OF
ELECTROSTATIC PRECIPITATOR
FOR
CLINKER COOLER
AT
Prepared By :
ELEX (India) Pvt. Ltd.
Plot No. A 97, Road No. 18,
Wagle Estate, Thane 400 604
1
TABLE OF CONTENTS
Precautions
- Electrostatic Precipitator
3.1 General
3.2 Casing
3.3 Hoppers
3.4 Internals
3.5 Electrical
6.1 Introduction
2
6.4 Casing Structures & Casing Shell & Ridges
6.18 Insulation
3
1.0 SALIENT FEATURES OF ELECTROSTATIC PRECIPITATOR
For treating of flue gases emanating from Clinker Cooler precipitators are
electrical fields (or systems) in the direction of the gas flow. The functional
parts (internals) and electrical accessories are being supplied for all of the
are number of gas ducts. A gas duct is formed by two consecutive rows of
the gas ducts and the collecting electrode rows will be one more than the
gas duct. Each field has got its own power source and main control.
4
TECHNICAL DATA OF ELECTROSTATIC PRECIPITATAOR
Field height 14 m
5
PRECAUTIONS
EXTRA CARE YOU TAKE DURING ERECTION WILL ENSURE TROUBLE FREE
OPERATION.
THE DRAWING.
ONLY.
INSPECT ALL WELD JOINTS FOR DEFECTS AND RECTIFY THEM TO AVOID LEAKAGE
6
IMPORTANT INSTRUCTIONS ELECTROSTATIC PRECIPITAORS DOs
01. ENSURE THE CORRECT DIMENSIONS OF THE COMPONENTS WITH THE HELP
CORRECT DIRECTION.
ERECTION.
06. ENSURE THAT THE HAMMERS OF RAPPING MECHANISM HIT AT THE CENTRE
OF RAPPING BAR.
7
IMPORTANT INSTRUCTIONS ELECTROSTATIC PRECIPITATORS DONTs
UPSIDE DOWN)
06. DO NOT FAIL TO MARK THE CENTRE LINE OF GAS PATH IN ROOF BEAMS
ELECTRODE FRAMES.
STRAIGHTNESS.
STRAIGHTNESS.
COMMISSIONING.
8
2.0 WORKING PRINCIPLE OF ELECTROSTATIC PRECIPITATOR
pressed to a special profile and the profile bar and discharge arm of the emitting
electrode made of thin sheet are fabricated into the desired form. A
negative polarity to the emitting electrodes and the positive polarity to collecting
electrodes which are also earthed. The dust laden flue gas passes between rows
of collecting and discharge electrodes. The high voltage induces ionization of gas
charges of the ions created travel towards the discharge electrodes and the
negative charges towards the collecting electrodes. On their way to the collecting
electrodes, the negative charges get deposited on the dust particles. Thus the
dust particles are electrically charged. In the presence of high electric field
between the electrodes the charged dust particles experience a force which
causes the particles to move towards the collecting electrodes and finally get
deposited on them. A minor portion of the dust particles which have acquired
positive charges get deposited on the emitting electrodes also. Periodically these
are dislodged from the electrodes by a process called rapping. The particles
then fall into the hoppers at the bottom. Through dust conveying system dust
9
3.0 CONSTRUCTIONAL FEATURES OF ELECTROSTATIC PRECIPITATOR
3.1 GENERAL
The Electrostatic Precipitator may be divided into two major groups, viz.,
electrical parts and mechanical parts. The various parts of precipitator
are illustrated in the EP General Arrangement drawing for a typical
precipitator. The Assembly of Precipitator is divided into sub-groups
which are numbered in the drawing. The electrical parts comprise of high
voltage rectifier, main and auxiliary controls, switches, heaters and inter-
locks. The Mechanical parts constituting the EP, consists of the casing
and functional parts forming internals of the precipitator.
3.2 CASING
3.3 HOPPERS
3.4 INTERNALS
For this purpose, rows of gas distribution plate with perforations are
located at the inlet of the casing. One set of gas distribution plates is
provided at the outlet of ESP.
