AIRWORTHINESS NOTICE
VERSION : 1.0
DATE OF IMPLEMENTATION : 15-10-2017
OFFICE OF PRIME INTEREST : AIRWORTHINESS DIRECTORATE
15/10/2017 AWNOT-093-AWRG-1.0
REQUIREMENTS FOR DOMESTIC MAINTENANCE TRAINING
ORGANISATION APPROVAL UNDER ANO-147
A. AUTHORITY:
A1. This Airworthiness Notice is issued under the authority vested in DG CAA in pursuance of Rule
no. 4 and sub-rule (3) & (5) of Rule 333 of Civil Aviation Rules, 1994 (CARs, 1994).
B. PURPOSE:
B1. Any Maintenance Training and/ or Examination conducted by a Maintenance Training
Organization towards issuance or change of PCAA ANO-066 Aircraft Maintenance Engineers
License (AML) shall be approved by PCAA under respective regulations i.e. ANO-147.
B2. This Airworthiness notice is being issued to describe in detail the requirements mentioned in
ANO-147 for initial, continuation and change in approval of domestic Maintenance Training
Organizations (MTOs).
C. SCOPE:
C1. This AWNOT is applicable to all approved and/ or prospective domestic Maintenance Training
Organizations under ANO-147.
D. DESCRIPTION:
D1. INITIAL APPROVAL:
D1.1 Time Frame: The normal timeframe to process initial ANO-147 approval is about 6
months from the initiation of MTOE & course approval forms scrutiny; however, the
amount of time taken is largely dependent on the ability of the maintenance training
organization to produce the quality of documentation required and to rectify non-
conformances that are identified during the approval process.
~ 6 months
Note 1: PCAA Physical Audit, Report Preparation & Debrief to Accountable Manager
D1.2 Submission of Application Package: The Application Package for grant of
maintenance training organization approval under ANO-147 shall be submitted to OPI
Airworthiness Field Office, based on the Principal Place of Business (station where
offices of Management personnel are present). The Application Package is to be
submitted under a covering letter containing:
D1.2.1 PCAA Form 12 (CAAF-612-AWRG) duly signed by the Accountable Manager.
D1.2.2 PCAA Form 4s (CAAF-604-AWRG) for Management Personnel as prescribed in
AWNOT-079-AWRG.
D1.2.3 Draft Maintenance Training Organization Exposition (MTOE) prepared in line
with PCAA MTOE User Guide attached as Appendix A to this AWNOT (1 hard
(spiral bind) + soft copy)
D1.2.4 Associated MTOE Documents (if any) e.g. TPM etc.
D1.2.5 Course Approval Package for Basic and/ or Type Training Courses as per
intended scope of approval. (The content of the Course Approval Package has
to be prepared in line with Guidelines on Course Approval Package attached as
Appendix B)
D1.2.6 Compliance Statement (Sample attached as Appendix C)
D1.2.7 Evidence of remittance of necessary Fee or Authorization of fee deduction as
per latest revision of AWNOT-003.
D1.3 Document Review: After initial scrutiny of the case, if PCAA finds that the application
package is up to the auditable standards, PCAA shall schedule an initial coordination
meeting with the Accountable Manager at Airworthiness Field Office during which PCAA
shall formally accept the application for further processing and brief the applicant on audit
methodology and subsequent course of actions.
D1.4 The applicant has to establish compliance of requirements mentioned in ANO 147, PCAA
MTOE User Guide and Guidelines on Course Approval Package before any Physical
Audit and/ or Question Data Bank review is scheduled. If required, the Document scrutiny
sessions can be arranged with representatives (Quality Manager and/ or Subject Matter
Experts (SMEs)) of the applicant organization.
D1.5 Processing Of PCAA Form 4s: The Accountable Manager shall submit the applications
for acceptance of following Management Personnel:
D1.5.1 Training Manager
D1.5.2 Quality Manager
D1.5.3 Examination Manager
D1.5.4 Chief Instructor (if nominated by the organization)
D1.5.5 Deputy Training Manager (if MTO has more than 1 approved station)
The applications shall be submitted on PCAA Form 4s to Airworthiness Field Office
along with all supporting documents, after ensuring that the candidates meet the
requirements laid down in latest revision of AWNOT-079. The process of acceptance of
Management personnel including review of credentials and scheduling of interview is
spread over the complete ANO-147 approval process.
D1.6 Audit Preparation: A Compliance Statement by Quality Manager of the organization
shall be submitted to PCAA confirming that processes/ procedures, facilities,
documentation and personnel of the organization are in compliance with requirements of
ANO-147. Sample of Compliance Statement is attached as Appendix C.
