In many cases, there are problems that impede the progress and development of drilling
the well, problems that influence by factors that have to do with formation properties or
issues with tools. To solve these problems, the most feasible is well intervention for
different purposes and put to reactivate the well bore. The Coiled Tubing method is a
modern method and increasingly used in the oil industry for its many economic and
systematic rehabilitation of the well advantages. It is merely a technique that is based, as
its name suggests, the use of a flexible pipe that can open a kind of window in the section
where the problem arises.
2
Asignatura: perforacin I
Carrera: Ing. Gas y petrleo
INDICE
Captulo 1................................................................................................................................5
Introduccin............................................................................................................................ 5
Captulo 2................................................................................................................................7
Marco Terico.........................................................................................................................7
1. Intervencin de Pozos.................................................................................................. 7
2. Razones para intervenir un pozo..................................................................................7
2.1.1. Invasin de agua salada.....................................................................................7
2.1.2. Agotamiento a baja recuperacin del intervalo.-.............................................. 8
2.1.3. Daos a las formaciones productoras.-............................................................. 9
2.1.4. Cementaciones primarias defectuosas.-.......................................................... 10
2.1.5. Desprendimientos y roturas en las tuberas de revestimientos.-.....................10
2.1.6. Alta relacin gas - aceite (Arga).-...................................................................11
2.1.7. Cambio de funcin del pozo.-.........................................................................12
3. Coiled tubing o tubera flexible.-............................................................................... 12
3.1. Descripcin del equipo de coiled tubing.-.......................................................... 13
3.2. Caractersticas.....................................................................................................15
3.3. Manufactura del coiled tubing.-..........................................................................17
4. Perforacin con coiled tubing.................................................................................... 22
4.1.1. Ventajas de perforacin con coiled tubing.-....................................................23
5. Aplicaciones del Coiled Tubing................................................................................. 24
Captulo 3..............................................................................................................................31
Definicin del Problema.......................................................................................................31
Captulo 4..............................................................................................................................31
Objetivos de la Investigacin................................................................................................31
Objetivo General...........................................................................................................31
Objetivos Especificos.-.................................................................................................31
Bibliografa........................................................................................................................... 32
Referencias............................................................................................................................32
LISTA DE GRFICOS E IMGENES
Introduccin
Captulo 2
Marco Terico
1. Intervencin de Pozos
Es el Proceso de Re perforacin, rehabilitacin, limpieza o reacondicionamiento de un
pozo existente para mejorar la produccin de petrleo o gas.
Estos problemas pueden ocasionar comunicacin del intervalo productor con otra
zona, debido a la deficiencia y canalizacin del cemento por el exterior de la TR,
originando la falta de control de los hidrocarburos que aporte del pozo o bien la
presencia de fluidos indeseables. una planeacin adecuada al elaborar el
programa de intervencin permitir ejecutar las operaciones necesarias para su
correccin.
3.2. Caractersticas
Una tubera apropiadamente diseada debe cumplir con los siguientes atributos para la
operacin planeada por el ingeniero.
Suficiente resistencia mecnica para resistir con seguridad la combinacin de
fuerzas que impone el trabajo.
Rigidez adecuada para ser corrida en el pozo hasta la profundidad requerida y/o
empujar con la fuerza debida.
4.1.1.1. Generales.-
4.1.1.2. Operativas
4.1.1.5. Requerimientos
Personal capacitado.
Equipo especial.
Presenta limitaciones en dimetro mximo de agujero y
profundidad.
c) Pesca.-
La intervencin del coiled tubing en operaciones de pesca ha crecido mucho en
los ltimos aos, en gran parte apoyado por el desarrollo de nuevas herramientas
para operar con dimetros pequeos. Su mayor capacidad de carga y la
capacidad de realizar lavados hidrulicos permiten realizar operaciones ms all
del mbito de wireline. La mayora de las herramientas de pesca convencional
pueden adaptarse al coiled tubing.
Ilustracin 20.- Herramientas de pesca
d) Fresado y Under Reaming.-
Los motores de fondo se utilizan para eliminar cemento e incrustaciones de
la caera de produccin o para elimina obstrucciones.
Para los casos en que la obstruccin se encuentra en un casing y debemos pasa
a travs de un tubing de menor dimetro, es posible utilizar Under Reamers.
La potencia debe ser calculada teniendo en cuenta:
Velocidad ascensional en los dimetros mayores.
Prdida de carga en el coiled tubing (mximo caudal de bombeo)
Caractersticas del motor de fondo
Ilustracin 21.- Incrustaciones de la caeria de produccion para eliminar obstrucciones
tomando en cuenta la velocidad y la capacidad de coiled tubing
El proceso montaje, prueba y desmontaje de la herramienta coiled tubing sigue los
siguientes pasos:
Cul es la importancia y cules son los factores y requerimientos del coiled tubing en el
proceso de perforacin y produccin petrolera y el impacto de su uso para determinar la
aplicacin para diferentes procesos que den eficacia a la rentabilidad del pozo?
Captulo 4
Objetivos de la Investigacin
Objetivo General
Objetivos Especificos.-
Gnzales J.C., T. M. ( (1998). ). DST Experience in High Performance Line Pipe and
Flowlines for Sour Services.
Referencias
Coiled tubing:
http://biblioteca.iapgg.org.ariapg/ArchivosAdjuntos/7jornaper/Gingins.pdf
http://www.monografias.com/trabajos11/pope/pope.shtml
El petrleo:
http://bo.kalipedia.com/tecnologia/tema/mecanismos-motores-energia/origen-
formacion-petroelo.html?x=20070822klpingtcn_78.Kes&ap=
EVALUACIN DEL DOCENTE