Anda di halaman 1dari 10

Table XVI.

Results of Field Tests on Pipe-Type Cable Installations


Voltage
Induced in
Drop Noncu rrent-
Applied Along Ca rrying
Voltage, Current, Pipe, Conductor,
Utility Company Description of Installation volts amperes volts volts
(Three 600-kcmil concentric round conductors
Detroit Edison .61/2-inch-diameter (inside) steel pipe with 1/4-inch wall 1280
115 12
Company Overall length of 34 982 feet 1240 252 766
Current returned on pipe
(Three 4/0 noncompact round conductors
San Antonio Public 51/i,-inch-diameter (inside) steel pipe with 1/4-inch wall 560
144 0* 350
Service Overall length of 17 692 feet
Current returned on pipe
(Three 1250-kcmil conductors
Public Service Gas 81/is-inch-diameter (inside) steel pipe with 1/4-inch wall 35
119 3.2
and Electric Overall length of 57 500 feet
Current returned on pipe
* Measured with voltmeter.

voltage induced in the pipe by the current flowing in the con- and suggests that these errors could be caused by a slight dis-
ductor is cancelled by a voltage induced in the pipe in an opposite placement in the position of the two potential leads. As the
direction by the return current flowing in the pipe. As any in- same cables with fixed potential leads were used in magnetic and
duced voltage must be the result of a mutual effect, it is my nonmagnetic pipes, I doubt that this is the explanation. It is
feeling that it must be assigned to the central conductors. This true that these measurements were made at the center of a 45-
agrees with comments already made and results in a net voltage foot test length. The measured values, especially at low cur-
drop along the pipe which is equal to the difference between the rents, were in the millivolt range, and it is conceivable that slight
IR drop and the induced voltage. errors resulting from stray fields may have been included in the
Mr. Mildner suggests that the measurement of voltage drops measurement. These errors may then have been enlarged by
measured along the pipe and the return conductors were in error converting the measurements to a 1000-foot basis.

Half-Wavelength Power Transmission Lines


F. J. Hubert, Member IEEE M. R. Gent, Member IEEE

Abstract: Because of the progressively greater distances from The succeeding years witnessed longer and higher voltage
sources of hydroelectric power to large load centers, there is a lines. Two of the notable ones are the Los Angeles Depart-
constant search for more efficient and less costly means of long-
distance transmission. This paper proposes a half-wavelength ment of Water and Power 265mile 287-kV Boulder lines,
transmission system for point-to-point transmission of power feeding Los Angeles, completed in 1936, and Sweden's 593-
to eliminate many of the operational and design problems asso- mile 380/420-kV line, completed in 1952. At present, Hydro-
ciated with conventional long transmission lines. Quebec of Canada is building a 700/735-kV 400-mile system
to draw on the abundant hydro potential of northern Canada.
Large load centers are often located at great distances from The design of economical ELD transmission lines is becom-
abundant sources of hydroelectric power. Because the long ing increasingly difficult due to the high cost of compensat-
electric power transmission line thus far is the only economical ing equipment. Instability precludes the transmission of
means of transporting this energy, utilities are developing power from a remote generator if the angle between the gen-
more interest in EHV and extra-long-distance (ELD) point- erator terminal voltage and the receiving end bus voltage is be-
to-point transmission lines. tween 90 and 180 electrical degrees. To provide a sufficiently
Historically, the first long high-voltage transmission line stable margin of safety, a criterion for preliminary studies of
appeared in 1914, when the Southern California Edison Com- approximately 30 electrical degrees has been suggested as the
pany placed in service the 150-kV 243-mile line from the maximum phase shift to be allowed over the line. At 60 c/s,
Sierra Mountains to Los Angeles; in 1924, it was changed a 250-mile line at surge impedance loading (SIL) has an angle
to 220 kV. of approximately 30. To maintain an angle of 300 for ELD
lines longer than 250 miles at SIL, 100-percent compensation
reommnde andappove bythe ranmision
Pape 31TP 5-12 is required of all lengths in excess of 250 miles. Therefore, as
and Distribution Committee of the IEEE Power Group for presenta- the line length increases, the cost per-unit length (including
tion at the IEEE Winter Power Meeting, New York, N. Y., January compensation) increases. Aside from the high capital
31-February 5, 1965. 1964;-
Manuscript submitted August 21, netet L ie rdc prtn rbes uha
made available for printing November 13, 1964. -lvsmn,EDle rdc prtn rbes uha
F. J HUERT nd. R GEN ar wih th Deartent f Wter surplus volt-amperes reactive (vars) during light load condi-
and Power, City of Los Angeles, Los Angeles, Calif. tions, Ferranti effect, and generator self-excitation.

IEEE TRANSACTIONS ON POWER APPARATUS AND 5Y5TEM5 VTOL. PAS-84, NO. 10 OCTOBER, 1965
Instead of shortening, if the line is electrically lengthened The following are computed per-unit (pu) values on a 1000-
so that its effective electrical length is between 1800 and 2700, MVA base:
an interesting phenomenon occurs. The system is as stable z=0.0123+jO.249 &/100 mi.
as one operating in the first quadrant (O to 900). For y=O+jO.167 mho/100 mi.
example, if the generator terminal voltage is 1900 with re-
spect to the load, the stability limit of the system is the same Zo -=1.22-jO.00303 ohm
as if the generator were operating at 100 from the load. In -o
addition, there are none of the usual long line operating where Zo is the surge impedance or characteristic impedance
polems
problems.
The most attractive feature of the half-wavelength system
ofwherlieZO isthe seriesimpedance oftharce lne, anpd te y s