Note: The effectiveness of Compliance Statement will be considered as a mean to establish the
competence of Quality manager towards Form-4 acceptance process.
D1.7 PCAA Physical Audit: PCAA team shall carry out an audit of the organization to
ascertain the capability as per intended scope of approval and compliance with ANO-147
requirements. During the audit, the Quality Manager shall accompany PCAA team for the
whole audit period.
Note: For organizations having their Principal place of business where Airworthiness Field Office is
not present, the organization shall be responsible to make all necessary logistic arrangements for
the PCAA inspector i.a.w. latest revision of AWNOT-003. (i.e. return ticket, accommodation,
transportation and daily allowances etc.).
D1.8 General Requirements for MTO: The organization shall ensure compliance with
requirements mentioned below along with all other requirements mentioned in ANO-147,
AWNOT-078 and AWNOT-079:
D1.8.1 Facilities:
D1.8.1.1. The size and structure of facilities shall ensure protection from the
prevailing weather elements and proper operation of all planned
training and examination on any particular day.
D1.8.1.2. Fully enclosed appropriate accommodation separate from other
facilities shall be provided for the instruction of theory and the
conduct of knowledge examinations.
D1.8.1.3. The accommodation environment (e.g. cleanliness, lighting, furniture
etc) shall be maintained such that students are able to concentrate
on their studies or examination as appropriate, without undue
distraction or discomfort.
~ 2 months
D2.2 Submission of Application Package: The Application Package for Continuation of
maintenance training organization approval under ANO-147 shall be submitted at least
two (02) months prior to expiry of approval to OPI Airworthiness Field Office (based on
Principal place of business) under a covering letter containing:
D2.2.1 PCAA Form 12 duly signed by the Accountable Manager
D2.2.2 Copy of PCAA Form 11
D2.2.3 Authorization of fee deduction as per latest revision of AWNOT-003
D2.3 Performance Monitoring of the Organization through Surveillance Audits: The
performance of Approved Maintenance Training Organization within a period of 12
months shall form basis of its Continuation of Approval. Airworthiness Field Offices
through Surveillance Audits (Scheduled and unscheduled) shall monitor the performance
of the organization giving special emphasis to Level 1 & Level 2 Findings.
D2.4 Based on the performance of MTO during the scheduled/ unscheduled surveillance
audits, Field Offices may choose to go for a complete audit or rely on Surveillance audit
reports of the organization in the preceding last year, before recommending the
continuation of approval.
D2.5 However, each approved station of all organizations shall be completely audited for
compliance with the ANO-147 at periods not exceeding 24 months. This shall include
monitoring of at least one training course and one examination performed by the MTO.
D2.6 The OPI Airworthiness Field Office shall coordinate with other Field Offices (if applicable)
and if satisfied, shall forward a consolidated Recommendation Report PCAA Form 22 to
HQs. Airworthiness Directorate at least 10 days prior to expiry of approval.
D2.7 Issuance of Continuation of Approval: On receipt of positive recommendations on
PCAA Form 22 along with supporting checklist/ documents from Airworthiness Field
Offices and confirmation of necessary PCAA fee as per latest revision of AWNOT-003, a
revised Maintenance Training Organization Approval Certificate on PCAA Form-11 shall
be issued to the Organization with validity for a period up to one year. After receipt of
revised PCAA Form-11, Quality Manager of the organization shall surrender the previous
Original Approval Certificate to HQs. Airworthiness Directorate within 01 week.
Review of submitted PCAA Audit Implementation of CAP (including PCAA Closure of Processing of final
application oackage (Note 1) Verification Audits) Findings Recommendations
2 weeks 1 week 1 months 1 week 1 week
~ 2 months
Note 1: Includes PCAA Physical Audit and subsequent Report Preparation.
D3.2 Changes to be notified to PCAA: Changes mentioned below may not necessarily
require to follow the procedure as mentioned in D3.3 but may require re-issuance of
PCAA Form 11. However, it may be noted that these changes require MTOE revision
D3.2.1 Change of the name of the organization: Requires issuance of Form 11.
Application shall be submitted as per Note of D3.3.
D3.2.2 Change of the PPB: Requires issuance of Form 11. Application should be
submitted as per Note of D3.3.
D3.2.3 Change in approved training locations: Application shall be submitted to
PCAA as per Para D3.3.
D3.2.4 Change of Accountable Manager: Does not require issuance of Form 11.
However, Draft MTOE is to be submitted for approval to OPI Airworthiness Field
Office.
D3.2.5 Change of nominated personnel: Does not require issuance of Form 11.
However, Draft MTOE is to be submitted for approval to OPI Airworthiness Field
Office.
