Anda di halaman 1dari 10

See

discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/260620647

Exploring Monte Carlo Simulation Applications


for Project Management

Article in IEEE Engineering Management Review January 2009


DOI: 10.1109/EMR.2009.5235458

CITATIONS READS

54 1,399

2 authors, including:

Young Hoon Kwak


George Washington University
59 PUBLICATIONS 1,978 CITATIONS

SEE PROFILE

All content following this page was uploaded by Young Hoon Kwak on 16 September 2015.

The user has requested enhancement of the downloaded file.


IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 37, NO. 2, SECOND QUARTER 2009 83

Exploring Monte Carlo Simulation


Applications for Project
Management
YOUNG HOON KWAK AbstractMonte Carlo simulation is a useful technique for modeling
Department of Decision Sciences, and analyzing real-world systems and situations. This paper is
School of Business, a conceptual paper that explores the applications of Monte Carlo
The George Washington University, simulation for managing project risks and uncertainties. The benefits
Washington, DC 20052, USA of Monte Carlo simulation are using quantified data, allowing project
kwak@gwu.edu managers to better justify and communicate their arguments when
senior management is pushing for unrealistic project expectations.
LISA INGALL Proper risk management education, training, and advancements in
IBM Systems Technology Group, computing technology combined with Monte Carlo simulation software
Silver Spring, MD, USA allow project managers to implement the method easily. In the field of
project management, Monte Carlo simulation can quantify the effects
of risk and uncertainty in project schedules and budgets, giving the
project manager a statistical indicator of project performance such as
Reprinted by permission from
target project completion date and budget.
Macmillan Publishers Ltd:
Risk Management 2007,
9, (44-57) 2007 published by Key words: Monte Carlo simulation, project management, risk
Palgrave Macmillan. analysis and management, exploratory study.

INTRODUCTION mathematical and scientific


situations, and it is mentioned
T HE area of risk management
has received significant
often in project management
curricula and standards,
recognition in the field of such as A Guide to the Project
project management in recent Management Body of Knowledge
years (Kwak and Stoddard, (Project Management Institute,
2004). Project managers and 2004). Monte Carlo simulation
their superiors discovered that has not yet, however, found
the process of identification, a strong footing in the actual
analysis, and assessment of practice of project management
possible project risks benefits in the real world.
them greatly in developing risk
mitigation and contingency plans This paper reviews the
for complex project (Charette, applications of Monte Carlo
1996). This planning, in turn, simulation and its relevance to
helps the project manager better risk management and analysis
handle the difficult situations in project management. It also
that invariably occur during outlines the uses of Monte Carlo
projects, and therefore allows simulation in other disciplines
for more successful project and in the field of project
completion. management. Finally, it discusses
the pros and cons of Monte
One method used by some Carlo simulation applications
project managers during the risk in project management
analysis process is Monte Carlo environment, some examples
simulation applications. This of proposed improvements or
activity has been widely used alternatives to Monte Carlo
for decades to simulate various simulation, and concludes with
84 IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 37, NO. 2, SECOND QUARTER 2009