of the line, z is the series impedance of the line, and y is the


is that the cost per-unit length decreases as the line.length
l llin- . ~shunt admittance of the line.
creases. At 60 c/s, viewing only the initial investment and From these data, the classical equation a +j3 = \/Zy can be
disregarding for the moment other advantages, the transition solved to determine the phase shift due to the characteristics
point between conventional and half-wave design would be of the line alone. In this equation, a is the attenuation con-
approximately 900 miles. stant in nepers per-unit length and f3 is the phase constant
The half-wave transmission line is not a new concept in that (phase shift at SIL) in radians per-unit length. For this
communication engineers have worked in terms of wavelength case, the attenuation constant is negligible compared to the
for many years. However, studies pertaining to transmission resulting phase shift.
of bulk power to a utility load on a half-wavelength system a+ __O_20_per____iles
have been virtually nonexistent. Generally speaking, the a+j3= V(o.0123+jO.249)(jO.167)=0.005+j0.204perl10miles.
communication engineer is not faced with the problem of in- (1)
stability because high-frequency loads usually consist of Therefore
T
passive impedandes. Similarly, he is not as concerned as the
utility engineer with the efficiency of the line because of the ,3=0.204 rad/100 mi. (2)
small amounts of power that his line is required to transfer.
This paper compares the advantages and disadvantages of or
a half-wave point-to-point transmission system with the afore- 9(0.204)=1.835 rad
mentioned problems in mind.
for the 900-mile transmission line. For this value of ,B there
Design is a phase shift 0 of
An explanation of the phenomenon of a half-wavelength 0=1.835(57.3)=1050. (4)
transmission line can best be illustrated by designing a hypo-
thetical line and conducting load flow, short circuit, and trans- For a half-wavelength system, another 750 of phase shift
ient stability studies. is necessary. However, as suggested earlier in the paper, to
The wavelength of an uncompensated overhead line is provide a 100 margin, the line is extended instead to 190 elec-
approximately 3000 miles. Changing the line parameters trical degrees in length, making the necessary additional
such as conductor size, grouping, phase spacing, and voltage phase shift 85. To achieve this 850 shift, T-section tuning
has practically no influence on the wavelength, provided the equipment is inserted in the system.
frequency is held constant. Assuming that all practical 60- The T sections may be placed in series anywhere in the line
e/s transmission lines are less than 180 electrical degrees in with the same overall result. However, because of the high-
length, two methods are presented for electrically increasing a voltage hazard near the center of the line during faults (ex-
900-mile 500-kV overhead line to a half-wavelength system. plained in detail later), the T sections should be placed as far
The first method places all tuning equipment at the ends of from the electrical center as possible. By dividing the T
the line; in the second, shunt capacitors are added along the sections into two equal portions and installing all the tuning
line to simultaneously increase the line's SIL and shorten equipment at the line terminals, the momentary high voltage
the 60-c/s wavelength. to which the equipment may be exposed is reduced. This
For two reasons the transmission system, including trans- also allows the transformers to serve as part of the branch of
formation, should be 100 or more longer than one-half of a two T sections. Fortunately, an appreciable range in the
wavelength. The first reason (discussed in more detail later) transformer impedances is obtainable, which gives flexibility in
is to reduce the required sensitivity of the generator var out- fitting transformers into the T sections. Additional benefits
put control and the second is to assure having a full half-wave- in reduced insulation are realized if the T sections are placed
length transmission line during temporary system reduced on the low-voltage side of the transformers.
speed operation. The wavelength is inversely proportional There are numerous methods of determining the number
to the frequency; therefore, if the system frequency drops and size of the T sections because there are many sizes of
5 percent, the wavelength increases 5 percent, thereby sections which would give satisfactory results. The method
electrically shortening the line. If a sufficient margin of employed here is dimensioning relatively small T sections of
safety is not provided, loss of power flow may occur. equal size to approximate 60-c/s transmission line operation.
The following have been assumed for the first design: The assumed line has a reactance of jO.249Q/100 mi or'
9(jO.249) pu total. To obtain the desired additional 850
1. Length: 900 miles. phase shift, a total impedance in the T sections of jl.81 ohms
2. Operating voltage: 500 kY. is required.
3. Type conductor: Twin Chukar 1780-kcmil, 1.6-inch-OD In this example, four T sections are used, two at each end
(outside diameter), ACSR (steel-reinforced aluminum cable), of the line. As show-n in Fig. 1, the transformers at both
18-inch spacing. ends make up part of the T sections. At the sending end, the
4. Phase spacing: 39 feet. inductors and capacitors necessary to complete the T sections

966 IEEE TRANSACTIONS. ON POWER APPARATUJS AND SYSTEMS OCTOBER.


900 MILE TRANSMISSION LINE netizing currents are assumed to be negligible because they
have no appreciable effect on the final results.
T SECTION Fig. 2 shows the calculated voltage at the receiving end,
JO.225 0.22 jO.225 0.165 JO.225 JO.225 10.225 LOAD the receiving end transformer high-voltage side, the sending
end transformer high-voltage side, and the generator termi-
nals, at 100-mile intervals along the transmission line. Note
jo.2921 1o292 jo.292 Xjo.292 that at SIL (820 MW), the voltage level varies less than 2
I>- l | - - percent. Except for the slight mismatch of the tuning equip-
ment, the voltage would be uniform from end to end.
SENDING
TRANSNGFORMDER ENDREIVNED
TRANSFORMER It should be noted that a load 20 percent greater than SIL
io.225 Jo.06 causes the peak value of voltage to rise 20 percent; conversely,
Fig.l. Tsectionsof500-kV900-milesingle-circuittwin-conduc- a 20-percent decrease causes a 20-percent voltage dip. Not
tor half-wavelength transmission system on 1000-MVA base shown on the graph is the no-load voltage profile. At zero
load (open receiving end), the voltage at the line's electrical
center is near zero in spite of the fact that both ends maintain
normal voltages.
It can be seen from Fig. 2 that the line voltage is extremely
are placed between the generator terminals and the low-volt- sensitive to the amount of power being transferred. How-
age side of the transformer bank, and at the receiving end, ever, regardless of load requirement, the sending end voltage
between the low-voltage side of the transformer bank and the is virtually unchanged if the receiving end voltage and fre-
load. The reactance needed for each of the T sections is jl.81 quency remain the same.
divided by 4, or jO.45 pu. The sending end transformer, with To substantiate the analytical approach just presented, an
J0.225 pu reactance, furnishes half the reactance of one T ac network calculator was used to conduct a load flow study
section. The assumed reactance of the receiving end trans- to show the system with its appropriate resistance included.
former is jO.06 pu ohm. The adjacent inductor is conse- Fig. 3 shows the system with the metered values given.
quently j0.165 pu ohm reactance so that the two in series make If the transmission system (including transformation) is
up half of the first receiving end T section. shorter than 1900, a special generator var control would be
The next step is determining the size of the shunt capaci-
tors for the T sections. The T-network equation that de-
scribes this situation is
z212
Z0= -+-. (5) 1000 MW
110
Rearranging (5) to solve for y gives z BM
820 MW
1
100' ._-
Z02 _z (6)
z 4 - 90 \
Substituting the established values for ZO (same as line) 640 MW
080-
and z (total T-section series inductive reactance) gives y= >
j0.292 mho pu admittance per T section.
The completed design, as shown in Fig. 1, requires 1170 70
Mvar of shunt capacitors and 1017 Mvar of series inductors for GEN 9 8 7 6 5 4 3 2 0 LOAD
a total of 2187 Mvar for the system. DISTANCE FROM RECEIVING END IN HUNDREDS OF MILES
Fig. 2. Voltage profile of 500-kV 900-mile half-wave transmis-
Load Flow sion system for different values of transmitted load
To illustrate the uniqueness of the half-wave transmission
line, a load flow and voltage study is presented. This study
covers three important conditions of line loading; SIL, load-
ing greater than SIL, and loading less than SIL. The SIL RECEIVALENTD
reference is used because it is the most efficient and natural
loading of an ELD line. This analysis consists of calculating
the sending end and line conditions for various receiving
end unity power factor loads. E I OOLI 190- VOLTS
SENERATORND GNLOCAL
GE=NERATION
The specified receiving end loads are 0.82, 1.0, and 0.64 pu P00
MVARS Q * 0 MVARS P20570
Q~~07OO MW
MVARS
ampere, representing SIL, loading greater than SIL, and less
than SIL, respectively. The potential is held at 1.0 pu vo]t- 826 760 A

age in all cases, satisfying the practical requirement that the 46 7 lI


receiving end voltage remain essentially unchanged from no I I I I~ LOAD
load to full load. The receiving end voltage angle is used as - - I
reference and held at zero degrees and all other angles in the E95X-280 VLSW
sytmaemeasured with respect to the receiving end. @283
P MWAR
Two approximations are made to simplify the calculations. Fig. 3. Results of ac network calculator load-flow study at SIL
First, the resistance is assumed to be negligible, thereby conducted over half-wave 500-kV 900-mile system (voltages are
creating a l.ossless system. Second, the transformer mag- in percent)