D3.2.6 Change of MTOE, associated procedures, lists and forms which does not
affect the scope of approval: Does not require issuance of Form 11. However,
Draft MTOE is to be submitted for approval to OPI Airworthiness Field Office.
D3.3 Submission of Application Package: If the Organization intends to enhance the
existing scope of approval granted by PCAA or intends to enhance the number of
approved station, the organization shall submit Application Package to concerned Local
Airworthiness Field Office under a covering letter containing:
D3.3.1 PCAA Form 12 (CAAF-612-AWRG) duly signed by the Accountable Manager
D3.3.2 Draft Amendment in Current MTOE (1 hard + soft copy)
D3.3.3 Course Approval Package (if applicable)
D3.3.4 Compliance statement by Quality Manager (Sample attached as Appendix C)
D3.3.5 Original PCAA Form-11
D3.3.6 Authorization of fee deduction as per latest revision of AWNOT-003
D3.4 Approval Process: The subsequent process for change in scope of approval shall be
same as described in Para D1.3 to Para D1.12 (as applicable).
D4.1 Major Changes: The PCAA must be notified within 01 week of any major changes or
revisions to the MTOE in respect to any of the items listed below:
D4.1.1 The name of the organization
D4.1.2 The locations of the organization
D4.1.3 The Accountable/Training Manager
Note: For any Major amendment in MTOE, 03 copies shall be submitted at Airworthiness Field Office in
A4 box folder with pages placed in separate plastic sheets.
D4.2 Minor Changes: Organization may make minor amendments, corrections and
changes to the aspects of the organization for items other than those listed above and
these can be defined as:
D4.2.1 Technical Procedures (that do not affect the scope of the approval)
D4.2.2 Typographical corrections for spelling mistakes
D4.2.3 Changes to the layout or appearance and/or when the text of a section
or paragraph is changed to improve the grammatical comprehension
(Where the intent of the original text remains unchanged)
D4.2.4 Training Course Supporting Documentation
D4.2.5 Training staff listed within section 1.5 as per the qualification procedures
as defined in section 3.6 Qualifying of Instructors
D4.2.6 Changes in Approved course list after receipt of course approval from
PCAA
D4.3 All of the above shall constitute a minor change in the MTOE revision number and
shall not be submitted for PCAA approval. However, any page where minor changes
have been incorporated shall be identified by printing the amended page on yellow
paper. In case of addition of amended pages, the page number may be sub
annotated with alphabets e.g. 11a, 11b, 11c etc. however, all must be inserted on
yellow paper.
D4.4 Where any minor amendment is incorporated within the MTOE, that revision number
shall be retained and sub annotated as MTOE Issue no. XX, Revision no. YY(a), with
further minor amendments with YY(b) and so on. Quality Manager shall circulate the
minor amendment along with List of Effective Pages, as per distribution list, within 01
week of minor amendment approval.
D4.5 On subsequent major amendment in MTOE, all yellow pages shall be converted to
normal paper for further inclusion in MTOE in standard pattern.
D4.6 The indirect approval of Minor amendments may be delegated to Quality Manager
provided that a procedure for such approvals is available in the MTOE and approved
by PCAA.
APPENDIX A
to AWNOT-093-AWRG-1.0 dated 15th October, 2017
PAGE I
(Title Page)
The Title page shall contain at least the following:
(Different Pages)
PAGE II
(Approval Record)
Prepared & reviewed by: Name of person in Organization Signature with date
Designation
Organization Name
PART 0 - INTRODUCTION
0.1 Table of Contents
For standardisation purposes and to facilitate the production of the MTOE by the ANO 147 maintenance
training organisation PCAA recommends adoption of the following format for the MTOE as per ANO 147
appendix I to AMCs. The maintenance training organisation should customise the document to suit their
organisation and may add pages/paragraphs as necessary
PART 1 MANAGEMENT
PART 4 APPENDICES
Where a Part is not used it should be shown in the Exposition as Not Applicable.