a recommendation that more to a wide variety of problems Although Monte Carlo simulation
project managers should take (Monte Carlo Method, 2005). is documented as a useful
advantage of this simple and Metropolis is actually credited method for project management
useful tool in managing project with naming the methodology applications, this method
risks and uncertainties. after the casinos of Monte has not been used much by
Carlo, and Ulam and Metropolis project managers in real-world
published their first paper on the situations, unless it is needed
OVERVIEW OF MONTE CARLO method in 1949 (Metropolis and by the organizations project
SIMULATION Ulam, 1949). management processes. Until
recently, it was difficult to find
Brief History of Monte Carlo software and hardware that could
Simulation The Monte Carlo Limited Applications to Project perform Monte Carlo simulation
simulation encompasses any Management With regards for projects. However, the primary
technique of statistical sampling to project management, Monte constraints with limited usage of
employed to approximate Carlo simulation is Monte Carlo simulation were with
solutions to quantitative project managers discomfort
problems (Monte Carlo Method, a technique that computes
or iterates the project cost with statistical approaches, lack
2005). A model or a real-life of thorough understanding of
system or situation is developed, or schedule many times
using input values selected the method, and the method was
and this model contains certain perceived as a burden rather
variables. These variables at random from probability
distributions of possible costs than a benefit to the organization
have different possible values, when Monte Carlo simulation
represented by a probability or durations, to calculate a
distribution of possible total was implemented heavily.
distribution function of the
values for each variable. The project cost or completion
Monte Carlo method simulates dates. (Project Management MONTE CARLO SIMULATION
the full system many times Institute, 2004). APPLICATIONS IN VARIOUS
(hundreds or even thousands It is generally mentioned DISCIPLINES
of times), each time randomly in project management Monte Carlo simulation has
choosing a value for each variable literature under the topic of been successful in areas
from its probability distribution. risk management, although it can outside of project management,
The outcome is a probability also be seen in the areas of time primarily in fields related to
distribution of the overall value management (scheduling) and modeling complex systems in
of the system calculated through cost management (budgeting). biological research, engineering,
the iterations of the model. geophysics, meteorology,
A standard approach to risk computer applications, public
The Monte Carlo method management of projects health studies, and finance.
simulates the full is outlined by the Project
system many times, Management Institute (2004) Biology and Biochemistry In
each time randomly that includes six processes: Risk the biology and biochemistry,
choosing a value for Management Planning, Risk Monte Carlo simulation has
each variable from its Identification, Risk Qualification, been used widely to model
probability distribution. Risk Quantification, Risk molecular activity. Berney and
Response Planning, and Risk Danuser (2003) described their
Monitoring and Control. Monte use of Monte Carlo simulation
The invention of this method, Carlo simulation is usually listed when modeling the fluorescence
especially the use of computers as a method to use during the resonance energy transfer (FRET)
in making the calculations, Risk Quantification process to technique, which measures
has been credited to Stanislaw better quantify the risks to the the interactions between two
Ulam, a mathematician working project schedule and budget. molecules. LeBlanc et al. (2003)
on the US Manhattan Project When this method is used, described the use of Monte
during World War II (Eckhardt, the project manager is able to Carlo simulations of molecular
1987). His work with Jon von justify a schedule reserve, budget systems belonging to complex
Neuman and Nicholas Metropolis reserve, or both to deal with the energetic landscapes, and offered
transformed statistical sampling issues that could adversely affect a new approach to improve the
from a mathematical curiosity to the project. convergence of these simulations.
a formal methodology applicable
EXPLORING MONTE CARLO SIMULATION APPLICATIONS FOR PROJECT MANAGEMENT 85

