Revision: A02
MASTER SCHEDULE FOR H1063 -
Ow ner: Geological Survey of India GSI GEOTECHNICAL RESEARCH VESSEL (REV. A02)
Updated:10/11/17
ID Task Name Duration Start Finish 2017 2018
Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 Master Schedule 592 days 25/01/17 15/01/19 Master Schedule
25/01 15/01
2 Project Contract signning (01st Payment) 0 days 25/01/17 25/01/17 Project Contract signning (01st Payment)
25/01
6 Equipment Production below main deck and Delivery 8 mons 02/01/18 07/08/18 Equipment Production below main deck and Delivery
02/01 07/08
7 Equipment Production above main deck and Delivery 11 mons 02/01/18 25/10/18 Equipment Production above main deck and Delivery
02/01 25/10
8 Basic & Detailed Design 279 days 09/01/18 11/12/18 Basic & Detailed Design
09/01 11/12
13 Steel plate ordered and delivery 3 mons 02/01/18 27/03/18 Steel plate ordered and delivery
02/01 27/03
18 Painting & Touch up 280 days 01/02/18 07/01/19 Painting & Touch up
01/02 07/01
19 Hull Blocks Fabrication 150 days 01/02/18 04/08/18 Hull Blocks Fabrication
01/02 04/08
21 Piping Installation & Fabrication 210 days 09/03/18 13/11/18 Piping Installation & Fabrication
09/03 13/11
22 Hull Blocks Erection 145 days 10/03/18 29/08/18 Hull Blocks Erection
10/03 29/08
24 Blocks Erection to be achieved 25% (02nd 0 days 22/05/18 22/05/18 Blocks Erection to be achieved 25% (02nd Payment)
Payment) 22/05
25 Insulation & Accomodation 185 days 19/04/18 24/11/18 Insulation & Accomodation
19/04 24/11
28 Load out (moving Vessel onto Floating Dock) 0 days 15/09/18 15/09/18 Load out (moving Vessel onto Floating Dock)
15/09
31 Inclining Test & Lightship Survey 3 days 09/11/18 11/11/18 Inclining Test & Lightship Survey
09/11 11/11
32 1st & 2nd Sea Trials (Including Drilling/Coring 26 days 26/11/18 21/12/18 1st & 2nd Sea Trials (Including Drilling/Coring systems) (04th Payment)
systems) (04th Payment) 26/11 21/12
33 Handover Preparation, defect items clearing 19 days 22/12/18 15/01/19 Handover Preparation, defect items clearing
22/12 15/01
Baseline Milestone Critical Progress Baseline Split Project Summary Inactive Milestone Manual Summary Rollup Deadline
Baseline Summary Task Milestone External Tasks Inactive Summary Manual Summary Baseline1
Critical Split Summary Progress External Milestone Manual Task Start-only Baseline
Critical Split Task Progress Summary Inactive Task Duration-only Finish-only