10
(ii) Discharge Electrode System
The collecting plates are made of steel sheets and shaped in special profile
by roll forming. These profile of the collecting plate lend mechanical
rigidity to it and also limit re-entrainment of collected dust during
rapping. The collecting plates of 500 mm width and 14 m length are
hung from the top.
11
The frequency of rapping is adjusted by controlling the operation of the
geared motor by means of programmer, mounted in the auxiliary control
panel.
3.5 Electrical
3.6 Interlock
12
4.0 HANDLING INSTRUCTIONS FOR ELECTROSTATIC PRECIPITATOR
COMPONENTS
(i) Do not use door handles and bolt holes for lifting the components.
(ii) Use stiffening beams for lifting slender members like roof panels, wall
panels and roof beams etc., to avoid distortion.
(iii) Do not use metal ropes for lifting collecting electrodes. Use only manila
ropes and lifting beams to avoid damage to the electrodes.
(iv) If top entry method is adopted, lift collecting electrodes to the top of
electrostatic precipitator in full packs by lifting beams
Open the packs at the top and the collecting electrode may be taken up
one by one.
(v) Handle emitting electrodes such that the surface does not get any scratch
or pittings.
13
5.0 STORAGE INSTRUCTIONS FOR ELECTROSTATIC PRECIPITATOR
COMPONENTS
Stack all components well above the ground level to protect against water,
dust and soiling. Minimum height above the ground level shall be 300 mm.
Casing panels hot and cold roof panels are to be stored on a horizontal plane
one over the other. While stacking sliding of one panel over the other should
be prevented by providing suitable supports.
Ensure that all the components of the High Voltage rectifier panels and
Auxiliary control panels (if provided) are perfectly closed to prevent damages
to cables by rodents and termites.
Keep the insulators over soft material to avoid any damage. Do not stack any
other material over the insulator and keep the insulator sufficiently away
from other materials so as to avoid the damage/cracks due to falling of
metallic parts.
14
The high voltage transformer rectifiers are to be stored in a fire proof
enclosure and should be well guarded from fire hazards.
15
6.0 ERECTION PROCEDURE FOR ELECTROSTATIC PRECIPITATOR
6.1 Introduction
6.2 Layout
(iii) Check, verify and log the measurements between the central line of the
side column pedestal. Ensure that this is within the tolerance of + 10 mm.
(iv) Measure and verify the distance between the central line of last row of
nearest building column pedestals and the fixed support of electrostatic
precipitator column pedestals. Ensure this is within the tolerance of + 10
mm.
(i) Place the bearings on top of steel insert plate. Ensure proper leveling.
(ii) Align the bearings with respect to the fix foot. Care should be taken to
ensure that the direction of the movement is along a line radiating from
the fix foot.
(iii) After checking of level and alignment, weld bottom plate of bearing
assembly with support column insert plate.
(iv) Do not remove any temporary locks now. The locks are to be removed only
after the ESP has been completely erected and ready for commissioning.
16
(v) Log all the measurement.
(i) Place external and internal bottom girder as per the drawings.
(ii) Check the dimensions as per drawing. The diagonal difference shall be
within 10 mm.
(iv) Place all the columns on the bottom girder as per the drawing and then
top external and internal girder, as per the drawing, and then place all the
pipe bracings as per the drawing. Also fix the top edge girder and beam of
the main ceiling on top girder as per the drawing.
(vi) Check the verticality on both axes of the columns within 1 mm per metre
height limited to 10 mm on the total height. Also check the level of top
girder and diagonals at top of the girder. The diagonal distance must be
within 10mm.
(vii) Weld the column base with the bottom girder, top girders, with columns,
pipe bracing with the top girder and column, and edge girder with the top
girder as per the drawing. to the top plates of supports as shown in the
drawing.
(xi) Check the fitment of the casing panel and weld the same as per drawing.
