CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

OBRA : AMPLIACION Y MEJORAMIENTO DE LA INSTITUCION EDUCATIVA N 80090 DE LA LOCALIDAD PUERTO MORIN DISTRITO DE VIRU, PROVINCIA DE VIRU - LA LIBERTAD
CLIENTE : MUNICIPALIDAD PROVINCIAL DE VIRU
LUGAR : VIRU - VIRU - LA LIBERTAD PRESUPUESTO TOTAL S/. 1,320,269.0
FECHA : JUNIO 2017 PLAZO EJECUCIN 180 DIAS CALENDARIOS

PARCIAL MES1 MES 2 MES 3 MES 4 MES 5


ITEM DESCRIPCION S/. 01-30 31-60 61-90 91-120 120-150
Dia 01

INSTALACION DE LA INSTITUCION EDUCATIVA


INICIAL N1735 EN EL C.P. DE HUANCAQUITO BAJO,
DISTRITO DE VIRU, PROVINCIA VIRU- LA LIBERTAD

ESTRUCTURAS 432,656.91 72,109.49 72,109.49 72,109.49 72,109.49 72,109.49


ARQUITECTURA 386,368.60 64,394.77 64,394.77 64,394.77 64,394.77 64,394.77
INTALACIONES SANITARIAS 27,048.47 13,524.24 13,524.24
INTALACIONES ELECTRICAS 126,858.25 63,429.13

PRESUPUESTO MES 01 MES 02 MES 03 MES 04 MES 05


COSTO DIRECTO 972,932.23 136,504.25 136,504.25 136,504.25 150,028.49 213,457.61
GASTOS GENERALES (10.00 %) 97,293.22 13,650.43 13,650.43 13,650.43 15,002.85 21,345.76
UTILIDAD (5.00 %) 48,646.61 6,825.21 6,825.21 6,825.21 7,501.42 10,672.88
SUB TOTAL 1,118,872.06 156,979.89 156,979.89 156,979.89 172,532.76 245,476.25
I.G.V. (18.00 %) 201,396.97 28,256.38 28,256.38 28,256.38 31,055.90 44,185.73
TOTAL PRESUPUESTO S/. 1,320,269.03 185,236.27 185,236.27 185,236.27 203,588.66 289,661.98
TOTAL A VALORIZAR S/. 185,236.27 S/. 185,236.27 S/. 185,236.27 S/. 203,588.66 S/. 289,661.98
% DE AVANCE PARCIAL 14.03% 14.03% 14.03% 15.42% 21.94%
% DE AVANCE ACUMULADO 14.03% 28.06% 42.09% 57.51% 79.45%
AMA VALORIZADO DE AVANCE DE OBRA
O MORIN DISTRITO DE VIRU, PROVINCIA DE VIRU - LA LIBERTAD

S/. 1,320,269.03
180 DIAS CALENDARIOS

MES 6 TOTAL
150-180 S/.
DIA 180

72,109.49 432,656.91
64,394.77 386,368.60
27,048.47
63,429.13 126,858.25

MES 06
199,933.38 972,932.23
19,993.34 97,293.22
9,996.67 48,646.61
229,923.38 1,118,872.06
41,386.21 201,396.97
271,309.59 1,320,269.03
S/. 271,309.59
20.55%
100.00%