NATURE OF TRAINING
I have enjoyed each and every day of my traineeship at the CWA. In fact, the
CWA is like a one stop shop dealing with water projects. I have had the
opportunity to monitor projects from scratch and followed it up to their
commissioning where all the main aspects of Civil Engineering activities are
dealt with. The training obtained through the core activities are namely:
Design
Supervision
Contract Management.
I received my training within the P&D section where all the planning and
design are undertaken for new contracts. Supervision and contract
management also fall under the P&D.
New contracts usually originate as Request for New Pipeline from the Ops
Section. These people are more aware of the existing water supply problems
which are as follows;
Obviously the Ops-Section do not have the necessary resources to carry out
such works and they revert to the P&D for new projects implementation.
Based of Ops-Section Priority list, a project is born and the inception stage
starts at the P&D. The project may be:
The bid documents for these two types of contracts are generally prepared
using the FIDIC 1999 Conditions of Contract. However, the Instruction to
Bidders (ITB) and Bidding Data Sheets (BDS) used are that from the
Procurement Policy Office (PPO). Documents from the PPO are of the World
Bank format and are governed by the Public Procurement Act of 2006.
Tendered contracts usually consist of major works where a study has been
undertaken beforehand and are above Rs 6M per package. They may also
be governed by the following:
These can be qualified as fast track contracts. Contractors are invited to bid
for works to be effected in the 6 CWA Zones. The contractors are required to
bid for works based on a fictitious though representative Bill of Quantities
(BOQ).
Responsive contractors go through an evaluation process whereby more
often the lowest bidder is awarded the Contracts in respective zones. The
Minor Works Contract is for a period of two years with an annual budget of
Rs 30 Million.
Contracts for Minor Works consist of work packages which are termed as
Work Orders amounting to a maximum of Rs 6M, each
I have been involved in the following projects and activities where the
different natures of training were acquired through my involvement.
C2013-33 Renewal of Service Main from St 55M Aug 13 Nov 13 Feasibility Study
Hubert to St Hilaire and adjoining Bid Document
laterals Sept 14 July 15 Supervision
Contract
Management
2 C2015-80 Rich En Eau Ville Noire 120M April 14- July 14 Feasibility Study
Estimate Jan 15 - April 15 Bid Document
I was mainly involved in Tendered Contracts as per Table 3 where I put into
contribution the Nature of Training received as per Table 2.
Though the core activities are more or less the same, there are no similar
contracts. Each one is unique.
Design,
Contract Management
Supervision.