Other areas of Monte Carlo for selected rain gauge networks should have in the target project
simulation usage related to in the Global Precipitation completion date or total project
biology are in the fields of Climatology Project (GPCP). duration. Project manager and
genetics and evolutionary In public health, simulation subject matter experts assigns a
studies. In genetics, Korol et al. has been used to estimate the probability distribution function
(1998) used Monte Carlo direct costs of preventing Type 1 of duration to each task or
simulation to demonstrate the diabetes using nasal insulin if it group of tasks in the project
advantages of multi-trait analysis was to be used as part of a routine network to get better estimates.
in detection of linked quantitative healthcare system (Hahl et al., A three-point estimate is often
trait effects. One challenge in the 2003). Phillips (2001) argued that used to simplify this practice,
field of evolutionary studies is Monte Carlo simulation should be where the expert supplies the
the assembly of a Tree of Life, used by research organizations most-likely, worst-case, and
a comprehensive phylogenetic to determine whether or not best-case durations for each task
tree used to better understand future possible research is really or group of tasks. The project
evolutionary processes. Salamin worth the cost and effort, by manager can then fit these
et al. (2005) have used Monte modeling possible outcomes of three estimates to a duration
Carlo simulation to reconstruct the research. Boinske (2003) probability distribution, such
large trees such as the Tree of used Monte Carlo simulation as a normal, Beta, or triangular
Life, with parameters inferred in personal financial planning, distribution, for the task. Once
from four large angiosperm DNA especially when estimating the simulation is complete, the
matrices, which could radically how much money one needs project manager is able to report
assist researchers in creating this for retirement and how much the probability of completing
tree. one can spend annually once the project on any particular
retirement has begun. date, which allows him/her
Engineering In the field of to set a schedule reserve for
computer engineering and the project. The above can be
design, Bhanot et al. (2005) APPLICATION OF MONTE CARLO easily completed using standard
described the use of simulation SIMULATION IN PROJECT project management software,
when optimizing the problem MANAGEMENT such as Microsoft Project or
layout of IBMs Blue Gene/L Primavera, along with Monte
supercomputer. In geophysical Review of Monte Carlo Carlo simulation add-ins, such
engineering, Monte Carlo analysis Simulation Applications as @Risk or Risk+.
has been used to predict slope in Project Management
stability given a variety of Monte Carlo simulation, while In cost management, project
factors (El-Ramly, Morgenstern not yet widely used in project manager can use Monte Carlo
and Cruden, 2002). In marine management, does get some simulation to better understand
engineering, Santos and Guedes exposure through certain project project budget and estimate
Soares (2005) described a management practices. This final budget at completion.
probabilistic methodology exposure is primarily in the areas Instead of assigning a probability
they have developed to assess of cost and time management distribution to the project task
damaged ship survivability based to quantify the risk level of a durations, project manager
on Monte Carlo simulation. Lei projects budget or planned assigns the distribution to the
et al. (1999) explained their completion date. Williams (2003) project costs. These estimates are
use of Monte Carlo simulation outlined how Monte Carlo normally produced by a project
in aerospace engineering to simulation is used in project cost expert, and the final product
geometrically model an entire management and explains how is a probability distribution
spacecraft and its payload, using it aids the project manager of the final total project cost.
The Integral Mass Model. in answering questions such Project managers often use this
as, What is the probability of distribution to set aside a project
Other Disciplines In meeting the project due date? budget reserve, to be used when
meteorology, Monte Carlo and, What is (say) the 90 percent contingency plans are necessary
simulation is used to confident project duration? to respond to risk events.
model weather systems and
their results. For instance, In time management, Monte Carlo Monte Carlo simulation can
Gebremichael et al. (2003) have simulation may be applied to also be used in other areas of
used Monte Carlo analysis to project schedules to quantify the project management, primarily
evaluate sampling uncertainty confidence the project manager
86 IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 37, NO. 2, SECOND QUARTER 2009