Chapter Page no. Issue no. Revision no. Rev. Date Chapter Page no. Issue no. Revision no. Rev. Date
PART 0 L2.3 1 of 1 1 1 01/01/12
Title 1 of 1 1 1 01/01/12 L2.4 1 of 2 1 1 01/01/12
0.1 1 of 1 1 0 19/12/06 2 of 2 1 1 01/01/12
0.2 1 of 3 1 1 01/01/12 L2.5 1 of 1 1 1 01/01/12
2 of 3 1 1 01/01/12 L2.6 1 of 1 1 0 19/12/06
3 of 3 1 1 01/01/12 L2.7 1 of 1 1 0 19/12/06
0.3 1 of 1 1 0 19/12/06 PART 3
0.4 1 of 1 1 0 19/12/06 3.1 1 of 1 1 1 01/01/12
0.5 1 of 1 1 0 19/12/06 3.2 1 of 2 1 0 19/12/06
0.6 1 of 1 1 0 19/12/06 2 of 2 1 0 19/12/06
0.7 1 of 1 1 0 19/12/06 3.3 1 of 1 1 1 01/01/12
0.8 1 of 1 1 0 19/12/06
PART 1
1.1 1 of 1 1 0 19/12/06
1.2 1 of 1 1 0 19/12/06
1.3 1 of 2 1 1 01/01/12
2 of 2 1 0 19/12/06
3.13 1 of 1 1 0 19/12/06
1.4 1 of 1 1 1 01/01/07
3.14 1 of 1 1 0 19/12/06
1.5 1 of 1 1 0 19/12/06
PART 4
1.6 1 of 1 1 1 01/01/07
4.1 1 of 1 1 0 19/12/06
1.7 1 of 1 1 1 01/01/07
4.2 1 of 1 1 0 19/12/06
1.8 1 of 1 1 0 01/01/12
4.3 1 of 1 1 0 19/12/06
1.9 1 of 1 1 1 01/01/07
4.4 1 of 1 1 0 19/12/06
1.10 1 of 1 1 0 19/12/06
PART 5
1.11 1 of 1 1 1 01/01/07
5.1 1 of 4 1 0 19/12/06
PART 2 1 0 19/12/06
2 of 4 1 0 19/12/06
2.1 1 of 1 1 0 19/12/06 3 of 4 1 0 19/12/06
2.2 1 of 1 1 1 01/01/07 4 of 4 1 0 19/12/06
2.3 1 of 1 1 0 19/12/06 5.2 1 of 1 1 0 19/12/06
5.3 1 of 1 1 0 19/12/06
5.4 1 of 1 1 0 19/12/06
5.5 1 of 1 1 0 19/12/06
PART 6
6.1 1 of 1 1 0 19/12/06
2.27 1 of 1 1 1 01/01/07 6.2 1 of 1 1 0 19/12/06
2.28 1 of 1 1 0 19/12/06 6.3 1 of 1 1 0 19/12/06
PART L2 6.4 1 of 1 1 0 19/12/06
L2.1 1 of 1 1 1 01/01/12
L2.2 1 of 1 1 0 19/12/06
* The list above is just an example and is not complete. Organizations are required to list all the pages of the MTOE in the
above table
Current Version:
MTOE Issue 2, Revision 0 dated 01/01/16
(Next Page)
FOREWORD
It may be preferable to include a foreword that explains the intent of the manual, i.e.
that it is a manual established to comply and to demonstrate compliance with ANO-147
requirements. The following is an example of possible foreword:
This manual has been prepared in order to support the Training School Limited ANO-
147 Maintenance Training Organisation Approval. The body of this Exposition is divided
into four parts.
PART 1 MANAGEMENT
PART 2 TRAINING AND EXAMINATION PROCEDURES
PART 3 TRAINING SYSTEM QUALITY PROCEDURES
PART 4 APPENDICES
NOTE:
This document is intended as guidance only. The headings and the numbering system should be used
but the contents have to be customised to include the applicant procedures and working documents.
Should a different numbering system be used for the Exposition, the applicant will be asked to provide a
cross reference document to ensure compliance.
CONTENTS
COVER PAGE
FOREWORD
CONTENTS
PART 1 MANAGEMENT
PART 4 APPENDICES
PART 1 MANAGEMENT
CONTENTS
PART 1: MANAGEMENT
This exposition defines the organisation and procedures upon which the PCAA ANO- 147
Organisation approval is based.
It is accepted that these procedures do not override the necessity of complying with any new or
amended regulation published by the PCAA from time to time where these new or amended
regulations are in conflict with these procedures.
It is understood that the PCAA will approve this organisation whilst the PCAA is satisfied that
the procedures are being followed. It is understood that the PCAA reserves the right to
suspend, vary or revoke the ANO-147 training system approval of the organisation, as
applicable, if the PCAA has evidence that the procedures are not followed and the standards
not upheld.
These procedures are approved by the undersigned and must be complied with, as applicable,
whenever knowledge or practical training is being progressed under the terms of the ANO-147
approval.
The undersigned fully accepts the duties and responsibilities of Accountable Manager as
defined in paragraph 1.3.1 of this exposition.
Signed .
Accountable Manager .
Notes: The Accountable Managers exposition statement should embrace the intent of
the above paragraphs and in fact this statement may be used without amendment. Any
modification to the statement should not alter the intent.