1965 HUBERT AND GENT: HALF-WAVELENGTH TRAN5M155ION LINES 967


necessary because the conventional voltage regulator would interest, not shown on Table I, are faults within the T sec-
not be of sufficient sensitivity. To illustrate this type of var tions. Three-phase faults at this point cause voltages up to
problem, consider the case of two generators tied directly to a seven times normal at the center of the line. However,
bus with no impedance between them. A cross-current com- locating the T sections within the sending and receiving sta-
pensator is required to control the tar flow of the generators. tions would minimize the occurrence of short circuits of this
Similarly, a transmission system of exactly 1800 would be nature and the high voltages associated with them. Never-
equivalent to a system with no series impedance between the theless, the possibility of this type of short circuit occurring
sending and receiving end, and some special means would necessitates the investigation of higher transformer insulation
have to be provided to control the current. For this reason, levels.
it is advisable, as stated before, to design the line for a mini- To control the high voltages resulting from faults near the
mum of 1900 operation. ends of the line, arc gaps could be used near the line's mid-
The advantage of the half-wavelength transmission system, point. In addition to collapsing the voltage, grounding the
as pointed out by this study, is that the generator appears to midpoint reduces the terminal breaker duty. The arc gaps
be separated from the load only by that portion of the line could be set above the gap required for minor lightning surges
that is in excess of 180 instead of the physical 900 miles. to a value necessary to handle only voltages resulting from
Therefore, the factors that limit line loading are efficiency, short circuits. The normal lightning surges could be handled
line insulation, and radio interference at the center of the by lightning arresters at the transformer high-voltage side.
line, and the thermal capability at the terminals. Stability Worth mentioning again in connection with short circuits is
is not a limiting factor when transmitting on a half-wavelength the unusually low magnitude of ground currents associated
line. with center of the line faults. For the cases of 1-, 2-, and 3-
phase-to-ground faults the follow-up current was less than SIL.
Shout Circuits
An extensive ac network calculator analysis was made of Stability
short-circuit currents and voltages. The results indicated The steady-state stability of a half-wave transmission sys-
that currents presented no unusual problems because their tem is unquestionable because, when properly designed, the
magnitudes were within accustomed ranges. The fault cur- generator appears as if it is only about 100 from the load.
rents varied widely with the fault location. Faults at the To study the transient stability of the half-wavelength
center of the line produced ground currents smaller than SIL transmission system, several cases were run on an ae network
and faults near either end of the system caused ground cur- calculator. To simulate actual system conditions as closely
rents in the order of 15 or 20 times SIL. as possible, typical kinetic energies and transient reactances
For the T-section design, studied in this paper in detail, a were assumed for both the sending and receiving end equiv-
subtransient reactance was assumed for the sending end alent generators. The internal impedances were 0.20 and
generator and also for the local generation equivalent. These 0.089 pu ohm reactance on a 1000-MVA base, respectively.
values were 15 percent and 7 percent, respectively, on a 1000- The kinetic energies assigned to the generators were 8100 and
MVA base. It was further assumed that the sending end 10 550 MW -s, respectively.
step-up transformer bank was delta-wye grounded and that Faults of exaggerated duration were employed to illustrate
the receiving end step-down transformer was a grounded wye the strong synchronous tie. In the case discussed here, a 2-
autotransformer bank. phase-to-ground fault was applied in the region of the receiving
Complete tests were made for 1-, 2-, and 3-phase-to-ground end network equivalent and was maintained for 17 cycles.
faults at all locations. The generator positive sequence The phasor diagrams of Figs. 4, 5, and 6 indicate the
currents varied from near zero for 3-phase faults 900 away to unusual transient reaction. These diagrams show the send-.
some high value related to the transient impedance for faults ing end generator and line voltage magnitude and angle with
near the generator terminals. respect to load, before the fault, 1 cycle after clearing (T= 18
Table I shows the more pertinent results of faults in terms cycles) and 11 cycles after clearing (T= 28 cycles).
of phase voltage. At the line ends (transformer high-voltage Comparing the phasor diagrams for before and immediately
side), highest voltages developed on the unfaulted phase dur- after the fault, Figs. 4 and 5, respectively, it can be seen that
ing a 2-phase-to-ground fault at the system's receiving end the terminal voltage angles never swing less than 1800 with
(load). For the 3-phase-to-ground fault, the transformer respect to each other, even though the sending end generator-
voltage rise vas slightly less severe. The faults of most is momentarily in the second quadrant with respect to the

Table 1. Percent Voltage at Sending and Receiving End Transformer High-Voltage Sides During 1-, 2-, and 3-Phase-to-
Ground Short Circuits
Percent Voltage at Sending End Percent Voltage at Receiving End
Transformer High-VoltageSide Transformer High-Voltage Side
Type Fault Fault Location Phase A Phase B Phase C Phase A Phase B Phase C
Thre-has
fe-paulse
I Sending end transformer, high-voltage side 0 0 0 166 166
Receiving end transformer, high-voltage side
222000
166
222 222
Load 190 190 190 232 232 232
Two-phase-to I Sending end transformer, high-voltage side 69 0 0 170 136 194
groPund faults -( Receiving end transformer, high-voltage side 265 242225 0 41
Load 68 178 167 163 0 219 226
Single-phase-to- I Sending end transformer, high-voltage side 099 74 171 49 165
ground faults -( Receiving end transformer, high-voltage side 235 180
99 0 89 79
Load 142 31 162 204 141 131

968 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS


OCTOBERL
go "0 T-28 CYCLES

500 400 300


600 MILES MILES MILES 200

L TRANSORMER 5\-4
40
TRANSFORM ER
S00
EIVING END
HIGH VOLTAGE// / SIDE
\
GENERATOR
'\_l 4e
HIDE _ o
/G ;
HIGH VOLTAGE TERMAL
-
SIDE LOADNA
IN'TERNALLA
270"

