4.03.04 CIMIENTO CORRIDO MEZCLA 1:10 CEMENTO HORMIGON 30% DE P.G. M3 49.02
EJE J 1.00 14.90 0.50 0.70 5.22
1.00 7.40 0.50 0.70 2.59
EJE 10 1.00 5.85 0.50 0.70 2.05
EJE 11 1.00 11.20 0.50 0.70 3.92
EJE 12 1.00 5.85 0.50 0.70 2.05
EJE 13 1.00 5.85 0.50 0.70 2.05
EJE B 1.00 17.32 0.50 0.70 6.06
EJE K 1.00 16.30 0.50 0.70 5.71
EJE 9 1.00 27.70 0.50 0.70 9.70
EJE 16 1.00 27.70 0.50 0.70 9.70
4.03.05 SOBRECIMIENTO MEZCLA 1:8 CEMENTO: HORMIGON + 25% P.M. M3 4.92
EJE J 1.00 14.90 0.15 0.70 1.56
1.00 7.40 0.15 0.30 0.33
EJE 10 1.00 5.85 0.15 0.70 0.61
EJE 11 1.00 11.20 0.15 0.70 1.18
EJE 12 1.00 5.85 0.15 0.70 0.61
EJE 13 1.00 5.85 0.15 0.70 0.61
4.03.06 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO M2 65.55
EJE J 2.00 14.90 0.70 20.86
2.00 7.40 0.30 4.44
EJE 10 2.00 5.85 0.70 8.19
EJE 11 2.00 11.20 0.70 15.68
EJE 12 2.00 5.85 0.70 8.19
EJE 13 2.00 5.85 0.70 8.19
4.03.07 GRADAS CONCRETO F'C= 140 KG/CM + 30% PG M3 3.00 AREA= 0.83 2.49
4.04 CONCRETO ARMADO
4.04.01 CIMIENTOS
4.04.01.01 ZAPATAS, CONCRETO F'C= 210 KG/CM2 M3 69.45
EJE K Z-1: 2.00 2.10 2.10 0.60 5.29
Z-4: 6.00 1.00 1.00 0.60 3.60
EJE J Z-2: 2.00 2.30 2.30 0.60 6.35
Z-4: 6.00 1.00 1.00 0.60 3.60
EJE I Z-2: 2.00 2.30 2.30 0.60 6.35
EJE G Z-2: 2.00 2.30 2.30 0.60 6.35
EJE F Z-2: 2.00 2.30 2.30 1.00 10.58
EJE E Z-2: 2.00 2.30 2.30 0.60 6.35
EJE D Z-2: 2.00 2.30 2.30 0.60 6.35
EJE C Z-2: 2.00 2.30 2.30 0.60 6.35
EJE B Z-1: 2.00 2.10 2.10 0.60 5.29
Z-4: 5.00 1.00 1.00 0.60 3.00
4.04.01.02 ZAPATAS, ACERO DE REFUERZO FY= 4200 KG/CM2 KG 1,962.23
NDE VARILLAS PESO (KG) = 5/8"