The duties of the Accountable Manager, as defined in the exposition for the purposes of the
ANO-147 approval, are delegated by the Accountable Manager to the:
-------------------------------------------------------------------------------------
1. This is an alternative available to any organisation where the person who would normally be the
Accountable Manager, by virtue of his/her position in the company/organisation, wishes to delegate
some of the duties and responsibilities to another Manager.
2. Where such duties are delegated, the corporate responsibilities as defined in the corporate commitment
must remain with the Accountable Manager.
The Managers specified above are identified and their credentials apart from the Accountable
Manager have been submitted on Form 4 to the PCAA.
Any changes to the above personnel shall be advised to the PCAA. Failure to do so may affect
the status of the ANO-147 approval.
The procedure regarding handing/ taking over charges of deputies in case of absence of Form-
4 holders to be described in detail.
1. Ensuring that all instruction and examinations carried out by the organisation meets the
standards required by PCAA.
2. Ensuring that the necessary finance, manpower resources and facilities are available to
enable the organisation to perform the knowledge and/or practical instruction and
examinations to which it is committed under the requirements ANO-147.
3. Chairing the annual meeting of senior staff to review the overall performance of the
organisation.
5. Ensuring that during periods of absence, control will be maintained for administration
purposes by (Insert name/position in organisation), who will accept full responsibility for
all training issues and related decisions.
a. Any additional duties and responsibilities within the organisation may be added or
delegated provided they do not conflict with those above, which constitute the
Accountable Managers responsibilities under ANO-147.
b. The organisation should decide who will be responsible for liaison with the PCAA and
show this in his/her terms of reference. If more than one person is nominated it must be
clearly shown what each person is responsible for with, as a general rule, no
overlapping of responsibility.
4. Sufficient staff with appropriate qualifications are selected, trained and developed, to
plan, perform, supervise, examine and assess students as required.
6. Knowledge examiners, instructors and assessors are fully trained and assessed
regularly for competence and that all records pertaining to these personnel are kept up
to date.
7. Sub-contract staff including any part time staff conform to the requirements of ANO-147
and the training procedures.
8. Office accommodation and facilities are available appropriate to the management of the
planned training and for the use of training staff.
10. That all approved courses and examinations are delivered to the standard and content
at the required level of knowledge, as specified in ANO-147.
12. There are sufficient storage facilities, tools, equipment, materials and publications
available to perform the planned practical tasks.
13. The interviewing of students prior to, during and on completion of the course is effective
and without bias.
14. Student and staff records are produced and stored in secure conditions.
15. Any person to whom any of these responsibilities may be delegated is aware of current
regulations.
16. Corrective action is carried out for the findings of quality audits.
17. The follow up and rectification of findings required to re-establish the required standards
of training, examination or maintenance standards.
Notes:
a. This paragraph should emphasise that the nominated post holder for training is
responsible to ensure that all training is carried out to an approved standard and
describes the extent of his authority as regards his ANO-147 responsibility.
b. These duties may be adjusted to suit the requirements of the PCAA ANO-147
Approved organisation but should not detract from the particular requirements of
ANO-147 or ANO-66.
The Quality Manager has direct access to the Accountable Manager in the event of any
reported discrepancy not being adequately attended to by the relevant person, or in
respect of any disagreement over the nature of the discrepancy.
5. All changes to the Exposition and associated manuals are notified immediately to
PCAA.
7. Knowledge examiners, instructors and assessors are fully trained and assessed
regularly for competence and that all records pertaining to these personnel are kept up
to date.
Notes:
a. These duties may be adjusted to suit the requirements of the ANO-147 approved
organisation but should not detract from the particular requirements of ANO-147
or ANO-66.
1. Secure facilities are available for the storage of examination papers prior to the
examination and for the storage of completed students answer papers.
3. The invigilation of examinations, ensuring that the conditions for examination comply
with Annex III, appendix II (for basic training) or appendix III, paragraph 3 (for type
training).
6. That sufficient questions are available to produce the examination papers required
to cover the syllabus in accordance with ANO 66 Appendix II and III.
7. The security and validity of all examinations are in accordance with the requirements
of ANO-66 and ANO-147.
3. Undertake duties of invigilator where he/she is not involved in the instruction of that
particular phase examination.
Notes:
a. The above paragraphs should emphasise that the nominated post holders for
examiner and/or assessor are responsible for ensuring that all examinations and
assessments are carried out to an approved standard and describes the extent of
his/her authority with regard to his/her ANO-147 responsibility. These duties may be
This paragraph should give broad figures to show that the number of people dedicated
to the performance of the approved training activity is adequate. It is not necessary to
give the detailed number of employees of the whole company but only the number of
those involved in training.