GENERATOR

/ O 10 25 50
/_O_10_25_50 % VOLTAGE SCALE
INTERNAL % VOLTAGE SCALE Fig. 6. Voltage phasor diagram of half-wavelength 500-kV
Fig. 4. Voltage phasor diagram of half-wavelength 500-kV 900-mile system at 28 cycles (11 cycles after clearing)
900-mile system at SIL under normal operating conditions

400
GENERATOR 90g T-18 CYCLES
w 360
~~~~TEs~~~~~~~~~~~~4 S~~~~~~~ _-
_ 0
o /NSENDING END
WINAL LOAD Z 300 _
180 0 FAULT

/~~~~~~~~~~~~0
aX
41// w~~

0 - o ~ 't' 4
0 10 25 50 0 RECEIVING END
N. 4r 4
%VOLTAGE SCALE 270 j 100 /

Fig. 5. Voltage phasor diagram of half-wavelength 500-kV


900-mile system after clearing of 17-cycle fault
-j

0 40 50 60 70
0 10 20 30
TIME IN CYCLES
load. While in the second quadrant, the sending end genera- Fig. 7. Swing curve of generator internal voltage angles for
tor is motoring, the power flow in the line is reversed, and fault of 17-cycle duration applied in region of receiving end
simultaneously the voltage along the line is oriented in the equivalent of half-wavelength 500-kV 900-mile system
opposite quadrant; therefore, the motoring generator is still
over 1800 from the other end. Using the phasor diagram for
reference, it can be said that the power flow is always in the
clockwise direction, taking the longest path measured in not only increases the SIL but lengthens the line electrically.
in terms of electrical degrees. For example, assume that the SIL of the line in the first design
To arrive at the conditions shown in Fig. 6 (T = 28 cycles), (900 miles of single-circuit twin Chukar at 500 kV) is to be
the motoring action of the generator and the turbine drive increased from 820 MW to 1400 MW.
combine to force the generator back into normal operation. For SIL of 1400 MW, the admittance necessary for this
Here, at 28 cycles, the power flow has again reversed and co- line would be
incidentally the voltage has flipped back towards its original
position. In tests at lower clearing times, the motoring gen- y =zIP =jO.249(1.4)' =jO.489-pu mho/100 mi. (7)
erator situation did not occur. on 1000-MVA base.
In summary, the remarkable transient stability of the half-
wavelength transmission system to a 'fault 1. . 1.
of extraordinary The
Teeoe h admittance
natural ifrneo ofO32hst emdpu/100
the line is i0.167 pwt mi.
duration iS self-evident In Fig. 7, the swing curve for the 17- shunt capacitors. A total of 9(0.322) (1,000) or 2900 Mvar,
cycle fault. distributed at 100-mile intervals along the line, is required to
Alternate Designs increase the SIL from 820 MW to 1400 MW.
DESIGN NUMBER
Two ~~~~~~~~Since the admittance of the line has been increased, the
phase shift over the line has also been increased. The new
If greater line-carrying capacity is desired without going to phase shift, 6, over the 900-mile line is:
higher voltages, the SIL of the line can be increased by adding______
shunt capacitors along the line. This additional admittance 0 =57.3LX/zy =57.3(9) X/(0.249)(0.489) =1800. (8)

1965 HUBERT AND GENT: HALF-WAVELENGTH TRANSMISSION LINES 969


Therefore, no additional terminal tuning equipment is system terminals and larger currents near the terminals. The
needed because the transformer impedance will add a suffi- flexibility of the half-wavelength line design offers a large variety
cient margin of safety to insure continual 180 operation. from which the engineer may select to fit a particular need.
Comparing the second design with the first, 33 percent more References
tuning equipment is necessary in terms of Mvar. However, [1] E. W. DuBois, J. F. Fairman, Jr., D. E. Martin, C. M. Murphy,
the line power transmitting capability has been increased and J. B. Ward, "Extra-long-distance transmission," Trans.
71 percent. This advantage in reduced capital cost per mega- AIEE (Power Apparatus and Systems), vol. 80, pp. 1108-1116,
watt must be weighed against the additional I2R losses in February 1962.
[2] S. B. Crary, Power System Stability, vols. I and II, New York:
the line. The efficiency of the line decreases when the SIL Wiley, 1947.
is increased with shunt capacitors. [31 Electrical
Central Stations Engineers
Transmission the Westinghouse Electric Corp.,
andofDistribution Reference Book, East
Pittsburgh, Pa.: Westinghouse Electric Corp., 1950.
[4] L. A. Ware and H. R. Reed, Communications Circuits, New York:
DESIGN NUMBER THREE Wiley, 1944.
[5] Y. I. Lyskov and N. N. Sokolov, "Characteristics of the tuned
In this third example, it is assumed that a single conductor transmission of ac power," Elekt. Stantsii, no. 5, pp. 46-50,
is used instead of twin conductor and that the shunt capaci- May 1963 (in Russian).
tor method of increasing the electrical length of the line would
be used.
It is assumed that 1150 MW is to be transmitted at SIL Discussion
for a distance of 900 miles at 500 kV over a 2'/2-inch-OD ex-
panded ACSR line, with 39-foot horizontal spacing. On a
1,000-MVA
The000tal admittane, z =j0.305 pu
base, z=jOired pu and
and y=jO137pu100mi.
y =jO.137 pu/100 mi. E. W. Kimbark (Bonneville Power Administration, Portland,
The total admittance required is Ore.): In some respects, a half-wavelength power transmission
line is like a high-voltage direct-current transmission line: 1) In
the present state of the art, both are most suitable for point-to-
y =z12=jO.305(1.15)2 =jO.403 pu/100 mi. (9) point transmission and not particularly for tapped loads or net-
working, 2) both overcome the limitation of distance due to
The shift in voltage angle, end-to-end, is: instability, and 3) if the half-wavelength is achieved by arti-
ficially increasing the electrical length through the addition of
0= 57.3L = 57.3(9) /(0.305)(O.403) = 1810. (10) lumpy terminal sections, the line bears a further resemblance to
the HV dc line in having more expensive terminals than the
Therefore, no additional tuning equipment is needed. ordinary ac line.
The total required charging is greater than the natural line A characteristic of the half-wave line that appears strange at
first sight is that, in the middle of the
light load and bulges at heavy load. A line,
charging; char
therefore,
g; shunt caacitos
terefoe shut capacitors arerequied at 100-
are required at100- the voltage sags at
short ac line with equal
mile intervals along the line. To make up the difference, terminal voltages does the contrary: the voltage at the middle
9(403-137) or 2400 Mvar is needed for the 900-mile line. exceeds the terminal voltage at light load and sags at heavy load.
This compares favorably with the first design which required Actually, of course, there is no inconsistency. The voltage
1170 Mvar ofof shunt capacitors and profiles of lossless lines of both lengths are appropriate segments
1170 1017 Mvar
and 1017 of series in-
ductorsMvar shunt capacitors
for a total of 2187 Mvar Mvar of series in-
of tuning equipment to
of the profile of a longer line, as indicated in Fig. 8.
For purposes of general interest and comparison, it would be
transmit 820 MW. well to have an estimate of kilovoltampere capacities and costs
of various components of the terminal equipment indicated in
Conclusion Fig. 1. An estimate of series capacitor and shunt reactor equip-
ment required to accomplish the same transmission would be
As increased attention is focusing on the more remote interesting for comparison. Would such a line, tuned to half
hydro-energy sources, need for a more economical trans- wave, be suitable for intermediate tapping, and what equipment
mission system is developing. As an alternate to dc and con- would be required?
ventional ac lines, a half-wave ac point-to-point transmission
system has been proposed with three designs or variations of
designs. The advantages of the half-wavelength trans-
mission line as compared to a conventionally designed ELD M
ac line are: 1'.0
1. For 60-c/s lines longer than 900 miles, the half-wavelength S R /
line would require less capital investment than a line of the same / \
rating, using series capacitor and shunt inductor compensation. /I
The need for tuning equipment decreases with distance up to z / I\