in program and portfolio puts oneself at risk of exceeding project schedules was also a
management when making the project targets. Monte Carlo problem. Dramatic improvements
capital budgeting and investment simulation aids the project in computing power and the
decisions. Smith (1994) outlined manager in quantifying and introduction of Monte Carlo
how simulation assists managers justifying appropriate project simulation software add-ins to
in choosing among different reserves to deal with the risk the popular project management
potential investments and events that will occur during the scheduling tools have made these
projects. He explained that by life of the project. concerns virtually obsolete.
replacing estimates of net cash
flow for each year with probability Williams (2003) gave a thorough Monte Carlo simulation showing
distributions for each factor explanation of the advantages of project duration distributions
affecting net cash flow, managers Monte Carlo simulation over other that are very wide is another
can develop a distribution of methods of project analysis that drawback. Williams (2003)
possible Net Present Values try to incorporate uncertainty. He explained that this was
(NPV) of an investment instead explained that although there are because the simulations simply
of a single value. This is helpful many analytical approaches to carry through each iteration
when choosing between different project scheduling, the problem unintelligently, assuming no
capital investment opportunities with these analytical approaches management action. In the
that may have similar mean NPV was the restrictive assumptions real world, it is likely that
but differing levels of variance in that they all require, making management will take action to
the NPV distribution. them unusable in any practical recover projects that are severely
situations. These analytical behind schedule, and some of
Monte Carlo simulation has been methods often only provided these actions may (though not
used in construction projects certain moments of the project always) help bring the project
to better understand certain duration, instead of project back into an acceptable schedule
risks to the project. For example, duration distributions, which range. Some researchers were
noise and its detrimental effects were much more useful in attempting to create models
on the surrounding community answering questions about that incorporate management
is a risk in many urban the confidence level of project action into the simulation, but
construction projects. Gilchrist completion dates. Program to-date these models have a high
et al. (2003) have developed Evaluation and Review Technique level of complexity while still not
a Monte Carlo simulation (PERT) was the previous method incorporating sufficient generality
model that allows construction of choice for evaluating project with sufficient transparency for
contractors to predict and schedule networks, but this practitioner acceptance (Williams,
mitigate the occurrence and method does not statistically 2003).
impact of construction noise on account for path convergence
their projects. This model was and therefore normally tends to Although Monte Carlo simulation
tested and validated using field underestimate project duration. is an extremely powerful
measurements during various Monte Carlo simulation, by tool, it is only as good as the
stages of the construction of an actually running through model it is simulating and the
eight-story parking garage in hundreds or thousands of information that is fed into it.
London, Ontario, Canada. project cycles handles these path If the project model or network
convergence situations. is lacking, the simulation will
Advantages of Monte Carlo not reflect real-world activities
Simulation Applications in Limitations of Monte Carlo accurately. If project task
Project Management The Simulation Applications in duration distributions used for
primary advantage of using Project Management The a project duration simulation
Monte Carlo simulation in primary drawbacks of Monte are incorrect or inadequate,
projects is that it is an extremely Carlo simulation in the past the simulation will be off as
powerful tool when trying to have been high use of computing well. Estimating the durations
understand and quantify the power and the amount of of project activities normally
potential effects of uncertainty time and resources spent to requires expert knowledge,
of the project. Without the complete the simulation activity and even when a three-point
consideration of uncertainty (Williams, 2003). A lack of estimate is given to incorporate
in both project schedules and easy-to-use software tools to uncertainty into the model, there
budgets, the project manager run complex simulation against is still some latent uncertainty
EXPLORING MONTE CARLO SIMULATION APPLICATIONS FOR PROJECT MANAGEMENT 87

in the three-point estimate. Prior contingency amount, and an approaches give drastically
experience and detailed data from overrun probability estimate, different variance results. Hurley
previous projects of the same type instead of the usual most-likely, (1998) suggested that each
are both useful in mitigating this worst case, and best case parameter should be modeled
estimate uncertainty, although estimates. over time as a Martingale with
these data are often not available. an additive error term having
Therefore, project manager Button (2003) has proposed shrinking variances, so the
must be very careful in both a way to improve the project error variance gets smaller
reviewing estimates and choosing models used in Monte Carlo in each successive period of
probability distributions with simulation, to better simulate the project. He argued that
which to model these estimates how organizations normally this approach results in more
to avoid Garbage In, Gospel Out get their work done in real realistic parameter time series
syndrome. life situations. He argued that are consistent with the initial
that because todays work assumptions about uncertainty,
environment rarely utilizes and that the resulting simulation
SUGGESTED IMPROVEMENTS the single project, dedicated is more accurate than other
OF MONTE CARLO SIMULATION
resource model, organizations methods. As this approach
APPLICATIONS IN PROJECT may find that traditional Monte gave results that are between
MANAGEMENT Carlo simulation of project the two existing approaches
Many researchers have proposed task durations is insufficient. and it is easily implemented
minor modifications to current Buttons model simulated both with existing software, it would
Monte Carlo simulation practice project and non-project work in a probably be beneficial to those
in real-life projects. Most of these multi-project organization, and making investment decisions to
attempts are to complement and it did this by modeling periodic use all three approaches and
mitigate the weaknesses of Monte resource output across all active give various weights to each
Carlo simulation. tasks for each resource, based on result, depending on previous
project task priority rules set by organization experience and data.
Graves (2001) discussed different the organizations management.
types of probability distributions There was a strong argument Monte Carlo simulation,
that can be used for project for the advanced accuracy of while not yet widely used
task duration estimates. He this model in multi-project in project management,
proposed using open-ended organizations where resources does get some exposure
distributions, namely the are diluted across many different through certain project
lognormal distribution, instead of projects and activities. However, management practices,
using closed-ended distributions the complexity of the model and primarily in the areas
(such as the triangular its non-existence in commercially of cost and time
distribution) in Monte Carlo available software packages management.
simulations. A closed-ended currently makes it a poor
distribution explicitly denies any candidate for practical use.
possibility of the task duration
Balcombe and Smith (1999)
completing before the minimum Other researchers attempted have revisited the process of
duration or continuing beyond to improve the performance quantifying investment risk
the duration upper limit. In of Monte Carlo simulation using Monte Carlo simulation
real world projects, this is not in the area of finance and and have identified areas
a realistic assumption, since project portfolio investment risk where current practices may
sometimes showstopper issues analysis. In the area of simulating be improved. Their primary
may come up that were never NPV of potential investments concern was creating a model
expected and cause problems and projects, Hurley (1998) that was as accurate as possible
in the project. An open-ended argued that the conventional without being too complex for
duration distribution allowed for approaches to multi-period practical applicability. They
possibility of exceeding the upper uncertainty, with regards to proposed that simulation models
limit of the task duration, making the variables used in the NPV include trends, cycles, and
the simulation more realistic. calculation and their probability correlations, where, in addition
Graves (2001) also suggested distributions, may be unrealistic to the information required for
that in creating this open-ended for some parameters, and the an NPV calculation, the appraiser
distribution, the project manager two currently most popular is only required to state likely
should get a base estimate, a
88 IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 37, NO. 2, SECOND QUARTER 2009