Notes:
a. According to the size and complexity of the organisation, this table may be further
developed OR the MTO may maintain a separate list of Instructional and Examination
staff duly referred in this section.
b. The ANO-147 examiners are the only persons allowed to produce/select examination
papers. They may nominate other persons to mark completed examinations. The
examiners and these persons should be other than the knowledge instructors involved
in the instruction of that particular module/sub-module.
This paragraph should list those address(s) at which instruction and/or practical training
are to be carried out for the duration of the ANO-147 course.
The names, address(s) and approval numbers of any proposed Aircraft Maintenance
ANO 145 Organisation at which it is proposed to carry out student practical training in
order to fulfil the requirements of ANO-147 may be kept in another document or
procedure and cross referenced here.
This paragraph should list those address(s) at which training beyond the capacity of the
ANO-147 Organisation may be carried out.
Include here the facilities such as desks, chairs, lockers, overhead projectors, other
teaching aids etc for each of the offices, classrooms, practical training workshops and
examination rooms provided.
This paragraph must contain a list of the ANO-147 course(s) for which approval is held.
This should also include Differences courses.
E.g. Airbus A319/320/321 (CFM 56) B1 - differences to A319/320/321 (V2500) B1.
Include here any cross references to the intended procedures for continued validity of
the approval in compliance with the requirements of ANO-147.A.155.
The organisations nominated person is responsible for informing the Agency of any
proposed changes.
Detail here or cross refer to the procedures to be followed for the amendment of the
exposition and any associated procedures and or documents.
CONTENTS
In this paragraph the organisation should detail the procedures in place in order to
organise the courses and to ensure that all necessary means are available to deliver in
good conditions and by appropriately qualified staff all the course elements as required
by the ANO 66 syllabus. Such procedures may include a formalised review of the
availability of required appropriate training rooms, materials, STDs, specialists and
resulting in tuition programme.
Training material should meet the requirements of ANO-66. It should also state how the
approved company produces a course for a new aircraft type. This would typically
include the production of the Training Needs Analysis and eventually a training
programme for the new aircraft that has to list what is being taught, to what level and for
how long. Once completed, this should be sent to the PCAA for review along with the
PCAA form used by the PCAA for approval of the course. This list must be given a
unique reference number and revision status. In order to get the course approved a set
of multi-choice questions and a copy of the course notes used by the student must also
be submitted.
The course notes must reflect the training programme and be given the same reference
number and revision status. See also the Guidelines on Course Approval Paclage for
further details.
This may cross refer to a separate procedure in which details of how the standard
course lecture notes are produced which would include content, indexing, chapter and
page numbering, font, etc, in the House Style.
This same procedure should also be utilised to list the responsibilities by ANO-66
module for the production, review & amendment of lecture notes.
Include cross references to any procedures used for the inclusion of other course
material, e.g. Aircraft Manuals, PCAA publications, and/or Standard Text Books used for
note preparation and available to students as reference material.
Procedure has to be laid down for revision of all approved courses within a prescribed
period to cater the advancements in the aircraft systems and documentation.
Cross reference to any procedures for the preparation of classrooms and reporting of
faults to any classroom equipment, general maintenance procedures and the control of
the teaching environment.
Cross reference to any procedures for the reporting of faults to any workshop
equipment, general maintenance procedures and the control of the teaching
environment.
Cross reference to procedures for the ordering and storage of aircraft release standard
consumable materials used in the production of practical tasks, and for the ordering and
acquisition of any new equipment required to complete the tasks.
Cross reference to the procedures for ensuring that all test equipment and/or tooling
requiring calibration are correctly forecast and expedited. Also cross reference to the
procedure for ensuring that all electrical equipment power supply feeder cables (from
wall socket to equipment) throughout the organisation are tested as required.
Describe the method utilised in teaching the Basic/Type knowledge and practical
training courses for which the organisation is approved.
Cross refer to procedures for the production, maintenance and security of student files.
These should include details of all student attendances, final knowledge examinations,
practical assessments and any re-examination carried out and their results by ANO-66
complete module for Basic Licence courses and for Type Training, information of those
courses completed, their content and at which levels at which they were instructed and
examined.
There should also be reference to the Basic work experience records required to be
kept by the student whilst he is undergoing his live operating aircraft experience.
The use of an Aircraft Maintenance Engineers Log Book is a good example.
Cross refer to procedures for the storage of staff and students records. These may be
electronically based provided that adequate safeguards are in place to prevent
unauthorised access and alteration.
