UNIVERSIDAD DE HUNUCO

E.A. P: ING. CIVIL

EJE "A"
1 2 3 4 5 6 7 8

.60 4.00 4.00 3.90 2.55 3.30 3.75 2.95

1 2 3 4 5 6 7 8

TRAMO "1 - 2":


METRADO DE CARGAS :
Carga Muerta (WD):
d L WD 1 2
Losa 2.4 0.2 2.15 1.03 2Tn/m
P. Propio 2.4 0.4 0.25 0.24 Tn/m
Acabados 0.1 - 2.3 0.23 Tn/m 1 3
P2
Tabiqueria 1.8 2.8 - 5.04 Tn/m
6.54 2Tn/m w

Carga Viva (WL):


Sobrecarga 0.4 - 2.15 0.86 Tn/m2
X

Carga Amplificada (W): 2


1 4.00 3
W = 1.4 WD + 1.7 WL
W = 10.621 Tn/m

Carga Puntual (P): 1 2


x= 1.60 m
Tabiqueria 1.8 2.8 0.55 2.77 Tn L= 4.00 m

DIAGRAMAS:

Reacciones: R1= 22.90 tn M1= -15.76 Tn.m


R2= 22.35 tn M2= -15.23 Tn.m
D.M.F
D.F.C
35.0 20.00
25.0 15.00
15.0
10.00
5.0
5.00
-5.0
0

4
0.4

0.8

1.2

1.6

2.4

2.8

3.2

3.6

0.00
-15.0
0

4
3.6
0.4
0.8
1.2
1.6

2.4
2.8
3.2

-25.0 -5.00
-35.0 -10.00
Mu= 8.21 Tn.m
CORTE 2-2
DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2 d
Fy= 4200 kg/cm2 h
r= 6 cm
d= 34 cm
Mu= 8.21 Tn.m
= 0.9
b

Curso: Concreto Armado I "B" HCO - 2017


h
UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 7.08 cm2 a= 6.67 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258

Cuantia de Diseo: Condicin de Diseo:



=

d= 0.00833 CUMPLE

Verificacin de Cuantia:

= Condicin:
=
2 1 0.59 =

CUMPLE
Ru= 28.413 = 0.00834

NMERO DE VARIILLAS:

7.08 cm2 Nv= 3


= Nv= = 2.49 Varillas #6
2.85 cm2 Nv= 2

As= 7.68 cm2 =2x 2.85 cm2 +1x 1.98 cm2


=2x Varillas #6 +1x Varillas #5
Condicin:
0.11 0.596 cm2 0.779 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 7.68 cm2
4 cm 0.953 1.905
r= 5.91 cm
d= 34.09 cm

Cuantias ():
Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.00901 max= 0.02258

CUMPLE

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Momento Nominal: Momento ltimo:


a= 7.23cm = 0.90
=
0.85
Mn= 9.832Tn.m Mu= 8.85Tn.m
= ( )
2
()
8.21 Tn.m 8.85Tn.m CORRECTO

CORTE "1-1" "3-3"


DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 15.76 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 15.65 cm2 a= 14.73 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258

Cuantia de Diseo: Condicin de Diseo:


=

d= 0.01841 CUMPLE

Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 54.525 = 0.01843

NMERO DE VARIILLAS:

15.65 cm2 Nv= 6


= Nv= = 5.49 Varillas #7
2.85 cm2 Nv= 5

As= 16.47 cm2 =3x 2.85 cm2 +1x 7.92 cm2


=3x Varillas #6 +1x Varillas #10

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL
Condicin:

0.11 0.818 cm2 1.722 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 16.47 cm2
4 cm 0.953 3.18
r= 6.54 cm
d= 33.46 cm

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.01969 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 15.50cm = 0.90
=
0.85
Mn= 17.782Tn.m Mu= 16.00Tn.m
= ( )
2
()
15.76 Tn.m 16.00Tn.m CORRECTO

TRAMO "2 - 3":


METRADO DE CARGAS :

Carga Muerta (WD): 2 3


d L WD
Losa 2.4 0.2 1.5 0.72 Tn/m 1 3
P. Propio 2.4 0.4 0.25 0.24 Tn/m 2
Tabiqueria 1.8 2.8 - 5.04 Tn/m w
Acabados 0.1 - 1.75 0.17 5Tn/m
6.17 5Tn/m
Carga Viva (WL):
Sobrecarga 0.4 - 1.5 0.60 Tn/m2 2
1 4.00 3
Carga Amplificada (W):