1500 miles, providing the necessary breakthrough of the cost D: I
barrier of an ac system. .'
2. Half-wavelength systems are completely free of the special > 0.5
problems of Ferranti effect, excessive charging current, and the W

possibility of generator self-excitation associated with generating -


plant start-up and energizing a long transmission line. For all >
practical loadings, the terminal voltage of the generator is
essentially constant.
3. The system is stable under severe fault conditions.
4. Unlike the ac lines of conventional design, the voltage of the
half-wave line in the regions away from the terminals is a function 0- _ D _TAC
of the transmitted load. The line potential automatically - \ ADDED \2-- ISAC
adjusts to different loading conditions. In any of the three _2X
ELD designs presented, the line megawatt capacity can be3
increased above SIL simply by dimensioning the system for Fig. 8. Voltage profile of lossless half-wavelength line and ac
higher operating voltage levels in the region awvay from the line

970 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS


OCTOBER
H. D. Hunkins and F. R. Schleif (U. S. Bureau of Reclamation, BILs, all become major problems because of this large funda-
Denver, Colo.): The nature of the Bureau of Reclamation's mnental frequency voltage variation. The transformer saturation
assignments in developing water resources and the associated may have two possible effects on such a system, the first provid-
power developments often commits it to large power projects ing some assistance in holding down voltages, but the second
a considerable distance from load centers. Hence, various forms introducing the possibility of resonant circuitry and still higher
of long-distance high-capacity electric power transmission receive voltages due to ferroresonance. In actual fact, lengthening
review for applicability, including such half-wavelength trans- the line to a half-wavelength does not eliminate such problems.
mission systems as described by the authors. Much theorizing is done but little mention is made of operating
The half-wave transmission system has intriguing charac- problems. How would the system, consisting of two such half-
teristics, many of which have been well set forth in the paper. wave lines in parallel for security, be energized and brought up
A few additional characteristics of interest are described in the to the 1900 operation? What loading can be used to maintain
following comments: By designing the line for operation at stability when one line is faulted and removed from service?
somewhat above surge impedance loading, the rise of voltage The investigation of transient stability studied for the half-wave
in the central section of the line can be utilized to effect an design considered a lengthy fault occurring in the receiving
increase onftransmission efficiency. The IAR losses of this portion systemiand not in the transmission system. How would the
are decreased at the expense of higher operating voltage level, half-wave system be operated during light system loading
Since the voltage transformation for this portion is achieved conditions? How would the authors propose protecting such
by the line itself, there is no corresponding increase of insulation a transmission system? All these questions point out the
expense for the terminal equipment, and the increase of line problems of operating such a transmission system in conjunction
insulation, if actually needed, is somewhat less expensive. Con- with a normal one.
versely, as shown by Fig. 2, the voltage decreases along the A consideration that might be investigated is the economics of
central portion of the line and the losses increase at light load, using this tuned-type ac transmission for up to 1500-mile trans-
The result is a load regulating effect upon the remote generating mission of large blocks of power. Comparison with alternative
station which has some desirable aspects. The point-to-point de transmission would then be of interest.
transmission capabilities of the half-wave line conceivably could
be overlaid upon a network. Since the line operates at phase
shifts of 180 to about 1900 from zero to full load, a fixed phase J. W. Skooglund (Westinghouse Electric Corporation, East
shift could be built in. Reconnecting one set of line terminals Pittsburgh, Pa.): The authors have presented a timely discus-
would provide 1200 of shift and a delta-wye transformer an sion of the application of the half-wavelength transmission line
additional 30f. A plus-minus 30tvariable phase shifter might to bulk power transmission. With present interest and emphasis
then provide the remaining phase shift required to match the on EHV and ELD transmission in the world today, it is appro-
network. priate that this subject be examined.
These rather cumbersome means of adjusting load flow upon I agree with the majority of the authors' technical conclusions,
a network serve to point up the superior flexibility of high-voltage but I believe some additional clarification of the economics of
dc transmission. This is at present committed to long-distance this transmission scheme is needed. It is stated that the half-
open-wire transmission by the economics of high-cost terminal wavelength system cost per-unit length decreases as the line
equipment and the lower cost intervening line. In addition, the length increases. This is certainly true, as the need for com-
high-voltage dc line offers potential advantages of rapid control pensation decreases, but the total cost still increases significantly
to improve the stability of the underlying network if such control with longer line lengths. General transmission economics are
is needed, and the ability to transfer power without synchronism not the subject being discussed here, but in my opinion, there
whenever this may be an advantage, is little justification for the economic development of remote
Aside from the complications of utilizing the half-wave trans- hydro sources 1000 to 1500 miles from the load.
mission, economic comparisons by the Russians (115] of the paper)
still indicate a substantial advantage in favor of the high-voltage STABILITY
dc transmission system. The results of the transient stability cases show that the system
Although the half-wave transmission system is intriguing and is stable for a long duration (17 cycle) fault applied in the re-
worth consideration for special future applications, it appears ceiving area. Was the line opened to clear the fault and then
that the advantages at present are still strongly in favor of the reclosed? Generally, in the study of ELD lines, a fault is as-
high-voltage dc transmission system for point-to-point service. sumed on the transmission line, the line is opened in clearing the
The possibilities for tapping a half-wavelength line are much fault, and then reclosed later. A fault at the sending end causes
less feasible than tapping a high-voltage dc line, acceleration of the machines, but even more acceleration is
produced during the dead time before reclosing. For this reason,
it is difficult to stabilize a remote source having only one out-
H. M. Ellis and D. G. McFarlane (British Columbia Hydro and going line.
Power Authority, Vancouver, B. C.): The authors have re- Should the development of a remote source be economically
viewed in some detail the use of a tuned circuit for transmitting feasible, the power would usually be considered firm and not
large blocks of power over considerable distances. A number of interruptable following faults. A typical conventional ac trans-
questions arise on a review of the paper. Mention is made of a mission system from such a source would consist of two parallel
break-even point for conventional system design and half-wave circuits sectionalized every 200 miles. It is typical design prac-
design at approximately 900 miles. Is this based on only one tice to deal with a permanent fault on one line section, and to
