MANAGEMENT TEMPLATE
Home Blog Management Template Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
This procedure outlines the system of control and inspections to be adopted for the fixing on site of tiles and mosaics.
Sign-up now! get useful contents into your email. Your email address.. SUBSCRIBE
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 1/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
SUBJECT: BY:
QA/QC ENGINEER
Ceramic Tiles, Terrazzo Tiles And Mosaics Method Statement APPROVED BY:
QEHS MANAGER
ACTION VERIFY
This procedure outlines the system of control and inspections to be adopted for the fixing on Manager Statement
site of tiles and mosaics.
Project Sample
2. PROCEDURE
Engineer approval
.1 A method statement shall be prepared and approved. It shall include:
Store- Instructions
i) Acceptance conditions for laying e.g. maximum moisture content of substrate,
levelness, soundness, cleanliness, environment. keeper FINI/05/A
Project FINI/05/A
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 2/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
ii) Surface preparation and bonding e.g. bonding agent, bed mix proportions, Manager
adhesives.
Project
iii) Specific requirements with regard to setting out, alignment of joints and cutting.
Engineer
iv) Method of protecting finished work.
.2 A sample of tiles shall be prepared on the wall in accordance with the specifications laid
down in the contract and approved by the Consultant.
.3 Storage of tiles:
i) Tiles shall be delivered to site palletised, on a clean hard surface free from
contamination by mud or surface water.
.4 The Project Director/Manager or his designate will confirm that materials are in
compliance with contract specification requirements.
.5 In the case of internal wall tiling, work will not proceed until all concealed conduits, pipes,
electrical cables and boxes etc. that penetrate the tiling have been fixed securely in position
and making good is complete. Obtain written clearance from MEP Co-ordinator that all their
works in that area is clear for taking up the tiling work.
PAGE 2 OF 3
SUBJECT: BY:
QA/QC Offline
ENGINEER
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 3/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
QEHS MANAGER
ACTION VERIFY
.6 Site operatives must observe the following while fixing tiles in addition to the Gen. FINI/05/A
specifications laid down in the contract document.
Foreman FINI/05/A
i) In the case of internal wall tiles, the setting out course or layout course is
established. Gen.
ii) The level and events of the wall surface should not exceed the allowable Foreman
tolerance as specified in the contract. Any such defect should be rectified before
proceeding further.
iii) While setting out for floor tiling, establish a datum level for the finished floor and
control the overall level of the finished floor by means of series of spot levels. The Site
Engineer will involve Consultants representative while fixing levels.
iv) Avoid cutting tiles as far as possible. If cutting cannot be avoided locate cut tiles
where they will be least noticeable, if in doubt refer to specification.
v) The sequence of fixing tiles shall be as follows unless specified otherwise in the
contract:
vii) Before placing the next tile take care to allow correct joint width by placing the
correct spacers in all corner joints.
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 4/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
viii) Do not start joint grouting work till tiles are properly fixed to the surface. Normally
the time period varies between 24 hrs to 48 hrs.
i) Protect external tiling and mosaics from rain and sun until the bed and joints have
set. Continue the protection for the period specified.
PAGE 3 OF 3
SUBJECT: BY:
QA/QC ENGINEER
QEHS MANAGER
ACTION VERIFY
ii) Do not allow tiling and mosaics to be wetted in shower bath areas for the period
as specified, until the bedding and joints have set and hardened.
iii) Do not permit any traffic at all on the flooring till the tiles are set afterwards permit
light foot traffic only.
iv) For general protection spread white no-staining saw dust over the floor but not
earlier than the period during which grout is hardened.
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 5/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
SUBCONTRACTOR: CLIENT
STAGE
ITEM
Checked
by Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 6/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
DATE
PREPARATION
PE
SE
3. Check storage condition of materials.SK4. Establish line and level.SU5. Check moisture content of substrate.GF6. Liaise with MEP
section for completion of their works.
PE/MEP
7. Acceptance of substrate
GF
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 7/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
PE
QA/QC
INSTALLATION
9. Check setting-out
SU
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 8/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
SU
GF
SE
APPROVAL TO PROCEED
QA/QC
POST 13. Check initial cleaning of work.GFINSTALLATION14. Check protection applied correctly.GF
APPROVAL TO PROCEED
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 9/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site Engineer, SU Surveyor, GF General
Foreman, SK Storekeeper
Download Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Word template:Ceramic Tiles,
Terrazzo Tiles and Mosaics Method Statement
Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer,
technical o ce engineer, planning engineer, planning manager, and nally planning department manager where he has been
involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt
Planning Engineer Est. Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP
certi ed from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of
planning and project management training on his website planningengineer.net, YouTube channel, and o ine courses since 2011.
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 10/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and
courses.
Download Planning Engineers Preparation Course for Men and Women abbreviations Mr., Mrs., Miss and Ms
February 11, 2014
Free
February 10, 2014
The application of Line of Balance (LOB) method in constr MEMO- 15 word templates
25 April, 2017 25 October, 2015
LEAVE A REPLY
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 11/12
11/16/2017 Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement Planning Engineer Est.
SEARCH
Search
PLANNING COURSES
Free
$665.00
$399.00
$149.00
$150.00
$119.00
Offline
https://planningengineer.net/ceramic-tiles-terrazzo-tiles-and-mosaics-method-statement/ 12/12