W = 1.4 WD + 1.7 WL
W = 9.665 Tn/m
2 3
L= 4.00 m

DIAGRAMAS:

Reacciones: R2= 19.33 tn M2= -12.89 Tn.m


R3= 19.33 tn M3= -12.89 Tn.m

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

D.F.C D.M.F
25.0 15.00
20.0
15.0 10.00
10.0
5.0 5.00
0.0
0

4
0.8

3.6
0.4

1.2

1.6

2.4

2.8

3.2
-5.0 0.00

4
2.4
2.8
3.2
3.6
0.4
0.8
1.2
1.6
-10.0
-15.0 -5.00
-20.0
-25.0 -10.00
Mu= 6.44 Tn.m

CORTE 2-2
DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 6.44 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 5.42 cm2 a= 5.10 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258

Cuantia de Diseo: Condicin de Diseo:



=

d= 0.00638 CUMPLE

Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 22.295 = 0.00638

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL
NMERO DE VARIILLAS:

5.42 cm2 Nv= 2


= Nv= = 1.90 Varillas #4
2.85 cm2 Nv= 1

As= 5.7 cm2 =2x 2.85 cm2 +0x


=2x Varillas #6 +0x
Condicin:

0.11 0.280 cm2 0.596 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 5.70 cm2
4 cm 0.953 1.905
r= 5.91 cm
d= 34.09 cm

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.00669 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 5.36cm = 0.90
=
0.85
Mn= 7.520Tn.m Mu= 6.77Tn.m
= ( )
2
()
6.44 Tn.m 6.77Tn.m CORRECTO

CORTE "1-1" Y "3-3"


DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 12.89 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 12.03 cm2 a= 11.32 cm

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL
CUANTIAS:
Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258

Cuantia de Diseo: Condicin de Diseo:



=

d= 0.01415 CUMPLE

Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 44.591 = 0.01416

NMERO DE VARIILLAS:

12.03 cm2 Nv= 5


= Nv= = 4.22 Varillas #6
2.85 cm2 Nv= 4

As= 12.42 cm2 =3x 2.85 cm2 +1x 3.87 cm2


=3x Varillas #6 +1x Varillas #7
Condicin:

0.11 0.390 cm2 1.323 cm2 CUMPLE


VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 12.42 cm2
4 cm 0.953 2.22
r= 6.06 cm
d= 33.94 cm
Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.01464 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 11.69cm = 0.90
=
0.85
Mn= 14.654Tn.m Mu= 13.19Tn.m
= ( )
2
()
12.89 Tn.m 13.19Tn.m CORRECTO

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

TRAMO "3-4":
METRADO DE CARGAS :

Carga Muerta (WD): 3 4


d L WD
Losa 2.4 0.2 2.15 1.03 2Tn/m
P. Propio 2.4 0.4 0.25 0.24 Tn/m 1 3
P2
Acabados 0.1 - 2.3 0.23 Tn/m
Tabiqueria 1.8 2.8 - 5.04 Tn/m w
6.54 2Tn/m
Carga Viva (WL):
Sobrecarga 0.4 - 2.15 0.86 Tn/m2 X
2
Carga Amplificada (W): 1 3.90 3

W = 1.4 WD + 1.7 WL
W = 10.621 Tn/m

Carga Puntual (P): 3 4


x= 2.60 m
Tabiqueria 1.8 2.8 0.55 2.77 Tn L= 3.90 m

DIAGRAMAS:

Reacciones: R3= 21.63 tn M3= -14.26 Tn.m


R4= 22.56 tn M4= -15.06 Tn.m
D.M.F
D.F.C
35.0 20.00
25.0 15.00
15.0
10.00
5.0
5.00
-5.0
0

4
0.4

0.8

1.2

1.6

2.4

2.8

3.2

3.6

0.00
-15.0

3.6
0.0
0.4
0.8
1.2
1.6
2.0
2.4
2.8
3.2

4.0
-25.0 -5.00
-35.0 -10.00
Mu= 7.77 Tn.m
CORTE 2-2
DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 7.77 Tn.m
= 0.9
REA DE ACERO:
b
8
= 2 4 2
0.85
( ) =
2 2
As= 6.66 cm2 a= 6.27 cm

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL
CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258
Cuantia de Diseo: Condicin de Diseo:

=

d= 0.00784 CUMPLE

Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 26.893 = 0.00784

NMERO DE VARIILLAS:

6.66 cm2 Nv= 3


= Nv= = 2.34 Varillas #6
2.85 cm2 Nv= 2

As= 6.97 cm2 =2x 2.85 cm2 +1x 1.27 cm2


=2x Varillas #6 +1x Varillas #4
Condicin:

0.11 0.308 cm2 0.733 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 6.97 cm2
4 cm 0.953 1.905
r= 5.91 cm
d= 34.09 cm

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.00818 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 6.56cm = 0.90
=
0.85
Mn= 9.021Tn.m Mu= 8.12Tn.m
= ( )
2
()
7.77 Tn.m 8.12Tn.m CORRECTO

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

CORTE "1-1" "3-3"


DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2
h d
r= 6 cm
d= 34 cm
Mu= 15.06 Tn.m
= 0.9
REA DE ACERO: b
8
= 2 4 2
0.85
( ) =
2 2
As= 14.72 cm2 a= 13.85 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258
Cuantia de Diseo: Condicin de Diseo:

=

d= 0.01732 CUMPLE

Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 52.123 = 0.01733
NMERO DE VARIILLAS:

14.72 cm2 Nv= 4


= Nv= = 3.80 Varillas #7
3.87 cm2 Nv= 3

As= 14.97 cm2 =3x 2.85 cm2 +1x 6.42 cm2


=3x Varillas #6 +1x Varillas #9
Condicin:

0.11 0.250 cm2 1.619 cm2 CUMPLE


VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 14.97 cm2
4 cm 0.953 2.86
r= 6.38 cm
d= 33.62 cm

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.01781 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 14.09cm = 0.90
=
0.85
Mn= 16.707Tn.m Mu= 15.04Tn.m
= ( )
2
()
15.06 Tn.m 15.04Tn.m REDISEAR

TRAMO "5 - 6":


METRADO DE CARGAS :

Carga Muerta (WD):


5 6
d L WD
Losa 2.4 0.2 2.05 0.98 4Tn/m 1 3
P. Propio 2.4 0.4 0.25 0.24 Tn/m 2
Tabiqueria 1.8 2.8 - 5.04 Tn/m w
Acabados 0.1 - 2.3 0.23 Tn/m
6.49 4Tn/m
Carga Viva (WL):
Sobrecarga 0.4 - 2.05 0.82 Tn/m2 2
1 3.30 3
Carga Amplificada (W):

W = 1.4 WD + 1.7 WL
W = 10.486 Tn/m
5 6
L= 3.30 m

DIAGRAMAS:

Reacciones: R5= 17.30 tn M5= -9.52 Tn.m


R6= 17.30 tn M6= -9.52 Tn.m
D.F.C D.M.F
20.0 12.00
15.0 10.00
10.0 8.00

5.0
6.00
4.00
0.0
2.00
0

3
1.5

3.5
0.5

2.5

-5.0
0.00
-10.0
4
0

3.6
0.4
0.8
1.2
1.6

2.4
2.8
3.2

-2.00
-15.0
-4.00
-20.0 -6.00

Mu= 4.76 Tn.m

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

CORTE 2-2
DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 4.76 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 3.91 cm2 a= 3.68 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258
Cuantia de Diseo: Condicin de Diseo:

=

d= 0.00460 CUMPLE
Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 16.463 = 0.00461

NMERO DE VARIILLAS:

3.91 cm2 Nv= 4


= Nv= = 3.08 Varillas #4
1.27 cm2 Nv= 3

As= 4.13 cm2 =3x 1.27 cm2 +1x 0.32 cm2


=3x Varillas #4 +1x Varillas #2
Condicin:

0.11 0.216 cm2 0.431 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 4.13 cm2
4 cm 0.953 1.27
r= 5.59 cm
d= 34.41 cm

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Cuantias ():
Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.00480 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 3.89cm = 0.90
=
0.85
Mn= 5.632Tn.m Mu= 5.07Tn.m
= ( )
2
()
4.76 Tn.m 5.07Tn.m CORRECTO

CORTE "1-1" Y "3-3"


DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 9.52 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 8.37 cm2 a= 7.88 cm
CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258
Cuantia de Diseo: Condicin de Diseo:

=

d= 0.00985 CUMPLE
Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 32.926 = 0.00986

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL
NMERO DE VARIILLAS:

8.37 cm2 Nv= 3


= Nv= = 2.94 Varillas #6
2.85 cm2 Nv= 2

As= 8.96 cm2 =1x 6.42 cm2 +2x 1.27 cm2


=1x Varillas #9 +2x Varillas #4
Condicin:

0.11 0.585 cm2 0.921 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 8.96 cm2
4 cm 0.953 2.86
r= 6.38 cm
d= 33.62 cm

Cuantias ():
Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.01066 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 8.43cm = 0.90
=
0.85
Mn= 11.064Tn.m Mu= 9.96Tn.m
= ( )
2
()
9.52 Tn.m 9.96Tn.m CORRECTO

TRAMO "6-7":
METRADO DE CARGAS : 6 7
Carga Muerta (WD):
d L WD
1 3
P2
Losa 2.4 0.2 2.15 1.03 2Tn/m
P. Propio 2.4 0.4 0.25 0.24 Tn/m w
Acabados 0.1 - 2.3 0.23 Tn/m
Tabiqueria 1.8 2.8 - 5.04 Tn/m
6.54 2Tn/m
Carga Viva (WL): X
Sobrecarga 0.4 - 2.15 0.86 Tn/m2 2
1 3.75 3
Carga Amplificada (W):

W = 1.4 WD + 1.7 WL
W = 10.621 Tn/m
6 7
Carga Puntual (P):
x= 0.80 m
Tabiqueria 1.8 2.8 0.55 2.77 Tn L= 3.75 m

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

DIAGRAMAS:

Reacciones: R6= 22.09 tn M6= -13.82 Tn.m


R7= 20.51 tn M7= -12.82 Tn.m
D.M.F
D.F.C
35.0 20.00
25.0 15.00
15.0
10.00
5.0
5.00
-5.0
0

4
1.5

2.5
0.5

3.5
0.00
-15.0

3.6
0.0
0.4
0.8
1.2
1.6
2.0
2.4
2.8
3.2

4.0
-25.0 -5.00
-35.0 -10.00
Mu= 5.98 Tn.m
CORTE 2-2
DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 5.98 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 5.00 cm2 a= 4.70 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258

Cuantia de Diseo: Condicin de Diseo:



=

d= 0.00588 CUMPLE

Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 20.678 = 0.00588

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

NMERO DE VARIILLAS:

5.00 cm2 Nv= 3


= Nv= = 2.52 Varillas #5
1.98 cm2 Nv= 2

As= 5.39 cm2 =2x 1.27 cm2 +1x 2.85 cm2


=2x Varillas #4 +1x Varillas #6
Condicin:

0.11 0.395 cm2 0.549 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 5.39 cm2
4 cm 0.953 1.905
r= 5.91 cm
d= 34.09 cm

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.00632 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 5.07cm = 0.90
=
0.85
Mn= 7.144Tn.m Mu= 6.43Tn.m
= ( )
2
()
5.98 Tn.m 6.43Tn.m CORRECTO

CORTE "1-1" "3-3"


DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 13.82 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 13.14 cm2 a= 12.37 cm

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258

Cuantia de Diseo: Condicin de Diseo:



=

d= 0.01546 CUMPLE
Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 47.815 = 0.01547

NMERO DE VARIILLAS:


= 13.14 cm2 Nv= 4
Nv= = 3.40 Varillas #7
3.87 cm2 Nv= 3

As= 13.62 cm2 =2x 2.85 cm2 +1x 7.92 cm2


=2x Varillas #6 +1x Varillas #10

Condicin:

0.11
0.477 cm2 1.446 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 .
2 =
Min Estri. Varilla As= 13.62 cm2
4 cm 0.953 3.18

r= 6.54 cm
d= 33.46 cm

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.01628 max= 0.02258


CUMPLE

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Momento Nominal: Momento ltimo:

= 0.90
= a= 12.82cm
0.85
Mn= 15.472Tn.m Mu= 13.93Tn.m
= ( )
2

()

13.82 Tn.m 13.93Tn.m CORRECTO

TRAMO "7 - 8":

METRADO DE CARGAS : 7 8
Carga Muerta (WD): 1 3
d L WD 2
Losa 2.4 0.2 2.05 0.98 4Tn/m w
P. Propio 2.4 0.4 0.25 0.24 Tn/m
Tabiqueria 1.8 2.8 - 5.04 Tn/m
Acabados 0.1 - 2.3 0.23 Tn/m
6.49 4Tn/m
Carga Viva (WL): 2
1 2.95 3
Sobrecarga 0.4 - 2.05 0.82 Tn/m2

Carga Amplificada (W):