line rather than a normal requirement of at least two lines in maintain stability through transmitting the total power across
parallel? the good parallel line section. Of a total transmission distance
The high initial cost of compensating equipment is pointed of 1000 miles with five sections, the loss of one section increases
out. However, initially the only compensating equipment the line impedance only 20 percent.
required in a conventional design is the shunt reactors, which n nIt appears that the half-wavelength line is not particularly
are a fraction of the total line costs. As the line loading increases, suited to sectionalizing. Therefore, a 2-parallel-line system
the requirement for series compensation arises and builds up must be designed to increase power transfer on one complete
until the ultimate system design is achieved. For example, the line by two to one, should one circuit suffer a permanent fault.
Peace River scheme of two 500-kV lines covering approximately Line impedance is increased 100 percent, and the voltage profile

mission system cost. For the half-wave design, compensating wvlngthnnnnnnnnnnnsystem?nnnnnnnnnnnnnnnnnnnnWouldnnnnnnnnnnnnnnnlossesnnnnnnnnnnnnnnnnnbennnnnnnnnexpectednnnnnnnnnnnnnnnnn


installedrquremmditeyat hefreachh Tsetiendnnnnnnofnnnnthennnnnnline, n n n n n n nnlines,nnnnnnnnnlossesnnnnnnnnnncannnnnnbennnnnannnsignificantnnnnnnnnnnnnnnnportionnnnnnnnnnnnofnnnnthennnnnntotale,hestransmissionoalacsyte? n L
transmission design is the large voltage fluctuations which can

arresters and spark gaps, insulation coordination and equipment


reasonablennnnnnnnnnnnnnnnnnnnnnnnonnnnnnnnthennnnnnnnnhalf-wavelengthnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnsystem.nnnnnnnnnnnnnnnnnnHowever,soaleo t

1965 HUBERT AND GENT: HALF-WAVELENGTH TRANSMISSiON LINES 971eeeeeeeeeeeee


concerned with the problem of establishing the BIL of the reflection factor becomes
sending and receiving end transformers and tuning equipment.
Transformer BIL is primarily determined by the lightning Ro(k-1)+jXL
arrester rating that can be applied at the transformer location. oLO(k+1)+jXL
Using the overvoltage values given in Table I and assuming
500-kV maximum operating voltage, a maximum 60-cycle voltage so that the reflected wave is no longer in time phase with the
of 2.65X500/-/'3=765-kV rms to ground is produced. This is incident wave at the receiving end and the voltage maxima or
the minimum arrester rating that can be used. Determining minima no longer occur at the receiving end of the line or at its
the BIL based on switching surge coordination with a 15 percent middle for a half-wave line.
margin The authors have chosen to locate the step-up and step-down
transformers on the line sides of the T sections. Since imped-
BIL = (765)\/2(1.65)(1.15) = 2460 kV. ances of the set of T sections on the sending and receiving ends
0.83 each correspond to the impedance of 343 miles of line, the high-
voltage bushings and windings of these transformers will be
This is a high BIL for a 5Q0-kV system and is much higher than subjected to the voltage stresses associated with that line location.
that required for the equivalent conventional ac system. Prim- Thus, for a receiving end load of 1.0 pu ampere (1.22SIL) at
arily for this reason, the authors' conclusion that 900 miles is unity power factor, the voltage on the high side of the bushings
the break-even point between half-wave and conventional ac is calculated to be 1.135/49 pu under normal conditions, or
transmission seems optimistic. Since the line costs are the same 131/2 percent higher than nominal voltage at the receiving end.
for both systems, any difference is in the terminal, switching, This is a severe overvoltage and it worsens the more the load
and compensating equipment. High BILs will significantly exceeds SIL.
increase equipment cost. The authors state that additional benefits in reduced insulation
In summary, it should be stated that the half-wavelength line are realized if the T sections are placed on the low-voltage side of
may have a significant place in the transmission of energy over the transformers. I would appreciate amplification of this point
long distances. However, for a proper comparison of the ad- in view of the previous remarks.
vantages and disadvantages of the half-wavelength system, the So far, attention has been directed only toward the load end.
factors discussed here should be considered in an economic There is also a reflection factor at the generator end which applies
evaluation. to the reflected waves returning from the load end
VRG ZG-ZO
PVG ==
VIC, ZG + ZO
G. I. Stillman (AEP Service Corp., New York, N. Y.): A
transmission line in a communications system is usually termi- where VIG is the wave returning from the load end, VRG is the
nated in a constant impedance. A transmission line in a power reflected wave at the generator end corresponding to VIG, and
system is usually terminated in an impedance which varies as ZG is the generator impedance. Since ZG is almost a pure
the load varies from peak load to light load during the course of reactance for a turbo- or hydro-generator, while Zo is almost
a time interval. The authors are proposing a transmission line a pure resistance, then
which is tuned to approximately half a wavelength and which XG-RO XG
is matched to the load only at unity power factor surge-impedance PVG =- G 1
=
/1r-2 tan-1
loading. At any load other than unity power factor SIL, there JXG+Ro -
is a mismatch between the load and the tuned line. The mis- Thus, the reflected wave will equal the incident wave but will be
match results in reflected voltage and current waves at the load
end ofine
the line..Theratiodofethenteflected
The ratio of the reflected voltage
voltagewave the
waveto the
shus,edeinefleeedhase
shifted
loIf theingenerator fromwit.
time phaseoutput it.
voltage is called VG, then the total
incident voltage wave at the load end is given by
voltage at the generator terminals is VT=VG+VIG+PVGVIG.
This equation indicates that the generator terminals can be
p VreflL ZL-ZO subjected to substantial overvoltages when the receiving end
Vin=L ZL+ZO load is larger than SIL and/or has a power factor other than
unity. I would appreciate the authors' comments on this point.
where ZL is the equivalent load impedance. Since Zo is usually The authors suggest that SIL of the design-number-two line
almost purely resistive while ZL in a power system is almost can be increased byspacing shunt capacitors at 100-mileintervals
never purely resistive (since loads are rarely unity power factor), along it. Aside from the Ferranti voltages possible, there is
it is apparent that there will be reflections at the load end, even another major problem. Spacing the capacitors at intervals
if the real part of ZL equals Zo, i.e., even at SIL if the load is not does not change the Z0 of the 100-mile line sections; each line
unity power factor. For this latter case, if ZL = RO + jXL and section "sees" a shunt capacitor (Xc) in parallel with the equiva-
ZO = Ro, the ratio of reflected voltage to incident voltage is lent impedance of the following line sections and shunt capacitors.
given by Thus, if the final 100-mile section at the receiving end is termi-
nated in Zo, the preceding 100-mile section sees an impedance of
XL 2 2RoXL XL /tn'.R Z
4
PVL '
XL' 4J?'+XL' X/4R02+XL2 XL 1 +jZo/Xlc
so that the reflected wave is smaller than the incident voltage Therefore, there will be reflections at this point and at each
wave and shifted in time phase from it. The total voltage at other point where shunt capacitors are connected. Such a
the load end is the vector sum of the incident and reflected waves. design would be subject to multiple reflections and to the ensuing
The authors avoid this problem by calculating their load flows possibilities of overvoltage, resulting in difficulties with relaying
for unity power factor loads at the receiving end. For the and lightning arrester application as well as insulation problems.
unity power factor case let ZL = kZo (corresponding to a load of I would appreciate the authors' comments on this point also.