(xiv) If facility is available assemble the inlet cone and outlet cone at ground
level or piece by piece erect the same at inlet and outlet of the electrostatic
precipitator. After proper fitment weld the same to make EP leak proof.
17
6.5 Hopper Assembly
(i) Pre-assemble the hopper on the ground. Match the total dimensions of a
particular hopper with the corresponding hopper opening dimension.
Complete the welding of the hopper. Fix and weld the inspection doors of
the hoppers.
(ii) Lift the hopper assembly and position it keeping the orientation of the
hopper door as per the General Arrangement drawing
(iv) Level the hopper bottom flange by spirit level and weld ensuring the
hopper bottom elevation as per the GA drawing.
NOTE: In most of the cases collecting electrode and discharge electrode are lifted
through the bottom of the ESP so hopper is to be erected after the
completion of the internals of the ESP Hopper
(i) Gas path Centre Line (GPCL) is a line which passes through the center of
the effective width of each pass. All internals are mounted only with
reference to these lines.
(ii) Mark the GPCL of the pass on the top flange of the first and last
transverse roof beams or the ends of longitudinal roof beam as the case
may be.
18
(iii) Stretch a twine between the markings and transfer the GPCL on all other
roof beam top flanges. Do not mark the GPCL on each roof beam by taking
separate measurements.
(iv) Punch all the GPCL markings on roof beams for reference.
(v) Transfer the GPCL from the top flange to the bottom flange of the roof
beam.
(i) The collecting electrode suspension is one of the vital components that
decide the effective voltage distance. Any deviation either in dimension of
the frames or in the disposition of frames with reference to the GPCL
would affect the performance of the electrostatic precipitator seriously.
(b) Check the gap between the channels of the suspension bar
(e) Fix guide angle, block for guide angle, bracket for guide angle,
walkway and guide and deflection plate
(iii) Place the suspension bar as per the drawing, and check the position with
the guide finger through plumb.
b) Also check the welding of nuts and bolts of the rapping bar.
19
6.9 Collecting Electrode
(i) There are many ways to lift the collecting electrodes to the desired position
so as to suspend them from the suspension bar. The method of lifting
brought into effect depends on the site condition:
a) From top
(iii) Fix the guide plates during lifting of the collecting plates.
(i) Place the protection tube with insulator housing on the main ceiling with
respect to the GPCL as per the drawing.
(ii) Place the discharge electrode suspension frame, traverse and RS-
Electrode, supporting traverse with respect to GPCL and protection tube.
Fix the entire assembly with temporary support.
(iii) Check for the alignment of (i) and (ii) and weld the protection tube with
the main ceiling.
(i) Check the straightness of discharge electrodes and keep the straightness
within 2mm maximum.
(iii) Fix the R.S. Electrode top and bottom part by bolt and nut.
(iv) Fix the discharge electrode with supporting traverse and stabilizing bar.
20
(v) Fix guide bar and connecting piece. Also fix the fixing traverse, stabilizing
traverse, and shackle as per the drawings.
(vi) Check the distance between the discharge electrode and collecting
electrode.
(vii) Place the supporting insulator on the protection tube and the insulator
cover on the supporting insulator. Put gasket in between the insulator
cover and supporting insulator and protection tube.
(viii) Put suspension tube, suspension link, nut and ball cup as per the
drawing.
(ix) Tightening all the nuts together/ one by one slowly so that the total load
of the discharge frame including that of the discharge electrode is
transferred on the supporting insulator slowly and hang on it rigidly.
(i) Hook the screen sheets through hanger already fixed with the supporting
cone.
(ii) Mount the angle traverse and tie rods and keep all the dimension as per
the drawing.
(v) Ensure that a minimum gap of 100 mm between the bottom edge of
screen sheets and front wall surface.
(vi) It is advisable to erect the inlet GD screen before arranging the collecting
electrodes in the first field.
