG Area Pit - Handover to Comm. prior to Combined Cycle 0 17-May-17 106

03PMS-BL00.3.3.3.16.D EDG Oily Drain Pit Sump 35 03-Apr-17 13-May-17 61

XAC03-33316D10 EDG Oily Drain Pit Sump - Sump Pump Installation 5 03-Apr-17 08-Apr-17 61

XAC03-33316D20 EDG Oily Drain Pit Sump - Piping to Oil Water Separator 30 08-Apr-17 12-May-17 61

XAC03-33316D30 EDG Oily Drain Pit Sump - Handover to Comm. prior to EDG Commissioning 0 13-May-17 61

03PMS-BL00.3.3.3.16.E GT Water Wash Pit 35 01-Feb-17 13-Mar-17 52

XAC03-33316E10 GT Water Wash Pit - Sump Pump Installation 5 01-Feb-17 06-Feb-17 52

XAC03-33316E20 GT Water Wash Pit - Piping 30 06-Feb-17 13-Mar-17 52

XAC03-33316E30 GT Water Wash Pit - Handover to Comm. prior to Combined Cycle 0 13-Mar-17 52

03PMS-BL00.3.3.3.17 Instrument
Ins & Service Air System (Common) 164 06-Feb-17 12-Aug-17 150

03PMS-BL00.3.3.3.17.0 Interface 114 06-Feb-17 16-Jun-17 171

XAC03-33317010 Interface - Instrument & Service Air System - MHO Pipe 0 06-Feb-17* 285

XAC03-33317020 Interface - Instrument & Service Air System - CTO 0 31-Mar-17* 214

XAC03-33317030 Interface - Instrument & Service Air System - MC 0 02-Jun-17 12

XAC03-33317040 Interface - Instrument & Service Air System - TOP 0 16-Jun-17 0

03PMS-BL00.3.3.3.17.1 Piping Work 130 16-Mar-17 12-Aug-17 150

XAC03-33317110 Piping Work - On HRSG Pipe Rack 10 16-Mar-17* 27-Mar-17 252

XAC03-33317120 Piping Work - On GTG Pipe Rack 33 01-Apr-17 10-May-17 214

XAC03-33317130 Piping Work - At Compressor Area to Pipe Rack 33 05-Apr-17* 12-May-17 12

XAC03-33317140 Piping Work - At WTP Area 20 05-Apr-17* 27-Apr-17 34

XAC03-33317150 Piping Work - Line Check 2 28-Apr-17 29-Apr-17 34

XAC03-33317160 Piping Work - Punch Clear 3 01-May-17 03-May-17 34

XAC03-33317170 Piping Work - Pneumatic Test 3 04-May-17 06-May-17 34

XAC03-33317180 Piping Work - Punch Clear 12 13-May-17 26-May-17 12

XAC03-33317190 Piping Work - Pneumatic Test 6 27-May-17 02-Jun-17 12

XAC03-333171A0 Piping Work - In STG Building 18 24-Jul-17 12-Aug-17 150

03PMS-BL00.3.3.3.18 Fu
Fuel Gas Distribution System 153 02-Feb-17 28-Jul-17 0

03PMS-BL00.3.3.3.18.0 Interface 153 02-Feb-17 28-Jul-17 0

XAC03-3331801A Interface - MHO Fuel Gas Filter - Fuel Gas Distribution System 0 02-Feb-17* 83

XAC03-33318020 Interface - CTO - Fuel Gas Distribution System 0 04-Feb-17* 82

XAC03-3331801B Interface - MHO Fuel Gas Pipe - Fuel Gas Distribution System 0 22-Feb-17* 41

XAC03-33318030 Interface - MC - Fuel Gas Distribution System 0 17-Jul-17* 5

XAC03-33318040 Interface - TOP - Fuel Gas Distribution System 0 28-Jul-17* 0

03PMS-BL00.3.3.3.18.1 Mechanical Work 15 04-Feb-17 22-Feb-17 82

XAC03-33318110 Mechanical Work - Gas Filter #31 Installation 5 04-Feb-17 10-Feb-17 82

XAC03-33318120 Mechanical Work - Gas Filter #32 Installation 6 15-Feb-17 22-Feb-17 82

03PMS-BL00.3.3.3.18.2 Piping Work 107 23-Feb-17 26-Jun-17 22

XAC03-33318210 Piping Work - On BOP Pipe Rack-Raw water 35 23-Feb-17* 04-Apr-17 41

XAC03-33318240 Piping Work - On Main Pipe Rack RE 32 28-Feb-17 06-Apr-17 57

XAC03-33318220 Piping Work - To FG Filter Skid #31 6 05-Apr-17 11-Apr-17 42

XAC03-33318230 Piping Work - To FG Filter Skid #32 6 05-Apr-17 11-Apr-17 41

XAC03-33318250 Piping Work - Filter Skid to GT#31 4 12-Apr-17 15-Apr-17 42

XAC03-33318260 Piping Work - Filter Skid to GT#32 6 12-Apr-17 18-Apr-17 41

XAC03-33318270 Piping Work - NDE (PT) 7 17-Apr-17 24-Apr-17 42

XAC03-33318280 Piping Work - Line Check 1 18-Apr-17 19-Apr-17 41

XAC03-33318290 Piping Work - Punch Clear 4 19-Apr-17 24-Apr-17 41

XAC03-333182A0 Piping Work - Pig Clean 4 24-Apr-17 28-Apr-17 41

XAC03-333182B0 Piping Work - Pneumatic Test 3 28-Apr-17 02-May-17 41

XAC03-333182C0 Piping Work - DOE Approval 29 02-May-17 05-Jun-17 41

XAC03-333182D0 Piping Work - Handover to Commissioning Walkdown 1 19-Jun-17* 19-Jun-17 22

XAC03-333182E0 Piping Work - Punch Clear 5 20-Jun-17 24-Jun-17 22

XAC03-333182F0 Piping Work - Handover to Commissioning 1 26-Jun-17 26-Jun-17 22

03PMS-BL00.3.3.3.19 Fuel
Fu Gas Heater System 153 02-Feb-17 27-Jul-17 4

03PMS-BL00.3.3.3.19.0 Interface 153 02-Feb-17 27-Jul-17 4

XAC03-33319010 Interface - MHO - Fuel Gas Heater 0 02-Feb-17* 121

XAC03-33319020 Interface - CTO - Fuel Gas Heater 0 04-Mar-17* 97

XAC03-33319030 Interface - MC - Fuel Gas Heater 0 17-Jul-17* 4

XAC03-33319040 Interface - TOP - Fuel Gas Heater 0 27-Jul-17 4

03PMS-BL00.3.3.3.19.1 Mechanical Work 3 04-Mar-17 08-Mar-17 97

XAC03-33319110 Mechanical Work - Fuel Gas Heater Installation 3 04-Mar-17 08-Mar-17 97

03PMS-BL00.3.3.3.19.2 Piping Work 21 08-Mar-17 31-Mar-17 106

XAC03-33319210 Piping Work - Fuel Gas Heater 15 08-Mar-17 24-Mar-17 97

XAC03-33319220 Piping Work - Line Check 2 24-Mar-17 27-Mar-17 97

XAC03-33319230 Piping Work - Punch Clear 3 27-Mar-17 30-Mar-17 97

XAC03-33319240 Piping Work - Pneumatic Test 1 30-Mar-17 31-Mar-17 106

03PMS-BL00.3.3.4 Electrical
Electri Package 341 08-Aug-16 06-Sep-17 129

03PMS-BL00.3.3.4.01 Generator
Ge Transformer 133 07-Jan-17 12-Jun-17 109

03PMS-BL00.3.3.4.01.0 Interface 133 07-Jan-17 12-Jun-17 109

XAC03-33401020 Interface - CTO - Generator Transformer 0 07-Jan-17 68

XAC03-33401010 Interface - MHO - Generator Transformer 0 09-Mar-17* 8

XAC03-3340103A Interface - MC - Generator Transformer (GTG#31,32) 0 18-Apr-17* 27

XAC03-3340103B Interface - MC - Generator Transformer (STG#30) 0 25-Apr-17* 30

XAC03-3340104A Interface - TOP - Generator Transformer (GTG#31,32) 0 12-Jun-17* 44

XAC03-3340104B Interface - TOP - Generator Transformer (STG#30) 0 12-Jun-17* 109

03PMS-BL00.3.3.4.01.1 GSUT 31 27 09-Mar-17 10-Apr-17 27

XAC03-33401110 GSUT 31 - On Base 1 09-Mar-17 09-Mar-17 8

XAC03-33401120 GSUT 31 - Assembly 13 16-Mar-17 31-Mar-17 8

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:48 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33401130 GSUT 31 - Insulation Oil Treatment and Filling 7 01-Apr-17 10-Apr-17 27

03PMS-BL00.3.3.4.01.2 GSUT 32 34 09-Mar-17 17-Apr-17 27

XAC03-33401210 GSUT 32 - On Base 1 09-Mar-17 09-Mar-17 16

XAC03-33401220 GSUT 32 - Assembly 13 16-Mar-17 31-Mar-17 16

XAC03-33401230 GSUT 32 - Insulation Oil Treatment and Filling 7 10-Apr-17 17-Apr-17 27

03PMS-BL00.3.3.4.01.3 ST 30 Tr 40 10-Mar-17 25-Apr-17 27

XAC03-33401310 ST 30 Transformer - On Base 1 10-Mar-17 10-Mar-17 34

XAC03-33401320 ST 30 Transformer - Assembly 13 17-Mar-17 01-Apr-17 34

XAC03-33401330 ST 30 Transformer - Insulation Oil Treatment and Filling 7 17-Apr-17 25-Apr-17 27

03PMS-BL00.3.3.4.02 Un
Unit Auxiliary Transformer 81 09-Mar-17 10-Jun-17 0

03PMS-BL00.3.3.4.02.0 Interface 81 09-Mar-17 10-Jun-17 0

XAC03-33402020 Interface - CTO - Unit Auxiliary Transformer 0 09-Mar-17* 60

XAC03-33402010 Interface - MHO - Unit Auxiliary Transformer 0 09-Mar-17* 47

XAC03-33402030 Interface - MC - Unit Auxiliary Transformer 0 03-May-17 27

XAC03-3340204B Interface - TOP - Unit Auxiliary Transformer (Ready for Power Receiving) 0 10-Jun-17 0