bounds for the variables of Skitmore and Ng (2002) proposed and the availability of Monte
interest at the beginning and end an analytical approach to Carlo simulation software. The
of the project life along with an estimating total project cost and lack of readily available fuzzy sets
approximate correlation matrix. its variance in place of Monte calculation tools also diminished
This approach seemed to be Carlo simulation. They argued the impact of this proposal,
a practical and possibly more that Monte Carlo simulation is since project managers would
accurate alternative to straight used for this calculation because be required to do the fuzzy sets
NPV simulation that does not others feel that analytical calculations.
incorporate trends, cycles, or approaches are too complicated,
correlations. but they have derived a relatively Owing to the need for
straightforward calculation powerful computing
Javid and Seneviratne (2000) to determine the project cost capability and resources
have developed a model to variance. Although this approach to complete the Monte
simulate investment risk, does seem straightforward for Carlo simulation, some
specifically for airport parking someone who actively performs researchers have proposed
facility construction and statistical calculations, it is not alternatives to Monte
development. This model takes necessarily practical for use by Carlo simulation in
a standard risk management project managers, especially assessing project risks.
approach, identifying the when there is no tool or interface
possible sources of risk on the currently available to assist the
project, and then estimating project manager in using it. One of the results of Monte
the probability distributions of Moreover, the authors failed to Carlo simulation of a project
certain parameters affecting the validate their results against network and schedule is a
rate of return, such as parking Monte Carlo simulation or real criticality index for each task,
demand and construction cost project results questioning the which reflects the rate at which
overruns. The model used Monte model accuracy. the task appears on the critical
Carlo simulation to estimate path of the project throughout
and understand the impacts Others were concerned with the the many simulation iterations.
of cash flow uncertainties on complexity involved in Monte Cho and Yum (2004) proposed
project feasibility and to provide Carlo simulation. Lorterapong a new analytical approach that
a sensitivity analysis. and Moselhi (1996) proposed the estimated the criticality index
use of fuzzy sets theory, instead of a task as a function of the
of Monte Carlo simulation, in tasks expected duration and
ALTERNATIVES TO MONTE analyzing project networks.
CARLO SIMULATION also analyzed the sensitivity of
Their method incorporated the expected project completion
APPLICATIONS IN PROJECT new techniques that represent
MANAGEMENT time with respect to each tasks
imprecise activity durations, expected duration. They found
Owing to the need for powerful calculate scheduling parameters, that this methods accuracy was
computing capability and and interpret the fuzzy results comparable to that of direct
resources to complete the that are generated through Monte Carlo simulation, with one
Monte Carlo simulation, some the calculations. They argued minor computational error, where
researchers have proposed that this new approach to the amount of change in project
alternatives to Monte Carlo project completion calculations completion time for a change in
simulation in assessing project produced results that are in task duration is underestimated
risks. While all of these proposals close agreement with those when the ratio of the standard
have certain advantages over obtained using Monte Carlo deviation of the task duration
Monte Carlo simulation in simulation. They also believed to the mean task duration is
one way or another, the recent that their model was necessary large. They also claimed that
advances in computing power and because Monte Carlo simulation their approach was better than
cost, as well as the availability requires complicated calculations Monte Carlo simulation because
of easy-to-use Monte Carlo that normally must be done it was computationally more
simulation software, make many by computers if they are to be efficient, requiring less iteration
of these researchers arguments completed in any reasonable than direct simulation. This
obsolete, or at the very least, less amount of time. Their argument, consideration, however, would
striking than they may have been however, was lessened by the only be critical in extremely large
even a few years ago. advancement of computing power project networks, which would
EXPLORING MONTE CARLO SIMULATION APPLICATIONS FOR PROJECT MANAGEMENT 89

