Costing for 15KL RCC tank

Sl.No Description of work Units Qty Rate Amount


1 Dismantling of RCC Cu.Mtr 2.3625 10500 24806.25
2 Excavation work Cu.Mtr 6.3 495 3118.5
3 Wet-Mix Cu.Mtr 3.9375 2900 11418.75
4 P.C.C Cu.Mtr 1.575 5500 8662.5
5 R.C.C Cu.Mtr 14.515 7600 110314
6 Shuttering work Sq.Mtr 90.35 650 58727.5
7 Plastering work Sq.Mtr 53.5 365 19527.5
8 Water proofing work Sq.Mtr 53.5 1250 66875
9 Acid tile linning work Sq.Mtr 53.5 3100 165850
10 Bore packing in tank Nos 4 1250 5000
11 Reinforcement Steel Kgs 2500 65 162500
12 Cement Bags 75 385 28875
13 Misc. LS 1 30000 30000
Total 695675
7.0

Costing for 10KL RCC tank


Sl.No Description of work Units Qty Rate Amount
1 Dismantling of RCC Cu.Mtr 2.3625 10500 24806.25
2 Excavation work Cu.Mtr 6.3 495 3118.5
3 Wet-Mix Cu.Mtr 3.9375 2900 11418.75
4 P.C.C Cu.Mtr 1.575 5500 8662.5
5 R.C.C Cu.Mtr 12.595 7600 95722
6 Shuttering work Sq.Mtr 71.15 650 46247.5
7 Plastering work Sq.Mtr 43.9 365 16023.5
8 Water proofing work Sq.Mtr 43.9 1250 54875
9 Acid tile linning work Sq.Mtr 43.9 3100 136090
10 Bore packing in tank Nos 4 1250 5000
11 Reinforcement Steel Kgs 2500 65 162500
12 Cement Bags 75 385 28875
13 Misc. LS 1 30000 30000
Total 623339
6.2

Costing for 5KL RCC tank


Sl.No Description of work Units Qty Rate Amount
1 Dismantling of RCC Cu.Mtr 1.0935 10500 11481.75
2 Excavation work Cu.Mtr 2.916 495 1443.42
3 Wet-Mix Cu.Mtr 1.8225 2900 5285.25
4 P.C.C Cu.Mtr 0.729 5500 4009.5
5 R.C.C Cu.Mtr 7.197 7600 54697.2
6 Shuttering work Sq.Mtr 44.61 650 28996.5
7 Plastering work Sq.Mtr 25.62 365 9351.3
8 Water proofing work Sq.Mtr 25.62 1250 32025
9 Acid tile linning work Sq.Mtr 25.62 3100 79422
10 Bore packing in tank Nos 4 1250 5000
11 Reinforcement Steel Kgs 2500 65 162500
12 Cement Bags 75 385 28875
13 Misc. LS 1 30000 30000
Total 453086.9
4.6
BOQ for 15KL RCC tank

Sl.No Description of work Units Nos L B D Qty


1 Dismantling of RCC Cu.Mtr 1 3.5 4.5 0.15 2.3625

2 Excavation work Cu.Mtr 1 3.5 4.5 0.4 6.3

3 Wet-Mix Cu.Mtr 1 3.5 4.5 0.25 3.9375

4 P.C.C Cu.Mtr 1 3.5 4.5 0.1 1.575

5 R.C.C
Wall starter Cu.Mtr 1 12 0.2 0.1 0.24
Base Concrete Cu.Mtr 1 3.5 4.5 0.3 4.725
Reintaining wall Cu.Mtr 2 2.5 3 0.2 3
Reintaining wall Cu.Mtr 2 3.5 3 0.2 4.2
Top slab Cu.Mtr 1 2.5 3.5 0.2 1.75
Inside IPS flooring Cu.Mtr 1 2 3 0.1 0.6
14.515
6 Shuttering work
Footing Sq.Mtr 2 3.5 0.3 2.1
Sq.Mtr 2 4.5 0.3 2.7
Reintaining wall Sq.Mtr 4 3.5 3 42
Reintaining wall Sq.Mtr 4 2.5 3 30
Slab Sq.Mtr 1 2.5 3.5 8.75
Starter 2 12 0.2 4.8
90.35
7 Plastering work
External Sq.Mtr 1 12 3 36
Slab Top & Bottom Sq.Mtr 2 2.5 3.5 17.5
53.5
8 Water proofing work Sq.Mtr 1 12 3 36
Sq.Mtr 2 2.5 3.5 17.5
53.5
9 Acid tile linning work Sq.Mtr 1 12 3 36
Sq.Mtr 2 2.5 3.5 17.5
53.5

