NAMA: KHARISMA ADAM RENCANA ANGGARAN BIAYA (RAB)

NIM: D1031161046
NO NAMA PEKERJAAN VOL HARGA SATUAN JUMLAH HARGA JUMLAH JUMLAH PEKERJA
1 PEK. PERSIAPAN Rp 19,131,734
1M PEMBUATAN PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER (P.PS. 01) 58 Rp 189,576 Rp
1
2 10,995,408 6 Rp 1,832,568
3 MEMBERSIHKAN LAHAN 210 Rp 20,412 Rp 4,286,520 6 Rp 714,420
4 PENGUKURAN DAN PEMASANGAN BOWPLANK 74.5 Rp 51,675 Rp 3,849,806 6 Rp 641,634
5 PEK. PONDASI Rp 92,506,409
6 MEGGALI TANAH SEDALAM 2.304 Rp 90,706 Rp 208,987 6 Rp 34,831
7 MENGURUG PASIR URUG 1.296 Rp 194,983 Rp 252,697 6 Rp 42,116
8 MEMBUAT 1 M LANTAI KERJA BETON MUTU F'C =7,4 MPA ( K 100), SLUMP (3-6) CM ,W/C =0,87 1.296 Rp 1,062,729 Rp 1,377,296 3 Rp 459,099
9 MEMASANG 1M2 BEKISTING UNTUK PONDASI 43.2 Rp 216,921 Rp 9,370,973 6 Rp 1,561,829
10 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR U 32 8.64 Rp 175,185 Rp 1,513,598 3 Rp 504,533
11 MEMBUAT 1 M BETON MUTU F'C =31,2 MPA ( K 350), COR PONDASI 43.2 Rp 1,540,164 Rp 66,535,064 3 Rp 22,178,355
12 MENGURUG KEMBALI TANAH 1M3 DENGAN TANAH PILIHAN 32.4 Rp 408,883 Rp 13,247,793 6 Rp 2,207,966
13 PEK. STRUKTUR Rp 86,470,636
14 MEMASANG 1M2 BEKISTING UNTUK SLOOF 0.432 Rp 229,934 Rp 99,331 3 Rp 33,110
15 MEMBUAT 1 M BETON MUTU F'C =31,2 MPA ( K 350), COR SLOOF 0.432 Rp 1,540,164 Rp 665,351 3 Rp 221,784
16 MEMASANG BEKISTING UNTUK KOLOM 46.8 Rp 234,853 Rp 10,991,105 10 Rp 1,099,110
17 MEMBUAT 1 M BETON MUTU F'C =31,2 MPA ( K 350), COR KOLOM 46.8 Rp 1,540,164 Rp 72,079,652 3 Rp 24,026,551
18 MEMASANG 1M2 BEKISTING UNTUK LANTAI 1.2 Rp 442,006 Rp 530,407 6 Rp 88,401
19 MEMBUAT 1 M BETON MUTU F'C =31,2 MPA ( K 350), COR LANTAI 1.2 Rp 1,540,164 Rp 1,848,196 6 Rp 308,033
20 PEMASANGAN 1M BEKISTING UNTUK TANGGA 1.2116 Rp 211,781 Rp 256,594 6 Rp 42,766
21 PEK. DINDING Rp 19,382,286
22 1M2 PASANG BATAKO TEBAL 12 MM LEBAR 30 PANJANG 7 CM 66 Rp 115,201 Rp 7,603,266 10 Rp 760,327
23 PEMASANGAN 1 M PLESTERAN 1SP:1PP TEBAL 15MM 132 Rp 89,235 Rp 11,779,020 10 Rp 1,177,902
24 PEK. PINTU DAN JENDELA Rp 35,141,816
25 MEMBUAT ,MEMASANG KUSEN PINTU DAN KUSEN JENDELA KAYU KELAS 2 0.676 Rp 19,446,999 Rp 13,146,171 6 Rp 2,191,029
26 KACA TEBAL 5MM 1M2 9.9 Rp 205,237 Rp 2,031,851 5 Rp 406,370
27 MEMBUAT 1M2 DAUN PINTU KAYU KELAS 2 22.4 Rp 891,241 Rp 19,963,794 10 Rp 1,996,379
28 PEK. ATAP Rp 82,013,599
MEMASANG BEKISTING UNTUK BALOK 132 Rp 412,995 Rp 54,515,307 10 Rp 5,451,531
29 MEMBUAT 1 M BETON MUTU F'C =31,2 MPA ( K 350), COR SLOOF 0.693 Rp 1,540,164 Rp 1,067,333 3 Rp 355,778
30 MEMASANG 1M3 KONSTRUKSI KUDA KUDA KAYU KELAS 2 0.6912 Rp 7,510,616 Rp 5,191,337 3 Rp 1,730,446
31 MEMASANG GORDENG KAYU KELAS 2 0.1536 Rp 8,080,147 Rp 1,241,111 3 Rp 413,704
32 PASANG ATAP SENG GELOMBANG BETUMEN 1M2 BESAR 142 Rp 118,756 Rp 16,863,352 2 Rp 8,431,676
33 PASANG ATAP SENG GELOMBANG BETUMEN 1M2 KECIL 26.4 Rp 118,756 Rp 3,135,158 1 Rp 3,135,158