03PMS-BL00.3.3.4.02.1 Electrical Work 47 10-Mar-17 03-May-17 27

XAC03-33402110 Unit Axiliary Transformer - On Base 1 10-Mar-17 10-Mar-17 47

XAC03-33402120 Unit Axiliary Transformer - Assembly 13 17-Mar-17 01-Apr-17 47

XAC03-33402130 Unit Axiliary Transformer - Insulation Oil Treatment and Filling 7 25-Apr-17 03-May-17 27

03PMS-BL00.3.3.4.03 MV Switchgear 142 30-Dec-16 12-Jun-17 0

03PMS-BL00.3.3.4.03.0 Interface 142 30-Dec-16 12-Jun-17 0

XAC03-33403020 Interface - CTO - MV Switchgear 0 30-Dec-16* 50

XAC03-33403010 Interface - MHO - MV Switchgear 0 30-Dec-16* 100

XAC03-33403030 Interface - MC - MV Switchgear 0 10-Mar-17* 68

XAC03-33403040 Interface - TOP - MV Switchgear 0 12-Jun-17 0

03PMS-BL00.3.3.4.03.1 Electrical Work 61 30-Dec-16 09-Mar-17 68

XAC03-33403120 6.6kV Switchgear - Electrical Work - channel base setting & on base 2 30-Dec-16 31-Dec-16 100

XAC03-33403110 6.6kV Switchgear - Electrical Work - Cabling (Power & Control/Panel to Panel) 55 30-Dec-16 02-Mar-17 50

XAC03-33403130 6.6kV Switchgear - Electrical Work - 6.6kV SWGR Install 9 02-Jan-17 12-Jan-17 100

XAC03-33403140 6.6kV Switchgear - Electrical Work - busbar connection 8 12-Jan-17 20-Jan-17 100

XAC03-33403150 6.6kV Switchgear - Electrical Work - busbar torque check (RFI) 1 21-Jan-17 21-Jan-17 100

XAC03-33403160 6.6kV Switchgear - Electrical Work - Hipot Test Busbar 2 23-Jan-17 24-Jan-17 100

XAC03-33403170 6.6kV Switchgear - Electrical Work - Handover to Commissioning Walkdown 1 03-Mar-17 03-Mar-17 68

XAC03-33403180 6.6kV Switchgear - Electrical Work - Punch Clear 4 04-Mar-17 08-Mar-17 68

XAC03-33403190 6.6kV Switchgear - Electrical Work - Handover to Commissioning 1 09-Mar-17 09-Mar-17 68

03PMS-BL00.3.3.4.04 LV Switchgear 163 09-Dec-16 16-Jun-17 0

03PMS-BL00.3.3.4.04.0 Interface 163 09-Dec-16 16-Jun-17 0

XAC03-3340402A Interface - CTO - LV Switchgear 0 09-Dec-16 82

XAC03-3340401A Interface - MHO - LV Switchgear 0 06-Jan-17* 100

XAC03-33404030 Interface - MC - LV Switchgear 0 03-Apr-17* 50

XAC03-33404040 Interface - TOP - LV Switchgear 0 16-Jun-17* 0

03PMS-BL00.3.3.4.04.1 AC LV Power System #30 76 06-Jan-17 03-Apr-17 50

XAC03-33404120 LV Switchgear (CCB 1F) - Electrical Work - Channel Base setting 2 06-Jan-17 07-Jan-17 100

XAC03-33404130 LV Switchgear (CCB 1F) - Electrical Work - 400V Main Switchgear Install 5 09-Jan-17 13-Jan-17 100

XAC03-33404140 LV Switchgear (CCB 1F) - Electrical Work - 400V Sub Switchgear Install 5 14-Jan-17 19-Jan-17 100

XAC03-33404110 LV Switchgear (CCB 1F) - Electrical Work - Cabling (Power & Control/Panel to Panel) 60 16-Jan-17 25-Mar-17 50

XAC03-33404150 LV Switchgear (CCB 1F) - Electrical Work - 400V Essential Switchgear Install 6 20-Jan-17 27-Jan-17 100

XAC03-33404160 LV Switchgear (CCB 1F) - Electrical Work - Handover to Commissioning Walkdown 1 27-Mar-17 27-Mar-17 50

XAC03-33404170 LV Switchgear (CCB 1F) - Electrical Work - Punch Clear 5 28-Mar-17 01-Apr-17 50

XAC03-33404180 LV Switchgear (CCB 1F) - Electrical Work - Handover to Commissioning 1 03-Apr-17 03-Apr-17 50

03PMS-BL00.3.3.4.05 LV Transformer 117 30-Jan-17 13-Jun-17 0

03PMS-BL00.3.3.4.05.0 Interface 117 30-Jan-17 13-Jun-17 0

XAC03-33405020 Interface - CTO - LV Transformer 0 30-Jan-17* 81

XAC03-33405010 Interface - MHO - LV Transformer 0 30-Jan-17* 81

XAC03-33405030 Interface - MC - LV Transformer 0 10-Mar-17* 75

XAC03-33405040 Interface - TOP - LV Transformer 0 13-Jun-17 0

03PMS-BL00.3.3.4.05.1 Electrical Work 28 30-Jan-17 02-Mar-17 81

XAC03-33405110 LV Transformer - Electrical Works - On base 1 30-Jan-17* 30-Jan-17 81

XAC03-33405120 LV Transformer - Electrical Works - Installation (cable tray, cables) 27 31-Jan-17 02-Mar-17 81

03PMS-BL00.3.3.4.06 Mo
Motor Control Center /Distribution Panel 163 09-Dec-16 16-Jun-17 14

03PMS-BL00.3.3.4.06.0 Interface 163 09-Dec-16 16-Jun-17 14

XAC03-33406020 Interface - MCC/Distribution Panel - CTO (ECB) 0 09-Dec-16 130

XAC03-33406010 Interface - MCC/Distribution Panel - MHO (ECB) 0 13-Jan-17* 102

XAC03-3340401B Interface - MCC/Distribution Panel - MHO (HRSG LCB) 0 14-Mar-17 45

XAC03-3340402B Interface - MCC/Distribution Panel - CTO (HRSG LCB) 0 14-Mar-17 45

XAC03-3340603A Interface - MCC/Distribution Panel - MC (ECB) 0 03-Apr-17* 71

XAC03-3340603B Interface - MCC/Distribution Panel - MC (HRSG LCB) 0 27-Apr-17* 57

XAC03-3340604B Interface - MCC/Distribution Panel - TOP (HRSC LCB) 0 05-Jun-17* 24

XAC03-3340604A Interface - MCC/Distribution Panel - TOP (ECB) 0 16-Jun-17* 6

03PMS-BL00.3.3.4.06.1 Electrical Work (ECB) 65 13-Jan-17 29-Mar-17 76

XAC03-33406110 Electrical Work - Install MCC & DCS Panel 5 13-Jan-17 18-Jan-17 102

XAC03-33406120 Electrical Work - Cabling Work 33 18-Jan-17 25-Feb-17 102

XAC03-33406130 Electrical Work - Devices, Conduit & Cabling Install 12 15-Mar-17 29-Mar-17 76

03PMS-BL00.3.3.4.06.2 Electrical Work (HRSG LCB) 50 15-Mar-17 11-May-17 45

XAC03-33406210 Electrical Work - Install MCC & DCS Panel 5 15-Mar-17 20-Mar-17 45

XAC03-33406220 Electrical Work - Cabling Work 33 20-Mar-17 27-Apr-17 45

XAC03-33406230 Electrical Work - Devices, Conduit & Cabling Install 12 27-Apr-17 11-May-17 45

03PMS-BL00.3.3.4.07 DC System & UPS System 61 01-Feb-17 13-Apr-17 12

03PMS-BL00.3.3.4.07.0 Interface 61 01-Feb-17 13-Apr-17 12

XAC03-33407020 Interface - CTO - DC / UPS System 0 01-Feb-17* 12

XAC03-33407010 Interface - MHO - DC / UPS System 0 02-Feb-17* 12

XAC03-33407030 Interface - MC - DC / UPS System 0 17-Mar-17* 22

XAC03-33407040 Interface - TOP - DC / UPS System 0 13-Apr-17* 12

03PMS-BL00.3.3.4.07.1 Battery & Charger System #30 16 02-Feb-17 20-Feb-17 12

XAC03-33407110 Electrical Work - Battery & Charger Hauling 3 02-Feb-17 04-Feb-17 12

XAC03-33407120 Electrical Work - Battery Rack Assembly 2 04-Feb-17 07-Feb-17 12

XAC03-33407130 Electrical Work - 220V DC Battery Install 11 08-Feb-17 20-Feb-17 12

03PMS-BL00.3.3.4.07.2 UPS System #30 22 21-Feb-17 17-Mar-17 12

XAC03-33407210 Electrical Work - 220V Charger Panel Install 4 21-Feb-17 24-Feb-17 12

XAC03-33407220 Electrical Work - 220V DC Distribution Board Install 3 24-Feb-17 28-Feb-17 12

XAC03-33407230 Electrical Work - Cable Pulling 7 01-Mar-17 08-Mar-17 12

XAC03-33407240 Electrical Work - Cable Termination 6 09-Mar-17 15-Mar-17 12

XAC03-33407250 Electrical Work - Cable Megger & Continuity Check (RFI) 2 16-Mar-17 17-Mar-17 12

03PMS-BL00.3.3.4.08 Emergency
Em DG System 133 30-Jan-17 04-Jul-17 25

03PMS-BL00.3.3.4.08.0 Interface 133 30-Jan-17 04-Jul-17 25

XAC03-33408020 Interface - Emergency DG System - CTO 0 30-Jan-17* 113

XAC03-33408010 Interface - Emergency DG System - MHO 0 22-Feb-17* 113

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:49 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33408030 Interface - Emergency DG System - MC 0 13-May-17* 61

