Technical Affairs Directorate - Water Projects Dept.
Site Works Inspection
Inspection Request for Pipeline Projects Date: ......./ ......../ ........ Contract Title :....................................................................................................................................... Contract No....:............................................................................. IR. No.:............................................ Contractor :............................................................................. Rev. No.:.......................................... Consultant :............................................................................. Location/Area:................................. Approved MST Ref ...................................................................... Chainage No.:................................. Approved ITP Ref & Clause: ........................................................ Drg./Sheet No.: .............................. 1. Setting out 2. Trial holes ( ) No. 3. Trench Excavation 4. Pipe/Joint wrapping 5. Bedding Material 6. Pipe laying 7. 9 bar test (Initial) 8. Surround Material 9. Backfilling (1st layer) 10. Trench marker tape 11. Backfilling (2nd layer) 12. ( )Swabbing 13. Sterilizing/ Water Sample 14. Final Pressure Test 15. GIS Data Collection 16. Other Allowable Water ..................... Lit. Taken Water .......................Lit.
Pipe Size Other
100mm 150mm 200mm 300mm 400mm 600mm 900mm 1200mm 1400mm 1600mm (mm) ( mm) Length *The Pipe Size from 600 mm to above, the final pressure test to be inspected by Operation Section
The above work has been completed according to Drawings/KAHRAMAA requirements & specifications and ready for inspection. (Drawing enclosed)
Contractors Representative Name Signature Date FOR THE USE OF CONSULTANT CONSULTANT Remarks..................................................................................................................................................... ...................................................... ........................... .................... Consultants Representative Name Signature Date FOR THE USE OF KAHRAMAA GIS Collected Not Collected ...................................... ............................ .................... GIS Surveyor Name... Signature ..................Date OS Remarks .................................................................................................................................................. Approved Not Approved ........................................ .......................... .................. Operation Engineer Name Signature Date TW Remarks................................................................................................................................................. Approved Not Approved .............................................. .......................... .................. Project Engineer Name Signature Date Note: 1- The role of KM GIS starts before the Surround Material. Contractor to make sure that the KM GIS Surveyor collects the data before Surround Material. 2- Copy to Operation Engineer for activity no. 14, the original copy to be signed by all participants 3- Copy to GIS Surveyor for activity no. 15 4- This site inspection does not relieve the contractor of any of his contractual obligations
TW-P6/F1 Issue 2 21/09/2015
Page 1 of 2 CC: Project Engineer /Consultant / Contractor
SR No. Beneficiary Name Scheme Name Purpose Amount Utr No. (Bank TXN Id) Bank TXN Date Status Failure Reason Credit Date Uidasper Bank Acctnumber Asperbank Favoringas Perbank Bankiinas Perbank