cause especially long time to alternatives have been brought usefulness of the method in
Monte Carlo simulation. While forward in order to respond project schedule, cost, and risk
this model did have potential for to observed deficiencies in management. This is primarily
applicability, the lack of a readily Monte Carlo simulation, namely due to its statistical nature,
available tool a project manager the computing power and which many project managers
could use to implement it limited time necessary to complete are reluctant to tackle. More
its practicality. a simulation. However, these project management education
concerns have drastically and training programs that
eliminated with recent demonstrate the simulation
SUMMARY, RECOMMENDATION, advancements in computing and hands on experience with
AND FUTURE DIRECTIONS
technology and the availability of the Monte Carlo Simulation
This research examines the Monte Carlo simulation software techniques to current and
Monte Carlo simulation method packages that integrate into potential project managers are
and its uses in various fields, popular project scheduling needed to overcome project
focusing primarily on its use in products. Most of the alternatives managers reluctance to use
the field of project management. to Monte Carlo simulation Monte Carlo simulation, once
Examples of practical use of that were identified were not the Monte Carlo simulation
the simulation method have expected to be as accurate as technique is thoroughly explained
been listed and discussed, as Monte Carlo simulation, and and demonstrated, hands-on
well as its advantages and none of them had a readily experience will allow project
limitations. With respect to the available tool to allow project managers to realize that the
use of Monte Carlo simulation in managers to easily implement statistical knowledge they
project management, researchers them into their current practice. are required to apply is quite
outlined how simulation is used Therefore, even in the face of minimal, and the tools are
in both project cost (budget) possible alternatives, Monte Carlo relatively easy to use once their
management and time (schedule) simulation still stands out as the project network and schedule
management and how these primary means of quantitatively have been created.
processes are integrated with analyzing project risks.
risk management to produce Business organizations that
reasonable project budget and Monte Carlo simulation can currently apply project
schedule reserves. The use of certainly be the project managers management processes and
Monte Carlo simulation in the best weapon for analyzing project practices must also realize the
area of investment risk analysis risks. It is an extremely powerful value of Monte Carlo simulation.
has also been discussed. tool that allows project managers They will be able to estimate and
to incorporate uncertainty and forecast more realistic project
Many researchers have proposed risk in their project plans and set schedules and budgets, with
improvements to the standard reasonable expectations on their reasonable reserves necessary
methods of Monte Carlo projects, with respect to both to deal with issues to predict,
simulation currently used schedule and budget. The results control, and complete more
in project management, and of simulation are quantifiable, projects successfully. If the value
most of these improvements allowing project managers of Monte Carlo simulation is
deserve strong consideration and to better communicate their realized, more project managers
possible future implementation, arguments when management will encourage the use of Monte
depending on individual project is pushing for unrealistic Carlo simulation on projects
needs and the practicality of the project expectations. Recent in their organizations. As
improvement. One would expect advancements in computing computing power and software
that as Monte Carlo simulation capability and Monte Carlo tools continue to improve, and
becomes more popular in project simulation software allow project once both business managers
management, more creative managers to implement the and project managers realize the
studies will propose practical, method with relative ease and value and practical applicability
applicable improvements to excitement. of Monte Carlo simulation to their
current practices and continue to projects and business results, the
contribute positively to the field. However, Monte Carlo simulation Monte Carlo simulation method
is still not a popular tool in will gradually become more
Few proposed alternatives to current project management popular and acceptable to the
Monte Carlo simulation have practice considering the practical project management community.
also been reviewed. These
90 IEEE ENGINEERING MANAGEMENT REVIEW, VOL. 37, NO. 2, SECOND QUARTER 2009