XAC03-33408040 Interface - Emergency DG System - TOP 0 04-Jul-17* 25

03PMS-BL00.3.3.4.08.1 Mechanical Work 4 23-Feb-17 27-Feb-17 113

XAC03-33408110 Mechanical Work - EDG Installation 4 23-Feb-17 27-Feb-17 113

03PMS-BL00.3.3.4.08.2 Piping Work 6 28-Feb-17 06-Mar-17 119

XAC03-33408210 Piping Work - EDG 6 28-Feb-17 06-Mar-17 119

03PMS-BL00.3.3.4.08.3 Electrical Work 12 28-Feb-17 13-Mar-17 113

XAC03-33408310 Electrical Work - Cabling/Termination 5 28-Feb-17 04-Mar-17 113

XAC03-33408320 Electrical Work - Handover Walk Down to Commissioning 1 07-Mar-17 07-Mar-17 113

XAC03-33408330 Electrical Work - Punch Clear 4 08-Mar-17 11-Mar-17 113

XAC03-33408340 Electrical Work - Handover to Commissioning 1 13-Mar-17 13-Mar-17 113

03PMS-BL00.3.3.4.09 Cable
Ca & Raceway 341 08-Aug-16 06-Sep-17 129

03PMS-BL00.3.3.4.09.0 Interface 341 08-Aug-16 06-Sep-17 129

XAC03-3340902I Interface - CTO - Cable Trench 6 (GSU Transformer area) 0 08-Aug-16 470

XAC03-3340902J Interface - CTO - Cable Trench (STG#30 - Pipe Rack RB) 0 15-Aug-16 465

XAC03-3340902A Interface - CTO - Cable & Raceway - E&C Building Ground Floor 0 27-Aug-16 100

XAC03-3340902K Interface - CTO - Cable Trench (STG#30 - Pipe Rack RB Road Crossing) 0 01-Sep-16 449

XAC03-3340902R Interface - CTO - Sleeper FDN for SWYD - Pipe Rack RB 0 14-Sep-16 438

XAC03-3340902L Interface - CTO - Cable Trench (STG Building) 0 19-Sep-16 434

XAC03-3340902M Interface - CTO - Cable Trench (GTG #31 Area) 33.00m 0 22-Sep-16 430

XAC03-3340901A Interface - MHO - Cable & Raceway - lot 1(ABPR3 Power Received) 0 11-Oct-16* 63

XAC03-3340902S Interface - CTO - Pipe Rack RB (BOP Area Road Crossing) 0 25-Nov-16 375

XAC03-3340902N Interface - CTO - Cable Trench (GTG #32 Area) 33.00m 0 28-Nov-16 374

XAC03-3340901B Interface - MHO - Cable & Raceway - lot 2 (Initial Fire) 0 15-Dec-16* 154

XAC03-3340902H Interface - CTO - Cable Trench (Road Crossing STG #30 - SWYD) 33.00 m. 0 03-Jan-17 343

XAC03-3340902D Interface - CTO - Cable & Raceway - E&C Building 1st Floor 0 07-Jan-17 8

XAC03-3340902C Interface - CTO - Cable & Raceway - (ABPR3 P/R btwn SWYD and ECB) 0 07-Jan-17* 14

XAC03-3340902G Interface - CTO - Cable Trench (E&C Building - Pipe Rack RE) 0 07-Jan-17 338

XAC03-3340902E Interface - CTO - Cable & Raceway - E&C Building 2nd Floor 0 12-Jan-17 1

XAC03-3340901C Interface - MHO - Cable & Raceway - lot 3 (ABPR3 Combined) 0 13-Jan-17* 54

XAC03-3340902B Interface - CTO - Cable & Raceway - E&C Building 3rd Floor 0 24-Jan-17 31

XAC03-3340902O Interface - CTO - Cable Trench (Road Crossing GTG 31 - SWYD ) 33.00 m. 0 28-Jan-17 319

XAC03-3340902Q Interface - CTO - Cable Trench (Road Crossing GTG 32 - E&C Building ) 33.00 m. 0 30-Jan-17 318

XAC03-3340902F Interface - CTO - Cable & Raceway - All Pipe Rack (ABPR3 Area) 0 10-Apr-17* 219

XAC03-3340903A Interface - MC - Cable & Raceway - (ABPR31 Initial Fire) 0 10-Apr-17* 54

XAC03-3340903B Interface - MC - Cable & Raceway - (ABPR3 Power Receive) 0 18-Apr-17* 252

XAC03-3340902P Interface - CTO - Cable Trench (Road Crossing GTG 32 - SWYD ) 33.00 m. 0 09-Jun-17 205

XAC03-3340903C Interface - MC - Cable & Raceway - (ABPR3 Combined) 0 06-Sep-17* 129

03PMS-BL00.3.3.4.09.1 Electrical Work 104 11-Oct-16 07-Feb-17 31

XAC03-33409110 Raceway Installation in E&C -Tray Installation GF (X1-X5) 26 11-Oct-16 09-Nov-16 63

XAC03-33409130 Raceway Installation in E&C -Tray Installation GF (X5-X7) 18 29-Oct-16 19-Nov-16 57

XAC03-33409120 Raceway Installation in E&C -Tray Installation 1F (X1-X5) 8 04-Nov-16 12-Nov-16 63

XAC03-33409140 Raceway Installation in E&C -Tray Installation 1F (X5-X7) 6 09-Jan-17 14-Jan-17 8

XAC03-33409150 Raceway Installation in E&C -Tray Installation 2F (X1-X5) 9 12-Jan-17* 23-Jan-17 1

XAC03-33409160 Raceway Installation in E&C -Tray Installation 2F (X5-X7) 7 16-Jan-17 23-Jan-17 1

XAC03-33409170 Raceway Installation in E&C -Tray Installation 3F 12 25-Jan-17 07-Feb-17 31

03PMS-BL00.3.3.5 C & I Package


P 199 12-Jan-17 31-Aug-17 134

03PMS-BL00.3.3.5.01 DCS
DC 177 08-Feb-17 31-Aug-17 134

03PMS-BL00.3.3.5.01.0 Interface 164 23-Feb-17 31-Aug-17 134

XAC03-3350102A Interface - CTO (E&C Building Panel Installation) 0 23-Feb-17* 36

XAC03-33501010 Interface - MHO - DCS (3F 0 23-Feb-17* 46

XAC03-3350102B Interface - CTO (HRSG Control Building Panel Installation) 0 14-Mar-17 281

XAC03-3350103A Interface - MC for ABPR3 Power Receiving 0 13-Apr-17* 29

XAC03-3350103B Interface - MC for BOP system 0 24-Apr-17* 47

XAC03-3350103C Interface - MC for ABPR3 GTG#1 I/F 0 24-Apr-17* 230

XAC03-3350104A Interface - TOP for Power Recieving 0 17-May-17* 0

XAC03-3350104B Interface - TOP for BOP system 0 08-Jun-17* 8

XAC03-3350103D Interface - MC for ABPR3 STG Steam Blowing out 0 03-Jul-17* 57

XAC03-3350104C Interface - TOP for ABPR3 GTG#1 I/F 0 01-Aug-17* 145

XAC03-3350104D Interface - TOP for ABPR3 Steam Blowing out 0 31-Aug-17* 5

03PMS-BL00.3.3.5.01.1 Electrical Work 36 08-Feb-17 21-Mar-17 31

XAC03-33501130 Electrical Wok - DCS (3F) - DCS Cable Pulling & Termination for Power Receiving Area 33 08-Feb-17 17-Mar-17 31

XAC03-33501110 Electrical Wok - DCS (3F) - Channel Base Material at Site 0 23-Feb-17 36

XAC03-33501120 Electrical Wok - DCS (3F) - Channel Base Setting 9 23-Feb-17 04-Mar-17 36

XAC03-33501140 Electrical Wok - DCS (3F) - DCS Installation 6 06-Mar-17 11-Mar-17 36

XAC03-33501150 Electrical Wok - DCS (3F) - Comissioning Handover Walk Down 1 18-Mar-17 18-Mar-17 31

XAC03-33501160 Electrical Wok - DCS (3F) - Punch Clear 1 20-Mar-17 20-Mar-17 31

XAC03-33501170 Electrical Wok - DCS (3F) - Handover to Commissioning 1 21-Mar-17 21-Mar-17 31

03PMS-BL00.3.3.5.02 St
Steam and Water Sampling System 126 02-Feb-17 28-Jun-17 55

03PMS-BL00.3.3.5.02.0 Interface 126 02-Feb-17 28-Jun-17 55

XAC03-3350201A Interface - MHO (Sampling Pipe) 0 02-Feb-17* 95

XAC03-3350201B Interface - MHO (Rack) 0 10-Mar-17* 133

XAC03-33502020 Interface - CTO SWAS 0 15-Mar-17* 129

XAC03-33502030 Interface - MC 0 29-May-17* 78

XAC03-33502040 Interface - TOP 0 28-Jun-17* 55

03PMS-BL00.3.3.5.02.1 Mechanical Work 1 15-Mar-17 16-Mar-17 129

XAC03-33502110 Mechanical Work - Sampling Rack Installation 1 15-Mar-17 16-Mar-17 129

03PMS-BL00.3.3.5.02.2 Piping #31 Work 34 02-Feb-17 13-Mar-17 95

XAC03-33502210 Piping #31 Work 34 02-Feb-17 13-Mar-17 95

03PMS-BL00.3.3.5.02.3 Piping #32 work 41 14-Mar-17 29-Apr-17 95

XAC03-33502310 Piping #32 Work 41 14-Mar-17 29-Apr-17 95

03PMS-BL00.3.3.5.02.4 Electrical Work 46 16-Mar-17 08-May-17 95

XAC03-33502410 Electrical Work - Conduit/Cabling 5 16-Mar-17 22-Mar-17 129

XAC03-33502420 Electrical Work - System Handover Walk Down 1 01-May-17 01-May-17 95

XAC03-33502430 Electrical Work - Punch Clear 5 02-May-17 06-May-17 95

XAC03-33502440 Electrical Work - Handover to Commissioning 1 08-May-17 08-May-17 95

