Board of Library Trustees Meeting

Capital Projects Report


November 15, 2017

Document #9C.1
Board of Library Trustees Meeting
November 15, 2017
Capitol View Library Project Information
Ward 7
Address 5001 Central Ave. SE
Councilmember Vincent Gray
Branch Manager TBD
Project Manager Jaspreet Pahwa

Project Budget $ 7,200,000


Additional funds added for Interior renovation $733,050
Project Milestones
Project Start Date May 2016
Library Close for Construction Winter 2017
Interim Library Open N/A
Interim Library Close N/A
New or Renovated Library Open
Exterior Renovation complete Summer 2018
Active Contractor(s):
Broughton / R.McGhee & Associates
GDG Construction, Fabricator Steel River Building Systems

Project Description/Status

Project Scope funded at $4.5 for interior spatial re-configuration, new Mechanical, Electrical & Plumbing systems, new windows,
reconfigured front entrance, roof replacement, new furniture, finishes & equipment. New $2.7M FY 18 funding will be spent on exterior
renovation including the modular interim library being planned to go on the grounds of JC Nalle during the exterior renovation phase.

Board of Library Trustees Meeting


November 15, 2017 Page 2
Cleveland Park Library Project Information
Ward 3
Address 3310 Connecticut Ave NW
Councilmember Mary Cheh
Branch Manager Barbara Gauntt
Project Manager Rauzia Ally

Project Budget $ 19,770,000

Project Milestones
Project Start Date March 2015
Library Close for Construction Fall 2016
Interim Library Open Fall 2016
Interim Library Close Summer 2018
New or Renovated Library Open Summer 2018

Active Contractors(s):
Gilbane/Perkins Eastman

Project Description/Status:
Demolition and construction of a new library on the same site. Foundations and Structural steel have been completed. The enclosure of
the building is being constructed now, both brick and limestone. Permanent power is scheduled for early December, with the building dry in
slated for late December. The Air Handling Units with conditioned air is scheduled for early January, and the elevator by mid January. From
January to March, completing interior finishes will be the major activities.

Board of Library Trustees Meeting


November 15, 2017 Page 3
Lamond-Riggs Library Project Information
Ward 5
Address 5401 South Dakota Ave. NE
Councilmember Kenyan McDuffie
Branch Manager Robin Imperial
Project Manager TBD

Project Budget $ 20,000,000

Project Milestones
Project Start Date 2018
Library Close for Construction TBD
Interim Library Open TBD
Interim Library Close TBD
New or Renovated Library Open TBD

Active Contractor(s):
Brailsford and Dunlavey

Project Description/Status:

Project funded in October 2017. Due diligence review is underway.

Board of Library Trustees Meeting


November 15, 2017 Page 4
Martin Luther King Jr. Memorial Library Project Information
Ward 2
Address 901 G Street NW
Councilmember Jack Evans
Library Manager N/A
Project Manager Andrew Blumenfeld

Project Budget $ 211,000,000

Project Milestones
Project Start Date August 2014
Library Close for Construction Spring 2017
Interim Library Open Spring 2017
Interim Library Close Spring 2020
New or Renovated Library Open Summer 2020

Active Contractor(s):
Martinez+Johnson/Mecanoo
Jair Lynch Development
Smoot / Gilbane

Project Description/Status:
MLK construction is well underway with much of the interior demolition and historic material salvage completed. The building is also wrapping up its
clearance of all hazardous materials as part of the demolition and has commenced the structural demolition to make way for the buildings newly designed
elements. Elements of the demolition will be ongoing until early 2018 and will be followed by the start of the mechanical and electrical system installation.
The project has also started the exterior building envelope remediation consisting of the removal of all glass, portions of the roof, and metal framing.
Scaffolding and tenting has been erected along the G Place elevation and is now starting on the 9th Street elevation to make way for the exterior structure

Board of Library Trustees Meeting


November 15, 2017 Page 5
Palisades Library Project Information
Ward 3
Address 4901 V Street, NW
Councilmember Mary Cheh
Branch Manager TBD
Project Manager Lisa Deanes

Project Budget $ 7,500,000

Project Milestones
Project Start Date October 2015
Library Close for Construction March 2017
Interim Library Open N/A
Interim Library Close N/A
New or Renovated Library Open Winter 2018

Active Contractor(s):

cox graae+spack / MCN Build

Project Description/Status:
Major renovation project that includes green roof, and upgrade to mechanical, plumbing and electrical systems. Project includes upgraded
furniture, fixtures and equipment. The faade has been modified to introduce more natural light and the floor plan provides more open flow of
traffic.

Board of Library Trustees Meeting


November 15, 2017

Page 6
Southeast Library Project Information
Ward 6
Address 403 7th Street SE
Councilmember Charles Allen
Branch Manager Maria Escher
Project Manager TBD

Project Budget $ 23,500,000

Project Milestones
Project Start Date 2019
Library Close for Construction TBD
Interim Library Open TBD
Interim Library Close TBD
New or Renovated Library Open TBD

Active Contractor(s):
TBD

Project Description/Status:

Planned major renovation starting FY19. A due diligence study to analyze the addition of a new sublevel to the library under 7th St to
Eastern Market Metro Park has been completed. Informal Site Survey conducted September 20, 2017.

Board of Library Trustees Meeting


November 15, 2017
Page 7
Southwest Library Project Information
Ward 6
Address 900 Wesley Place SW
Councilmember Charles Allen
Branch Manager Kimberly Knight
Project Manager Jaspreet Pahwa

Project Budget * $ 18,000,000

Project Milestones
Project Start Date Summer 2017
Library Close for Construction Fall 2018
Interim Library Open Fall 2018
Interim Library Close Early 2020
New or Renovated Library Open Early 2020

Active Contractor(s):
Turner Construction / Perkins+Will

Project Description/Status:
Project is funded in FY2017 for a new LEED certified branch library. Design started in July 2017 with Perkins+ Will & Turner Construction. Two
community meetings held in July and September culminated in a successful concept design. The library is proposed to be all above ground
and is gearing up to go through the approval process of ANC, Zoning, and Commission of Fine Arts.

Board of Library Trustees Meeting


November 15, 2017 Page 8
West End Library Project Information
Ward 2
Address 1121 24th ST NW
Councilmember Jack Evans
Branch Manager Kevin Osborne
Project Manager Jaspreet Pahwa

Public-Private
Project Budget Partnership

Project Milestones
Project Start Date June 2013
Library Close for Construction June 2014
Interim Library Open June 2014
Interim Library Close Nov 9 2017
New or Renovated Library Open Dec 9, 2017

Active Contractor(s):
Eastbanc / Clark Construction

Project Description/Status:

The West End Library is part of a mixed-use project built by EastBanc real estate development company that features a 20,000 square foot library. All
public functions are at entry level, and staff spaces on the mezzanine level. Project is substantially complete and close-out phase including warranty