REFERENCES
Balcombe, K. and Smith, L. (1999). Refining the User of Monte Carlo
Techniques for Risk Analysis in Project Planning. The Journal of
Development Studies. 36(2), p. 113.
Berney, C. and Danuser, G. (2003). FRET or No FRET: A Quantitative
Comparison. Biophysical Journal. 84(6), p. 3992.
Bhanot, G., Gara, A., Heidelberger, P., Lawless, E., Sexton, J. C. and
Walkup, R. (2005). Optimizing Task Layout on the Blue Gene/L
Supercomputer. IBM Journal of Research and Development. 49(2/3),
p. 489.
Boinske, C. (2003). How Much Can I Spend? Journal of Financial Service
Professionals. 57(1), p. 33.
Button, S. (2003). Project Duration Prediction Using a Monte Carlo
Simulation of the Periodic Output of the Project Resources. Monte Carlo
Methods and Applications. 9(3), p. 217.
Charette, N. (1996). Large-Scale Project Management is Risk Management.
IEEE Software. 13(4), pp. 110117.
Cho, J.-G. and Yum, B.-J. (2004). Functional Estimation of Activity
Criticality Indices and Sensitivity Analysis of Expected Project
Completion Time. Journal of the Operational Research Society. 55(8),
p. 850.
Eckhardt, R. (1987). Stan Ulam, John von Neumann, and the Monte Carlo
Method. Los Alamos Science. Special Issue(15), pp. 131137.
El-Ramly, H., Morgenstern, N. and Cruden, R. (2002). Probabilistic Slope
Stability Analysis for Practice. Canadian Geotechnical Journal. 39(3),
p. 665.
Gebremichael, M., Krajewski, W.F., Morrissey, M., Langerud, D., Huffman,
G. J. and Adler, R. (2003). Error Uncertainty Analysis of GPCP Monthly
Rainfall Products: A Data-Based Simulation Study. Journal of Applied
Meteorology. 42(12), p. 1837.
Gilchrist, A., Allouche, E. and Cowan, D. (2003). Prediction and Mitigation
of Construction Noise in an Urban Environment. Canadian Journal of
Civil Engineering. 30(4), p. 659.
Graves, R. (2001). Open and Closed: The Monte Carlo Model. PM Network.
15(12), pp. 3741.
Hahl, J., Simell, T., Kupila, A., Keskinen, P., Knip, M., Ilonon, J. and
Simell, O. (2003). A Simulation Model for Estimating Direct Costs of
Type 1 Diabetes Prevention. Pharmacoeconomics. 21(5), p. 295.
Hurley, W. (1998). On the Use of Martingales in Monte Carlo Approaches
to Multiperiod Parameter Uncertainty in Capital Investment Risk
Analysis. The Engineering Economist. 43(2), p. 169.
Javid, M. and Seneviratne, P. (2000). Investment Risk Analysis in Airport
Parking Facility Development. Journal of Construction Engineering and
Management. 126(4), p. 298.
Korol, A. B., Ronin, Y.I., Nevo, E. and Hayes, P.M. (1998). Multi-Interval
Mapping of Correlated Trait Complexes. Heredity. 80(3), p. 273.
Kwak, Y. H. and Stoddard, J. (2004). Project Risk Management: Lessons
Learned from Software Development Environment. Technovation: An
International Journal of Technical Innovation, Entrepreneurship and
Technology Management. 24(11), pp. 915920.
LeBlanc, B., Braunschweig, B., Toulhoat, H. and Lutton, E. (2003).
Improving the Sampling Efficiency of Monte Carlo Molecular
Simulations: An Evolutionary Approach. Molecular Physics. 101(22),
p. 3293.
Lei, F., Ferguson, C., Bird, J.A., Lockley, J. J. and Dean, J. A. (1999).
The INTEGRAL Mass ModelTIMM. Astrophysical Letters and
Communications. 39(16), p. 841.
EXPLORING MONTE CARLO SIMULATION APPLICATIONS FOR PROJECT MANAGEMENT 91