03PMS-BL00.3.3.5.03 Co
Continuous Emission Monitoring System 122 10-Mar-17 28-Jul-17 3

03PMS-BL00.3.3.5.03.0 Interface 122 10-Mar-17 28-Jul-17 3

XAC03-33503020 Interface - CTO 0 10-Mar-17* 59

XAC03-33503010 Interface - MHO 0 13-May-17* 3

XAC03-33503030 Interface - MC 0 28-Jun-17* 3

XAC03-33503040 Interface - TOP 0 28-Jul-17* 3

03PMS-BL00.3.3.5.03.1 Mechanical Work 40 13-May-17 28-Jun-17 3

XAC03-33503110 Mechanical Work - Installation 1 13-May-17* 13-May-17 3

XAC03-33503120 Mechanical Work - Tubing Installation 33 15-May-17 22-Jun-17 3

XAC03-33503130 Mechanical Work - Handover to Commissioning 1 22-Jun-17 22-Jun-17 3

XAC03-33503140 Mechanical Work - Punch Clear 4 23-Jun-17 27-Jun-17 3

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:50 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-33503150 Mechanical Work - Handover to Commissioning 1 28-Jun-17 28-Jun-17 3

03PMS-BL00.3.3.5.04 Clock
Cl System 44 09-May-17 28-Jun-17 23

03PMS-BL00.3.3.5.04.0 Interface 0 09-May-17 09-May-17 23

XAC03-33504010 MHO - Clock System 0 09-May-17* 23

03PMS-BL00.3.3.5.04.1 Electrical Work 44 09-May-17 28-Jun-17 23

XAC03-33504110 Electrical Work - Clock System Installation 14 09-May-17 24-May-17 23

XAC03-33504120 Electrical Work - Cable Pulling 30 24-May-17 28-Jun-17 23

03PMS-BL00.3.3.5.05 Co
Communication System (Common) 141 12-Jan-17 24-Jun-17 33

03PMS-BL00.3.3.5.05.0 Interface 141 12-Jan-17 24-Jun-17 33

XAC03-33505020 CTO - Communication System 0 12-Jan-17 123

XAC03-3350501A MHO - Lot - 1 Communication Bulk Materials 0 30-Jan-17 108

XAC03-3350501B MHO - Lot - 2 Communication System 0 11-Mar-17* 73

XAC03-33505030 MC - Communication System 0 16-Jun-17 33

XAC03-33505040 TOP - Communication System 0 24-Jun-17 33

03PMS-BL00.3.3.5.05.1 Electrical Work 44 27-Apr-17 16-Jun-17 33

XAC03-33505110 Electrical Work - Fixture Installation 39 27-Apr-17 10-Jun-17 33

XAC03-33505120 Electrical Work - Cable Pulling 27 16-May-17 16-Jun-17 33

03PMS-BL00.3.3.5.06 Primary
Pr Energy System 114 23-Feb-17 04-Jul-17 128

03PMS-BL00.3.3.5.06.0 Interface 114 23-Feb-17 04-Jul-17 128

XAC03-33506020 Intercase - CTO - PES Panel Installation 0 23-Feb-17* 191

XAC03-33506010 MHO - PES 0 06-May-17* 128

XAC03-33506030 MC - PES 0 26-Jun-17* 128

XAC03-33506040 TOP - PES 0 04-Jul-17* 128

03PMS-BL00.3.3.5.06.1 Electrical Work 44 06-May-17 26-Jun-17 128

XAC03-33506110 Electrical Work - PES Installation 14 06-May-17 23-May-17 128

XAC03-33506120 Electrical Work - Cable Pulling 30 23-May-17 26-Jun-17 128

03PMS-BL00.3.4 COLD CO
COMMISSIONING WORK 169 01-Apr-17 14-Oct-17 2

03PMS-BL00.3.4.1 Major Equipment Package 104 16-Jun-17 14-Oct-17 2

03PMS-BL00.3.4.1.01 Ga
Gas turbine & Generator #31 (Siemens) 40 16-Jun-17 01-Aug-17 0

XAC03-34101100 GT #31 Cold Commissioning - GT #31 Power Energize 1 16-Jun-17 17-Jun-17 0

XAC03-34101200 GT #31 Cold Commissioning - Pre-Commissioning 23 30-Jun-17 27-Jul-17 0

XAC03-34101300 GT #31 Cold Commissioning - Lube Oil / Control Oil Flushing 6 17-Jul-17 24-Jul-17 0

XAC03-34101400 GT #31 Cold Commissioning - CO2 Spray Test 2 24-Jul-17 26-Jul-17 0

XAC03-34101500 GT #31 Cold Commissioning - Turning Operation Test 3 27-Jul-17 31-Jul-17 0

XAC03-34101600 GT #31 Cold Commissioning - Cranking Test 1 31-Jul-17 01-Aug-17 0

03PMS-BL00.3.4.1.02 Ga
Gas turbine & Generator #32 (Siemens) 23 26-Jul-17 22-Aug-17 0

XAC03-34102100 GT #32 Cold Commissioning - GT #32 Power Energize 1 26-Jul-17 27-Jul-17 1

XAC03-34102200 GT #32 Cold Commissioning - Pre-Commissioning 17 27-Jul-17 16-Aug-17 1

XAC03-34102300 GT #32 Cold Commissioning - Lube Oil / Control Oil Flushing 5 04-Aug-17 10-Aug-17 2

XAC03-34102400 GT #32 Cold Commissioning - CO2 Spray Test 3 10-Aug-17 14-Aug-17 2

XAC03-34102500 GT #32 Cold Commissioning - Turning Operation Test 2 16-Aug-17 18-Aug-17 1

XAC03-34102600 GT #32 Cold Commissioning - Cranking Test 3 19-Aug-17 22-Aug-17 0

03PMS-BL00.3.4.1.05 St
Steam Turbine & Generator (Siemens) 54 12-Aug-17 14-Oct-17 2

03PMS-BL00.3.4.1.05.1 Pre-Commissioning 45 12-Aug-17 04-Oct-17 9

XAC03-34105110 Pre-Commissioning - Checking & Readiness for Operation - Oil-pumps Power-supply 0 12-Aug-17 45

XAC03-34105120 Pre-Commissioning - Checking & Readiness for Operation - Preparingof oil system 1 14-Aug-17 14-Aug-17 45
flushing
XAC03-34105130 Pre-Commissioning - Checking & Readiness for Operation - Oilsystemflushing 3 15-Aug-17 18-Aug-17 45

XAC03-34105140 Pre-Commissioning - Checking & Readiness for Operation - Blowingof steam 0 29-Sep-17 9
piping-Finished
XAC03-34105150 Pre-Commissioning - Checking & Readiness for Operation - Checking of main piping 1 29-Sep-17 30-Sep-17 9
connection
XAC03-34105160 Pre-Commissioning - Checking & Readiness for Operation - Checking of insulation 1 30-Sep-17 02-Oct-17 9
resistance of generator
XAC03-34105170 Pre-Commissioning - Checking & Readiness for Operation - Connection of turbine and 1 30-Sep-17 02-Oct-17 9
generator coupling
XAC03-34105180 Pre-Commissioning - Checking & Readiness for Operation - Close of bearing pedestals 3 30-Sep-17 04-Oct-17 9

XAC03-34105190 Pre-Commissioning - Checking & Readiness for Operation - Installationof turbine and 3 30-Sep-17 04-Oct-17 9
piping insulation
XAC03-341051A0 Pre-Commissioning - Checking & Readiness for Operation - Installation of turbine and 1 03-Oct-17 04-Oct-17 9
piping sensors
XAC03-341051B0 Pre-Commissioning - Checking & Readiness for Operation - Turbine ready for the test 0 04-Oct-17 9

03PMS-BL00.3.4.1.05.2 Cold Test Commissioning 36 02-Sep-17 14-Oct-17 2

XAC03-34105210 Cold tests Commissioning - Electronic control system activation 3 02-Sep-17 07-Sep-17 12

XAC03-34105220 Cold tests Commissioning - Finishing erection check 3 02-Sep-17 07-Sep-17 12

XAC03-34105230 Cold tests Commissioning - Instrument ation activation & Loop test 10 04-Sep-17 16-Sep-17 17

XAC03-34105240 Cold tests Commissioning - Turbine special measurement adjustment 3 07-Sep-17 11-Sep-17 12

XAC03-34105250 Cold tests Commissioning - Putting of eletric consumers into operation 3 11-Sep-17 14-Sep-17 12

XAC03-34105260 Cold tests Commissioning - Puttingof pneumatically driven valves/check valve into 2 14-Sep-17 16-Sep-17 12
operation
XAC03-34105270 Cold tests Commissioning - Adjustment of switches 1 16-Sep-17 18-Sep-17 12

XAC03-34105280 Cold tests Commissioning - Steam Blow Restoration Finished 0 29-Sep-17 0

XAC03-34105290 Cold tests Commissioning - Preliminary oil system preparation 2 29-Sep-17 02-Oct-17 2

XAC03-341052A0 Cold tests Commissioning - Test of HP control oil unit 2 29-Sep-17 02-Oct-17 2

XAC03-341052B0 Cold tests Commissioning - Turning gear put into operation 1 02-Oct-17 03-Oct-17 2

XAC03-341052C0 Cold tests Commissioning - Test of safety block 1 03-Oct-17 04-Oct-17 2

XAC03-341052D0 Cold tests Commissioning - Test of safety block - SAT 1 04-Oct-17 05-Oct-17 2

XAC03-341052E0 Cold tests Commissioning - Speed measurement- SAT 1 04-Oct-17 05-Oct-17 2

XAC03-341052F0 Cold tests Commissioning - Adjustingof turbine control valves/adaptive stage actuators 1 05-Oct-17 06-Oct-17 2

XAC03-341052G0 Cold tests Commissioning - Test of operating automatics 2 05-Oct-17 07-Oct-17 2

XAC03-341052H0 Cold tests Commissioning - Checkof alarm signals and protections 1 05-Oct-17 06-Oct-17 2

XAC03-341052I0 Cold tests Commissioning - Test of turbine protectio ns 1 06-Oct-17 07-Oct-17 7

