JADWAL PELAKSANAAN REVIEW DESAIN

PRINSIP DESAIN SHORP DRAWING


NO. NAMA BANGUNAN LOKASI DIUKUR GBR SITUASI DIREVISI SKET/DIMENSI ASISTENSI DIKERJAKAN TARGET SELESAI STATUS KETERANGAN
EL.DASAR MULAI OLEH
1 2 3 4 5 6 7 8 9 10 11 12 13

STA P.0+00 - P.55+00


1 Bang. Talang Drainase (B.Pp.1b) P.2+00 A
2 Bang. Talang Tersier (B.Pp.1c) P.4+37 A
3 Bang. Corongan & Sadap (B.Pp.1) P.8+00 - - - - - - - - - Dihilangkan
4 Bang. Talang Sungai Kecil (B.Pp.1d) P./A.10+00 A
5 Bang. Corongan (B.Cr.Pp.2) P./A10+42,39 P Proses di UGM
6 Bang. Talang Sungai Progo (B.Pp.1e) P./A.13+00 A
7 Bang. Syphon & Pelimpah (B.Pp.1f) P.A.13+92,7 A
8 Bang. Talang Progo (B.Pp.1g) P./A.14' A
9 Bang. Talang Tersier (B.Pp.1h) P.A15'+27,40 - - - - - - - - - Existing
10 Bang. Corongan )B.Cr.Pp.3) A.15+57,90 A
11 Bang. Talang Pringkudo (B.Pp.1s) P.16' - - - - - - - - - Existing
12 Bang. Cross Drain (B.Pp.1y) P.17+73 - - - - - - - - - Existing
13 Bang. Gorong-gorong Pembuang (B.Pp.1k) P.20' - - - - - - - - - Existing
14 Bang. Penguras & Syphon (B.Pp.1l) P.23+00 - - - - - - - - - Existing
15 Bang. Corongan (B.Cr.Pp.4) P.24+52,20 A
16 Bang. Talang Kali Banger (B.Pp.1m) P.26+31,30 - - - - - - - - - Existing
17 Bang. Corongan (B.Cr.Pp.5) P.27+76,31 A
18 Bang. Gorong-gorong Jalan baru (B.Pp.1n) P.28+00 P
19 Bang. Talang Tersier (B.Pp.1o) P.28+43,79 P
20 Bang. Talang Cross Drain (B.Pp.1p) P.30+23,20 A
21 Bang. Corongan (B.Cr.Pp.6) P.33+60,09 A
22 Bang. Talang Cross Drain (B.Pp.1q) P.34+00 Cahyo 1 Nov 2016 P
23 Bang. Gorong-gorong Jalan Bramen (B.Pp.1r) P.35+00 Bp. Manis Cahyo 1 Nov 2016 P Ganti Per Tebing
24 Bang. Corongan (B.Cr.Pp.7) P.35+71,37 Cahyo 1 Nov 2016 P
25 Sadap & Gorong-gorong (B.Pp.1) P.37+50 A
26 Bang. Sadap Terjun (B.Pp.2) P.39+56,5 A
27 Bang. Pelimpah, Penguras (B.Pp.aa) dan talang P.40+17 Bp. Supri Bp. Supri 1 Nov 2016 Blm ada desain
28 Bang. Corongan (B.Cr.Pp.8) P.44+7,60 Cahyo 1 Nov 2016 P
29 Bang. Sadap Terjun (B.Pp.3) P.45+31,50 A
30 Bang. Plat Layan (B.Pp.4a) P.46+59,40 Cahyo / Ipung 1 Nov 2016 P
31 Bang. Corongan Terjun (B.Cr.Pp.9) P.48+21 A
32 Bang. Terjun (B.Pp.4b) P.49+53,5 A
33 Bang. Cross Drain (B.Pp.4c) P.50+57,40 Bpk.Har / Supri 1 Nov 2016 Blm ada desain
34 Bang. Corongan Terjun (B.Cr.Pp.10) P.50+83 Bpk.Har / Supri 1 Nov 2016 P
35 Bang. Cross Drain , Plat Layan (B.Pp.4d) P.52+45,40 Bpk.Har / Ali 1 Nov 2016 P
36 Bang. Gorong-gorong Pembuang (B.Pp.4e) P.53+26,70 Bpk.Har / Ali 1 Nov 2016 P
37 Bang. Talang Sedimen (B.Pp.Seduren 4f) P.54+26,30 Trisno P
38 Bang. Terjun (B.Pp.4g) P.54+51,40 A
39 Bang. Corongan & Plat Layan (B.Cr.Pp.11) P.55+88,10 A