10 Bore packing in tank Nos 4

BOQ for 10KL RCC tank

Sl.No Description of work Units Nos L B D Qty


1 Dismantling of RCC Cu.Mtr 1 3.5 4.5 0.15 2.3625

2 Excavation work Cu.Mtr 1 3.5 4.5 0.4 6.3

3 Wet-Mix Cu.Mtr 1 3.5 4.5 0.25 3.9375

4 P.C.C Cu.Mtr 1 3.5 4.5 0.1 1.575

5 R.C.C
Wall starter Cu.Mtr 1 12 0.2 0.1 0.24
Base Concrete Cu.Mtr 1 3.5 4.5 0.3 4.725
Reintaining wall Cu.Mtr 2 2.5 2.2 0.2 2.2
Reintaining wall Cu.Mtr 2 3.5 2.2 0.2 3.08
Top slab Cu.Mtr 1 2.5 3.5 0.2 1.75
Inside IPS flooring Cu.Mtr 1 2 3 0.1 0.6
12.595
6 Shuttering work
Footing Sq.Mtr 2 3.5 0.3 2.1
Sq.Mtr 2 4.5 0.3 2.7
Reintaining wall Sq.Mtr 4 3.5 2.2 30.8
Reintaining wall Sq.Mtr 4 2.5 2.2 22
Slab Sq.Mtr 1 2.5 3.5 8.75
Starter 2 12 0.2 4.8
71.15
7 Plastering work
External Sq.Mtr 1 12 2.2 26.4
Slab Top & Bottom Sq.Mtr 2 2.5 3.5 17.5
43.9
8 Water proofing work Sq.Mtr 1 12 2.2 26.4
Sq.Mtr 2 2.5 3.5 17.5
43.9
9 Acid tile linning work Sq.Mtr 1 12 2.2 26.4
Sq.Mtr 2 2.5 3.5 17.5
43.9

10 Bore packing in tank Nos 4

BOQ for 5KL RCC tank

Sl.No Description of work Units Nos L B D Qty


1 Dismantling of RCC Cu.Mtr 1 2.7 2.7 0.15 1.0935

2 Excavation work Cu.Mtr 1 2.7 2.7 0.4 2.916


3 Wet-Mix Cu.Mtr 1 2.7 2.7 0.25 1.8225

4 P.C.C Cu.Mtr 1 2.7 2.7 0.1 0.729

5 R.C.C
Wall starter Cu.Mtr 1 8.4 0.2 0.1 0.168
Base Concrete Cu.Mtr 1 2.7 2.7 0.3 2.187
Reintaining wall Cu.Mtr 2 2.1 2 0.2 1.68
Reintaining wall Cu.Mtr 2 2.1 2 0.2 1.68
Top slab Cu.Mtr 1 2.1 2.1 0.2 0.882
Inside IPS flooring Cu.Mtr 1 2 3 0.1 0.6
7.197
6 Shuttering work
Footing Sq.Mtr 2 2.7 0.3 1.62
Sq.Mtr 2 2.7 0.3 1.62
Reintaining wall Sq.Mtr 4 2.1 2 16.8
Reintaining wall Sq.Mtr 4 2.1 2 16.8
Slab Sq.Mtr 1 2.1 2.1 4.41
Starter 2 8.4 0.2 3.36
44.61
7 Plastering work
External Sq.Mtr 1 8.4 2 16.8
Slab Top & Bottom Sq.Mtr 2 2.1 2.1 8.82
25.62
8 Water proofing work Sq.Mtr 1 8.4 2 16.8
Sq.Mtr 2 2.1 2.1 8.82
25.62
9 Acid tile linning work Sq.Mtr 1 8.4 2 16.8
Sq.Mtr 2 2.1 2.1 8.82
25.62

10 Bore packing in tank Nos 4