XAC03-341052J0 Cold tests Commissioning - Binary signals/Buttons- SAT 1 06-Oct-17 07-Oct-17 2

XAC03-341052K0 Cold tests Commissioning - Measurement of levels, pressures and temperatures - SAT 1 06-Oct-17 07-Oct-17 2

XAC03-341052L0 Cold tests Commissioning - ST Interlocking Test 5 07-Oct-17 13-Oct-17 2

XAC03-341052M0 Cold tests Commissioning - STG Interlocking Test 6 07-Oct-17 14-Oct-17 2

XAC03-341052N0 Cold tests Commissioning - Preparationof Gen. protections and AVR for primary tests 3 07-Oct-17 11-Oct-17 2

XAC03-341052O0 Cold tests Commissioning - Cooling systems preparation 2 07-Oct-17 10-Oct-17 2

XAC03-341052P0 Cold tests Commissioning - Condensate systems preparation 2 10-Oct-17 12-Oct-17 2

03PMS-BL00.3.4.2 Unit Package


P 90 01-Apr-17 15-Jul-17 33

03PMS-BL00.3.4.2.04 Water
Wa Treatment Plant (Common) 23 06-Apr-17 03-May-17 8

XAC03-34204300 Pre-Commissioning - PLC Program Loading 19 06-Apr-17* 27-Apr-17 12

XAC03-34204100 Pre-Commissioning - Prepare Temporary Pow er 0 03-May-17* 8

XAC03-34204200 Pre-Commissioning - Prepare Temporary Air (N2) 0 03-May-17* 8

03PMS-BL00.3.4.2.10 Ch
Chemical dosing system for HRSG Unit #30 1 14-Jul-17 15-Jul-17 33

XAC03-34210100 Pre-Commissioning - Sequence Check 1 14-Jul-17 14-Jul-17 33

XAC03-34210200 Pre-Commissioning - Chemical doosing system for HRSG Energize 0 15-Jul-17 33

03PMS-BL00.3.4.2.11 Ch
Chemical dosing system for CT Unit #30 20 01-Apr-17 25-Apr-17 52

XAC03-34211100 Pre-Commissioning - Chemical dosing system Power Receive 0 01-Apr-17 64

XAC03-34211200 Pre-Commissioning - Seaquence check 1 07-Apr-17 08-Apr-17 60

XAC03-34211300 Handover to Commissioning Walkdown 1 18-Apr-17 19-Apr-17 52

XAC03-34211400 Punch Clear 4 20-Apr-17 24-Apr-17 52

XAC03-34211500 Handover to Commissioning 1 25-Apr-17 25-Apr-17 52

03PMS-BL00.3.4.2.15 11
115kV Switch Yard 38 05-Apr-17 18-May-17 18

03PMS-BL00.3.4.2.15.1 Test Work Preparation 2 05-Apr-17 06-Apr-17 1

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:51 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-34215110 Pre-Commissioning - SWYD Work Preparation Site and Tool Mobilization 1 05-Apr-17 05-Apr-17 1

XAC03-34215120 Pre-Commissioning - SWYD Work Preparation Work Preparation 1 06-Apr-17 06-Apr-17 1

03PMS-BL00.3.4.2.15.2 Auxiliary System Test Work 12 06-Apr-17 20-Apr-17 42

XAC03-34215210 Pre-Commissioning - SWYD Auxiliary System AC Board 3 06-Apr-17 10-Apr-17 42

XAC03-34215220 Pre-Commissioning - SWYD Auxiliary System DC Board 3 06-Apr-17 10-Apr-17 42

XAC03-34215230 Pre-Commissioning - SWYD Auxiliary System Substation Ground Continuity Test 1 18-Apr-17 19-Apr-17 42

XAC03-34215240 Pre-Commissioning - SWYD Auxiliary System Substation Grounding System 1 19-Apr-17 20-Apr-17 42

03PMS-BL00.3.4.2.15.3 115 kV HV Equipment Test Work 38 05-Apr-17 18-May-17 18

XAC03-34215310 Pre-Commissioning - 115 kV HV Equipment GIS PASS M0 29 05-Apr-17 08-May-17 18

XAC03-34215320 Pre-Commissioning - 115 kV HV Equipment - Circuit Breaker 3 28-Apr-17 01-May-17 18

XAC03-34215330 Pre-Commissioning - 115 kV HV Equipment - Current Transformer 4 03-May-17 06-May-17 18

XAC03-34215340 Pre-Commissioning - 115 kV HV Equipment - Voltage Transformer 3 08-May-17 11-May-17 18

XAC03-34215350 Pre-Commissioning - 115 kV HV Equipment - Surge Arrester 2 12-May-17 13-May-17 18

XAC03-34215360 Pre-Commissioning - 115 kV HV Equipment - Earthing Switch 1 15-May-17 15-May-17 18

XAC03-34215370 Pre-Commissioning - 115 kV HV Equipment - Bus Connection 2 16-May-17 18-May-17 18

03PMS-BL00.3.4.2.15.4 Control Protection and Metering Equipment 20 06-Apr-17 29-Apr-17 1

XAC03-34215410 Pre-Commissioning - Control Protection and Metering Equip. - Distance Relay (REL670) 3 06-Apr-17 10-Apr-17 1

XAC03-34215420 Pre-Commissioning - Control Protection and Metering Equip. - Line Differential Relay 4 10-Apr-17 14-Apr-17 1
(RED670)
XAC03-34215430 Pre-Commissioning - Control Protection and Metering Equip. - Bus Differential Relay 1 14-Apr-17 15-Apr-17 1
(REB670)
XAC03-34215440 Pre-Commissioning - Control Protection and Metering Equip. - Transformer Differential 3 15-Apr-17 19-Apr-17 1
Relay (RET650)
XAC03-34215450 Pre-Commissioning - Control Protection and Metering Equip. - Transformer Differential 3 20-Apr-17 22-Apr-17 1
Relay (RET630)
XAC03-34215460 Pre-Commissioning - Control Protection and Metering Equip. - Combine Relay (REF630) 3 22-Apr-17 26-Apr-17 1

XAC03-34215470 Pre-Commissioning - Control Protection and Metering Equip. - Revenue Meter 1 26-Apr-17 27-Apr-17 1

XAC03-34215480 Pre-Commissioning - Control Protection and Metering Equip. - Universal Meter 1 27-Apr-17 28-Apr-17 1

XAC03-34215490 Pre-Commissioning - Control Protection and Metering Equip. - Transducer 1 28-Apr-17 29-Apr-17 1

03PMS-BL00.3.4.2.19 ST Building Overhead Crane 4 21-Apr-17 26-Apr-17 33

XAC03-34219100 Pre-Commissioning - Energize 2 21-Apr-17 24-Apr-17 33

XAC03-34219200 Pre-Commissioning - Function Check 2 24-Apr-17 26-Apr-17 33

03PMS-BL00.3.4.5 C & I Package


P 17 13-Apr-17 02-May-17 12

03PMS-BL00.3.4.5.01 DCS
DC 17 13-Apr-17 02-May-17 12

XAC03-34501100 Pre-Commissioning - DCS (3F) - Power up 5 13-Apr-17 18-Apr-17 12

XAC03-34501200 Pre-Commissioning - DCS (3F) - Pre-operation start 0 19-Apr-17 12

XAC03-34501300 Pre-Commissioning - DCS (3F) - Loop Check for Power Receiving Area 12 19-Apr-17 02-May-17 12

03PMS-BL00.3.5 HOT COM


COMMISSIONING WORK 346 20-Jan-17 01-Jan-18 32

03PMS-BL00.3.5.1 Major Equipment Package 164 21-Jul-17 01-Jan-18 0

03PMS-BL00.3.5.1.01 Ga
Gas turbine & Generator #31 (Siemens) 8 01-Aug-17 10-Aug-17 0

XAC03-35101100 GT #31 Commissioning - GT #31 Initial Firing 1 01-Aug-17* 02-Aug-17 0

XAC03-35101200 GT #31 Commissioning - FSNL Test and Over Speed Test 2 03-Aug-17 04-Aug-17 0

XAC03-35101300 GT #31 Commissioning - Generator No Load Test 1 05-Aug-17 05-Aug-17 0

XAC03-35101400 GT #31 Commissioning - Initial Synchronization 1 06-Aug-17 07-Aug-17 0

XAC03-35101500 GT #31 Commissioning - Unit Load Up Test and Water Injection Test 3 07-Aug-17 10-Aug-17 0

03PMS-BL00.3.5.1.02 Ga
Gas turbine & Generator #32 (Siemens) 7 23-Aug-17 31-Aug-17 0

XAC03-35102100 GT #32 Commissioning - GT #32 Initial Firing 1 23-Aug-17* 24-Aug-17 0

XAC03-35102200 GT #32 Commissioning - FSNL Test and Over Speed Test 1 24-Aug-17 24-Aug-17 0

XAC03-35102300 GT #32 Commissioning - Generator No Load Test 1 25-Aug-17 25-Aug-17 0

XAC03-35102400 GT #32 Commissioning - Initial Synchronization 2 26-Aug-17 28-Aug-17 0

XAC03-35102500 GT #32 Commissioning - Unit Load Up Test and Water Injection Test 2 29-Aug-17 31-Aug-17 0

03PMS-BL00.3.5.1.03 HRSG
HR #31 (Vogt Power) 32 31-Jul-17 05-Sep-17 0

03PMS-BL00.3.5.1.03.1 Commissioning for Simple Cycle 8 31-Jul-17 08-Aug-17 19

XAC03-35103110 Commissioning for Simple Cycle - Bypass Damper Operation Check 8 31-Jul-17 08-Aug-17 19

03PMS-BL00.3.5.1.03.2 Commissionig for Combined Cycle 32 31-Jul-17 05-Sep-17 0

XAC03-35103210 Combined for Combined Cycle - Sequence / Loop Check 14 31-Jul-17 15-Aug-17 0

XAC03-35103220 Combined for Combined Cycle - Valve Function Check 12 15-Aug-17 29-Aug-17 0

