H1028 Legs Delivery and Pre-Joining at PVC-MS

(From section 5 to section 8)


(Updated: 27-May)
H1028
Legs Fabrication schedule Delivery to PVC-MS schedule Pre-Joining at PVC-MS schedule
No. Fab.
section Delivery to Delivery to Start pre - Start pre - Remark
place Finish Finish Progress Progress
(Plan) (Actual)
Delay (-) (%)
PVC-MS PVC-MS Delay (-) joining joining Delay (-) (%)
(Plan) (Actual) (Plan) (Actual)
1 5AP 03-May 20-May -16 100.0% 21-May -12
2 6AP 11-May 22-May -10 100.0% 23-May -13
VSP 9-May
3 7AP 11-May 22-May -10 100.0% 23-May -13 09-May 24-May -14 1.0%
Not yet
4 8AP 05-May
finish
-20 99.0% 28-May -18 12-May Not yet start -14
5 5FP Done Done 100.0% 03-May

6 6FP SSY Done Done 100.0% 3-May 03-May

7 7FP Done Done 100.0% 03-May 03-May 12-May -9 28.0%

8 8FP VSP 03-May 11-May -8 100.0% 10-May 17-May -7 09-May 18-May -9 22.0%

9 5FS 26-Apr 16-May -18 100.0% 17-May -11


10 6FS SSY 26-Apr 16-May -18 100.0% 5-May 17-May -11 05-May 24-May -17 2.0%

11 7FS 27-Apr 16-May -17 100.0% 17-May -11 08-May 24-May -14 4.0%

12 8FS VSP 16-May 19-May -4 100.0% 10-May 19-May -9 11-May 22-May -10 8.0%

13 5AS 14-May 26-May -11 100.0% 28-May -18


Not yet
14 6AS 13-May
finish
-13 97.0% 28-May -18 08-May Not yet start -17
VSP 8-May
Not yet
15 7AS 16-May
finish
-11 93.0% 28-May -18 11-May Not yet start -15
Not yet
16 8AS 18-May
finish
-9 84.0% 28-May -18 14-May Not yet start -12