W = 1.4 WD + 1.7 WL 7 8
W = 10.486 Tn/m L= 2.95 m
DIAGRAMAS:
Reacciones: R7= 15.47 tn M7= -7.60 Tn.m
R8= 15.47 tn M8= -7.60 Tn.m
D.F.C D.M.F
20.0 12.00
15.0 10.00
10.0 8.00
5.0 6.00
4.00
0.0
2.00
0

3
1.5

3.5
0.5

2.5

-5.0
0.00
-10.0
0

3
2.5

3.5
0.5

1.5

-2.00
-15.0
-4.00
-20.0 -6.00

Mu= 3.80 Tn.m


CORTE 2-2
DISEO DE VIGA:
h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 3.8 Tn.m
= 0.9
b
Curso: Concreto Armado I "B" HCO - 2017
UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL
b
REA DE ACERO:
8
= 2 4 2
( ) 0.85
2 =
2
As= 3.09 cm2 a= 2.91 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258
Cuantia de Diseo: Condicin de Diseo:


=

d= 0.00364 CUMPLE
Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 13.156 = 0.00364

NMERO DE VARIILLAS:

3.09 cm2 Nv= 3


= Nv= = 2.43 Varillas #4
1.27 cm2 Nv= 2

As= 3.25 cm2 =2x 1.27 cm2 +1x 0.71 cm2


=2x Varillas #4 +1x Varillas #3
Condicin:

0.11 0.159 cm2 0.340 cm2 CUMPLE

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 3.25 cm2
4 cm 0.953 1.27
r= 5.59 cm
d= 34.41 cm

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.00378 max= 0.02258


CUMPLE

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Momento Nominal: Momento ltimo:


a= 3.06cm = 0.90
=
0.85
Mn= 4.488Tn.m Mu= 4.04Tn.m
= ( )
2
()
3.80 Tn.m 4.04Tn.m CORRECTO

CORTE "1-1" Y "3-3"


DISEO DE VIGA:

h= 40 cm
b= 25 cm
F'c= 210 kg/cm2
Fy= 4200 kg/cm2 h d
r= 6 cm
d= 34 cm
Mu= 7.60 Tn.m
= 0.9
b
REA DE ACERO:

8
= 2 4 2
0.85
( ) =
2 2
As= 6.50 cm2 a= 6.12 cm

CUANTIAS:

Cuantia Mxima:
=
Zona
6000
Sismica 0.50 = 0.85 1
NO Sismica 0.75 + 6000
1 0.85
max= 0.02258
Cuantia de Diseo: Condicin de Diseo:

=

d= 0.00765 CUMPLE

Verificacin de Cuantia:
Condicin:
=
=
2 1 0.59 =

CUMPLE
Ru= 26.312 = 0.00765

NMERO DE VARIILLAS:

6.50 cm2 Nv= 3


= Nv= = 2.28 Varillas #6
2.85 cm2 Nv= 2

As= 6.97 cm2 =2x 2.85 cm2 +1x 1.27 cm2


=2x Varillas #6 +1x Varillas #4
Condicin:
0.11 0.468 cm2 0.715 cm2 CUMPLE

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

VERIFICAMOS:
Recubrimiento (r): rea de Acero (As):

= 4 . =
2
Min Estri. Varilla As= 6.97 cm2
4 cm 0.953 1.905
r= 5.91 cm
d= 34.09 cm

Cuantias ():

Mnima: Diseo: Mxima:


= 0.7 = = 0.50

min= 0.00242 d= 0.00818 max= 0.02258

CUMPLE

Momento Nominal: Momento ltimo:


a= 6.56cm = 0.90
=
0.85
Mn= 9.021Tn.m Mu= 8.12Tn.m
= ( )
2
()
7.60 Tn.m 8.12Tn.m CORRECTO

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

45.2552 45.2552

DFC DMF
X Y
0 22.905 X Y
0.4 18.656 0 -15.76 Tn.m 15.76
0.8 14.408 0.4 -7.45 Tn.m 7.45
1.2 9.605 0.8 -0.83 Tn.m 0.83
1.6 5.912 1.2 4.08 Tn.m -4.08
1.6 3.140 1.896 1.6 7.30 Tn.m -7.30
2 -1.109 1.931 8.21 Tn.m -8.21
2.4 -5.357 2 8.26 Tn.m -8.26
2.8 -9.605 2.4 7.52 Tn.m -7.52
3.2 -13.854 2.8 5.08 Tn.m -5.08
3.6 -18.102 3.2 0.94 Tn.m -0.94
4 -22.350 3.6 -4.90 Tn.m 4.90
4 -15.23 15.23