XAC03-35103230 Combined for Combined Cycle - #31 Blowing Out 6 30-Aug-17 05-Sep-17 0

03PMS-BL00.3.5.1.04 HRSG
HR #32 (Vogt Power) 70 21-Jul-17 29-Sep-17 0

03PMS-BL00.3.5.1.04.1 Commissioning for Simple Cycle 7 21-Jul-17 28-Jul-17 8

XAC03-35104110 Commissioning for Simple Cycle - Bypass Damper Operation Check 7 21-Jul-17 28-Jul-17 8

03PMS-BL00.3.5.1.04.2 Commissioning for Combined Cycle 62 28-Jul-17 29-Sep-17 0

XAC03-35104210 Commissioning for Combined Cycle - Sequence / Loop Check 14 28-Jul-17 14-Aug-17 8

XAC03-35104220 Commissioning for Combined Cycle - Valve Function Check 12 14-Aug-17 28-Aug-17 8

XAC03-35104230 Commissioning for Combined Cycle - #32 Blowing Out 5 06-Sep-17 12-Sep-17 0

XAC03-35104240 Commissioning for Combined Cycle - #31 & 32 Blowing Out 3 12-Sep-17 15-Sep-17 0

XAC03-35104250 Commissioning for Combined Cycle - Restoration 12 15-Sep-17 29-Sep-17 0

03PMS-BL00.3.5.1.05 St
Steam Turbine & Generator (Siemens) 93 30-Sep-17 01-Jan-18 0

03PMS-BL00.3.5.1.05.1 ST Commissioning 25 30-Sep-17 30-Oct-17 0

XAC03-35105110 Condenser Hotwell Vacuum-up & ST Start-up - Turbine Bypass Restoration 3 30-Sep-17 04-Oct-17 0

XAC03-35105120 Condenser Hotwell Vacuum-up & ST Start-up - Turbine Bypass Cont - Valve Simulation 2 04-Oct-17 06-Oct-17 0
Test
XAC03-35105130 Condenser Hotwell Vacuum-up & ST Start-up - Gland Steam Supply & Tuning, 2 06-Oct-17 09-Oct-17 0
Condenser Hotwell Vacuum-up
XAC03-35105150 Condenser Hotwell Vacuum-up & ST Start-up - HRSG Drum Level Tuning & DSH 3 09-Oct-17 12-Oct-17 1
Control Tuning
XAC03-35105140 Condenser Hotwell Vacuum-up & ST Start-up - Tuning for Steam Purity 6 09-Oct-17 16-Oct-17 0

XAC03-35105160 Condenser Hotwell Vacuum-up & ST Start-up - HRSG Safety Valve Test 2 12-Oct-17 14-Oct-17 1

XAC03-35105170 Condenser Hotwell Vacuum-up & ST Start-up - Turbine Full Byapass operation 3 12-Oct-17 16-Oct-17 0

XAC03-35105180 Condenser Hotwell Vacuum-up & ST Start-up - ST Initial Start-up, FSNL, Mechanical 1 16-Oct-17 17-Oct-17 0
Check, Over speed test
XAC03-35105190 Condenser Hotwell Vacuum-up & ST Start-up - STG Electrical Primary protection Test 4 17-Oct-17 21-Oct-17 0

XAC03-351051A0 Condenser Hotwell Vacuum-up & ST Start-up - STG AVR Tuning, Dummy Syn Test 2 17-Oct-17 19-Oct-17 2

XAC03-351051B0 Condenser Hotwell Vacuum-up & ST Start-up - STG Initial-Syn, Loading by 1-1-1 1 21-Oct-17 23-Oct-17 0

XAC03-351051C0 Condenser Hotwell Vacuum-up & ST Start-up - Loading by 2-2-1 & Load rejection test 2 23-Oct-17 25-Oct-17 0

XAC03-351051D0 Condenser Hotwell Vacuum-up & ST Start-up - Condenser Hotwell Cleaning 3 25-Oct-17 28-Oct-17 0

XAC03-351051E0 Condenser Hotwell Vacuum-up & ST Start-up - Extraction steam tuning & Back-up 1 28-Oct-17 30-Oct-17 0
system testing
03PMS-BL00.3.5.1.05.2 Overall Commissioning 63 30-Oct-17 01-Jan-18 0

XAC03-35105210 Overall Combined Cycle Operation - ASC Start-up & Shutdown Tuning 7 30-Oct-17 07-Nov-17 0

XAC03-35105230 Overall Combined Cycle Operation - ASC Start-up & Shutdown Test 12 07-Nov-17 21-Nov-17 0

XAC03-35105240 Overall Combined Cycle Operation - 2-2-1 Full block 1-1-1 Half block operation tuning 3 14-Nov-17 17-Nov-17 0
& test
XAC03-35105250 Overall Combined Cycle Operation - GT-ST Capability operation test 4 17-Nov-17 22-Nov-17 0

XAC03-35105260 Overall Combined Cycle Operation - Extraction Change-over Test, Capacity test, ST trip 2 22-Nov-17 24-Nov-17 0
Back-up test
XAC03-35105270 Overall Combined Cycle Operation - IMO Response Test 2 24-Nov-17 27-Nov-17 0

XAC03-35105280 Overall Combined Cycle Operation - AGC Test 2 27-Nov-17 29-Nov-17 0

XAC03-35105290 Overall Combined Cycle Operation - Preparation for Performance Test & 3 29-Nov-17 02-Dec-17 0
Pre-performance check
XAC03-351052A0 Overall Combined Cycle Operation - RATA test 4 02-Dec-17 06-Dec-17 0

XAC03-351052B0 Overall Combined Cycle Operation - Performance Test 5 06-Dec-17 12-Dec-17 0

XAC03-351052C0 Overall Combined Cycle Operation - Emission Measurement 3 06-Dec-17 09-Dec-17 19

XAC03-351052D0 Overall Combined Cycle Operation - PEA 24h RTR 2 12-Dec-17 14-Dec-17 0

XAC03-351052E0 Overall Combined Cycle Operation - RTR 15 14-Dec-17 30-Dec-17 0

XAC03-351052F0 ABPR3 Target T/O (Turn Over) 0 01-Jan-18* 0

03PMS-BL00.3.5.2 Unit Package


P 162 20-Jan-17 25-Jul-17 166

03PMS-BL00.3.5.2.04 Water
Wa Treatment Plant (Common) 31 03-May-17 08-Jun-17 8

XAC03-35204100 Commissioning - Commissioning of Pre-Treatment System 5 03-May-17 09-May-17 8

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:52 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-35204200 Commissioning - Commissioning of Demin Water System 26 09-May-17 08-Jun-17 8

XAC03-35204300 Commissioning - Service Water Ready of In-Service 0 09-May-17 34

XAC03-35204500 Commissioning - Demin Water Ready of In-Service 0 08-Jun-17 8

03PMS-BL00.3.5.2.06 Cooling
Co Tower 40 09-May-17 24-Jun-17 5

XAC03-35206100 Commissioning - Sequence Check 8 09-May-17 18-May-17 30

XAC03-35206200 Commissioning - Fan Motor No Loading Test / Heat Run 7 16-Jun-17 24-Jun-17 5

03PMS-BL00.3.5.2.09 Co
Condenser Ball Cleaning System 8 17-Jul-17 25-Jul-17 71

XAC03-35209100 Commissioning - Sequence Check 4 17-Jul-17 20-Jul-17 71

XAC03-35209200 Commissioning - Operation Check 4 20-Jul-17 25-Jul-17 71

03PMS-BL00.3.5.2.10 Ch
Chemical dosing system for HRSG Unit #30 5 18-Jul-17 24-Jul-17 33

XAC03-35210100 Commissioning - Operation Test 3 18-Jul-17 20-Jul-17 33

XAC03-35210200 Commissioning - Flushing 2 21-Jul-17 24-Jul-17 33

XAC03-35210300 Commissioning - Chemical doosing system for HRSG in Service 0 24-Jul-17 33

03PMS-BL00.3.5.2.11 Ch
Chemical dosing system for CT Unit #30 6 16-Jun-17 23-Jun-17 6

XAC03-35211100 Commissioning - Operation Check 4 16-Jun-17 21-Jun-17 6

XAC03-35211200 Commissioning - Flushing 2 21-Jun-17 23-Jun-17 6

XAC03-35211300 Commissioning - Chemical dosing for CT in service 0 23-Jun-17 6

03PMS-BL00.3.5.2.14 Fir
Fire Fighting System 67 10-Mar-17 26-May-17 218

03PMS-BL00.3.5.2.14.1 Commissioning - Fire Pupmp Station 11 22-Apr-17 04-May-17 10

XAC03-35214110 Commissioning - Fire Pupmp Station - Pump Station Temporary Power Supply 1 22-Apr-17* 22-Apr-17 10
Preparation
XAC03-35214120 Commissioning - Fire Pupmp Station - Pump Station-Sequence/Function Check 3 24-Apr-17 26-Apr-17 10

XAC03-35214130 Commissioning - Fire Pupmp Station - Pump Station & Ring Main Pipe Water Filling 1 27-Apr-17 27-Apr-17 10

XAC03-35214140 Commissioning - Fire Pupmp Station - Pumps Suction & Recirculation Line Water 2 27-Apr-17 28-Apr-17 10
Flushing
XAC03-35214150 Commissioning - Fire Pupmp Station - Jockey Pump Motor No-Load Test 1 29-Apr-17 29-Apr-17 10

XAC03-35214160 Commissioning - Fire Pupmp Station - Jockey Pump Heat Run 1 01-May-17 01-May-17 10

XAC03-35214170 Commissioning - Fire Pupmp Station - Engine Fire Pump Heat Run 1 02-May-17 02-May-17 10

XAC03-35214180 Commissioning - Fire Pupmp Station - Motor Fire Pump Motor No-Load Tes t (After 1 03-May-17 03-May-17 10
Power Receiving)
XAC03-35214190 Commissioning - Fire Pupmp Station - Motor Fire Pump Heat Run (After Power 1 04-May-17 04-May-17 10
Receiving)
03PMS-BL00.3.5.2.14.2 Commissioning - Each Transformer Water Flushing & Spray Test 22 02-May-17 26-May-17 8

