7 Grouting Drawing Visual, 100% - Joints free from loose material Engineer /
Contract Specs. - Jointing mortar stiff, slump free & Foremen/
BS 8000 Part 11 workable Quality Engineer
BS 5385 - Joints filling material for wall shall be stiff
Mfr's. data sheet and self supporting
- Tiles not disturbed
- No air trapped
- Surplus jointing material cleaned from tile
- Finish joints neatly & face of tile cleaned
and polished
- Use coloured grout if specified
QC~PLAN.
Project No. & Name:
Name of Client/ Consultant:
9 Protection Drawing Visual, 100% - Protected from rain & dust Engineer /
Contract Specs. - No traffic permitted for 24 hours Foremen/
BS 8000 Part 11 - Light foot traffic allowed after 24 hours Quality Engineer
BS 5385 - Normal traffic allowed after 7 days
Mfr's. data sheet -Covered with polyethene sheet/ paper
board sheet/ plywood etc.
10 Final Inspection Drawing Visual, 100% - Pattern, slope & finishing to match Engineer /
Contract Specs. drawings Foremen/
- Free from stains & spatter Quality Engineer
QC~PLAN.
Ceramic Tiling (Wall & Floor)
Doc.No.CIVIL QC~Plan- 017/ REV. 0
RECORD
RECORD
--
RECORD