Should the Management wish to contract out part of the practical training (not including
live operating aircraft experience), control procedures must be in place. These
Any training carried out at address not listed at 1.6 above must be approved by the
PCAA and control procedures must be in place to ensure that the proposed contract
organisation is in compliance with the requirements of ANO-66 & ANO-147.
A contract must be in place with the proposed organisation in which it is agreed that
access is granted to the PCAA for the purpose of Audit.
Ref:
Type of Training/Examinations:*
Date of Training/Examinations:*
Proposed Location:
I confirm that the essential requirements of ANO-147.100 to ANO-147.135 as appropriate, will be met.
Signature:
Date:
Application approved:
Reason:
Signature:
Date:
For Aircraft Maintenance Licence (AML) course a High level document detailing the
course examinations, when each ANO-66 module is to be examined and to what ANO-
66 level. This should include the knowledge, practical and on job training elements and
how the number of hours of each comply with the percentage requirements of AMC
147A.200.
For aircraft type training, the course syllabus should be used to prepare an examination
schedule. The examination schedule should detail the examinations to be set at the end
of each major phase within the syllabus. A final examination should be conducted at the
end of the type training course. The final examination should be recorded. Refer to
(ANO-66) Appendix III, paragraphs 2.2 - 2.4
For AML courses detail the preparation and security of Examination papers. Number of
Questions and Timing must be in accordance with ANO 66 Appendix II.
For Type training it is sufficient to detail the preparation and security procedures in place
for the production and storage of examination papers
Cross refer to procedure to be followed by the Examiner and Invigilator in preparing the
examination room for examinations.
An invigilators ready reference sheet for briefing the candidates prior to the examination
should be available in procedures and cross referenced here.
A procedure should be in place for checking that all the pages of each examination
paper are complete at examination completion and that all examination papers are
accounted for.
Both the written element and the multi-choice question elements should be marked to
75% with no penalty marking. (ANO-66) Appendix II.
All wall charts and/or other visual teaching aids should be removed from the
examination room.
Cross refer to procedures used for assessment of student hand skills, and the standard
tasks set throughout the course. A set number of mandatory tasks should be assessed
to have been completed to a satisfactory standard.
Cross refer to procedures for the marking of completed examination papers and the
recording of results.
A copy of each examination paper, the student number/identification list, a practical task
results list, an examination results list and all examination papers for each complete
module must be stored for a period of five years.
Electronic means of storage may be utilised as required, provided the usual computer
security systems are in place.
Cross refer to the control procedure in common with part 2.8 above. This location must
comply with the requirements of 2.10, 2.11, 2.12, 2.13, 2.14 and 2.15 above.
2.17 Preparation, control and issue of Basic/Type training course certificates: (ANO-
147.A.145)
The certificates should be prepared to reflect that illustrated in (ANO-147) appendix III
and tightly controlled prior to issue, with a system in place to ensure that each copy is
numbered as part of a sequence and recorded as issued to a candidate by name.
CERTIFICATE OF RECOGNITION
CERTIFICATE OF RECOGNITION
CONTENTS
As per the AMC ANO 147.A.130 (2), an external auditor may be contracted by the
smaller organisation for the purposes of the quality audit.
The purpose of the audit plan is to meet part of the needs of the ANO-147 approval.
Cross refer to the various procedures required for quality auditing, reporting findings and
levels with any corrective actions required.
A management control and follow up system must also be in place and may not be
contracted out.
Cross reference to any quality procedures manual if available is permitted, but this
system must relate to and make reference to the relevant ANO-147 paragraphs.
Must be audited annually, but may be part of the rolling audit procedure.
Cross refer to procedures for the reporting of findings and for corrective actions.
Where relevant include procedures for the employment of part time or contract
instructors.
All staff should have an appreciation of the contents of ANO-66 and ANO-147.
*Note: Guidance for acceptable qualifications is proposed in the Annex 1 to the present
MTOE guidance.
Examiners should have a full understanding of all the requirements of ANO-66 and
ANO-147.
The company must maintain a record of all training staff which must include details of
the scope of their authorisation.
Training staff must be provided with evidence of the scope of their authorisation.
a. Name
b. Date of Birth
c. Personnel Number
d. Experience
e. Qualifications relevant to the approval
The records may be kept in any format (hard copy or computer based) subject to the
usual security requirements.
The instructor should be given reasonable access on request to his/her own records.
The authorisation document should be in a style that makes its scope clear to instructors
and any authorised person that may be required to examine the document. Where
codes are used to define scope, an interpretation document should be readily available.
Instructional staff are not required to carry the authorisation document at all times but
should produce it within a reasonable time of a request from an authorised person.
Authorised persons, apart from the organisations quality department must include
PCAA.