XAC03-35214220 Commissioning - Each Transformer Water Flushing & Spray Test - Ring Main Pipe 1 02-May-17 02-May-17 19
Water Flushing
XAC03-35214230 Comm. - Each Trans Water Flushing & Spray Test - Water Flushing Each Transformer 6 03-May-17 09-May-17 19
(Spray Nozzle & Detector Installation)
XAC03-35214210 Commissioning - Each Transformer Water Flushing & Spray Test - Function/Sequence 6 15-May-17 22-May-17* 8
Check All Transformers
XAC03-35214240 Commissioning - Each Transformer Water Flushing & Spray Test - Spray Test in Each 4 22-May-17 26-May-17 8
Transformers
03PMS-BL00.3.5.2.14.3 Commissioning - Sprinkler System 23 27-Mar-17 21-Apr-17 20

XAC03-35214310 Commissioning - Sprinkler System - E&C Bldg Cable Cellar 2 27-Mar-17* 28-Mar-17 29

XAC03-35214320 Commissioning - Sprinkler System - EDG Station 9 08-Apr-17* 18-Apr-17 20

XAC03-35214330 Commissioning - Sprinkler System - FF Pump Station 3 19-Apr-17* 21-Apr-17 20

03PMS-BL00.3.5.2.14.4 Commissioning - Indoor Hydrant 22 20-Apr-17 16-May-17 132

XAC03-35214410 Commissioning - Indoor Hydrant - E&C Bldg 3 20-Apr-17* 24-Apr-17 19

XAC03-35214420 Commissioning - Indoor Hydrant - STG Bldg 3 13-May-17* 16-May-17 132

03PMS-BL00.3.5.2.14.5 Commissioning - Outdoor Hydrant 2 10-Mar-17 11-Mar-17 274

XAC03-35214510 Commissioning - Outdoor Hydrant - Around Plant (ABPR3) 2 10-Mar-17* 11-Mar-17 274

03PMS-BL00.3.5.2.14.6 Commissioning - Fire Alarm System 9 17-Apr-17 26-Apr-17 244

XAC03-35214610 Commissioning - Fire Alarm System - Function/Sequence Check All Area ABPR3 Plant 9 17-Apr-17* 26-Apr-17 244

03PMS-BL00.3.5.2.15 11
115kV Switch Yard 34 29-Apr-17 08-Jun-17 0

XAC03-35215100 Commissioning - Control and Interlocking with Witness 25 29-Apr-17 29-May-17 1

XAC03-35215200 Commissioning - DCS Loop check, Miscellaneous check 17 17-May-17 06-Jun-17 0

XAC03-35215300 Commissioning - CT,VT Primary/Secondary Loop Test 3 29-May-17 01-Jun-17 1

XAC03-35215400 Commissioning - Back Energize test 2 01-Jun-17 03-Jun-17 1

XAC03-35215500 Commissioning - 24h Soak Test 2 06-Jun-17 08-Jun-17 0

03PMS-BL00.3.5.2.19 ST Building Overhead Crane 2 26-Apr-17 28-Apr-17 33

XAC03-35219100 Commissioning - Load Test 2 26-Apr-17 28-Apr-17 33

XAC03-35219200 Commissioning - Ready for In Service 0 28-Apr-17 33

03PMS-BL00.3.5.2.20 GT Evaporator 2 20-Jan-17 23-Jan-17 166

XAC03-35220100 Commissioning - GT Evaporator 2 20-Jan-17 23-Jan-17 166

03PMS-BL00.3.5.3 Process
Proces Package 174 09-Mar-17 30-Aug-17 47

03PMS-BL00.3.5.3.04 Aux
Au Steam System 7 22-Aug-17 30-Aug-17 0

XAC03-35304100 Commissioning - Sequence Check 2 22-Aug-17 24-Aug-17 0

XAC03-35304200 Commissioning - Operation Check / Flushing 5 24-Aug-17 30-Aug-17 0

03PMS-BL00.3.5.3.05 Condensate
Co Water System 18 12-Jun-17 01-Jul-17 91

XAC03-35305100 Commissioning - Condensate Water System Sequence Check 6 12-Jun-17 17-Jun-17 91

XAC03-35305200 Commissioning - CEP Motor Test Run 1 19-Jun-17 19-Jun-17 91

XAC03-35305300 Commissioning - CEP Motor Alignment and Coupling 1 20-Jun-17 21-Jun-17 91

XAC03-35305400 Commissioning - CEP Heat Run 3 21-Jun-17 23-Jun-17 91

XAC03-35305500 Commissioning - Condensate Water System Operation Check / Flushing 7 24-Jun-17 01-Jul-17 91

03PMS-BL00.3.5.3.06 HP Feedwater System 37 10-May-17 21-Jun-17 60

XAC03-35306100 Commissioning - HP Boiler Feed Water System Sequence Check 6 10-May-17 16-May-17 83

XAC03-35306200 Commissioning - HP BFP Motor Test Run 2 13-Jun-17 14-Jun-17 60

XAC03-35306300 Commissioning - HP BFP Motor Alignment and Coupling 1 15-Jun-17 15-Jun-17 60

XAC03-35306400 Commissioning - HP BFP Heat Run 2 15-Jun-17 17-Jun-17 60

XAC03-35306500 Commissioning - HP Boiler Feed Water System Operation Check / Flushing 3 17-Jun-17 21-Jun-17 60

03PMS-BL00.3.5.3.07 LP Feedwater System 16 06-Jun-17 24-Jun-17 57

XAC03-35307100 Commissioning - LP Boiler Feed Water System Sequence Check 6 06-Jun-17 13-Jun-17 60

XAC03-35307200 Commissioning - LP BFP Motor Test Run 1 16-Jun-17 17-Jun-17 57

XAC03-35307300 Commissioning - LP BFP Motor Alignment and Coupling 1 17-Jun-17 19-Jun-17 57

XAC03-35307400 Commissioning - LP BFP Heat Run 2 19-Jun-17 21-Jun-17 57

XAC03-35307500 Commissioning - LP Boiler Feed Water System Operation Check / Flushing 3 21-Jun-17 24-Jun-17 57

03PMS-BL00.3.5.3.08 Main
Ma Cooling Water System 19 03-Jul-17 25-Jul-17 71

XAC03-35308100 Commissioning - Main Cooling Water System Sequence Check 6 03-Jul-17 10-Jul-17 71

XAC03-35308200 Commissioning - MCW Pump Motor Test Run 1 10-Jul-17 11-Jul-17 71

XAC03-35308300 Commissioning - MCW Pump - Motor Alignment and Coupling 1 11-Jul-17 12-Jul-17 71

XAC03-35308400 Commissioning - MCW Pump Heat Run 3 12-Jul-17 15-Jul-17 71

XAC03-35308500 Commissioning - Main Cooling Water System Operation Check / Flushing 5 15-Jul-17 21-Jul-17 71

XAC03-35308600 Commissioning - MCW Pipe Restoration 3 21-Jul-17 25-Jul-17 71

03PMS-BL00.3.5.3.09 Au
Auxiliary Cooling Water System 18 09-Jun-17 30-Jun-17 0

XAC03-35309100 Commissioning - ACW Water System Sequence Check 6 09-Jun-17 16-Jun-17 0

XAC03-35309200 Commissioning - ACW Pump Motor Test Run 1 16-Jun-17 17-Jun-17 0

XAC03-35309300 Commissioning - ACW Pump - Motor Alignment and Coupling 1 19-Jun-17 19-Jun-17 0

XAC03-35309400 Commissioning - ACW Pump Heat Run 3 20-Jun-17 22-Jun-17 0

XAC03-35309500 Commissioning - ACW System Operation Check / Flushing 4 22-Jun-17 27-Jun-17 0

XAC03-35309600 Commissioning - ACW Pipe Restoration 3 28-Jun-17 30-Jun-17 0

03PMS-BL00.3.5.3.10 CT Make up Water 24 26-May-17 23-Jun-17 6

XAC03-35310100 Commissioning - CT Make-up System Sequence Check / Loop Check 6 26-May-17 02-Jun-17 18

XAC03-35310200 Commissioning - CT Make-up Pump - Motor Test Run & Pump Heat Run 1 16-Jun-17 17-Jun-17 6

XAC03-35310300 Commissioning - CT Make-up System Operation Check / Flushing 5 17-Jun-17 23-Jun-17 6

03PMS-BL00.3.5.3.11 Clo
Closed Cycle Cooling Water System 39 17-May-17 30-Jun-17 0

XAC03-35311100 Commissioning - CCCW System Sequence Check / Loop Check 6 17-May-17 23-May-17 23

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018

ABPR3 Combined Cycle Cogeneration Plant Project Date: 09-Jul-16


Baseline
Project Control No.: ABPR3-G-T-PJ-0005 Page No.:53 of 53
Activity ID Activity Name Original Start Finish Total 2016 2017 2018
Duration Float Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
XAC03-35311200 Commissioning - CCCW Pump Motor Test Run 1 16-Jun-17 17-Jun-17 3

XAC03-35311300 Commissioning - CCCW Pump - Motor Alignment and Coupling 1 17-Jun-17 19-Jun-17 3

XAC03-35311400 Commissioning - CCCW Pump Heat Run 1 22-Jun-17 22-Jun-17 0

XAC03-35311500 Commissioning - CCCW System Operation Check / Flushing 5 22-Jun-17 28-Jun-17 0

XAC03-35311600 Commissioning - CCCW Pipe Restoration 2 29-Jun-17 30-Jun-17 0

XAC03-35311700 Commissioning - CCCW System Stand-by for In-service 0 30-Jun-17 0

03PMS-BL00.3.5.3.12 Condenser
Co Vacuum System 21 31-May-17 23-Jun-17 99

XAC03-35312100 Commissioning - CVP System Sequence Check 6 31-May-17 06-Jun-17 107

XAC03-35312200 Commissioning - CVP Motor Test Run 2 16-Jun-17 19-Jun-17 99

XAC03-35312300 Commissioning - CVP Alignment and Coupling 1 19-Jun-17 20-Jun-17 99