34 PEK. PLAFOND Rp 22,205,416
35 PEMASANGAANGAN 1M2 RANGKA LANGIT LANGIT (50X10)CM , KAYU KELAS 2 105 Rp 155,298 Rp 16,306,319 10 Rp 1,630,632
36 MEMASANG 1M2 LANGIT LANGIT GRC 105 Rp 56,182 Rp 5,899,096 10 Rp 589,910
37 PEK. LANTAI Rp 77,096,082
38 PEMASANGAN 1 M LANTAI KERAMIK 40 CM X 40 CM POLISHED (SETARAF INDOGRES) 215.5 Rp 348,241 Rp 75,045,936 16 Rp 4,690,371
39 LANTAI KERAMIK 20X20 WC 8 Rp 256,268 Rp 2,050,146 2 Rp 1,025,073
40 PEK. INSTALASI & SANITASI Rp 4,363,842
41 PEMASANGN KLOSET JONGKOK KERAMIK 2 Rp 606,855 Rp 1,213,710 3 Rp 404,570
42 MEMASANG 1M PIPAS GALVANIS 30 Rp 60,088 Rp 1,802,654 3 Rp 600,885
43 MEMASANG 1 BUAH KERANG AIR 7 Rp 101,718 Rp 712,023 3 Rp 237,341
44 MEMASANG 1M PIPA PVC TIPE UNTUK AIR KOTOR 24 Rp 26,477 Rp 635,455 3 Rp 211,818
JUMLAH Rp 438,311,819
NAMA: KHARISMA ADAM TIME SCEDULE
NIM: D1031161046 KURVA S Chart
Chart Title
Title
120.00
BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 BULAN 7 BULAN 8
NO JENIS PEKERJAAN DURASI HARGA PROSENTASE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
100.00
1 PEK. PERSIAPAN 1 Rp 19,131,734 4.36 4.36
2 PEK. PONDASI 6 Rp 92,506,409 80.00 21.11 3.52 3.52 3.52 3.52 3.52 3.52
3 PEK. STRUKTUR 10 Rp 86,470,636 19.73 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97
4 PEK. LANTAI 3 Rp 19,382,286 60.00 4.42 1.47 1.47 1.47
5 PEK. ATAP 4 Rp 35,141,816 8.02 2.00 2.00 2.00 2.00
6 PEK. PLAFOND 4 Rp 82,013,599 40.00 18.71 4.68 4.68 4.68 4.68
7 PEK. DINDING 4 Rp 22,205,416 5.07 1.27 1.27 1.27 1.27
20.00
8 PEK. PINTU DAN JENDELA 1 Rp 77,096,082 17.59 17.59
9 PEK. INSTALASI & SANITASI 1 Rp 4,363,842 1.00 1.00
0.00
JUMLAH Rp438,311,819 1
100.00 2 3 4 5 6 7 8 9 10 11 12 13 14
14 15 16 17
17 18
18 19
19 20
20 21
21 22
22 23
23 24
24 25
25 26
26 27
27 28
28 29
29 30
30 31
31
RENCANA PROGRES MINGGUAN (%) 0.00 7.88 3.52 3.52 3.52 3.52 5.49 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97 3.45 1.47 1.47 2.00 2.00 2.00 2.00 4.68 4.68 4.68 4.68 1.27 1.27 1.27 1.27 18.58
RENCANA PROGRES KOMULATIF (%) 0.00 7.88 11.40 14.92 18.43 21.95 27.44 29.42 31.39 33.36 35.33 37.31 39.28 41.25 43.23 46.67 48.15 49.62 51.62 53.63 55.63 57.64 62.32 66.99 71.67 76.35 77.62 78.88 80.15 81.42 100.00
REALISASI MINGGUAN (%) 0.00 6.43 3.20 2.53 3.53 3.00 5.20 1.98 1.98 1.90 1.98 1.00 2.20 1.98 2.00 3.00 1.00 1.00 4.20 4.20 2.00 2.00 4.00 4.68 5.00 4.68 5.20 4.43 1.00 1.00 13.70
KOMULATIF REALISASI MINGGUAN (%) 0.00 6.43 9.63 12.16 15.69 18.69 23.89 25.87 27.85 29.75 31.73 32.73 34.93 36.91 38.91 41.91 42.91 43.91 48.11 52.31 54.31 56.31 60.31 64.99 69.99 74.67 79.87 84.30 85.30 86.30 100.00
DIFERENSIASI (%) -1.45 -1.77 -2.76 -2.74 -3.26 -3.55 -3.55 -3.54 -3.61 -3.60 -4.58 -4.35 -4.34 -4.32 -4.76 -5.24 -5.71 -3.51 -1.32 -1.32 -1.33 -2.01 -2.00 -1.68 -1.68 2.25 5.42 5.15 4.88 0.00