1/k SIL) where k is a real number. The VSWR (voltage stand-
ing-wave ratio) = Vmax/Vmi,, = k. The voltage reflection
factor PVL =(k-1 )/(k + 1). Jfk> 1, the incident and reflected
voltage waves are in time phase at the load end, giving a voltage F. J. Hubert and M. R. Gent: We wish to thank Mr. E. W.
maximum (Vmnax) there. A quarter wavelength from this point, Kimbark for his enlightening discussion. In response to his
there is avoltage minimum (Vmin), and from the VSWR formula, request for comparisons of kVA capacities, we have prepared
Vmin =1/k Vmax. A similar analysis may be made for k < 1. a table of estimates, Table II. This lists megavar capacities
Thus, the voltage at the center of a half-wave line is greater of the various tuning equipment components for the three de-
or less than the voltage at the receiving end in the same pro- signs presented in the paper, as compared to the equivalent
portion as the receiving end load is greater or less than SIL, quantity of series capacitors and shunt inductors required for a
provided that the receiving end load is also unity power factor. single-circuit 30 line to accomplish the same transmission.
This iS shown in Fig. 2. When the receiving end load is not In terms of megavar, the component requirements are similar
unity power factor, say ZL = kR0 + jXL and Z0 = Ro, the only for design 1. The megavar requirements of the 300 line

97 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS OCTOBER


Table II switching surges. The half-wave system does not have high-
33
voltage switches and associated surges; therefore, the insulation
Design Number
Design Number 1
1 22
requirements are not out of proportion, and protection of trans-
MW Load 820 1400 1150 formers and other equipment, application of lightning arresters
and spark gaps, insulation coordination and equipment BILs
seem minor problems when compared with those of a 900-mile
Series inductor Mvar 1017 0 0
Shunt capacitor Mvar 1170 2900 2400 30'Thesystem.
Total Mvar Total-Mvar2187
2187 -900
2900 2400-
2400
problems of a half-wave system have not been totally
resolved; however, we forsee no difficulties in operating such a
30 line system in conjunction with a normal one. In response to
Series capacitor Mvar 1078 3660 3035 questions regarding system operation:
Shunt inductor Mvar 1075 770 632
Total Mvar 2153 4430 3667 1. A system of two such half-wave lines in parallel would be
energized and synchronized as any other ac system. For
example, if the first line is energized from the receiving end, the
sending end voltage would be of correct magnitude (since there
is no Ferranti voltage) but 1800 out of phase. The sending end
generator would be synchronized and put on the line as in any
for designs 2 and 3 are much more. Difficulty was encountered other system. As the generator picks up load, the phase shift
in obtaining consistent installed-cost estimates of 500-kY tuning gradually advances from 180 to 190 when full load is reached.
equipment (instead of low-voltage as suggested in paper); how- The second line could be energized from either end. There
ever, at present, series inductors appear to be less expensive would be a 100 phase between the fully loaded line and the
than series capacitors and conversely, shunt capacitors less unloaded line; however, this presents no problem. As in any
than shunt inductors. All else being equal in cost, we feel that ac system, a voltage phase shift exists across the last breaker
the comparison indicates that for transmission of these loads, to be closed when a parallel line is placed in service.
the 900-mile 500-kV half-wave line is less expensive than the
single-circuit 300 line. 2. The limiting factor of a half-wave system is voltage, not
In regard to the question of tapping such a line, the half-wave stability. The additional load that the remaining circuit can
characteristics would, in that case, be lost. A 900-mile line with carry is almost directly related to the additional 60-cycle voltage
intermediate taps should be designed in the conventional manner the center of the line can withstand.
with no tuning equipment. 3. The half-wave line has none of the light system loading
Mr. Hunkins and Mr. Schleif have suggested a good way of condition problems that exist on 300 lines, such as excessive
overlaying a half-wave system on a network. Another way of charging current. Except for the difference in IaR loss, the half-
obtaining the 1800 phase shift would be to simply reverse all the wave line can be operated from no load to full load, as if it were
leads on one side of a transformer. In this case, an autotrans- only 1 mile in length instead of 900 miles.
former could not be used on the end where the reversal would 4. Protecting such a system can be accomplished with distance
be performed.
As to comparison with dc transmission, our intent was merely relays atect
4. in
at 300-mile intervals and a transfer
a witheme.tance
tem an ansfertrip scheme. Pro-
to present an alternate method for the engineer to use if it fitted tection of a half-wave system is simple when compared to prob-
a particular need. Certainly dc transmission offers many lems posed by the unpredictable operation of the series capacitors'
advantages; however, stability is not one of them. The strong arc gap of a 900-mile 30 line.
synchronous tie of the half-wave system would do more to
stabilize the underlying network than the rapid control of dc Mr. Skooglund's discussion calls for a more complete look at
power flow. the stability studies. For the study presented in the paper,
We did not obtain the same results as the Russians on relative the applied fault was not in the half-wave system but in the
costs of ac and dc. At this stage of the art, precise cost com- receiving end equivalent. Therefore, the half-wave line was not
parison is impossible; however, we find ae and dc competitive opened. Another transient stability study was made for a 3-
in price, depending on the distance and quantity of power to be phase fault of 5-cycle duration at the sending end of the line
delivered. (transformer high-voltage side). It showed that reclosure is
It is true that the half-wave line cannot be tapped and remain required at 17 cycles (12 cycles after clearing) in order to main-
a half-wave line. However, provisions could be made for tapping tain the tie. The synchronizing force is so great that the genera-
at some future date, simply by removing the tuning equipment tor output, and correspondingly the center of line voltage, jumped
and operating the line sections in the conventional manner. to three times full-load value at time of reclosing.
We wish to thank Mr. Ellis and Mr. McFarlane for their Should it be desirable to construct two outgoing circuits,
discussion and will attempt to answer their questions. The instead of a single circuit, there would be virtually no stability
900-mile break-even point of the conventional system and the problem. Reliability can be further improved by having no
half-wave design is practically independent of the number of intermediate switching station, which reduces the system re-
parallel circuits. Dimensioning of ELD line conductors is liability and by widely separating the rights of way.
usually based on efficiency resulting in oversized conductors in The half-wave system effective impedance does double with
terms of radio interference and thermal limit; consequently, one circuit out; however, the prefault impedance is so low that
the conductor of a 2-circuit half-wave system would be identical even when doubled, it is still lower than the impedance of a two
to a 2-circuit 300 system. It might be desirable to install circuit 300 system with no outage.
transformers of higher current-carrying capacity in each half- We have considered the P2R losses. With low-loss reactors
wave circuit, the cost of which would be offset by lack of high- and with all lines in, the full-load losses are identical to the losses