XAC03-35312400 Commissioning - CVP Heat Run 3 20-Jun-17 23-Jun-17 99

03PMS-BL00.3.5.3.13 Ra
Raw Water Distribution System (Common) 8 05-Apr-17 13-Apr-17 24

XAC03-35313100 Commissioning - Raw Water Pump - Sequence Check 4 05-Apr-17 08-Apr-17 24

XAC03-35313200 Commissioning - Raw Water Pump - Motor Test Run & Pump Heat Run (by Temp. 2 08-Apr-17 11-Apr-17 24
Power)
XAC03-35313300 Commissioning - Raw Water System - Operation Check / Flushing 2 11-Apr-17 13-Apr-17 24

03PMS-BL00.3.5.3.14 Service
Se water Distribution System 22 26-May-17 21-Jun-17 36

XAC03-35314100 Commissioning - SW Pump - Sequence Check 4 26-May-17 31-May-17 50

XAC03-35314200 Commissioning - SW Pump - Motor Tes t Run & Pump Heat Run 2 16-Jun-17 19-Jun-17 36

XAC03-35314300 Commissioning - SW System - Operation Check / Flushing 2 19-Jun-17 21-Jun-17 36

03PMS-BL00.3.5.3.15 De
Demineralized water Distribution System 26 26-May-17 21-Jun-17 0

XAC03-35315100 Commissioning - DM Pump - Sequence Check 4 26-May-17 31-May-17 14

XAC03-35315200 Commissioning - DM Pump - Motor Test Run & Pump Heat Run 3 16-Jun-17 19-Jun-17 0

XAC03-35315300 Commissioning - DM Water System - Operation Check / Flushing 2 19-Jun-17 21-Jun-17 0

03PMS-BL00.3.5.3.16 Waste
Wa water collection System 54 20-Mar-17 20-May-17 63

03PMS-BL00.3.5.3.16.1 Retention Pit / Emergency Pit 13 05-May-17 20-May-17 63

XAC03-35316110 Commissioning - Retention Pit / Emergency Pit - Sequence Check 8 05-May-17 15-May-17 63

XAC03-35316120 Commissioning - Retention Pit / Emergency Pit - Pump Heat Run 5 15-May-17 20-May-17 63

03PMS-BL00.3.5.3.16.2 CT/CWP Area Pit 13 20-Mar-17 04-Apr-17 103

XAC03-35316210 Commissioning - CT/CWP Area Pit - Sequence Check 9 20-Mar-17 30-Mar-17 103

XAC03-35316220 Commissioning - CT/CWP Area Pit - Pump Heat Run 4 30-Mar-17 04-Apr-17 103

03PMS-BL00.3.5.3.16.3 Oily Water Separator 13 25-Mar-17 10-Apr-17 98

XAC03-35316310 Commissioning - Oily Water Separator - Sequence Check 9 25-Mar-17 05-Apr-17 98

XAC03-35316320 Commissioning - Oily Water Separator - Pump Heat Run 4 05-Apr-17 10-Apr-17 98

03PMS-BL00.3.5.3.17 Instrument
Ins & Service Air System (Common) 86 09-Mar-17 16-Jun-17 0

XAC03-35317100 Commissioning - Sequence Check 2 09-Mar-17 11-Mar-17 81

XAC03-35317200 Commissioning - Operation Test 2 11-Mar-17 14-Mar-17 81

XAC03-35317300 Commissioning - Air Blow 1 08-May-17 09-May-17 34

XAC03-35317400 Commissioning - Ready for In-Service 0 16-Jun-17 0

03PMS-BL00.3.5.3.18 Fu
Fuel Gas Distribution System 14 17-Jul-17 01-Aug-17 0

XAC03-35318100 Commissioning - Civil/Mech/Elec Handover Inspection to Commissioning 4 17-Jul-17 20-Jul-17 5

XAC03-35318200 Commissioning - Safety Walk Down 2 21-Jul-17 22-Jul-17 5

XAC03-35318300 Commissioning - Stand By for Fuel Gas In 1 28-Jul-17 29-Jul-17 0

XAC03-35318400 Commissioning - Fuel Gas Filling 2 29-Jul-17 01-Aug-17 0

XAC03-35318500 Commissioning - Fuel Gas In-service EPC Scope to GT #31 0 01-Aug-17 0

03PMS-BL00.3.5.3.19 Fuel
Fu Gas Heater 10 17-Jul-17 27-Jul-17 4

XAC03-35319100 Commissioning - Fire Gas Heater 10 17-Jul-17 27-Jul-17 4

03PMS-BL00.3.5.4 Electrical
Electri Package 99 10-Mar-17 16-Jun-17 121

03PMS-BL00.3.5.4.01 Generator
Ge Transformer 47 18-Apr-17 10-Jun-17 110

03PMS-BL00.3.5.4.01.1 GSUT 31 47 18-Apr-17 10-Jun-17 45

XAC03-35401110 Commissioning - GSUT 31 Transformer Sequence/Function Check 5 18-Apr-17 22-Apr-17 27

XAC03-35401120 Commissioning - GSUT 31 Transformer Soak Test 1 08-Jun-17* 09-Jun-17 45

XAC03-35401130 Commissioning - GSUT 31 Transformer Energized 1 09-Jun-17 10-Jun-17 45

03PMS-BL00.3.5.4.01.2 GSUT 32 42 22-Apr-17 10-Jun-17 64

XAC03-35401210 Commissioning - GSUT 32 Transformer Sequence/Function Check 4 22-Apr-17 27-Apr-17 27

XAC03-35401220 Commissioning - GSUT 32 Transformer Soak Test 1 08-Jun-17* 09-Jun-17 64

XAC03-35401230 Commissioning - GSUT 32 Transformer Energized 1 09-Jun-17 10-Jun-17 64

03PMS-BL00.3.5.4.01.3 ST #30 Tr 38 27-Apr-17 10-Jun-17 110

XAC03-35401310 Commissioning - ST 30 Transformer Sequence/Function Check 4 27-Apr-17 02-May-17 27

XAC03-35401320 Commissioning - ST 30 Transformer Soak Test 1 08-Jun-17* 09-Jun-17 110

XAC03-35401330 Commissioning - ST 30 Transformer Energized 1 09-Jun-17 10-Jun-17 110

03PMS-BL00.3.5.4.02 Un
Unit Auxiliary Transformer 33 03-May-17 10-Jun-17 0

XAC03-35402100 Commissioning - Unit Axiliary Transformer Sequence/Function Check 4 03-May-17 08-May-17 27

XAC03-35402200 Commissioning - Unit Axiliary Transformer Soak Test 1 08-Jun-17* 09-Jun-17 0

XAC03-35402300 Commissioning - Unit Axiliary Transformer Energized 1 09-Jun-17* 10-Jun-17 0

03PMS-BL00.3.5.4.03 MV Switchgear 61 13-Apr-17 12-Jun-17 0

XAC03-35403100 6.6kV Switchgear - Commissioning - Sequence / Function Check 12 13-Apr-17 26-Apr-17 39

XAC03-35403200 6.6kV Switchgear - Commissioning - Energize (Station Power Receiving) 3 10-Jun-17 12-Jun-17 0

03PMS-BL00.3.5.4.04 LV Switchgear 57 13-Apr-17 16-Jun-17 0

XAC03-35404100 Commissioning - Sequence / Function Check 12 13-Apr-17 26-Apr-17 41

XAC03-35404200 Commissioning - Energizing LVSWGR 3 14-Jun-17 16-Jun-17 0

XAC03-35404300 Commissioning - 400VAC Ready for Supply 0 16-Jun-17 0

03PMS-BL00.3.5.4.05 LV Transformer 83 10-Mar-17 13-Jun-17 0

XAC03-35405100 Commissioning - Sequence/Function Check 7 10-Mar-17 17-Mar-17 75

XAC03-35405200 Commissioning - Power Receiving from 6.6kV MV SWGR & Soaking 1 13-Jun-17* 13-Jun-17 0

03PMS-BL00.3.5.4.07 DC System & UPS System 12 29-Mar-17 13-Apr-17 12

XAC03-35407100 Commissioning - DC & UPS Sequence Check 5 29-Mar-17 04-Apr-17 12

XAC03-35407200 Commissioning - DC & UPS Charging & Load Test 6 05-Apr-17 11-Apr-17 12

XAC03-35407300 Commissioning - DC & UPS Energized 1 12-Apr-17 12-Apr-17 12

XAC03-35407400 Commissioning - 220VDC Ready for Supply 0 13-Apr-17 12

03PMS-BL00.3.5.4.08 Emergency
Em DG System 9 13-May-17 24-May-17 61

XAC03-35408100 Commissioning Work - Commissioning 9 13-May-17 24-May-17 61

03PMS-BL00.3.5.5 C & I Package


P 53 29-May-17 28-Jul-17 107

03PMS-BL00.3.5.5.02 St
Steam and Water Sampling System 3 29-May-17 31-May-17 78

XAC03-35502100 Commissioning - Steam and Water Sampling System Commissioning 2 29-May-17 30-May-17 78

XAC03-35502200 Commissioning - Steam and Water Sampling System Sampling System In-service 1 31-May-17 31-May-17 78

03PMS-BL00.3.5.5.03 Co
Continuous Emission Monitoring System 26 29-Jun-17 28-Jul-17 3

XAC03-35503100 Commissioning - CEMS Setting / Commissioning 26 29-Jun-17 28-Jul-17 3

03PMS-BL00.3.5.5.04 Clock
Cl System 7 28-Jun-17 06-Jul-17 23

XAC03-35504100 Commissioning - Clock System Commissioning 7 28-Jun-17 06-Jul-17 23

03PMS-BL00.3.5.5.05 Communication
Co System 7 16-Jun-17 24-Jun-17 33

XAC03-35505100 Commissioning - Communication System Commissioning 7 16-Jun-17 24-Jun-17 33

03PMS-BL00.3.5.5.06 Primary
Pr Energy System 7 26-Jun-17 04-Jul-17 128

XAC03-35506100 Commissioning - PES Commissioning 7 26-Jun-17 04-Jul-17 128

Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary

Anda mungkin juga menyukai