Any member of the PCAA is classed as an authorised person when investigating the
records system for initial and continued approval or when the PCAA has cause to doubt
the competence of a particular instructor.
PART 4 APPENDICES
CONTENTS
This section should include examples of all documents and forms used by the
organisation in the conduct of its ANO-147 function.
Some examples are listed below:
This section should contain the signed approval document issued by the Agency for
each approved course.
Self explanatory.
APPENDIX B
to AWNOT-093-AWRG-1.0 dated 15th October, 2017
The application for approval of basic and/ or Type Training Courses shall be submitted to
Airworthiness Field Office on the prescribed Application Form. The Application Forms can be accessed
online through PCAA website www.caapakistan.com.pk.
Following minimum documents shall be submitted along with the application form, otherwise the
case may be returned un-actioned by the Airworthiness Field Office.
1.1 Lesson Plan/ Training Plan (day wise distribution of syllabus content)
1.2 Course Breakdown (topic wise distribution of syllabus)
1.3 Training notes in electronic format for complete course
1.4 Workshop exercises Training & Assessment Booklets with cross reference of sub-modules
(Basic Course)
1.5 OJT exercises Training & Assessment Booklets with cross reference of sub-modules (Basic
Course)
1.6 Practical Element Training Booklet (Type Course)
1.7 Practical Element Assessment Booklet (Type Course)
1.8 Course Flow chart from entry to course completion
1.9 Sample examination question paper for each module, MCQs & Essay as applicable (Basic
Course)
1.10 Sample examination question paper for each phase (Type Course)
1.11 Colour photographs for classroom and proposed examination hall (at least 03 each), for
initial approval or addition of training location
1.12 Qualification details of Instructors for each module/ Type course to ascertain the capability
of organization for intended scope of approval
1.13 Any other applicable document
The training notes designed for Basic Training courses shall cover all areas as defined in PCAA
ANO-066 Regulation Appendix I Basic Knowledge Requirements.
A thorough review of the training materials shall be undertaken to ensure they are applicable and
relative to the training objectives. This may be done by taking into account the following:
a. Each ATA chapter/sub chapter to be accordingly reviewed for its base technical content
level against the required PCAA ANO 66 Regulations Appendix III Levels for each area
or concern.
b. The training notes shall be provided to the candidates in electronic or hard copy format.
c. The notes to be subdivided where applicable and page marked to ensure quick
reference for the students when training.
d. All the training notes must be headed with a ATA reference front page, with the required
PCAA ANO-066 Appendix III levels annotated accordingly.
e. Material on continuing airworthiness information relevant to the type is to be provided to
the students and instructor for discussion as/if applicable during the training.
f. The training and materials shall be specifically designed to accommodate the following
training goals within the sub-training objectives (as required per ATA chapter)
i. General Overview
ii. Description of operation
iii. Locations of Major Components
iv. Normal and Standby Functions
v. Troubleshooting and BITE data
vi. System adjustments / rigging
vii. Any specialist tooling
viii. MEL and Dispatch Limitations
3. QUESTION DATABASE
The PCAA requirements regarding Question Database have been duly prescribed in latest
revision of AWNOT-078 and ANO-147.
The distribution of questions shall be clearly provided for each ATA chapter in the Application
Form. Moreover, the Course Breakdown shall contain the distribution of questions at Sub-Chapter level
(where applicable, when the tuition hour for sub-chapter is more than 01 hour) to ensure compliance of
requirements laid down at Para D6.3 of AWNOT-078.
APPENDIX C
to AWNOT-093-AWRG-1.0 dated 15th October, 2017
It is certified that the submitted application package for Initial/ Change in approval of
Maintenance Training Organization under ANO-147 has been thoroughly reviewed by the
undersigned for compliance with requirements laid down in ANO-147 and associated
Airworthiness Regulations.
Moreover, the undersigned has carried out complete document review and physical audits of
the organization to establish compliance with ANO-147 requirements. Following areas were
checked and found satisfactory:-
In view of above, PCAA is requested to process the submitted application and a physical audit
of the facilities may be scheduled.
Name: ___________________
Date: ___________________
APPENDIX D
to AWNOT-093-AWRG-1.0 dated 15th October, 2017
Organization
No
Satisfactory
??
Yes
Accepted copy of
MTOE shall be
No Yes retained for further
Organization contacted
Satisfactory approval from
for rectification of
?? DAW
deficiencies
Formulation of team to
Continue on next page. conduct physical audit
of training organization
Corrective measures
Findings recorded on Findings conveyed to and tentative dates
Part 4 of Form 22. the organization in provided by
writing organization.
Rectification of deficiency
No Yes
(organization may be Satisfactory? PCAA Form 11
contacted for further prepared
clarifications)