21
6.13 Rapping Mechanism for Collecting Electrodes
b) Place all bearing block & bracket as well as roller & bushing as per the
drawing.
c) Place the shaft on roller and bushing along with coupling/ bearing, after
straightening the shaft and removing the rust from the shaft surface. The
distance between the center line of the shaft and the center line of the
rapping bar anvil should be as per drawing. Also make one hole in the
casing so that shaft can pass through the casing, with its drive placed
outside the casing.
d) Fix bushing ( Packing Box) from outside the casing to make it leak proof
e) Support for drive should be fixed outside the casing as per the drawing,
also check the physical height of the Collecting Electrode Geared Motor
and keep some packing(bed plates) provision for easy alignment.
f) Fix all the rapping hammer on the shaft in such a fashion that each
hammer maintains a uniform angle of separation between them. Also
check the center line of rapping hammer, and the center line of rapping
bar anvil should match vertically.
h) Also fix in the first field GD screen rapping arrangement which includes
hammer, GD rapping bar etc. as per drawing.
NOTE : Mark the correct direction of rotation of the shaft and fix the
Direction Marker at a prominent place on the gear unit. Paint a caution
DONT REVERSE THE ROTATION on the bracket. Reverse rotation will
cause serious damage to the rapping bar, rapping bar guide and shaft and
disrupt the alignment of the electrodes.
a) Place all bearing block & bracket as well as roller & bushing as per
drawing
22
b) Place the shaft on roller and bushing along with pin wheel, lever and
coupling after, straightening the shaft and removing the rust from the
shaft surface. The distance between the center line of the shaft and the
center line of the anvil should be as per the drawing.
c) Fix the geared motor along with eccentric and swing bearing also put the
gasket in between insulator housing and geared motor.
d) Fix the ratchet, along with lifting rod and rapping insulator and adjust
the lifting rod, lever and ratchet in such a fashion that, when geared
motor runs, pin wheel should rotate the shaft in a proper manner. Thrust
bearing is also to be fixed properly as its keeps the axis of rotation of the
pin wheel constant.
NOTE : Please maintain all the dimensions as per the drawings, otherwise it
will be difficult to maintain the rapping mechanism of the discharge
electrode in working condition.
(i) Compete the erection of balance roof panels. Welding shall be leak proof.
(ii) Also take care that the T/R set handling system, while erecting main
ceiling and insulator house roof .
(i) Insulator house wall and root are to be fixed as per drawing
(ii) T/R set is to be placed and connected with the Bus Coupler as per
drawing
(i) All inspection doors for hopper, casing and roof are to be fixed and seal
welded per drawing. Ensure that there shall be no projection inside the
hopper/the casing. Ensure that the doors close freely. Bolt the earthing
cables on to the door and the flange.
23
6.18 Insulation :
(ii) Insert and tack weld the retainers on the fixing pin, so as to retain the
insulation, just upto the height of the stiffener.
(iii) Place the mineral wool mattress and press them on to the pins.
(iv) Sew the wire nettings of the mattresses at the ends by sewing wires.
(v) Tie the binding wires across the fixing pins below the retainers.
(vi) Fix the casing support to the retainers by using the self tapping screws.
(vii) Lay the outer casings over the casing supports by screwing self tapping
screws.
(viii) Take care while lapping the outer casing that no rain water enters into the
insulation.
(iv) Heaters :-
Mount the support insulator heaters. Ensure that the heaters sit
properly and concentric to the support insulators
(i) Ensure that the walls roof and hopper walls do not have any holes.
(ii) Ensure that all temporary stays, supports, etc., used during erection are
removed.
(iii) Ensure that the nuts and bolts in the rapping mechanism as well as on
the emitting frames are locked by tack welding, after trial run of 48 hrs
and clearance of the commissioning engineer.
(iv) Ensure that no welding beads, projections or sharp edges are left in the
vicinity where flash-overs will occur during operation. Check all critical
dimension and compare the same with log dimension.
24
(v) Ensure that the earthing handles are welded on to the emitting framework
nearer to the inspection door. Ensure that all earthing cables are properly
fitted at doors and connections.
(vii) Remove all foreign materials like welding rods, cut bits, wooden planks
etc., from inside the EP.
25