voltage switching stations used on 30 systems. For these of a 300 system. The economical conductor size and voltage
reasons, the break-even point for conventional and half-wave are determined in the same manner for both systems. Similar
design is approximately 900 miles for both 1-line and the 2- conductor and voltage produce similar losses.
parallel-line systems. Concerning the short-circuit voltage, we have revised our
The possibility of ferroresonance was an oversight on our thinking and now believe the transformer should be at the
part. Because of this hazard, we have modified our thinking system's ends. In addition to reducing the possibility of ferro-
and would place the tuning equipment on the line side of the resonance, the tuning equipment (low-pass filters) will prevent
transformer, instead of on the low-voltage side, as the trans- lightning surges from impinging the transformer. Only the first
former would not be subjected to high-voltage and the associated inductor on the line side would require a high BIL. By employ-
ferroresonance during short circuits. The probability of ferro- ing Pi sections instead of T sections, the insulation level of even
resonance could be further reduced by installing air-core inductors the first inductor could be reduced if the capacitors are grounded
in the tuning equipment. wye-connected. There is some question as to whether lightning
The large fundamental frequency voltage variation is not as arresters would be needed since a capacitor bank connected in
serious as it may appear at first glance. A 500-kY line of con- wye with the neutral grounded has the ability of sloping off
ventional design can withstand 60-c/s voltages of 1000 kV, since the front and reducing the crest of lightning surges. Finally,
minimum insulation requirements are usually determined by half-wave systems do not have any high-voltage switching surges,

1965 HUBERT AND GENT: HALF-WAVELENGTH TRANSMISSION LINES 973


further reducing the system's insulation requirements. 0.82-pu current, not 1 pu, as he indicated.
In his discussion, Mr. Stillman has presented a detailed The authors no longer feel that the tuning equipment should
analysis of mismatch loading. However, the receiving network be on the low-voltage side. However, the statement in the paper
of a long power transmission line consists of generators, in addi- "additional benefits in reduced insulation are realized" applied
tion to the loads, which absorb all fluctuations of the load. to the tuning equipment and not the transformers.
These generators hold the frequency and voltage relatively In design number two, Ferranti voltages are not possible
constant at the receiving end network. Because of this, power since at power frequencies the lumped capacitors at 100-mile
flow on a half-wave line is easily controlled at the sending end, intervals behave as if the capacitance were distributed uni-
watts by the governor and vars by the voltage regulator. No formly along the entire length of the section. If the capacitors
problem is encountered transmitting SIL at unity PF. are grounded wye-connected, high-frequency currents such as
The 13.5 percent overvoltage that concerned Mr. Stillman on are produced by lightning surges are bled off to ground through
the high side bushing is present because the line was designed for the relatively low-impedance capacitors.

Sheath Overvoltages in High-Voltage Cables


Resulting from Special Sheath-Bonding
Connections
E. H. Ball E. Occhini G. Luoni

Abstract: Systems of sheath bonding which eliminate sheath fact that appreciable voltages may arise at various points
losses in single-core cables cause sheath overvoltages as a result of the sheath circuit because of transients or faults, will be
of transients and faults. Equations for transient sheath voltages
are derived for the first incident wave, through the use of equiva- discussed i this paper which iS a sequel to [1], which dealt
lent circuits to represent bonding points. The method is ex- with earlier phases of the work presented here. Some of the
tended to subsequent reflections with a digital computer; cal- material in the earlier paper is repeated here if it seems vital
culated results are given for several values of the relevant param- to provide a complete picture. Hence, the present paper
eters, and the effect of these parameters is discussed. Transient
sheath voltages can be limited by the surge diverter described in supersedes rather than supplements the prevous one.
this paper; and the necessary sheath insulation levels, with and
without surge diverters, are discussed. Equations for sheath Types of Sheath Bonding Considered
overvoltages caused by external steady-state faults are given.
Calculated and measured sheath voltages when compared, show The following section describes the principal methods, used
reasonable agreement for both transient and steady-state cases. in Great Britain, of bonding the sheaths of single-core cables
to eliminate sheath losses.
The rapid growth of loads to be transmitted bv power cables
in recent years has directed the attention of cable engineers in SINGLE-POINT BONDING
Great Britain to the advantages of special sheath-bonding Short cable circuits, mostly interconnections within a sub-
connections. These special methods of connection are station or terminations of an overhead line into a substation,
applicable to single-core cables and replace the traditional have frequently been dealt with by bonding and earthing
method of bonding and earthing the sheaths at both ends of the three sheaths at only one point along the cable route.
the cable route. They have the object of eliminating or This point is normally at one end or at the center.
greatly reducing the circulating currents in the sheaths and, The British Electricity Boards have imposed limitations on
hence, the sheath losses. As a result, thev considerably sheath voltages resulting from full-load current in the cable
increase the current rating of the cables. conductors which, until recently, have been 10 volts at an
While those bonding methods are not new and some have exposed termination and 50 volts for an underground sheath.
been widely used in the United States, they were not intro- The first limitation was recently raised to 25 volts; the second
duced in Great Britain until six or seven years ago, but are now is under review for possible revision.
firmly established. Some of the load transmission require- The difference between these two limitations has initiated
ments of the Central Electricity Generating Board at 275 kV the use of a further type of single-point bonding in which
or 400 kV could not be met by a single circuit without some sheaths are earthed at the terminations and interrupted at
method of eliminating sheath losses. some point along the lengths, usually the center. This per-
It has been recognized that the introduction of special mits employment of longer cable lengths inasmuch as the
sheath-bonding methods brings disadvantages as well as limitation of sheath voltage is not so severe.
advantages. The disadvantages, mainly associated with the These bonding methods are variations of single-point bond-
ing in that each length of sheath is earthed at only one point
- by- the Insulated
Paper 31 TP 65-128, recommended and approved ~~~~~andthere are no connections between sheaths except at the
Conductors Committee of the IEEE Power Group for presentation earth point.
at the IEEE Winter Power Meeting, New York, N. Y., January 31-
February 5, 1965. Manuscript submitted November 6, 1964; CROSS BONDING
made available for printing January 4, 1965.
E. H. BALL is with the Pirelli General Cable Works, Ltd., South- Longer cable circuits have been dealt with by the Kirke-
amptonl, England; and E. OCCHINI and G. LUTONI are with Pirelli, Searing type of cross bonding [2], [3] adapted to cables laid
S.p.A., Milan, Italy. in flat formation by combining transposition and sheath bond-
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS VOL. PAS-84a NO. 10 OCTOBER, 1965

Anda mungkin juga menyukai