STA P.55+00 - P.119+69


1 Bang. Gorong-gorong & Terjun (B.Pp.4) P.57+24,70 Bpk.Haryono
2 Bang. Syphon (B.Pp.5a) P.60+52,26 A
3 Bang. Corongan (B.Cr.Pp.12) P.62+73 1 Nov 2016
4 Bang. Talang Sungai Jreng (B.Pp.5b) P.63+75,10 Pramea
5 Bang. Talang Tersier (B.Pp.5c) P.64+00
6 Bang. Sadap & Gorong-gorong (B.Pp.5) P.64+29,90
7 Bang. Talang Tersier (B.Pp.6a) P.65+63,10
8 Bang. Coorngan (B.Cr.Pp.13) P.67+14 Pramea 1 Nov 2016
PRINSIP DESAIN SHORP DRAWING
NO. NAMA BANGUNAN LOKASI DIUKUR GBR SITUASI DIREVISI SKET/DIMENSI ASISTENSI DIKERJAKAN TARGET SELESAI STATUS KETERANGAN
EL.DASAR MULAI OLEH
Bang. Gorong-gorong Irigasi & Gorong-gorong Jalan
(B.Pp.6b) P.67+99
9
10 Bang. Corongan (B.Cr.Pp.14) P.69+00 Pramea 1 Nov 2016
11 Bang. Coorngan (B.Cr.Pp.15) P.72+43,40
12 Bang. Talang Tersier (B.Pp.6c) P.75+05
13 Bang. Talang Tersier (B.Pp.6d) P.76+65
14 Bang. Gorong-gorong Jalan Ds. Rowo (B.Pp.6f) P.77+79 A
15 Bang. Sadap (B.Pp.6) P.78+50 A
16 Bang. Gorong-gorong Pembuang (B.Pp.7a) P.79+40
17 Bang. Gorong-gorong Jalan ke Sawah (B.Pp.7b) P.80+00
18 Bang. Sadap & Gorong-gorong (B.Pp.7) P.81+50
Bang. Gorong-gorong Jalan Ds. Belkg Kec. Rowo
P.82+00
19 (B.Pp.8a) A
Bang. Terjun & Gorong-gorong depan Kel. Rowo
P.82+50 A
20 (B.Pp.8b)
21 Plat Layan ke Makam (B.Pp.8c) P.84+21,07 A
22 Bang. Gorong-gorong & Sadap (B.Pp.8) P.85+70
23 Bang. Gorong-gorong Pembuang (B.Pp.9a) P.86+69,42
24 Plat Layan (B.Pp.9b) P.88+37
25 Bang. Talang Jalan (B.Pp.9c) Masjid Rowo P.89+24,64 A
26 Bang. Gorong-gorong Pembuang (B.Pp.9d) P.89+63,14
27 Bang. Sadap (B.Pp.9) P.91+10,44
28 Bang. Talang Jalan (B.Pp.10a) P.93+00 - - - - - - - - - Dihilangkan
29 Bang. Talang Jalan (B.Pp.10b) P.94+15,94 A
30 Bang. Gorong-gorong Pembuang (B.Pp.10c) P.94+88,94
31 Bang. Corongan & Talang Tersier (B.Cr.Pp.16) P.96+30,80
Bang. Talang Tersier & Gorong-gorong Jalan
P.98+75
32 Kenteng (B.Pp.10d)
33 Bang. Talang Tersier (B.Pp.10e) P.101+38
Bang. Gorong-gorong Jalan & Talang Tersier P.102+72,7 A
34 (B.Pp.10f)
35 Bang. Sadap & Pelimpah (B.Pp.10) P.105+59,70 Bpk.Haryono
Bang. Gorong-gorong Jalan & Talang Tersier
P.107+54
36 (B.Pp.11a)
37 Bang. Corongan (B.Cr.Pp.17) P.110+32,20
38 Bang. Talang Sungai Broboh (B.Pp.11b) P.110+55
39 Bang. Corongan (B.Cr.Pp.18) P.111+62.20
40 Bang. Gorong-gorong Jalan Gesing (B.Pp.11c) P.113+46
41 Bang. Talang Sungai Gesing (B.Pp.11d) P.113+66
42 Bang. Talang Tersier (B.Pp.11e) P.114+42
43 Bang. Sadap (B.Pp.11) P.115+35,70
44 Bang. Gorong-gorong Pembuang (B.Pp.12a) P.117+29
45 Bang. Sadap Terjun (B.Pp.12) P.117+98,40
46 Bang. Akhir (B.Pp.13a) P.119+69

Note :
A = Approved (Final)
P = Proses Penyempurnaan Asistensi