Varillas #2
Varillas #3
Varillas #4
Varillas #5
Varillas #6
Varillas #7
Varillas #8
Varillas #9
Varillas #10
Varillas #11
Varillas #12

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

DFC DMF
X Y
X Y
0 19.33
0.4 15.46 0 -12.89 Tn.m 12.89
0.8 11.60 0.4 -5.93 Tn.m 5.93
1.2 7.73 0.8 -0.52 Tn.m 0.52
1.6 3.87 1.2 3.35 Tn.m -3.35
2 0.00 1.6 5.67 Tn.m -5.67
2.4 -3.87 2 6.44 Tn.m -6.44
2.8 -7.73 2.4 5.67 Tn.m -5.67
3.2 -11.60 2.8 3.35 Tn.m -3.35
3.6 -15.46 3.2 -0.52 Tn.m 0.52
4 -19.33 3.6 -5.93 Tn.m 5.93
4 -12.89 Tn.m 12.89

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

44.19312 44.19312

DFC DMF
X Y
0 21.635 X Y
0.4 17.386 0.0 -14.26 Tn.m 14.26
0.8 13.138 0.4 -6.46 Tn.m 6.46
1.2 9.814 0.8 -0.35 Tn.m 0.35
1.6 4.641 1.2 4.05 Tn.m -4.05
2 0.393 2.037 1.6 6.76 Tn.m -6.76
2.6 -5.980 2.0 7.76 Tn.m -7.76
2.6 -8.752 2.04 7.77 Tn.m -7.77
3.2 -15.124 2.4 7.07 Tn.m -7.07
3.6 -19.372 2.6 6.09 Tn.m -6.09
3.9 -22.559 3.2 -1.07 Tn.m 1.07
3.6 -7.97 Tn.m 7.97
3.9 -15.06 15.06

Varillas #2
Varillas #3
Varillas #4
Varillas #5
Varillas #6
Varillas #7
Varillas #8
Varillas #9
Varillas #10
Varillas #11
Varillas #12

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

6
DFC DMF
3 X Y
X Y
0 17.30
0.4 13.11 0 -9.52 Tn.m 9.52
0.8 8.91 0.4 -3.43 Tn.m 3.43
1.2 4.72 0.8 0.97 Tn.m -0.97
1.65 0.00 1.2 3.70 Tn.m -3.70
2 -3.67 1.65 4.76 Tn.m -4.76
2.4 -7.86 2 4.12 Tn.m -4.12
3
2.8 -12.06 2.4 1.81 Tn.m -1.81
3.3 -17.30 2.8 -2.18 Tn.m 2.18
3.3 -9.52 Tn.m 9.52
6

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

7
3

3 42.6 42.6

DFC DMF

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

X Y
0 22.095 X Y
0.4 17.846 0.00 -13.82 Tn.m 13.82
0.8 13.598 0.40 -5.83 Tn.m 5.83
0.8 10.826 0.80 0.46 Tn.m -0.46
1.2 6.578 1.20 3.94 Tn.m -3.94
1.6 2.329 1.819 1.60 5.72 Tn.m -5.72
2 -1.919 1.819 5.98 Tn.m -5.98
2.4 -6.167 2.00 5.80 Tn.m -5.80
2.8 -10.416 2.40 4.19 Tn.m -4.19
3.2 -14.664 2.80 0.87 Tn.m -0.87
3.75 -20.505 3.20 9.16 Tn.m -9.16
3.75 -12.82 Tn.m 12.82

Varillas #2
Varillas #3
Varillas #4
Varillas #5
Varillas #6
Varillas #7
Varillas #8
Varillas #9
Varillas #10
Varillas #11
Varillas #12

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

DFC DMF
X Y
X Y
0 15.47
0.4 11.27 0 -7.60 Tn.m 7.60
0.8 7.08 0.4 -2.26 Tn.m 2.26
1.2 2.88 0.8 1.41 Tn.m -1.41
1.475 0.00 1.2 3.41 Tn.m -3.41
2 -5.50 1.475 3.80 Tn.m -3.80
2.4 -9.70 2 2.36 Tn.m -2.36
2.8 -13.89 2.4 -0.68 Tn.m 0.68
2.95 -15.47 2.8 -5.40 Tn.m 5.40
2.95 -7.60 Tn.m 7.60

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017


UNIVERSIDAD DE HUNUCO
E.A. P: ING. CIVIL

Curso: Concreto Armado I "B" HCO - 2017