Lorterapong, P. and Moselhi, O. (1996). Project-Network Analysis


Using Fuzzy Sets Theory. Journal of Construction Engineering and
Management. 122(4), p. 308.
Metropolis, N. and Ulam, S. (1949). The Monte Carlo Method. Journal of
the American Statistical Association. 44(247), pp. 335341.
Monte Carlo Method (2005). [Online]. [1 December 2005]. Available
from World Wide Web: http://www.riskglossary.com/link/
monte_carlo_method.htm.
Phillips, C. (2001). The Economics of More Research is Needed.
International Journal of Epidemiology. 30(4), p. 771.
Project Management Institute (2004). ANSI Standard #ANSI/PMI
99-001-2004; 2004. A Guide to the Project Management Body of
Knowledge: PMBOK Guide, (3rd ed.) Newton Square, Pennsylvania;
Project Management Institute.
Salamin, N., Hodkinson, T. and Savolainen, V. (2005). Towards Building
the Tree of Life: A Simulation Study for All Angiosperm Genera.
Systematic Biology. 54(2), p. 183.
Santos, T. and Guedes Soares, C. (2005). Monte Carlo Simulation of
Damaged Ship Survivability. Proceedings of the Institution of Mechanical
Engineers, Part M: Journal of Engineering for the Maritime Environment.
219(1), p. 25.
Skitmore, M. and Ng, S. (2002). Analytical and Approximate Variance of
Total Project Cost. Journal of Construction Engineering and Management.
128(5), p. 456.
Smith, D. (1994). Incorporating Risk into Capital Budgeting Decisions
Using Simulation. Management Decision. 32(9), p. 20.
Williams, T. (2003). The Contribution of Mathematical Modeling to
the Practice of Project Management. IMA Journal of Management
Mathematics. 14(1), p. 3.

Young Hoon Kwak, Ph.D., earned his M.S. and Ph.D. in Engineering and Project
Management from the University of California at Berkeley. His main research
interests include project management and control, risk management, and technology
management. He is currently an Associate Professor of Project Management at the
Department of Decision Sciences at The George Washington Universitys Business
School. He is serving as a Specialty Editor for Journal of Construction Engineering and
Management, and a member of the Editorial Review Board for Project Management
Journal. He was the co-principal investigator of Project Management Institute
(PMI)s path-breaking research Benefits of Project Management: Financial and
Organizational Rewards to Corporations. For more information, visit his website at
http://home.gwu.edu/~kwak (kwak@gwu.edu).

Lisa Ingall, PMP is a Master of Science in Project Management candidate at The


George Washington University and an IBM Certified Senior Project Manager in IBMs
Systems Technology Group. She has been leading projects in IBMs mainframe storage
software organization for over 5 years, from small programming enhancements in
support of new data storage products to new releases of z/OS Data Facility Storage
Management Subsystem (DFSMS) and z/OS Network File System (NFS). She is
currently integrating Monte Carlo analysis into her organizations standard processes
in order to better manage project schedule and budget risk.

View publication stats

Anda mungkin juga menyukai